EP1352130A1 EP01997595A EP01997595A EP1352130A1 EP 1352130 A1 EP1352130 A1 EP 1352130A1 EP 01997595 A EP01997595 A EP 01997595A EP 01997595 A EP01997595 A EP 01997595A EP 1352130 A1 EP1352130 A1 EP 1352130A1
Authority
EP
European Patent Office
Prior art keywords
mesh
paving
stones
casting
joints
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP01997595A
Other languages
English (en)
French (fr)
Inventor
Knud Anker Rasmussen
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ABC-Mats GmbH
Original Assignee
ABC-Mats GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ABC-Mats GmbH filed Critical ABC-Mats GmbH
Publication of EP1352130A1 publication Critical patent/EP1352130A1/de
Withdrawn legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/0012Producing brick netting
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C5/00Pavings made of prefabricated single units
    • E01C5/06Pavings made of prefabricated single units made of units with cement or like binders

Definitions

  • the invention relates to partly a paving comprising at least one element with a number of cast paving stones laid and vibrated with intermediate joints on a foundation of a particulate material which also completely or partly fills the joints and at least one mesh embedded in the stones and joining the stones of the element, partly a mould and a method for manufacturing such an element.
  • Paving stones for e.g. pavements, parking areas, and parks are normally laid on a foundation one after the other at a joint distance from each other.
  • the joints are subsequently filled with a mineral, particulate joint filling material, such as sand, which is spread and swept down into the joints.
  • the paving is vibrated so that the foundation is compacted to become compact and solid and the filler material is compacted in the joints.
  • a joint of this kind is vulnerable to softening and washing-out of the joint filler during e.g. heavy showers when the rain water can penetrate down into the joint filler and further down into the foundation which thereby is softened.
  • the softened paving is loaded by the traffic of e.g. cars and lorries, the paving will sink.
  • the joint filler is softened gradually in order to be washed away in the end so that the paving stones will be loose.
  • the thus loaded paving is extremely uneven and therefore difficult to drive or walk on. In order to avoid accidents and damages to e.g. vehicles, it is therefore necessary to repair the damaged and uneven pavings.
  • the costs of maintaining stone pavings of this kind are therefore very high and the re-laying is hard and time-consuming as the stones are to be laid again stone by stone with a uniform joint distance across the entire damaged area .
  • An element consisting of paving stones is known from US 5,615,971.
  • the stones in this element are kept together by a single, elastic connecting links or an elastic mesh making it possible to vary the distance between the individual stone during the laying according to needs and wishes.
  • elastically deforming the connecting link or mesh By elastically deforming the connecting link or mesh, the shape of the element can be changed so that it can be made to follow curved edges.
  • this elastic mesh has a varying mesh size which leaves large joint openings between the individual stones.
  • a mesh or single connecting link designed in this way cannot keep the joint filler in the joint after laying of the stone element.
  • the object of the invention is to provide a paving of the kind mentioned in the opening paragraph, in which the joint filler is kept stably and firmly embedded in the joint between the stones even during heavy showers and cleaning with sweeping and sucking machines.
  • Another object of the invention is to provide a paving having a pre-determined joint spacing which can be laid more quickly than hitherto known without employment of great manpower and which is quickly, simple and inexpensive to manufacture.
  • a third object of the invention is to provide a mould for manufacturing an element for such a paving.
  • a fourth object of the invention is to provide a method for manufacturing the paving.
  • the novel and unique features according to the invention, whereby this is achieved, is the fact that at least the part of the mesh which is in the joints has a small-meshed structure and that the mesh is embedded in the upper part of the stones.
  • the elements forming the stone paving can preferably be laid on top of a graded levelling course of e.g. sand, rubble, or bitusand known from the Japanese patent application no. 9- 316808 and the German Auslegeschri t DE 1093396, by gripping the corner stone of each element, tightening its mesh and laying it in its place in the paving.
  • the distance of the mesh between the joint will in this way correspond to the joint spacing which advantageously will have a pre-determined size across the entire paving.
  • Particulate joint filler such as e.g. sand, bitusand, rubble and the like or pulverised cinder material which complies with possible legal requirements to depositing, will in the following generally be referred to as joint filler sand and the individual particles as grain of sand.
  • filler sand having a grain size corresponding to or smaller than the size of a mesh in the small-meshed structure of the mesh is swept across the paving .
  • the meshes in the small-meshed structure of the mesh can be rectangular and of a size that allows the largest grains of sand to pass.
