EP0670399B1 - Lifting scaffold platform - Google Patents

Lifting scaffold platform Download PDF

Info

Publication number
EP0670399B1
EP0670399B1 EP95102391A EP95102391A EP0670399B1 EP 0670399 B1 EP0670399 B1 EP 0670399B1 EP 95102391 A EP95102391 A EP 95102391A EP 95102391 A EP95102391 A EP 95102391A EP 0670399 B1 EP0670399 B1 EP 0670399B1
Authority
EP
European Patent Office
Prior art keywords
frame according
lift
lift frame
movable
facade
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Revoked
Application number
EP95102391A
Other languages
German (de)
French (fr)
Other versions
EP0670399A1 (en
Inventor
Paul Lingen
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
THEELEN, JOERG
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=6511719&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=EP0670399(B1) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Individual filed Critical Individual
Publication of EP0670399A1 publication Critical patent/EP0670399A1/en
Application granted granted Critical
Publication of EP0670399B1 publication Critical patent/EP0670399B1/en
Anticipated expiration legal-status Critical
Revoked legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B9/00Kinds or types of lifts in, or associated with, buildings or other structures
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F11/00Lifting devices specially adapted for particular uses not otherwise provided for
    • B66F11/04Lifting devices specially adapted for particular uses not otherwise provided for for movable platforms or cabins, e.g. on vehicles, permitting workmen to place themselves in any desired position for carrying out required operations
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B9/00Kinds or types of lifts in, or associated with, buildings or other structures
    • B66B9/16Mobile or transportable lifts specially adapted to be shifted from one part of a building or other structure to another part or to another building or structure
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B9/00Kinds or types of lifts in, or associated with, buildings or other structures
    • B66B9/16Mobile or transportable lifts specially adapted to be shifted from one part of a building or other structure to another part or to another building or structure
    • B66B9/187Mobile or transportable lifts specially adapted to be shifted from one part of a building or other structure to another part or to another building or structure with a liftway specially adapted for temporary connection to a building or other structure
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/26Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail
    • B66C23/28Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail constructed to operate at successively higher levels
    • B66C23/283Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes for use on building sites; constructed, e.g. with separable parts, to facilitate rapid assembly or dismantling, for operation at successively higher levels, for transport by road or rail constructed to operate at successively higher levels with frameworks composed of assembled elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/18Scaffolds primarily resting on the ground adjustable in height
    • E04G1/20Scaffolds comprising upright members and provision for supporting cross-members or platforms at different positions therealong

