FR2534952A1 FR8316528A FR8316528A FR2534952A1 FR 2534952 A1 FR2534952 A1 FR 2534952A1 FR 8316528 A FR8316528 A FR 8316528A FR 8316528 A FR8316528 A FR 8316528A FR 2534952 A1 FR2534952 A1 FR 2534952A1
Authority
FR
France
Prior art keywords
pile
ground
process according
liquid
casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
FR8316528A
Other languages
French (fr)
Inventor
John Peter Everett
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Frankignoul Pieux Armes
Original Assignee
Frankignoul Pieux Armes
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Frankignoul Pieux Armes filed Critical Frankignoul Pieux Armes
Publication of FR2534952A1 publication Critical patent/FR2534952A1/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/62Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/26Placing by using several means simultaneously

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

L'INVENTION CONCERNE L'INSTALLATION DE PIEUX. ON INSTALLE UN PIEU OU DES ELEMENTS ANALOGUES TELS QU'UN TUBAGE PROVISOIRE OU PERMANENT 2 DANS LE SOL EN L'ENFONCANT OU EN L'Y POUSSANT ET EN INTRODUISANT EN MEME TEMPS UNE SUBSTANCE LIQUIDE 7 APTE A LA PRISE TELLE QUE DU COULIS OU DU BETON LIQUIDE ENTRE LE COTE DU PIEU ET LE SOL DANS LEQUEL CE DERNIER EST ENFONCE. LA PRESENCE DE LA SUBSTANCE LIQUIDE, ENTRE LE COTE DU PIEU ET LE SOL, REDUIT LES FORCES DE FRICTION NORMALEMENT ENGENDREES, REDUISANT AINSI L'ENERGIE REQUISE POUR ENFONCER LE PIEU DANS LE SOL. L'INVENTION EST UTILISEE POUR INSTALLER, DANS LE SOL, DES PIEUX ET D'AUTRES ELEMENTS SEMBLABLES, NOTAMMENT DES TUBAGES PROVISOIRES OU PERMANENTS.THE INVENTION RELATES TO THE INSTALLATION OF PILES. A PILE OR SIMILAR ELEMENTS, SUCH AS A TEMPORARY OR PERMANENT PIPING 2, ARE INSTALLED IN THE SOIL BY PUSHING OR PUSHING IT AND AT THE SAME TIME INTRODUCING A LIQUID SUBSTANCE 7 SUITABLE FOR SETTING SUCH AS GROUT OR GROUT LIQUID CONCRETE BETWEEN THE SIDE OF THE PILE AND THE GROUND IN WHICH THE LATTER IS SENT. THE PRESENCE OF THE LIQUID SUBSTANCE, BETWEEN THE SIDE OF THE PILE AND THE GROUND, REDUCES THE FRICTION FORCES NORMALLY GENERATED, THUS REDUCING THE ENERGY REQUIRED TO DRIVE THE PILE INTO THE GROUND. THE INVENTION IS USED TO INSTALL, IN THE SOIL, PILES AND OTHER SIMILAR ELEMENTS, IN PARTICULAR TIMING OR PERMANENT TUBING.

Description

La présente invention concerne l'installa-The present invention relates to the installation

tion, dans le sol, de pieux et autres éléments sembla-  in the soil of piles and other similar elements.

bles, y compris des tubages provisoires ou permanents de pieux Pour plus de commodité, sauf indication spécifique contraire, tous ces éléments seront dési-  including temporary or permanent casings for piles For convenience, unless specifically indicated otherwise, all these elements will be required.

gnés ci-après par l'appellation "pieux" et il est en-  hereinafter referred to as "pious" and it is

tendu que l'expression "pieux", utilisée dans la pré-  tended that the term "piles", used in the preface

sente spécification, englobe tous ces éléments.  This specification encompasses all these elements.