  • a vibrator such as a pan vibrator
  • the stone paving is vibrated against the levelling course whereby sand from this layer will penetrate into the joint at the same time as particulate * joint filler, such as sand, is vibrated down into the joint until the entire joint is full of- sand.
  • the vibrated grains of sand turn over and over during the vibration and form a compact mass in which the orientation of the grains of sand is changed in relation to the orientation they had when they were filled into the joint.
  • the plate structure which is also known as base gravel has a very small pore volume and can therefore not absorb large amounts of rain water.
  • the meshes in the part of the mesh that is embedded in the stoned are sufficiently large to allow casting material to pass during the casting process.
  • Casting material such as concrete often has a content of pebbles and slightly larger particles, and these can easily pass through the large meshes and be distributed in a mould. The casting process thus takes place easily and quickly.
  • the embedded mesh advantageously serves for holding a number of paving stones together in an element so that several stones can be laid quickly and easily in one work operation.
  • the size of a mesh in the part of the mesh that is embedded in the stones constitutes about 50%, preferably 75% and especially 95% of the surface area of one stone .
  • the mesh is made of a material which is not or only very slowly is degraded upon action of the surrounding environment, the paving can easily be re-laid or repaired according to wishes and needs as one single element can be moved as a coherent unit.
  • Such an element with a number of cast paving stones with intermediate joints and embedded mesh can, in particularly expedient manner, be cast in a moult comprising partly a lower mould having a casting chamber for each stone, said chamber having a height corresponding to the distance of the mesh from the top of the stones, partly an upper form having casting chambers corresponding to the casting chambers of the lower form.
  • the form can be designed with any desired size with regard to e.g. thickness, extent, or shape of a stone, as one or more meshes intended therefore belong to each individual mould.
  • the element can be cast in such a mould by means of a method comprising an initial step in which a lower form having a chamber for each stone, that has a height corresponding to the distance of the mesh from the top of the stones is placed on a foundation with a casting opening in the casting chambers facing upwards.
  • the mesh is first placed on the top of the lower form so that the casting openings are covered by the large meshes in the mesh and the small-meshed structure covers the area between the casting openings.
  • an upper form is then placed having casting chambers corresponding to the casting chambers of the lower form.
  • the upper and lower forms together form a casting mould with casting chambers in which the casting material is cast to stones that are mutually joined by means of the mesh.
  • the casting material is allowed to harden before the mould is separated and the elements removed.
  • the same mould can be used for several castings.
  • the lower form can be filled with one or several natural stones, coloured stones or embossing pieces in the initial step in order to thereby be able to easily manufacture paving elements having different patterns and appearances.
  • texts and directions for parking areas can advantageously already be present in the paving element before it is laid.
  • the mesh can optionally be adhered to said at least one natural stone.
  • the casting material will in itself adhere to both the mesh and the natural stone during the actual casting.
  • Fig. 1 is a diagrammatic plan view of a paving according to the invention with six paving elements
  • Fig. 2 is a plan view of a mesh in a paving element according to the invention
  • Fig. 3 is a plan view of a paving element according to the invention
  • Fig. 4 is on a larger scale a fractional sectional view through a casting mould for cast paving stones, and
  • Fig. 5 is a side elevational view of a section of a completely laid paving with filled joints.
  • the paving is made of cast concrete stones and that the particulate material used as foundation and for filling the joints is sand.
  • Fig. 1 shows a complete paving 1 consisting in this case of six elements 2. One of these elements is indicated by the shown broken line. Each element 2 consists of sixteen stones 4 separated by sand-filled joints 3.
  • Fig. 2 shows a mesh 5 embedded in the stones 4 at a distance from the top of the stones.
  • the mesh is concealed by the sand in the joints.
  • the mesh 5 is formed by a large number of wires preferably placed mainly perpendicular to each other to form partly a small-meshed structure 6 for covering the joints 3 between the cast stones 4 of the element, partly a large-meshed structure 7 for at least partly embedment in the stones 4.
  • the mesh size varies according to needs and in dependence of the nature and quality of the concrete and filler sand.
  • the meshes in the small-meshed structure 6 in figs . 2 and 3 have both square and rectangular openings. However, the openings can advantageously also be either only square or only rectangular as different combinations of number of openings having different sizes and shapes can be expedient for different purposes .