Definitions

  • the invention relates to a mast according to the preamble of claim 1.
  • a mast with two scaffolding masts is known, a rack being provided on the scaffolding masts, which meshes with a motor-driven gear.
  • the gear wheel is arranged on a work platform, so that this work platform can be adjusted in height along the scaffolding mast by means of the driven gear wheel. It is also possible in this way to adjust the height of a working bridge between two masts by means of gears and gear drives assigned to the individual masts.
  • the mast is built up in shots by placing the masts in shots by hand.
  • a scaffold for repair work on facades and eaves which has a walkable scaffold bridge between two mobile masts, the scaffold bridge at work height on rails or trusses attached there can be moved towards the facade.
  • DE-OS 31 14 602 describes a device for work scaffolding with a lifting and lowering work platform with associated safety device.
  • the work platform is arranged between four recessed guide rails and connected to the guide rails on both sides by a lifting mechanism and a suspension.
  • a support bar is arranged on both sides of the work platform, with the help of which the work platform is placed on the scaffolding towers.
  • Drop pawls are arranged on the support bar, which prevents the working platform from falling by snapping into the recesses in the guide rails when the chain of the lifting mechanism breaks.
  • the aerial work platform with a height-adjustable work platform connected to a frame has a work platform with at least two cross beams which are arranged at a distance from one another and can be connected to one another by longitudinal beams and which are provided with guide members via which the cross beams are each adjustable in height on or in a stand.
  • the invention has for its object to provide a mast of the type mentioned in such a way that the scaffold builds up and dismantles itself by the scaffold's own facilities, so that comparatively few operators are required to build a relatively large scaffold.
  • the mast it should be possible with the mast that, in the case of a mast with a multiplicity of scaffold masts arranged next to one another, at least one driving platform, or else several driving platforms, can be moved independently of one another along the scaffolding masts.
  • a lifting scaffold is reached which can be assembled by a few people, in particular with the aid of the scaffold mast transport device coupled to the carriage, in that the carriage transports the individual scaffolding parts, in particular the scaffolding masts, in shots upwards along the scaffolding masts already attached to the facade.
  • no auxiliary equipment such as a crane or the like, is required to assemble and disassemble the scaffold.
  • the scaffold mast has two support profiles with racks.
  • the carriage is equipped with couplings in such a way that it can take on additional functions such as crane replacement, personnel lift, material lift and the like.
  • One of the devices that can be coupled to the slide is expediently a scaffold mast transport device. - It is therefore possible to use the sled along additional scaffolding masts along partially erected scaffolding masts to be transported upwards to further assemble the scaffold or vice versa to transport scaffold mast sections from top to bottom when dismantling the mast.
  • One of the devices that can be coupled to the slide can also be expediently designed as a personnel and / or material lift. - This allows people to drive or climb the scaffold when the scaffold is finished and it is also possible to transport the materials and tools required for the work to be carried out.
  • the personnel and / or material lift is expediently pivotable on both sides around the scaffolding mast towards the facade.
  • one of the devices that can be coupled to the sled is a crane. - This makes it possible to unload materials from the mast itself from trucks and the like, without the need for an additional crane or truck crane.
  • the length of the driving platform can advantageously be freely determined between the scaffolding masts.
  • an elevator platform railing facing the facade is to be used to expand the stage floor towards the facade.
  • An electric or electrohydraulic drive for the gearwheels is expediently provided on the slide.
  • the mast can be designed so that the driving platforms have electrical or electro-hydraulic drives for driving the gear wheels.
  • At least one gear wheel may be provided to prevent the carriage and the platform from falling, or to be equipped with a device for this purpose.
  • the first driving platform can be inserted between the scaffolding masts and, to put on the next scaffolding mast shot, move up to the upper end of the scaffolding masts that are already standing.
  • a fitter traveling in the driving platform is able to attach the next raised scaffold mast shot to the already standing scaffold mast and to the facade. After at least two scaffolding mast shots have been added, the fitter can use the platform to drive to the end point of the scaffolding masts that were previously raised and wait for the next scaffolding mast shot to be raised there for further extension. With an additional fitter for picking up the mast parts on the floor or on the platform, two fitter are therefore sufficient to quickly cover large facade areas with mobile scaffolding.
  • stage floor is created by folding the railing on the facade side of the driving platform towards the stage floor, which fills the space between the facade and the stage.
  • any number of lifting platforms can be moved independently of one another along the scaffolding masts between the individual scaffolding masts.
  • the driving platforms Via the pantographs on the scaffolding mast, the driving platforms can be equipped with electricity for the tools of the fitters.
  • the length of the platform between the masts is freely selectable via individually connected stage segments. This makes it possible that adjacent lifts do not interfere with their height adjustment. This means that neighboring lifts can overtake or encounter each other.
  • Each of the scaffold bays formed by two neighboring scaffolding masts is completely independent of the scaffold bays adjacent to it with regard to the height adjustment of the driving platforms.
  • the slide can be equipped with additional functions by means of several interchangeable modules, for example a crane boom, which can transport large and heavy components to the roof similar to an otherwise usual construction crane when a scaffolding mast extends above the roof, or one Passenger and / or material lift, which can not only move fitters and material between the individual driving platforms onto the roof, but can also be swung into the building or into the building through the openings in the building.
  • a crane boom which can transport large and heavy components to the roof similar to an otherwise usual construction crane when a scaffolding mast extends above the roof
  • Passenger and / or material lift which can not only move fitters and material between the individual driving platforms onto the roof, but can also be swung into the building or into the building through the openings in the building.
  • a scaffold mast can be connected, for example, to a slide with a crane module and to any number of slides with lift modules, which can be moved independently of one another.
  • the mast 10 shown in the drawing has a plurality of scaffolding masts 11, which stand on the floor 12 or on a platform located above the floor level and can be extended in sections are.
  • Driving platforms 13 are provided between the scaffolding masts 11.
  • the scaffolding masts 11 are fastened to the building facade 15 by means of a plurality of holding supports 14.
  • the scaffold mast 11 consists of two support profiles 16, 17 and a corner profile 18, the support profiles 16, 17 and the corner profile 18 forming an isosceles triangle in plan view.
  • the support profiles 16, 17 and the corner profile 18 are stabilized via transverse and oblique struts 19, 20, 21.
  • Driving profiles 22, 23 are provided on the support profiles 16, 17.
  • a busbar 24 is provided on the struts 19 and a busbar 25 is provided on the struts 21.
  • the driving profile 22 is fastened to the inner profile flange 26 on the inner side of the support profile 16, while the free profile flange 27 is bent inwards by 90 °.
  • a rack 28 is provided, in which a gear 29 of a slide 30 runs.
  • a support wheel 31 is provided on the opposite side of the free flange 27.
  • the dash-dotted line 32 shown in the drawing represents a line of symmetry or, in plan view, a surface of symmetry between the left and the right area of the lifting mast 11 shown in FIG. 8.
  • the components shown on the right-hand side correspond to the plane of symmetry 32 33, 34, 35, 36, 37 the components 26, 27, 28, 29, 31 shown on the left side of the plane of symmetry 32.
  • a driving platform 38 with railings 39, 40, 41 and with a displaceable railing 42 is arranged on the right side of the plane of symmetry 32 of FIG. 4, a driving platform 38 with railings 39, 40, 41 and with a displaceable railing 42 is arranged.
  • a bearing block 44 is provided on the driving platform 38, on which two gear wheels 45 to be driven are provided, which run in a rack 46 of the support profile 17.
  • two opposite rollers 47, 48 are provided on the bearing block 44 and, in addition, a roller 50 in a further bearing block 49, which ensures that the gear 45 remains in constant contact with the rack 46.
  • the gear 45 is driven via the shaft 51.
  • a current collector 52 is provided on the bearing block 44, which is held displaceably in the busbar 25 or slides in the busbar 25.
  • a pantograph 53 is provided on the carriage 30, which is firmly guided in the busbar 24 or slides in the busbar 24.
  • the driving platform 54 has railings 55, 56 which correspond to the railings 39, 41.
  • the railing 57 which corresponds to the railing 42, is displaceable on the left side of the plane of symmetry 32 to the facade 15 and the folding railing 39 or 55 is lowered towards the facade, so that the driving platform 54 lies quite close to the facade 15, so that any Accidents are excluded.
  • the length-adjustable holding support 14 is arranged between a bearing 59 and a hook 60.
  • a motor 61 which drives the drive shaft 51 via a gear 62 and via gear wheels 63, 64.
  • a lift 65 is arranged on the slide 30 in FIG. 5 and can be pivoted relative to the slide 30 in joints 66, 67. In the embodiment shown on the left, the lift 65 is pivoted by 90 ° with respect to the longitudinal orientation of the scaffolding around the joint 66.
  • the material and / or passenger lift 65 is aligned in the direction of the scaffold.
  • the lift 65 has pivotable doors 68, 69 through which the individual stages can be operated or reached, provided the stage itself is not moved.
  • FIG. 6 differs from that shown in FIGS. 7 and 8 in that a crane 70 with a divided crane boom 71 is provided instead of the elevator 65.
  • the other arrangements are the same or similar or known to the arrangements described above.
  • a clamp 72 is provided on the slide 30 of the scaffold mast 11, the two jaws 73, 74 of which can be opened and closed by a wheel 75.
  • a scaffold mast section 76 is clamped between the two jaws 73, 74, which is pivoted by 180 ° relative to the scaffold mast 11 that has already been set up and can be raised in this state by means of the slide 30 and the pliers 72 and is pivoted back by 180 ° at the desired height , so that it is aligned with the already erected scaffold mast 11 and can be placed on it and connected to it.
  • the carriage 30 is shown in detail in FIG.
  • a rod 77 is to be driven via the motor 61, which has two worms 78, 79, via which the four gear wheels 29 are to be driven by means of axes 80, 81.
  • the support rollers are also shown.
  • a round disk 82 is provided in FIG. 7, which is fastened to the pliers 72 of the slide 30.
  • a bearing block 83 is provided on the disk 82, on which the bearing block 85 is articulated in a joint 84.
  • a multi-stage cylinder 88 is located in a joint 86 of the plate 82 and a joint 87 of the bearing block 85 provided, with the aid of which the joint 86 can be pivoted on a circular arc around the joint 84 until the disk 82 assumes the position provided perpendicularly thereto.
  • a drive chain 91 is provided between two sprockets 89, 90 so that a positive synchronism can be achieved here.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Transportation (AREA)
  • Automation & Control Theory (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Movable Scaffolding (AREA)
  • Types And Forms Of Lifts (AREA)
  • Cyclones (AREA)

Abstract

Each scaffolding mast has at least one support profile, on which at least one first toothed bar is provided which meshes with gearwheels arranged on the work platforms. At least one second toothed bar (46) for a slide is provided, which has gearwheels in its drive system. On the scaffolding mast current rails (24,25) are provided and current take-offs (52) on the work platforms and the slide. The scaffolding mast has two support profiles (17) with toothed bars. A scaffolding mast transport device is couplable to the slide. A personnel and/or material lift is couplable to the slide and is pivotable to both sides of the mast towards the facade (15) of the building.

Description

Die Erfindung betrifft ein Hubgerüst gemäß Oberbegriff des Anspruchs 1.The invention relates to a mast according to the preamble of claim 1.

Aus der US-PS 4 293 054 ist ein Hubgerüst mit zwei Gerüstmasten bekannt, wobei an den Gerüstmasten eine Zahnstange vorgesehen ist, die mit einem motorgetriebenen Zahnrad kämmt. Das Zahnrad ist an einer Arbeitsplattform angeordnet, so daß diese Arbeitsplattform mittels des angetriebenen Zahnrades in der Höhe entlang dem Gerüstmast verstellbar ist. Außerdem ist es auf diese Weise möglich, eine Arbeitsbrücke zwischen zwei Masten mittels jeweils den einzelnen Masten zugeordneter Zahnräder und Zahnradantriebe die Arbeitsbrücke in der Höhe zu verstellen.From US-PS 4,293,054 a mast with two scaffolding masts is known, a rack being provided on the scaffolding masts, which meshes with a motor-driven gear. The gear wheel is arranged on a work platform, so that this work platform can be adjusted in height along the scaffolding mast by means of the driven gear wheel. It is also possible in this way to adjust the height of a working bridge between two masts by means of gears and gear drives assigned to the individual masts.

Das Hubgerüst jedoch wird schußweise aufgebaut, indem von Hand die Masten schußweise aufgesetzt werden.The mast, however, is built up in shots by placing the masts in shots by hand.

Aus der DE-OS 35 26 105 ist ein Gerüst für Reparaturarbeiten an Fassaden und Dachtraufen bekannt, das eine begehbare Gerüstbrücke zwischen zwei fahrbaren Hubgerüsten aufweist, wobei die Gerüstbrücke in Arbeitshöhe auf dort angebrachten Laufschienen oder Traversen in Richtung Fassade verschiebbar ist.From DE-OS 35 26 105 a scaffold for repair work on facades and eaves is known, which has a walkable scaffold bridge between two mobile masts, the scaffold bridge at work height on rails or trusses attached there can be moved towards the facade.