On effectue habituellement l'installation de pieux en appliquant, à un pieu, des chocs axiaux de percussion au moyen d'unn marteau ou en faisant tourner le pieu et en lui appliquant en même temps une force axiale pour l'enfoncer dans le sol Un inconvénient associé à ces deux méthodes d'installation réside dans le fait que des forces de friction sont engendrées  Piling is usually accomplished by applying axial percussion impacts to a pile by means of a hammer or by rotating the pile and at the same time applying an axial force to drive it into the ground. disadvantage associated with these two methods of installation is that friction forces are generated

entre les côtés du pieu et le sol, ces forces augmen-  between the sides of the pile and the ground, these forces increase

tant l'énergie requise pour chasser le pieu dans le sol, de même que l'énergie requise pour retirer les  the energy required to drive the pile into the ground, as well as the energy required to remove the

tubages ou mandrins de pieux.casings or mandrels of piles.

Un objet de la présente invention est d'at-  An object of the present invention is to

ténuer l'inconvénient mentionné ci-dessus Un procédé d'installation d'un pieu suivant l'invention consiste à orienter le pieu par rapport au sol dans lequel il doit être installé, enfoncer ou  to mitigate the disadvantage mentioned above A method of installing a pile according to the invention consists in orienting the pile relative to the ground in which it is to be installed, to drive or

pousser le pieu dans le sol et, en même temps, intro-  push the pile into the ground and, at the same time,

duire une substance liquide apte à la prise entre le  to obtain a liquid substance suitable for

côté du pieu et le sol dans lequel ce dernier est en-  side of the pile and the soil in which the pile is

foncé.dark.

Le pieu est avantageusement enfoncé ou pous-  The pile is advantageously depressed or pushed

sé dans le sol en lui appliquant une force axiale et en le faisant tourner sur son axe De préférence, la force axiale est appliquée par des chocs de percussion exercés au moyen d'un marteau Les chocs du marteau et la rotation du pieu peuvent avoir lieu simultanément  in the soil by applying an axial force to it and rotating it on its axis Preferably, the axial force is applied by percussion impacts exerted by means of a hammer Hammer shocks and the rotation of the pile can take place simultaneously

253495 ?253495?

ou alternativement La rotation peut s'effectuer  or alternatively The rotation can be done

dans une direction ou elle peut être de type oscil-  in one direction or it can be oscil-

lant. La substance liquide apte à la prise qui peut être, par exemple, du béton ou du coulis liquide,  lant. The liquid substance suitable for setting which may be, for example, concrete or liquid slurry,

est avantageusement introduite en prévoyant un réser-  is advantageously introduced by providing a reser-

voir de cette substance à ltendroit o le pieu pénètre dans le sole ce réservoir permettant l'écoulement du coulis ou du béton entre le côté du pieu et le sol  see this substance where the pile enters the bottom of the tank allowing the flow of grout or concrete between the side of the pile and the ground

sous l'action de la gravité.under the action of gravity.

Le pieu peut être creux Dans ce cas, la substance liquide apte à la prise peut, en outre ou en variante, être introduite à l'intérieur du pieu au cours de son installation, ce qui peut être réalisé  The pile may be hollow In this case, the liquid substance capable of setting can, in addition or alternatively, be introduced inside the pile during its installation, which can be achieved

en pratiquant, dans la paroi du pieu, des ouvertures.  by practicing openings in the wall of the pile.

par lesquelles le coulis ou le béton s'écoule à l'in-  by which grout or concrete flows

térieur du pieu.inside the pile.

De plus, suivant l'invention, un pieu pou-  In addition, according to the invention, a pile can

vant être utilisé dans le procédé défini ci-dessus comprend un organe creux allongé le long de la paroi  For use in the method defined above, there is an elongate hollow member along the wall.

duquel des ouvertures sont pratiquées à intervalles.  which openings are made at intervals.

Le pieu peut avoir n'importe quelle section transversale appropriée permettant de ménager un espace libre entre le côté du pieu et le soldans lequel ce dernier est enfoncé ou poussé lors de sa rotation sur  The pile may have any suitable cross-section to allow free space between the side of the pile and the hammer where the latter is depressed or pushed during its rotation on

son axe C'est ainsi que le pieu peut avoir une sec-  This is how the stake can have a sec-

tion transversale carrée En variante, le pieu peut  As a variant, the pile can be

avoir une section transversale circulaire, un ou plu-  have a circular cross-section, one or more

sieurs éléments longitudinaux étant prévus sur sa face  if longitudinal elements are provided on its face

extérieure en ressortant vers l'extérieur.  outside coming out.