  • the openings in the large-meshed structure 7 is chosen so large that the concrete is freely allowed to pass during the casting process.
  • Fig. 3 is a plan view of a finished cast element 2 with embedded mesh 5 and sixteen stones 4.
  • the small-meshed structure 6 of the mesh 5 is in the joints 3 between the stones 4 whereas the large-meshed structure 7 is embedded in the stones 4 and consequently is not visible in the figure.
  • the mesh 5 joins the stones 4 together to a manageable unit.
  • the size of at least one mesh in the part of the mesh which is in the joints is for example smaller than 100 mm 2 , preferably smaller than 50 mm 2 and especially smaller than 35 mm 2 , in order to allow grains of sand having typical diameters of between 0 and 6 mm to pass, and the size of a mesh in the part of the mesh embedded in the stones is preferred about 50%, preferably 75% and especially 95% of the surface area of one stone .
  • the size of at least one mesh in the large-meshed structure 7 embedded in the stones 4 is larger than about 1 cm 2 and smaller than the surface area of one stone 4.
  • Fig. 4 is a fractional view of a mould 8 for manufacturing an element 2 of the kind shown in fig. 3 with a mesh 5 of the kind shown in fig. 2.
  • the mould 8 is serving for casting an element 2 with a number of stones 4 with intermediate joints 3 and embedded mesh 5 by means of a lower form 9 and an upper form 10.
  • the lower form 9 has casting chambers 11 each having a height "a" corresponding to the distance of the mesh 5 from the top 12 of the stones 4.
  • the upper form 10 has casting chambers 13 corresponding to the casting chambers 11 of the lower form 9 and having a height "b" .
  • the lower form 9 is placed on a foundation with the casting opening of the casting chambers 11 facing upwards.
  • the mesh 5 is placed on the top of the lower form 9 so that its large-meshed structure 7 will cover the casting opening and the small-meshed structure 6 the partition between the casting chambers 11.
  • the upper form 10 is placed on top of the lower form 9 so that each casting chamber 13 of the upper form 10 will correspond to a casting chamber 11 in the lower form 9.
  • the mould is filled with concrete 14 possibly having a content of larger particles 15, and when the concrete has hardened, the form is separated and the finished element removed.
  • the mesh 5 is now binding the stones 4 to a coherent element 2 which, with fixed joints "c", is ready to be used for a concrete stone paving.
  • the moulds can preferably be made of a synthetic polymer, such as polypropylene or polyethylene, which is partly elastic so that the stones easily can be removed from the moulds.
  • Fig. 5 is a fractional sectional view of a paving with four stones 4.
  • a layer of levelled sand 18 is placed in a thickness of about 3 cm.
  • a number of elements 2 are laid with a joint spacing "c" and forming the paving 1.
  • the joints 3 are filled with filler sand 19 which has passed the meshes in the small-meshed structure 6 in loose condition.
  • the mesh 5 is embedded very near the top 12 of the stones 4 and as an example, the mesh is embedded between 5 and 15 mm from the top of the stones, embedment of the mesh about 15 mm from the top of the stones being especially preferred.
  • the invention is not limited to the above-mentioned dimensions of joint spacing, stone thickness, stone sizes and mesh sizes, as any advantageous combination of the size of e.g. particles in commercially available filler sand sets limits to e.g. mesh sizes in the small-meshed structure, and the content of the casting material of larger particles sets limits to the mesh size of the large-meshed structure.
  • strips of mesh with a small-meshed structure can be used instead of a coherent mesh within the scope of the invention. These mesh strips are laid during the casting process on the partitions of the lower form 9 and are extending into the mould chambers with a part that is sufficiently large for the stones to cohere securely in a whole element 2.
  • Areas which are to be paved but where a whole element is too large can be covered with a section of an element as the desired section is made merely by cutting the mesh between the stones.
  • the small-meshed structure 6 of the mesh allows the sand in loose condition to pass the meshes and fill the joints with filler sand.
  • sand from the levelled layer 18 will rise into the joints 3 at the same time as filler sand 19 is vibrated down into the joints.
  • the sand is compacted in the filled joint and the sand is packed to a compacted mass which, due to the plate effect, now no longer can pass the mesh even if the joints are subjected to heavy showers or to sweeping/suction machines. Filling and vibration can possibly be repeated in the cases where joint refilling is required.
  • the moisture degree in the layer 18 can be adjusted as desired and as may be required.
  • the moisture degree can advantageously be utilised in case of joint filling from the bottom as it has proven that the higher a moisture content in the layer, the more sand will penetrate up into the joint from the bottom.
  • the small-meshed mesh advantageously is keeping the filler sand in the joint, elements can be manufactured with a hitherto novel and unknown large joint spacing between the cast paving stones.
  • the elements are easy and quick to lay and it is furthermore easy to stack and transport a large amount of elements as the embedded mesh will eliminate the risk of the stones falling apart and that stacks of stones is overturning.