In der DE-OS 31 14 602 ist eine Einrichtung für Arbeitsgerüste mit heb- und senkbarer Arbeitsbühne mit zugehöriger Sicherheitsvorrichtung beschrieben. Die Arbeitsbühne ist zwischen vier mit Aussparungen versehenen Führungsschienen angeordnet und an beiden Seiten über einen Hubmechanismus und eine Aufhängung mit den Führungsschienen verbunden. An beiden Seiten der Arbeitsbühne ist ein Auflageriegel angeordnet, mit dessen Hilfe die Arbeitsbühne auf den Gerüsttürmen aufgelegt wird. Auf dem Auflageriegel sind Fallklinken angeordnet, die einen Absturz der Arbeitsbühne verhindert, indem sie beim Reißen der Kette des Hubmechanismus in die Aussparungen der Führungsschienen einrasten.DE-OS 31 14 602 describes a device for work scaffolding with a lifting and lowering work platform with associated safety device. The work platform is arranged between four recessed guide rails and connected to the guide rails on both sides by a lifting mechanism and a suspension. A support bar is arranged on both sides of the work platform, with the help of which the work platform is placed on the scaffolding towers. Drop pawls are arranged on the support bar, which prevents the working platform from falling by snapping into the recesses in the guide rails when the chain of the lifting mechanism breaks.

Aus der DE-OS 34 15 074 ist eine Hubarbeitsbühne, insbesondere eine Arbeitsbühne für Bauhandwerker bekannt. Die Hubarbeitsbühne mit einer höhenverstellbar mit einem Gestell verbundenen Arbeitsplattform weist eine Arbeitsplattform mit wenigstens zwei auf Abstand voneinander angeordneten und durch Längsträger miteinander verbindbaren Querträgern auf, die mit Führungsgliedern versehen sind, über die die Querträger jeweils höhenverstellbar an oder in einem Ständer geführt sind.From DE-OS 34 15 074 an aerial work platform, in particular a work platform for construction workers is known. The aerial work platform with a height-adjustable work platform connected to a frame has a work platform with at least two cross beams which are arranged at a distance from one another and can be connected to one another by longitudinal beams and which are provided with guide members via which the cross beams are each adjustable in height on or in a stand.

Der Erfindung liegt die Aufgabe zugrunde, ein Hubgerüst der einleitend genannten Art so auszubilden, daß sich das Gerüst durch gerüsteigene Einrichtungen selbst aufbaut und abbaut, so daß zum Aufbau auch eines relativ großen Gerüstes vergleichsweise wenige Bedienungspersonen erforderlich sind. Desgleichen soll mit dem Hubgerüst möglich sein, daß bei einem Hubgerüst mit einer Vielzahl von nebeneinander angeordneten Gerüstmasten zwischen je zwei benachbarten Gerüstmasten wenigstens eine Fahrbühne, oder aber auch mehrere Fahrbühnen unabhängig voneinander an den Gerüstmasten entlang verfahren werden können.The invention has for its object to provide a mast of the type mentioned in such a way that the scaffold builds up and dismantles itself by the scaffold's own facilities, so that comparatively few operators are required to build a relatively large scaffold. Likewise, it should be possible with the mast that, in the case of a mast with a multiplicity of scaffold masts arranged next to one another, at least one driving platform, or else several driving platforms, can be moved independently of one another along the scaffolding masts.

Diese Aufgabe wird erfindungsgemäß mit den Merkmalen des Kennzeichens des Anspruchs 1 gelöst.This object is achieved with the features of the characterizing part of claim 1.

Auf diese Weise gelangt man zu einem Hubgerüst, das von wenigen Personen insbesondere mit Hilfe des am Schlitten angekuppelten Gerüstmasttransportgerätes aufgebaut werden kann, indem der Schlitten die einzelnen Gerüstteile, insbesondere die Gerüstmaste schußweise entlang der bereits an der Fassade befestigten Gerüstmaste nach oben transportiert. Insbesondere sind keine gerüstfremden Hilfsmittel, etwa ein Kran oder dgl. zum Aufbau und Abbau des Gerüstes erforderlich.In this way, a lifting scaffold is reached which can be assembled by a few people, in particular with the aid of the scaffold mast transport device coupled to the carriage, in that the carriage transports the individual scaffolding parts, in particular the scaffolding masts, in shots upwards along the scaffolding masts already attached to the facade. In particular, no auxiliary equipment, such as a crane or the like, is required to assemble and disassemble the scaffold.

Hierdurch ist es möglich, daß die Fahrbühnen in einem zwischen zwei benachbarten Gerüstmasten gebildeten Gerüstfeld unabhängig von den Fahrbühnen des benachbarten Gerüstfeldes entlang der Gerüstmaste höhenverstellbar sind, ohne daß sich Fahrbühnen benachbarter Gerüstfelder dabei gegenseitig behindern, was bedeutet, daß die Fahrbühnen sich gegenseitig überholen bzw. begegnen können.This makes it possible for the driving platforms in a scaffolding field formed between two adjacent scaffolding masts to be adjustable in height independently of the driving platforms of the adjacent scaffolding field along the scaffolding masts, without the moving platforms of adjacent scaffolding fields interfering with one another, which means that the driving platforms overtake one another or can meet.

Statt eines Trageprofils besteht auch die Möglichkeit, daß der Gerüstmast zwei Tragprofile mit Zahnstangen aufweist.Instead of a support profile, there is also the possibility that the scaffold mast has two support profiles with racks.

Es empfiehlt sich, daß der Schlitten durch Kupplungen so ausgerüstet ist, daß er zusätzliche Funktionen übernehmen kann, wie beispielsweise Kranersatz, Personallift, Materiallift und dergleichen.It is recommended that the carriage is equipped with couplings in such a way that it can take on additional functions such as crane replacement, personnel lift, material lift and the like.

Zweckmäßig ist eines der am Schlitten ankuppelbaren Geräte ein Gerüstmasttransportgerät. - Somit ist es möglich, mit dem Schlitten entlang bereits teilweise aufgebauter Gerüstmaste weitere Gerüstmastmodule nach oben zum weiteren Aufbau des Gerüstes zu transportieren bzw. umgekehrt Gerüstmastschüsse beim Abbauen des Hubgerüstes von oben nach unten zu transportieren.One of the devices that can be coupled to the slide is expediently a scaffold mast transport device. - It is therefore possible to use the sled along additional scaffolding masts along partially erected scaffolding masts to be transported upwards to further assemble the scaffold or vice versa to transport scaffold mast sections from top to bottom when dismantling the mast.

Eines der am Schlitten ankuppelbaren Geräte kann zweckmäßig auch als Personal- und/oder Materiallift ausgebildet sein. - Dadurch können bei fertigem Gerüst Personen das Gerüst befahren bzw. besteigen und außerdem ist es möglich die bei den auszuführenden Arbeiten erforderlichen Materialien und Werkzeuge zu transportieren.One of the devices that can be coupled to the slide can also be expediently designed as a personnel and / or material lift. - This allows people to drive or climb the scaffold when the scaffold is finished and it is also possible to transport the materials and tools required for the work to be carried out.

Zweckmäßig ist der Personal- und/oder Materiallift zu beiden Seiten um den Gerüstmast herum zur Fassade hin verschwenkbar.The personnel and / or material lift is expediently pivotable on both sides around the scaffolding mast towards the facade.

Mitunter ist es zweckmäßig, daß eines der am Schlitten ankuppelbaren Geräte ein Kran ist. - Dadurch besteht die Möglichkeit, Materialien vom Hubgerüst aus selbst von Lastkraftwagen und dergleichen abzuladen, ohne daß es eines zusätzlichen Krans bzw. Autokrans bedarf.Sometimes it is useful that one of the devices that can be coupled to the sled is a crane. - This makes it possible to unload materials from the mast itself from trucks and the like, without the need for an additional crane or truck crane.