Le cadre de l'invention englobe également un pieu après son installation conformément au procédé  The scope of the invention also includes a pile after its installation in accordance with the method

de l'invention.of the invention.

On décrira ci-après à titre d'exemple une forme de réalisation de l'invention en se référant aux dessins annexés dans lesquels: la figure 1 est une vue en coupe illustrant l'installation d'un pieu suivant l'invention; et  An embodiment of the invention will now be described by way of example with reference to the accompanying drawings, in which: FIG. 1 is a sectional view illustrating the installation of a pile according to the invention; and

les figures 2 et 3 sont des vues en pers-  Figures 2 and 3 are views in

S pective de tubages de pieux suivant l'invention,  S pective of pile casings according to the invention,

Dans cette forme de réalisation de 1 linven-  In this embodiment of 1 linven-

tion, un pieu doit être installé dans le sol de niveau indiqué par le chiffre de référence 1 ' L 8 installation  a pile must be installed in the ground level indicated by the reference number 1 'L 8 installation

doit être effectuée au moyen d'un tubage de pieu provi-  shall be carried out by means of a temporary stake casing

soire 2 tel que celui représenté en figure 2 ou en fi-  2 as shown in Figure 2 or in

gure 3 Le tubage de pieu 2 illustré en figure 2 est  Figure 3 The pile casing 2 illustrated in Figure 2 is

sous forme d'un tube métallique creux à section trans-  in the form of a hollow metal tube with a trans-

versale carrée le long de chaque paroi latérale duquel des ouvertures 3 sont pratiquées à intervalles Le tubage de pieu 2 illustré en figure 3 est sous forme  square versal along each side wall of which openings 3 are made at intervals The pile casing 2 illustrated in Figure 3 is in the form of

d'un tube métallique creux à section transversale cir-  a hollow metal tube with a circular cross-section

culaire dont la paroi latérale comporte des ouvertures 3 à intervalles espacés O En outre, le tubage de pieu 2 illustré en figure 3 comporte des éléments longitudinaux 4 sur sa face extérieure, ces éléments ressortant radialement vers l'extérieur Chaque élément 4 comporte  the side wall comprises openings 3 at spaced intervals O Furthermore, the pile casing 2 illustrated in FIG. 3 comprises longitudinal elements 4 on its outer face, these elements emerging radially outwardly.

un bord d'attaque 4 a et un bord de fuite 4 b.  a leading edge 4a and a trailing edge 4b.

Afin d'installer un pieu suivant cette forme de réalisation de luinvention,, on place un pied 5 sur le sol 1 et on oriente verticalement un tubage de pieu 2 du type décrit ci-dessus, une extrémité de ce tubage étant placée sur le pied 5 O Un récipient 6, qui peut comporter une base 6 a et une paroi amovible 6 b, est situé autour du pied 5 et est rempli d'une substance liquide appropriée apte à la prise telle que du béton  In order to install a pile according to this embodiment of the invention, a foot 5 is placed on the ground 1 and a pile casing 2 of the type described above is oriented vertically, one end of this casing being placed on the foot. A container 6, which may comprise a base 6a and a removable wall 6b, is located around the foot 5 and is filled with a suitable liquid substance suitable for setting such as concrete

ou du coulis liquide 7.or liquid slurry 7.

Le tubage de pieu 2 passe-à travers une table rotative appropriée indiquée schématiquement par le chiffre de référence 8, cette table permettant de faire tourner le tubage 2 sur son axe A l'extrémité supérieure du tubage de pieu 2, est adapté un chapeau  The pile casing 2 passes through a suitable rotary table schematically indicated by the reference numeral 8, this table making it possible to rotate the casing 2 on its axis A at the upper end of the pile casing 2, is adapted a cap

approprié 9 destiné à le protéger contre les détério-  9 to protect it against

rations résultant des chocs exercés par un marteau  rations resulting from shocks exerted by a hammer

indiqué schématiquement par le chiffre de référence 10.  schematically indicated by reference numeral 10.