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)
EP01997595A 2000-11-27 2001-11-26 Pflasterung aus elementen mit gegossenen pflastersteinen und giesswerkzeug und verfahren zur herstellung solch eines elements Withdrawn EP1352130A1 (de)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
DK200001780 2000-11-27
DK200001780A DK173970B1 (da) 2000-11-27 2000-11-27 belaegning af elementer med stoebte belaegningssten, og form og fremgangsmade til fremstilling af et sadant element
PCT/DK2001/000781 WO2002042562A1 (en) 2000-11-27 2001-11-26 A paving of elements with cast paving stones and mould and method for manufacturing such an element

Publications (1)

Publication Number Publication Date
EP1352130A1 true EP1352130A1 (de) 2003-10-15

Family

ID=8159868

Family Applications (1)

Application Number Title Priority Date Filing Date
EP01997595A Withdrawn EP1352130A1 (de) 2000-11-27 2001-11-26 Pflasterung aus elementen mit gegossenen pflastersteinen und giesswerkzeug und verfahren zur herstellung solch eines elements

Country Status (5)

Country Link
EP (1) EP1352130A1 (de)
AU (1) AU2002223017A1 (de)
DK (1) DK173970B1 (de)
NO (1) NO20032179D0 (de)
WO (1) WO2002042562A1 (de)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7353034B2 (en) 2005-04-04 2008-04-01 X One, Inc. Location sharing and tracking using mobile phones or other wireless devices
SG166022A1 (en) * 2009-04-22 2010-11-29 Housing & Dev Board Paver pre-stressor apparatus and associated methods
JP6383342B2 (ja) * 2015-11-10 2018-08-29 大成ロテック株式会社 ブロック舗装構造およびその構築方法

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2812753A1 (de) * 1978-03-23 1979-10-04 Sf Vollverbundstein Verlegeeinheit aus beton-pflastersteinen
DE4138564A1 (de) * 1991-11-23 1993-05-27 Sf Vollverbundstein Pflastersteinsatz sowie verfahren und vorrichtung zum herstellen desselben
ITTN980012A1 (it) * 1998-07-21 2000-01-21 Riccardo Dallapiccola Formazione pannelli per rivestimenti e pavimentazioni in porfido

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See references of WO0242562A1 *

Also Published As

Publication number Publication date
NO20032179L (no) 2003-05-14
NO20032179D0 (no) 2003-05-14
AU2002223017A1 (en) 2002-06-03
WO2002042562A1 (en) 2002-05-30
DK173970B1 (da) 2002-03-18
DK200001780A (da) 2002-05-28

Similar Documents

Publication Publication Date Title
JPH04506552A (ja) 舗装面用角舗装材
US20060107610A1 (en) Methods for making composite tiles
JPH01102103A (ja) 歩道板構成用基枠
CA2052301A1 (en) Method of producing patterned shaped article
HUT74233A (en) Structure of a walking surface for horses, in particular for a riding area and a method of producing the same
WO2002042562A1 (en) A paving of elements with cast paving stones and mould and method for manufacturing such an element
EP1483451A1 (de) Betonstein
US20110061331A1 (en) Paving stone device and method
WO1996031656A1 (en) Paving block and method of manufacturing same
JPS59134204A (ja) タイル貼コンクリ−ト平板ブロツク及びその製造方法
EP0039555B1 (de) Strassenpflaster
JP2530645B2 (ja) 透水性舗装用ブロツク並びにその製造方法並びにこれを用いた透水性舗装方法
US20230002979A1 (en) Paving device
JPH0949202A (ja) 化粧板
CN108589461B (zh) 一种中空模型及应用该中空模型的园林道路施工工艺
JP2618776B2 (ja) ブロックの敷設方法
EP0191081B1 (de) Vorrichtung zum vibrieren von baumaterialien für strassendecken während dem aufbringen und verdichten
KR100741410B1 (ko) 흡수성 포장층의 시공방법
JP5505931B2 (ja) 舗装路、舗装路の修復方法及び舗装路の製造方法
JPS5851203Y2 (ja) コンクリ−ト舗装体
US125798A (en) Improvement in forming blocks for pavements
KR100559746B1 (ko) 도로경계석 제조방법
KR100540443B1 (ko) 포장용 블록의 충격 흡수용 패드와, 이를 이용한 포장용블록의 시공방법
JPH0355301A (ja) 踏盤類の敷設枠
JPH0529721B2 (de)

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20030627

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE TR

AX Request for extension of the european patent

Extension state: AL LT LV MK RO SI

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20050601