In weiterer Ausgestaltung der Erfindung kann das Hubgerüst so ausgebildet sein, daß die Fahrbühnen mit einem Positioniergerät zum genauen manipulieren von Bauteilen ausgerüstet sind, welches mit einer fahrbaren Lafette über die gesamte Länge und Breite der Fahrbühne bewegbar ist. - Mit einem derartigen roboterartige arbeitenden Positioniergerät besteht die Möglichkeit, die Bewegungen

  • a) Heben und Senken,
  • b) Seitenverschieben nach rechts und links,
  • c) Längsverschieben nach vorn und zurück,
  • d) Neigen um eine horizontale Achse oben nach rechts und links,
  • e) Drehen um eine vertikale Achse rechtsherum und linksherum und
  • f) Schwenken um eine horizontale Querachse
durchzuführen und das Aufnehmen, Bewegen, Halten und Abgeben von Bauteilen zu ermöglichen.In a further embodiment of the invention, the mast can be designed so that the driving platforms are equipped with a positioning device for the precise manipulation of components, which can be moved with a movable carriage over the entire length and width of the driving platform. - With such a robot-like positioning device, there is the possibility of the movements
  • a) lifting and lowering,
  • b) shifting to the right and left,
  • c) longitudinal displacement forward and backward,
  • d) tilting to the right and left about a horizontal axis,
  • e) rotating around a vertical axis clockwise and counter clockwise and
  • f) pivoting about a horizontal transverse axis
perform and allow the picking up, moving, holding and dispensing of components.

Vorteilhafterweise ist die Fahrbühne in ihrer Länge zwischen den Gerüstmasten frei festlegbar.The length of the driving platform can advantageously be freely determined between the scaffolding masts.

Es empfiehlt sich, daß die Fahrbühnen auf Schienen horizontal und parallel zur Fassade verfahrbar sind.It is recommended that the platforms can be moved horizontally and parallel to the facade.

Des weiteren ist es zweckmäßig, wenn ein zur Fassade weisendes Fahrbühnengeländer zur Erweiterung des Bühnenbodens zur Fassade hin zu nutzen ist.Furthermore, it is expedient if an elevator platform railing facing the facade is to be used to expand the stage floor towards the facade.

Zweckmäßig ist an dem Schlitten ein elektrischer oder elektrohydraulischer Antrieb für die Zahnräder vorgesehen.An electric or electrohydraulic drive for the gearwheels is expediently provided on the slide.

In weiterer Ausgestaltung der Erfindung kann das Hubgerüst so ausgebildet sein, daß die Fahrbühnen elektrische oder elekrohydraulische Antriebe zum Antrieb der Zahnräder aufweisen.In a further embodiment of the invention, the mast can be designed so that the driving platforms have electrical or electro-hydraulic drives for driving the gear wheels.

Vorteilhafterweise sind je Antrieb zwei Zahnräder übereinanderliegend vorgesehen.Two gears are advantageously provided one above the other for each drive.

Es besteht auch die Möglichkeit, daß je Antrieb zwei Zahnräder gegenüberliegend vorgesehen sind.There is also the possibility that two gears are provided opposite each drive.

Zweckmäßig sind an den Tragprofilen der Gerüstmaste gegenüberliegend je zwei Zahnstangen vorgesehen, in denen je ein Zahnrad läuft.Two racks, in each of which a gearwheel runs, are expediently provided on the supporting profiles of the scaffolding masts.

Es ist jedoch auch möglich, daß wenigstens ein Zahnrad zur Sicherung gegen Absturz des Schlittens und der Fahrbühne vorgesehen ist bzw. mit einer Vorrichtung zu diesem Zweck ausgestattet ist.However, it is also possible for at least one gear wheel to be provided to prevent the carriage and the platform from falling, or to be equipped with a device for this purpose.

Zur Vermeidung von Unfällen empfiehlt es sich, daß je eines der übereinander liegenden Zahnräder zur Sicherung gegen Absturz des Schlittens und der Fahrbühne vorgesehen ist.To avoid accidents, it is recommended that one of the superimposed gears is provided to prevent the carriage and the platform from falling.

Nach dem Aufstellen von mindestens zwei parallelen Gerüstmasten kann die erste Fahrbühne zwischen den Gerüstmasten eingefügt werden und zum Aufsetzen des nächsten Gerüstmastschusses bis an das obere Ende der bereits stehenden Gerüstmaste fahren.After setting up at least two parallel scaffolding masts, the first driving platform can be inserted between the scaffolding masts and, to put on the next scaffolding mast shot, move up to the upper end of the scaffolding masts that are already standing.

Ein in der Fahrbühne mitfahrender Monteur ist in der Lage, den nächsten hochgefahrenen Gerüstmastschuß am bereits stehenden Gerüstmast und an der Fassade zu befestigen. Nachdem mindestens zwei Gerüstmastschüsse aufgestockt worden sind, kann der Monteur mit der Fahrbühne bis zum Endpunkt der vorher aufgestockten Gerüstmaste fahren und dort für die weitere Aufstockung das Hochfahren des nächsten Gerüstmastschusses abwarten. Mit einem zusätzlichen Monteur zum Aufnehmen der Mastteile am Boden bzw. auf der Plattform sind somit zwei Monteure ausreichend, um in kurzer Zeit große Fassadenflächen mit Fahrgerüsten zu belegen.A fitter traveling in the driving platform is able to attach the next raised scaffold mast shot to the already standing scaffold mast and to the facade. After at least two scaffolding mast shots have been added, the fitter can use the platform to drive to the end point of the scaffolding masts that were previously raised and wait for the next scaffolding mast shot to be raised there for further extension. With an additional fitter for picking up the mast parts on the floor or on the platform, two fitter are therefore sufficient to quickly cover large facade areas with mobile scaffolding.

Durch das Verfahren der Fahrbühnen auf horizontalen Schienen senkrecht zur Fassadenwand und in entgegengesetzter Richtung ergibt sich der Vorteil, daß zwischen der Fassade und der Fahrbühne keine absturzgefährdenden Zwischenräume belassen sind.By moving the driving platforms on horizontal rails perpendicular to the facade wall and in the opposite direction, there is the advantage that there are no gaps between the facade and the driving platform that could cause a fall.

Darüber hinaus besteht die Möglichkeit, eventuell vorstehende Bauteile der Fassade zu umfahren.There is also the option of bypassing any projecting components on the facade.

Dies kann auch dadurch erreicht werden, daß durch Einfalten des fassadenseitigen Geländers der Fahrbühne zum Bühnenboden hin ein zusätzliches Stück Bühnenboden geschaffen wird, das den Freiraum zwischen Fassade und Bühne ausfüllt. Dies hat zudem den Vorteil, daß nach Ablassen des Geländers zwischen dem Monteur und der Fassade keine störenden Bauteile der Fahrbühne mehr vorhanden sind.This can also be achieved in that an additional piece of stage floor is created by folding the railing on the facade side of the driving platform towards the stage floor, which fills the space between the facade and the stage. This also has the advantage that after lowering the railing between the fitter and the facade, there are no more disturbing components of the driving platform.