Pour installer le pieu, on enfonce tout  To install the pile, you press everything

d'abord le tubage 2 dans le sol 1 sous l'action combi-  first the casing 2 in the soil 1 under the combined action

née des chocs intermittents du marteau 10 et de la ro-  intermittent shocks from hammer 10 and rock

tation du tubage au moyen de la table rotative 8 A mesure que le tubage de pieu 2 est ainsi enfoncé dans le sol, le coulis ou le béton liquide s'écoule par gravité dans l'espace Il ménagé entre le côté du tubage  Tapping the casing by means of the rotary table 8 As the casing of pile 2 is thus driven into the ground, the grout or the liquid concrete flows by gravity into the space It formed between the casing side

de pieu et le sol On comprendra que, grâce à la con-  of pile and soil It will be understood that, thanks to the

figuration du tubage de pieu 2, cet espace 1 l est ainsi formé lors de la rotation de ce tubage En même tempse le coulis ou le béton s'écoule via les ouvertures 3 à  figuration of the pile casing 2, this space 1 l is thus formed during the rotation of this casing At the same time the grout or the concrete flows via the openings 3 to

lintérieur du tubage 2-Inside the casing 2-

Les coins du tubage de pieu (dans le cas du tubage illustré en figure 2) et les éléments 4 (dans le  The corners of the pile casing (in the case of casing shown in Figure 2) and the elements 4 (in the

cas du tubage illustré en figure 3) ont également ten-  tubing illustrated in Figure 3) also tend to

dance à chasser le coulis ou le béton vers l'extérieur dans le sol 1 De la sorte, dans un sol approprié, le diamètre définitif du pieu sera beaucoup plus grand que celui du tubage 2 e De la sorte également, on obtiendra, à l'interface comprise entre le sol et le coulis ou le béton, un moyen de mélange améliorant  In this way, in a suitable soil, the final diameter of the pile will be much larger than that of the casing 2. In this way too, we will obtain interface between the floor and grout or concrete, an improving mixing means

la liaison finale entre le pieu et le sol.  the final connection between the pile and the ground.

On considère que l'introduction du coulis ou du béton liquide entre le côté du tubage de pieu 2  It is considered that the introduction of grout or liquid concrete between the side of the pile casing 2

et le sol a pour effet de réduire les forces de fric-  and the soil has the effect of reducing the forces of

tion s'exerçant normalement dans cette zone, réduisant ainsi ipso facto l'énergie requise pour enfoncer le  this zone, thus reducing ipso facto the energy required to drive the

tubage de pieu dans le sol.pile casing in the ground.

Dès que le tubage de pieu 2 a été enfoncé dans le sol jusqu'à la profondeur requise, on peut, au besoin, laisser descendre une enveloppe appropriée d'armature en acier (non représentée) le long de la face intérieure du tubage de pieu 2 Le tubage peut alors être retiré de la manière habituelle en laissant  As soon as the pile casing 2 has been driven into the ground to the required depth, a suitable steel reinforcement shell (not shown) may be dropped down along the inside of the pile casing as needed. 2 The casing can then be removed in the usual way leaving

le pied 5 à la base du pieu L'extraction est beau-  the foot 5 at the base of the pile The extraction is

S coup plus aisée qu'avec des pieux classiques en raison  It's easier than with conventional piles due to

du coulis ou du béton entourant le tubage 2 En va-  grout or concrete surrounding the casing 2

riante, avant ou pendant l Venfoncement du tubage 2, on peut laisser descendre une cage d'armature appropriée (non représentée) le long de la face intérieure de ce  Before or during the penetration of casing 2, a suitable reinforcing cage (not shown) can be lowered along the inner face of this casing 2.

tubage 2 lorsque cela s'impose.casing 2 when required.

On peut envisager de nombreuses formes de réalisation de l'invention sans se départir du cadre  Many embodiments of the invention can be envisaged without departing from the scope of the invention.

de cette dernière tel qu Oil est défini ci-après.  of the latter as oil is defined below.

Par exemple, les ouvertures 3 peuvent être omises dans le tubage de pieu 2, auquel cas, 1 Pintés rieur de ce dernier peut être rempli de béton à grande hauteur d'affaissement lorsque ce tubage a été enfoncé  For example, the openings 3 may be omitted in the pile casing 2, in which case the inside of the casing may be filled with high-slump concrete when this casing has been inserted.

dans le sol à la profondeur requise.  in the soil to the required depth.

De plus, l'installation d'un pieu peut être  In addition, the installation of a pile can be

effectuée en appliquant une force axiale de non-per-  performed by applying an axial force of non-per-

cussion à n'importe quel endroit du pieu et ce, en lieu et place d'un marteau 100 L'invention est également applicable à l'installation de pieux composites Dans ce cas, un  The invention is also applicable to the installation of composite piles. In this case, a

pieu préfabriqué ayant, par exemple, une section trans-  prefabricated pile having, for example, a trans-

versale carrée, est enfoncé dans le sol de la manière décrite ci-dessusen adaptant un patin approprié à son extrémité inférieure Dès que le pieu préfabriqué est enfoncé dans le sol, l'installation est achevée et le  square-shaped, is pressed into the ground in the manner described above by fitting a suitable pad to its lower end As soon as the prefabricated pile is driven into the ground, the installation is completed and the

coulis déversé prend pour former un pieu composite.  Spilled grout takes to form a composite pile.

De plus, les ouvertures 3 pratiquées dans  In addition, the openings 3 made in

le tubage de pieu 2 peuvent être omises et des ouver-  pile casing 2 may be omitted and openings

tures peuvent être pratiquées dans le bord de fuite 4 b des éléments 4 L'intérieur du tubage 2 peut alors  can be made in the trailing edge 4b of the elements 4 The inside of the casing 2 can then

être utilisé à des fins diverses, ainsi qu'on le sou-  be used for a variety of purposes, as

lignera ci-après.lignera below.

Par exemple, dans ce cas, le tubage 2 peut être enfoncé dans le sol au moyen d'un marteau tombant  For example, in this case, the casing 2 can be driven into the ground by means of a falling hammer

sur un "bouchon" de béton ou une autre matière appro-  on a concrete "plug" or other suitable material

S priée prévue au fond du tubage-2 et ce, conjointement  S provided at the bottom of casing-2 and this, jointly

avec la rotation de ce dernier jusqu'à ce que la pro-  with the rotation of the latter until the

fondeur requise soit atteinte Ensuite, on empêche  required melter is reached Then, we prevent

une pénétration complémentaire du tubage 2 et l'on -  a complementary penetration of the casing 2 and the -

forme une base élargie en dessous du fond du tubage 2 en expulsant le bouchon et des charges successives de béton ou d'une autre matière appropriée moyennant l'application de chocs directs d'un marteau tombant à l'intérieur du tubage 2 Au besoin, on peut ensuite laisser descendre une cage d'armature le long de la face intérieure du tubage 2 et l'on peut remplir l'intérieur de ce dernier avec du coulis ou du béton  forms an enlarged base below the bottom of the casing 2 by expelling the plug and successive loads of concrete or other suitable material through the application of direct impacts of a hammer falling inside the casing 2 If necessary, a reinforcement cage can then be lowered along the inner face of the casing 2 and the interior of the casing 2 can be filled with grout or concrete

à grande hauteur d'affaissement.at high height of subsidence.

En variante, le tubage 2 peut être enfoncé  Alternatively, the casing 2 can be depressed

au moyen du "bouchon" décrit ci-dessus, mais sans for-  by means of the "cap" described above, but without any

mer une base élargie au moyen de ce "bouchon".  sea an enlarged base by means of this "cork".

Selon une autre possibilité, on peut former une base élargie comme décrit ci-dessus, mais le tubage  Alternatively, an enlarged base can be formed as described above, but the casing

2 est alors enfoncé par le marteau 10.  2 is then depressed by the hammer 10.

Etant donné que, dans le procédé suivant l'invention, on fait tourner un pieu, on peut également prévoir,-sur le pieu, des éléments d'alésage appropriés lorsque les conditions du sol exigent un accroissement  Since, in the process according to the invention, a pile is rotated, suitable boring elements can also be provided on the pile when the soil conditions require an increase in

du diamètre du pieu à n'importe quel niveau requis.  pile diameter at any required level.