Zwischen den einzelnen Gerüstmasten können beliebig viele Fahrbühnen unabhängig voneinander an den Gerüstmasten entlang verfahren werden. Über die am Gerüstmast befindlichen Stromabnehmer können die Fahrbühnen mit Strom für die Werkzeuge der Monteure ausgestattet werden. Die Fahrbühnenlänge zwischen den Masten ist über einzeln zu verbindende Bühnensegmente frei wählbar. Hierdurch ist es möglich, daß sich benachbarte Fahrbühnen bei ihrer Höhenverstellung nicht behindern. Das bedeutet, daß benachbarte Fahrbühnen sich gegenseitig überholen bzw. begegnen können. Jedes der von zwei benachbarten Gerüstmasten gebildetes Gerüstfeld ist von den ihm benachbarten Gerüstfeldern völlig unabhängig, was die Höhenverstellung der Fahrbühnen angeht.Any number of lifting platforms can be moved independently of one another along the scaffolding masts between the individual scaffolding masts. Via the pantographs on the scaffolding mast, the driving platforms can be equipped with electricity for the tools of the fitters. The length of the platform between the masts is freely selectable via individually connected stage segments. This makes it possible that adjacent lifts do not interfere with their height adjustment. This means that neighboring lifts can overtake or encounter each other. Each of the scaffold bays formed by two neighboring scaffolding masts is completely independent of the scaffold bays adjacent to it with regard to the height adjustment of the driving platforms.

Zur Montage großer Bauteile können mehrere Bühnen gekuppelt werden. An der Fahrbühne sind über horizontale, parallel zur Fassade verlaufende Führungsschienen auf einer Lafette laufende Positioniergeräte vorgesehen, die im einzelnen die Funktionen

  • a) Aufnehmen von Platten oder stabförmigen Bauteilen vom Boden oder vom Materiallift,
  • b) Bewegen dieser Platten,
  • c) genaues Positionieren dieser Bauteile und
  • d) Abgeben dieser Bauteile nach dem Befestigen an der Fassade
ausführen können.Several platforms can be coupled to assemble large components. Positioning devices running on horizontal rails parallel to the facade are provided on the driving platform
  • a) Picking up plates or rod-shaped components from the floor or from the material lift,
  • b) moving these plates,
  • c) exact positioning of these components and
  • d) Deliver these components after fastening them to the facade
can execute.

Nachdem alle Gerüstmaste aufgestellt sind, kann der Schlitten durch mehrere auswechselbare Module mit zusätzlichen Funktionen ausgestattet werden, zum Beispiel einem Kranausleger, der bei einem oben über das Dach hinausgehenden Gerüstmast große und schwere Bauteile ähnlich einem sonst üblichen Baukran auf das Dach befördern kann, oder einem Personen- und/oder Materiallift, der nicht nur Monteure und Material zwischen den einzelnen Fahrbühnen auf das Dach sondern durch Einschwenken bis an die Fassade oder an Bauwerksöffnungen in das Gebäude hinein befördern kann.After all scaffolding masts have been set up, the slide can be equipped with additional functions by means of several interchangeable modules, for example a crane boom, which can transport large and heavy components to the roof similar to an otherwise usual construction crane when a scaffolding mast extends above the roof, or one Passenger and / or material lift, which can not only move fitters and material between the individual driving platforms onto the roof, but can also be swung into the building or into the building through the openings in the building.

An einem Gerüstmast können in zweckmäßiger Anordnung zum Beispiel ein Schlitten mit Kranmodul und ein bis beliebige viele Schlitten mit Liftmodulen angeschlossen sein, die unabhängig voneinander verfahren werden können.In a practical arrangement, a scaffold mast can be connected, for example, to a slide with a crane module and to any number of slides with lift modules, which can be moved independently of one another.

Die Erfindung wird nachfolgend anhand eines in der Zeichnung dargestellten Ausführungsbeispieles des näheren erläutert.The invention is explained below with reference to an embodiment shown in the drawing.

Es zeigt

Fig. 1
eine Vorder- und Seitenansicht auf den stehenden Mast des Hubgerüstes,
Fig. 2
eine Draufsicht auf den Gerüstmast gemäß Fig. 1,
Fig. 3
drei Ansichten des Schlittens, davon die Draufsicht mit Mast
Fig. 4
eine Draufsicht auf einen Gerüstmast mit beidseitig angeschlossenen Fahrbühnen,
Fig. 5
eine Draufsicht auf das Hubgerüst ähnlich Figur 4, mit Lift in Fahrstellung (rechte Darstellung) und in eingeschwenkter Stellung (linke Darstellung),
Fig. 6
eine Draufsicht auf das Hubgerüst mit angebautem Kran, im übrigen ähnlich Figur 5,
Fig. 7
eine Seitenansicht des Gerüstes mit Schlitten, Masttransportmodul und einem noch zu montierenden Mastteil sowie einer Vorderansicht des Masttransportmoduls mit Schlitten,
Fig. 8
eine Seitenansicht des Masttransportmoduls beim Aufnehmen eines noch zu nomtierenden Mastteiles und
Fig. 9
als Zusammenstellungszeichnung ein Hubgerüst mit vier nebeneinander angeordneten Gerüstmasten unter Bildung von drei zwischen je zwei benachbarten Gerüstmasten gebildeten Gerüstfeldern, in denen jeweils mehrere Fahrbühnen höhenverstellbar angeordnet sind und bei denen an den einzelnen Masten Schlitten höhenverstellbar vorgesehen sind.
It shows
Fig. 1
a front and side view of the standing mast of the mast,
Fig. 2
2 shows a plan view of the scaffolding mast according to FIG. 1,
Fig. 3
three views of the sled, of which the top view with mast
Fig. 4
a plan view of a scaffold mast with driving platforms connected on both sides,
Fig. 5
4 shows a top view of the mast similar to FIG. 4, with the lift in the driving position (right illustration) and in the pivoted-in position (left illustration),
Fig. 6
4 shows a plan view of the lifting frame with the crane attached, otherwise similar to FIG. 5,
Fig. 7
2 shows a side view of the scaffolding with a slide, mast transport module and a mast part still to be assembled, and a front view of the mast transport module with slide,
Fig. 8
a side view of the mast transport module when receiving a still to be nominated mast part and
Fig. 9
as an assembly drawing, a lifting scaffold with four scaffolding masts arranged next to each other, forming three scaffolding fields formed between two adjacent scaffolding masts, in which A plurality of lifting platforms are each arranged to be adjustable in height and in which sleds are provided to be adjustable in height on the individual masts.

Das in der Zeichnung dargestellte Hubgerüst 10 hat mehrere Gerüstmasten 11, die auf dem Boden 12 bzw. auf einer oberhalb der Bodenhöhe befindlichen Plattform stehen und schußweise verlängerbar sind. Zwischen den Gerüstmasten 11 sind Fahrbühnen 13 vorgesehen. Die Gerüstmasten 11 sind mittels mehrerer Haltestützen 14 an der Gebäudefassade 15 befestigt.The mast 10 shown in the drawing has a plurality of scaffolding masts 11, which stand on the floor 12 or on a platform located above the floor level and can be extended in sections are. Driving platforms 13 are provided between the scaffolding masts 11. The scaffolding masts 11 are fastened to the building facade 15 by means of a plurality of holding supports 14.

Wie sich insbesondere aus den Figuren 1 und 2 ergibt, besteht der Gerüstmast 11 aus zwei Trageprofilen 16, 17 und einem Eckprofil 18, wobei die Trageprofile 16, 17 und das Eckprofil 18 in der Draufsicht ein gleichschenkliges Dreieck bilden. Die Trageprofile 16,17 und das Eckprofil 18 sind über quer und schräg verlaufende Streben 19,20,21 stabilisiert.As can be seen in particular from Figures 1 and 2, the scaffold mast 11 consists of two support profiles 16, 17 and a corner profile 18, the support profiles 16, 17 and the corner profile 18 forming an isosceles triangle in plan view. The support profiles 16, 17 and the corner profile 18 are stabilized via transverse and oblique struts 19, 20, 21.