Claims (10)

REVENDICATIONS 1. Procédé en vue d'installer un pieu dans le sol, caractérisé en ce qu'il consiste à enfoncer ou pousser un pieu ( 2) dans le sol ( 1,) et, en même temps, introduire une substance liquide ( 7) apte à la prise entre le côté extérieur du pieu ( 2) et le sol ( 1) dans lequel-ce  A method for installing a pile in the ground, characterized in that it consists in driving or pushing a pile (2) into the ground (1) and, at the same time, introducing a liquid substance (7). adapted to grip between the outer side of the pile (2) and the ground (1) in which it dernier doit être enfoncé.last must be depressed. 2. Procédé suivant la revendication 1, caractérisé en ce que le pieu ( 2) est enfoncé ou poussé dans le sol ( 1) en lui appliquant une force axiale et en  2. Method according to claim 1, characterized in that the pile (2) is depressed or pushed into the ground (1) by applying an axial force and le faisant tourner sur son axe.turning it on its axis. 3.D Procédé suivant la revendication 2, caractérisé en ce que la force axiale est appliquée au  3. Process according to claim 2, characterized in that the axial force is applied to the moyen de chocs de percussion exercés par un marteau ( 10).  means of percussion impacts exerted by a hammer (10). 4 Procédé suivant la revendication 3, caractérisé en ce que les chocs de marteau et la rotation  4 Process according to claim 3, characterized in that the hammer shocks and the rotation du pieu ( 2) ont lieu simultanément.  of the pile (2) take place simultaneously. 5. Procédé suivant la revendication 3, caractérisé en ce que les chocs de marteau et la rotation du  5. A method according to claim 3, characterized in that the hammer shocks and the rotation of the pieu ( 2) ont lieu alternativement.pile (2) take place alternately. 6, Procédé suivant l'une quelconque des  6, Process according to any one of revendications 2 à 5, caractérisé en ce que la rotation  Claims 2 to 5, characterized in that the rotation s'effectue dans une direction.in one direction. 7. Procédé suivant l'une quelconque des  7. Process according to any one of revendications 2 à 5, caractérisé en ce que la rotation est  Claims 2 to 5, characterized in that the rotation is de type oscillant -oscillating type - Procédé suivant l'une quelconque des  Process according to any one of revendications 1 à 7, caractérisé en ce que la substance  Claims 1 to 7, characterized in that the substance liquide ( 7) apte à la prise est choisie parmi le coulis  liquid (7) suitable for setting is selected from the grout liquide ou le béton liquide.liquid or liquid concrete. 9, Procédé suivant l'une quelconque des  9, Process according to any one of revendications 1 à 8, caractérisé en ce que la substance  Claims 1 to 8, characterized in that the substance liquide ( 7) apte à la prise est introduite en prévoyant un réservoir ( 6) à l'endroit o le pieu ( 2) pénètre dans le sol c 1) ce réservoir < 6) permettant à la substance liquide ( 7) apte à la prise de s'écouler entre le côté extérieur du  liquid (7) is introduced by providing a reservoir (6) where the pile (2) enters the ground c 1) the tank <6) allowing the liquid substance (7) adapted to the taken to flow between the outside of the pieu ( 2) et le sol ( 1) sous l'action de la gravité.  pile (2) and the ground (1) under the action of gravity. 10. Procédé selon l'une quelconque des  10. Process according to any one of revendications 1 à 9, caractérisé en ce que le pieu ( 2) est  Claims 1 to 9, characterized in that the pile (2) is creux et en ce que l'on introduit une substance liquide ( 7)  hollow and in that a liquid substance is introduced (7) apte à la prise à l'intérieur du pieu ( 2).  able to grip inside the pile (2). 11 Pieu destiné à être installé selon le procédé conforme à la revendication 10 caractérisé en ce qu'il comprend un organe allongé le long de la paroi duquel  11 pile intended to be installed according to the process according to claim 10 characterized in that it comprises an elongated member along the wall of which des ouvertures ( 3) sont pratiquées à intervalles, par les-  openings (3) are made at intervals, by means of quelles la substance liquide ( 7) apte à la prise s'écoule à  the liquid substance (7) capable of setting l'intérieur du pieu ( 2).the inside of the pile (2). 12. Pieu destiné à être installé selon le  12. pile to be installed in accordance with procédé conforme à l'une quelconque des revendications l à 10,  process according to any one of claims 1 to 10, caractérisé en ce qu'il possède une section transversale con-  characterized in that it has a cross-section çue pour ménager un espace libre ( 11) entre sa paroi latérale extérieure et le sol ( 1) dans lequel il est enfoncé ou poussé  designed to provide a free space (11) between its outer side wall and the ground (1) in which it is depressed or pushed lors de sa rotation sur son axe.when rotating on its axis. 13. Pieu suivant la revendication 12,  Pile according to claim 12, caractérisé en ce qu'il a une section transversale cérrée.  characterized in that it has a cross-section of grain. 14. Pieu suivant la revendication 12, caractérisé en ce qu'il a une section transversale circulaire, un ou plusieurs éléments longitudinaux ( 4) étant prévus sur sa face extérieure, ces éléments ressortant vers l'extérieur  14. pile according to claim 12, characterized in that it has a circular cross section, one or more longitudinal elements (4) being provided on its outer face, these elements emerging outwards. de ce pieu ( 2).of this stake (2). 15. Pieu, caractérisé en ce qu'il est ins-  15. Stake, characterized in that it is tallé par le procédé conforme à l'une quelconque des revendi-  by the process according to any of the claims cations 1 à 10.cations 1 to 10.
FR8316528A 1982-10-20 1983-10-18 METHOD FOR INSTALLING A PIEU IN THE SOIL, AND PIEU USED THEREIN Pending FR2534952A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
GB08230017A GB2129471A (en) 1982-10-20 1982-10-20 Installation of piles

Publications (1)

Publication Number Publication Date
FR2534952A1 true FR2534952A1 (en) 1984-04-27

Family

ID=10533736

Family Applications (1)

Application Number Title Priority Date Filing Date
FR8316528A Pending FR2534952A1 (en) 1982-10-20 1983-10-18 METHOD FOR INSTALLING A PIEU IN THE SOIL, AND PIEU USED THEREIN

Country Status (10)

Country Link
BE (1) BE898026A (en)
BR (1) BR8305766A (en)
DE (1) DE3337994A1 (en)
FI (1) FI833758A (en)
FR (1) FR2534952A1 (en)
GB (1) GB2129471A (en)
GR (1) GR78698B (en)
LU (1) LU85052A1 (en)
NL (1) NL8303531A (en)
ZA (1) ZA837623B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112323792B (en) * 2020-11-03 2022-07-15 北京顺义建筑企业集团公司 Internal-driving hammer pile pipe for holding-pressing type hammering pressure-grouting pile

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3404740A (en) * 1966-02-01 1968-10-08 Clemens B. Hoppe Apparatus for installing piling
US3638433A (en) * 1969-03-28 1972-02-01 James L Sherard Method and apparatus for forming structures in the ground
FR2180405A5 (en) * 1972-04-14 1973-11-23 Steding Jerry
US4009582A (en) * 1975-10-29 1977-03-01 Interpile Usa, Inc. Method for forming deep cast-in-place caseless concrete piles
US4018056A (en) * 1975-07-18 1977-04-19 Interpile Usa, Inc. Apparatus for forming cast-in-place caseless concrete piles and the like
GB1506388A (en) * 1975-05-23 1978-04-05 Lilley Waddington Ltd Excavation of bore holes

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE656012A (en) * 1963-12-05
DE1634470A1 (en) * 1965-11-04 1970-10-29 Mueller Ludwig Foundation stake
BE791062A (en) * 1971-12-14 1973-03-01 Taranto Rosanna PROCESS FOR CONSOLIDATION OF FURNISHED AND PILLAR FLOORS, PROVIDED WITH SEPARATE BALLS AND SPACES, CONSTRUCTED BY THIS PROCEDURE
JPS5346109A (en) * 1976-10-08 1978-04-25 Wataru Nakanishi Method of forming underground pile
GB2064627B (en) * 1979-12-11 1983-09-21 Piling Tech Ltd Method of piling