An den Trageprofilen 16,17 sind Fahrprofile 22,23 vorgesehen. Außerdem sind an den Streben 19 eine Stromschiene 24 und an den Streben 21 eine Stromschiene 25 vorgesehen.Driving profiles 22, 23 are provided on the support profiles 16, 17. In addition, a busbar 24 is provided on the struts 19 and a busbar 25 is provided on the struts 21.

Wie sich insbesondere und im einzelnen aus Figur 2 ergibt, ist an der inneren Seite des Trageprofils 16 das Fahrprofil 22 mit dem inneren Profilflansch 26 befestigt, während der freie Profilflansch 27 um 90° nach innen gebogen ist. An dem freien Profilflansch 27 ist eine Zahnstange 28 vorgesehen, in der ein Zahnrad 29 eines Schlittens 30 läuft. Auf der gegenüberliegenden Seite des freien Flansches 27 ist ein Stützrad 31 vorgesehen.As can be seen in particular and in detail from FIG. 2, the driving profile 22 is fastened to the inner profile flange 26 on the inner side of the support profile 16, while the free profile flange 27 is bent inwards by 90 °. On the free profile flange 27, a rack 28 is provided, in which a gear 29 of a slide 30 runs. A support wheel 31 is provided on the opposite side of the free flange 27.

Die in der Zeichnung dargestellte strichpunktierte Linie 32 (Fig. 4) stellt eine Symmetrielinie bzw. in der Draufsicht eine Symmetriefläche zwischen dem linken und dem rechten Bereich des in Figur 8 dargestellten Hubmastes 11. Somit entsprechen die auf der rechten Seite der Symmetrieebene 32 dargestellten Bauteile 33,34,35,36,37 den auf der linken Seite der Symmetrieebene 32 dargestellten Bauteile 26,27,28,29,31.The dash-dotted line 32 shown in the drawing (FIG. 4) represents a line of symmetry or, in plan view, a surface of symmetry between the left and the right area of the lifting mast 11 shown in FIG. 8. The components shown on the right-hand side correspond to the plane of symmetry 32 33, 34, 35, 36, 37 the components 26, 27, 28, 29, 31 shown on the left side of the plane of symmetry 32.

Auf der rechten Seite der Symmetrieebene 32 der Figur 4 ist eine Fahrbühne 38 mit Geländern 39,40,41 sowie mit einem verschiebbaren Geländer 42 angeordnet. An der Fahrbühne 38 ist ein Lagerbock 44 vorgesehen, an dem zwei anzutreibende Zahnräder 45 vorgesehen sind, die in einer Zahnstange 46 des Trageprofils 17 laufen. Außerdem sind an dem Lagerbock 44 zwei gegenüberliegende Laufrollen 47,48 vorgesehen sowie darüber hinaus in einem weiteren Lagerbock 49 eine Laufrolle 50, wodurch sichergestellt ist, daß das Zahnrad 45 ständig in sicherem Kontakt mit der Zahnstange 46 bleibt. Der Antrieb des Zahnrades 45 erfolgt über die Welle 51.On the right side of the plane of symmetry 32 of FIG. 4, a driving platform 38 with railings 39, 40, 41 and with a displaceable railing 42 is arranged. A bearing block 44 is provided on the driving platform 38, on which two gear wheels 45 to be driven are provided, which run in a rack 46 of the support profile 17. Furthermore two opposite rollers 47, 48 are provided on the bearing block 44 and, in addition, a roller 50 in a further bearing block 49, which ensures that the gear 45 remains in constant contact with the rack 46. The gear 45 is driven via the shaft 51.

An dem Lagerbock 44 ist ein Stromabnehmer 52 vorgesehen, der in der Stromschiene 25 verschieblich gehalten ist bzw. in der Stromschiene 25 schleift. Desgleichen ist an dem Schlitten 30 ein Stromabnehmer 53 vorgesehen, der in der Stromschiene 24 fest geführt ist bzw. in der Stromschiene 24 schleift.A current collector 52 is provided on the bearing block 44, which is held displaceably in the busbar 25 or slides in the busbar 25. Likewise, a pantograph 53 is provided on the carriage 30, which is firmly guided in the busbar 24 or slides in the busbar 24.

Auf der linken Seite der Symmetriefläche 32 sind die vorstehend beschriebenen Verhältnisse gleich. Die Fahrbühne 54 hat Geländer 55,56, die den Geländern 39,41 entsprechen. Das Geländer 57, das dem Geländer 42 entspricht, ist auf der linken Seite der Symmetrieebene 32 zur Fassade 15 verschieblich und das Faltgeländer 39 bzw. 55 zur Fassade hin abgelassen, so daß die Fahrbühne 54 ziemlich nahe an der Fassade 15 anliegt, so daß etwaige Unfälle ausgeschlossen sind.The relationships described above are the same on the left side of the symmetry surface 32. The driving platform 54 has railings 55, 56 which correspond to the railings 39, 41. The railing 57, which corresponds to the railing 42, is displaceable on the left side of the plane of symmetry 32 to the facade 15 and the folding railing 39 or 55 is lowered towards the facade, so that the driving platform 54 lies quite close to the facade 15, so that any Accidents are excluded.

Zwischen dem Eckprofil 18 und einem in der Fassade 15 eingesetzten Dübel 58 ist zwischen einem Lager 59 und einem Haken 60 die längenveränderbare Haltestütze 14 angeordnet.Between the corner profile 18 and a dowel 58 inserted in the facade 15, the length-adjustable holding support 14 is arranged between a bearing 59 and a hook 60.

Gemäß der Darstellung in Figur 4 ist ein Motor 61 vorgesehen, der über ein Getriebe 62 sowie über Zahnräder 63,64 die Antriebswelle 51 antreibt.According to the illustration in FIG. 4, a motor 61 is provided which drives the drive shaft 51 via a gear 62 and via gear wheels 63, 64.

Außerdem ist in Figur 5 an dem Schlitten 30 ein Lift 65 angeordnet, der in Gelenken 66,67 gegenüber dem Schlitten 30 verschwenkbar ist. Im links dargestellten Ausführungsbeispiel ist der Lift 65 um 90° gegenüber der Längsausrichtung des Gerüstes um das Gelenk 66 geschwenkt.In addition, a lift 65 is arranged on the slide 30 in FIG. 5 and can be pivoted relative to the slide 30 in joints 66, 67. In the embodiment shown on the left, the lift 65 is pivoted by 90 ° with respect to the longitudinal orientation of the scaffolding around the joint 66.

BezugszeichenlisteReference list

1010th
HubgerüstMast
1111
GerüstmastScaffolding mast
1212th
Bodenground
1313
FahrbühneDriving platform
1414
HaltestützenSupport brackets
1515
GebäudefassadeBuilding facade
1616
TrageprofilWearing profile
1717th
TrageprofilWearing profile
1818th
EckprofilCorner profile
1919th
Strebestrut
2020th
Strebestrut
2121
Strebestrut
2222
FahrprofileDriving profiles
2323
FahrprofileDriving profiles
2424th
StromschieneTrack
2525th
StromschieneTrack
2626
ProfilflanschProfile flange
2727
ProfilflanschProfile flange
2828
ZahnstangeRack
2929
ZahnstangeRack
3030th
Schlittencarriage
3131
StützradJockey wheel
3232
SymmetrieebenePlane of symmetry
3333
BauteilComponent
3434
BauteilComponent
3535
BauteilComponent
3636
BauteilComponent
3737
BauteilComponent
3838
FahrbühneDriving platform
3939
Geländerrailing
4040
Geländerrailing
4141
Geländerrailing
4242
Geländerrailing
4343
------
4444
LagerbockBearing block
4545
Zahnradgear
4646
ZahnstangeRack
4747
LaufrolleRoller
4848
LaufrolleRoller
4949
LagerbockBearing block
5050
LaufrolleRoller
5151
Wellewave
5252
StromabnehmerPantograph
5353
StromabnehmerPantograph
5454
FahrbühneDriving platform
5555
Geländerrailing
5656
Geländerrailing
5757
Geländerrailing
5858
DübelDowels
5959
Lagercamp
6060
Hakenhook
6161
Motorengine
6262
Getriebetransmission
6363
Zahnradgear
6464
Zahnradgear
6565
Liftlift
6666
Gelenkjoint
6767
Gelenkjoint
6868
Türdoor
6969
Türdoor
7070
Krancrane
7171
KranauslegerCrane boom
7272
KlammerBracket
7373
Backento bake
7474
Backento bake
7575
Radwheel
7676
GerüstmastschußScaffolding mast shot
7777
Stangepole
7878
Schneckeslug
7979
Schneckeslug
8080
Achseaxis
8181
Achseaxis
8282
Scheibedisc
82a82a
Positionposition
8383
LagerbockBearing block
8484
Gelenkjoint
8585
------
8686
Gelenkjoint
8787
------
8888
------
8989
ZahnkranzSprocket
9090
ZahnkranzSprocket
9191
AntriebsketteDrive chain

Gemäß der rechten Darstellung nach Figur 5 ist der Material- und/oder Personenlift 65 in Richtung des Gerüstes ausgerichtet. Der Lift 65 hat schwenkbare Türen 68,69, durch die die einzelnen Bühnen zu bedienen bzw. zu erreichen sind, sofern die Bühne nicht selbst verfahren wird.5, the material and / or passenger lift 65 is aligned in the direction of the scaffold. The lift 65 has pivotable doors 68, 69 through which the individual stages can be operated or reached, provided the stage itself is not moved.

Die in Figur 6 dargestellte Anordnung unterscheidet sich von derjenigen, die in den Figuren 7 und 8 dargestellt ist, dadurch, daß anstelle des Liftes 65 ein Kran 70 mit einem geteilten Kranausleger 71 vorgesehen ist. Die übrigen Anordnungen sind den vorstehend beschriebenen Anordnungen gleich bzw. ähnlich oder aber bekannt.The arrangement shown in FIG. 6 differs from that shown in FIGS. 7 and 8 in that a crane 70 with a divided crane boom 71 is provided instead of the elevator 65. The other arrangements are the same or similar or known to the arrangements described above.

In Figur 7 ist an dem Schlitten 30 des Gerüstmastes 11 eine Klammer 72 vorgesehen, deren beide Backen 73,74 durch ein Rad 75 zu öffnen und zu schließen sind. Zwischen den zwei Backen 73,74 ist ein Gerüstmastschuß 76 eingeklemmt, der gegenüber dem bereits aufgebauten Gerüstmast 11 um 180° verschwenkt ist und in diesem Zustand mittels des Schlittens 30 und der Zange 72 angehoben werden kann und in der gewünschten Höhe um 180° zurückgeschwenkt wird, damit er mit dem bereits aufgebauten Gerüstmast 11 fluchtet und auf diesen aufgestellt und mit diesem verbunden werden kann.In FIG. 7, a clamp 72 is provided on the slide 30 of the scaffold mast 11, the two jaws 73, 74 of which can be opened and closed by a wheel 75. A scaffold mast section 76 is clamped between the two jaws 73, 74, which is pivoted by 180 ° relative to the scaffold mast 11 that has already been set up and can be raised in this state by means of the slide 30 and the pliers 72 and is pivoted back by 180 ° at the desired height , so that it is aligned with the already erected scaffold mast 11 and can be placed on it and connected to it.

In Figur3 ist der Schlitten 30 im einzelnen dargestellt. Über den Motor 61 ist eine Stange 77 anzutreiben, die zwei Schnecken 78,79 aufweist, über die mittels Achsen 80,81, die vier Zahnräder 29 anzutreiben sind. Desgleichen sind die Stützrollen dargestellt.The carriage 30 is shown in detail in FIG. A rod 77 is to be driven via the motor 61, which has two worms 78, 79, via which the four gear wheels 29 are to be driven by means of axes 80, 81. The support rollers are also shown.

In der Figur 7 ist eine runde Scheibe 82 vorgesehen, die an der Zange 72 des Schlittens 30 befestigt ist. An der Scheibe 82 ist ein Lagerbock 83 vorgesehen, an dem in einem Gelenk 84 der Lagerbock 85 gelenkig gelagert ist. In einem Gelenk 86 der Platte 82 und einem Gelenk 87 des Lagerbocks 85 ist ein mehrstufiger Zylinder 88 vorgesehen, mit dessen Hilfe das Gelenk 86 auf einem Kreisbogen um das Gelenk 84 soweit verschwenkt werden kann, bis die Scheibe 82 die senkrecht dazu vorgesehene Position einnimmt.A round disk 82 is provided in FIG. 7, which is fastened to the pliers 72 of the slide 30. A bearing block 83 is provided on the disk 82, on which the bearing block 85 is articulated in a joint 84. A multi-stage cylinder 88 is located in a joint 86 of the plate 82 and a joint 87 of the bearing block 85 provided, with the aid of which the joint 86 can be pivoted on a circular arc around the joint 84 until the disk 82 assumes the position provided perpendicularly thereto.

Außerdem ist zwischen zwei Zahnkränzen 89,90 eine Antriebskette 91 vorgesehen, damit hier ein Zwangsgleichlauf zu erzielen ist.In addition, a drive chain 91 is provided between two sprockets 89, 90 so that a positive synchronism can be achieved here.

Claims (18)

  1. Lift frame (10) comprising a plurality of frame uprights (11), which are shoot-like extendable and between which are height-variably situated platforms (13), wherein the frame uprights may be fixed on the facade of a building by a plurality of holders,
    characterised in
    - that every frame upright (11) comprises at least one carrier section (16) on which is provided at least one first rack (28) with which engage pinions (29) situated on the movable platforms and driven by drives (61),
    - that at least one second rack (46) is provided for every frame upright, along which rack (46) is height-displaceably arranged a carriage (30) with pinions (29) and a drive for these pinions (29), and
    - that current supply bars (24, 25) are provided on the frame upright (11) and current collectors (52, 53) are provided on the movable platforms (38, 54) and the carriage (30).
  2. Lift frame according to claim 1, characterised in that the frame upright (11) comprises two carrier sections (16, 17) with racks (28, 46).
  3. Lift frame according to claim 1 or 2, characterised in that one of the devices which can be coupled to the carriage (30) is a frame upright transport device.
  4. Lift frame according to any one of the preceding claims, characterised in that one of the devices which can be coupled to the carriage (30) is a lift for persons or material (65).
  5. Lift frame according to claim 4, characterised in that the lift for persons or material is tiltable to both sides about the frame upright (11) towards the facade (15).
  6. Lift frame according to any one of the preceding claims, characterised in that one of the devices which can be coupled to the carriage (30) is a crane (70).
  7. Lift frame according to any one of the preceding claims, characterised in that the movable platforms (38, 54) is provided with a positioning device which is movable along the whole width of the movable platform (38, 54) by a movable mounting.
  8. Lift frame according to any one of the preceding claims, characterised in that the movable platform (38, 54) is along its length freely fixable between the frame uprights (11).
  9. Lift frame according to any one of the preceding claims, characterised in that the movable platforms (38, 54) are movable on rails horizontally and parallel to the facade (15).
  10. Lift frame according to any one of the preceding claims, characterised in that a guard rail (39, 40, 41, 42, 55, 56, 57) of the movable platform pointing to the facade (15) may be used for widening of the platform floor towards the facade (15).
  11. Lift frame according to any one of the preceding claims, characterised in that an electric or electrohydraulic drive for the pinions (29) is provided on the carriage (30).
  12. Lift frame according to any one of the preceding claims, characterised in that the movable platforms (38, 54) have electric or electrohydraulic drives for driving the pinions (45).
  13. Lift frame according to any one of the preceding claims, characterised in that two pinions (29, 45) are provided one above the other for every drive.
  14. Lift frame according to any one of claims 1 to 12, characterised in that two pinions (29, 45) are provided opposite to each other for every drive.
  15. Lift frame according to any one of the preceding claims, characterised in that two racks (28, 46), positioned opposite to each other, are provided on every carrier section (16, 17) of the frame uprights (11), one pinion (29, 45) running in every rack.
  16. Lift frame according to any one of claims 1 to 14, characterised in that two racks (28, 46), positioned opposite to each other, are provided on every carrier section (16, 17) of the frame uprights (11), more than one pinion (29, 45) running in every rack.
  17. Lift frame according to any one of the preceding claims, characterised in that at least one pinion (29, 45) is provided to safeguard against the crash of the carriage (30) and the movable platform (38, 54) or a device is provided for this purpose.
  18. Lift frame according to any one of the preceding claims, characterised in that between the individual frame uprights any number of movable platforms may be displaceable along the frame uprights independently of each other.
EP95102391A 1994-03-03 1995-02-21 Lifting scaffold platform Revoked EP0670399B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE4406987A DE4406987C1 (en) 1994-03-03 1994-03-03 Lift scaffolding with several masts standing on at least one platform
DE4406987 1994-03-03