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3404740A (en) * 1966-02-01 1968-10-08 Clemens B. Hoppe Apparatus for installing piling
US3638433A (en) * 1969-03-28 1972-02-01 James L Sherard Method and apparatus for forming structures in the ground
FR2180405A5 (en) * 1972-04-14 1973-11-23 Steding Jerry
GB1506388A (en) * 1975-05-23 1978-04-05 Lilley Waddington Ltd Excavation of bore holes
US4018056A (en) * 1975-07-18 1977-04-19 Interpile Usa, Inc. Apparatus for forming cast-in-place caseless concrete piles and the like
US4009582A (en) * 1975-10-29 1977-03-01 Interpile Usa, Inc. Method for forming deep cast-in-place caseless concrete piles

Also Published As

Publication number Publication date
NL8303531A (en) 1984-05-16
ZA837623B (en) 1984-07-25
BR8305766A (en) 1984-05-29
FI833758A0 (en) 1983-10-17
LU85052A1 (en) 1984-03-22
DE3337994A1 (en) 1984-04-26
FI833758A (en) 1984-04-21
GB2129471A (en) 1984-05-16
BE898026A (en) 1984-02-15
GR78698B (en) 1984-09-27

Similar Documents

Publication Publication Date Title
EP3002371B1 (en) Machine and method for building columns in a floor
EP0747537B1 (en) Drive-out drill and method for the construction of ground screw-piles
FR2960570A1 (en) WALL FORMED IN A SOIL, COMPRISING A HOLLOW PREFABRICATED ELEMENT, AND METHOD OF MAKING SUCH A WALL
EP1087063B1 (en) Device for drilling and anchoring and method for installing ground anchors
CH642141A5 (en) UNDERGROUND PASSAGE AND METHOD FOR CONSTRUCTING THE PASSAGE.
EP1793045A1 (en) Gripping device for a micro pile head and tension test apparatus including such a device
FR2535760A1 (en) METHOD AND APPARATUS FOR REALIZING IN SITU CONCRETE PILES WITH EXTENDED BASES
FR2534952A1 (en) METHOD FOR INSTALLING A PIEU IN THE SOIL, AND PIEU USED THEREIN
FR2737525A1 (en) Ground fixing peg for posts - comprises single anchor, forced into ground, having two webs surrounding and reinforcing central sheath, sheath cut with horizontal slots delimiting alternate hollow and projecting portions
EP0034106B1 (en) Earth-compression drill bit with plane closing disc
EP1441076A1 (en) Injectable micropile
FR2524030A1 (en) Anchor head for progressively contracted composite tie rod - has truncated anchoring pin wedged into anchoring ring orifice
FR1464392A (en) Method for establishing a concrete foundation, including concrete foundation piles, and tubes with ribs or radial appendages
FR2575776A1 (en) Method of constructing cast-in-place concrete pile
BE1006194A5 (en) Drilling device and process for the formation of piles or the like
FR2535759A1 (en) METHOD FOR FORMING CONCRETE PILES AND NEW PREPARATORY PIEU FOR THIS PROCESS
FR2600686A1 (en) Improvements to reinforced concrete screw piles, by adding anchoring teeth
EP3205775A1 (en) Drilling tool and method of drilling
FR2502208A1 (en) Ground stabilisation and strengthening procedure - has grout injection rods acting as ground anchors forced into ground by vibrating percussion hammer
FR2754006A1 (en) METHOD FOR SETTING UP A GROUND ANCHORING, ANCHORING AND LANDING AND THRESHING TOOL FOR EXECUTING THE PROCESS
BE508872A (en)
FR2615880A1 (en) Method for integrating consolidating frames or the like into vertical sloping or counter-sloping ground, and tools for its implementation
WO1986005834A1 (en) Dowel fitted with a sleeve, for fixing posts or pickets in the ground
BE513698A (en)
BE518438A (en)