Publications (2)

Publication Number Publication Date
EP0670399A1 EP0670399A1 (en) 1995-09-06
EP0670399B1 true EP0670399B1 (en) 1997-07-30

Family

ID=6511719

Family Applications (1)

Application Number Title Priority Date Filing Date
EP95102391A Revoked EP0670399B1 (en) 1994-03-03 1995-02-21 Lifting scaffold platform

Country Status (8)

Country Link
US (1) US5992565A (en)
EP (1) EP0670399B1 (en)
JP (1) JPH07259322A (en)
KR (1) KR950031861A (en)
AT (1) ATE156226T1 (en)
CA (1) CA2143813A1 (en)
DE (2) DE4406987C1 (en)
ES (1) ES2107869T3 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102017109839A1 (en) * 2017-05-08 2018-12-20 Kewazo Gmbh Scaffold transport system, method for controlling a scaffold transport system and use of a scaffold transport system

Families Citing this family (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4443629C3 (en) * 1994-12-08 2001-10-25 Geda Dechentreiter Gmbh & Co K Overload protection for a construction elevator
SE516701C2 (en) * 1999-11-04 2002-02-12 Alimak Ab Elevator system
KR20010099053A (en) * 2001-08-20 2001-11-09 백수곤 The universal rapid installing scaffolding
US20030213655A1 (en) * 2002-05-20 2003-11-20 Andre St-Germain Tower for supporting an elevator thereon
FR2872841A1 (en) * 2004-07-12 2006-01-13 Fixator Soc Par Actions Simpli PLATFORM SUPPORT DEVICE FOR ELEVATION OF LOADS OR PEOPLE ALONG A WORK
DE102006055253B4 (en) 2006-04-05 2018-09-27 Sew-Eurodrive Gmbh & Co Kg conveyor
DE102006029653B4 (en) * 2006-06-28 2009-02-12 Doka Industrie Gmbh Lifting platform and method for building a lifting platform
WO2012140278A1 (en) * 2011-04-14 2012-10-18 Mantenimientos Eléctricos Campo De Aviación, S.L. Repair/cleaning scaffolding tower for wind turbines
US9150397B2 (en) * 2011-09-27 2015-10-06 Chicago Bridge & Iron Company Freestanding elevator platform system
CN103375022B (en) * 2012-04-13 2016-09-21 保定市裕升建筑安装股份有限公司 Multi-functional dynamic rail attached lifting scaffold
CN103375023A (en) * 2012-04-27 2013-10-30 广州市达蒙建筑技术有限公司 Attached type lifting scaffold
CN103821341B (en) * 2014-03-10 2015-11-18 成都嘉泽正达科技有限公司 Attaching automatic lifting multilayer operation platform
DE102015004392A1 (en) * 2015-04-10 2016-10-13 Senvion Gmbh Person lifting device for wind turbine towers
DE102016223913A1 (en) * 2016-12-01 2018-06-07 Thyssenkrupp Ag Elevator system with a busbar and a pantograph
DE102016125549A1 (en) * 2016-12-23 2018-06-28 Tries Gmbh & Co. Kg Climbing device with a climbing rail
US11053699B2 (en) * 2017-10-27 2021-07-06 Doka Gmbh Climbing shoe, safety screen support system and safety screen system
CN109704248B (en) * 2019-01-17 2023-12-29 大连理工大学 Foldable lifting aircraft maintenance scaffold unit
CN112942785A (en) * 2019-12-11 2021-06-11 上海雅跃智能科技有限公司 Climbing frame with running rail
US20210261273A1 (en) * 2020-02-21 2021-08-26 Daniel Johnston Aircraft gantry system
CN112854701A (en) * 2021-01-15 2021-05-28 施明娣 But height-adjusting's stable form engineering construction scaffold

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT237875B (en) * 1962-06-01 1965-01-11 Giuseppe Pieri Dismountable framework

Family Cites Families (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2390284A (en) * 1942-04-15 1945-12-04 Franks Mfg Corp Derrick structure
US3085650A (en) * 1961-01-26 1963-04-16 Andrew W Merk Orchard platform
US3548970A (en) * 1968-08-05 1970-12-22 Ralph W Hutchens Sr Scaffolding and material handling system
DE2163507A1 (en) * 1971-12-21 1973-07-05 Harald Kreybu SCAFFOLDING, ESPECIALLY FOR PAINTING
DE2347974A1 (en) * 1972-09-25 1974-04-04 Eaton Corp ELECTRIC MOTOR DRIVEN CONVEYOR TROLLEY FOR ITEMS TO BE STORED
US3878916A (en) * 1973-02-07 1975-04-22 Jr Gerome R White Rack and pinion drive counterbalanced hoist systems
FR2222304B1 (en) * 1973-03-20 1976-09-10 Sedit
US4294332A (en) * 1979-04-13 1981-10-13 Ready Delbert L Scaffold with gear drive
US4293054A (en) * 1980-05-19 1981-10-06 Piat Impalcature Automatiche S.P.A. Scaffolding for supporting lifting working bridges and platforms
DE3114602A1 (en) * 1981-04-10 1984-04-26 VEB Kombinat für Baureparaturen und Rekonstruktion, DDR 7010 Leipzig Device for scaffoldings with raisable and lowerable working platform
DD230514A3 (en) * 1983-08-16 1985-12-04 Dresden Baumechanisierung ADDITIONAL EQUIPMENT FOR HEIGHT-ADJUSTABLE WORKING RACKS
DE3415074A1 (en) * 1984-04-21 1985-10-24 Lissmac Maschinenbau GmbH, 7971 Aitrach LIFTING LIFT
DD244274A3 (en) * 1984-08-10 1987-04-01 Dresden Bauinvest GERUEST FOR REPAIR WORK ON FACADES AND ROOF ROOFS
US4655319A (en) * 1985-01-18 1987-04-07 Gilbert Loix Folding ladder
FR2651820B1 (en) * 1989-09-11 1991-12-27 Boudrot Charles TELESCOPIC DEVELOPMENT SCAFFOLD FOR ALL WORKS AT LARGE HEIGHTS.
FR2667582B1 (en) * 1990-10-04 1995-06-30 Cgti DEVICE FOR LIFTING AND INSTALLING EQUIPMENT AT THE TOP OF A STRONG STRUCTURE.
US5067587A (en) * 1990-12-28 1991-11-26 William F. Mims, Jr. Service platform for mobile scaffolding unit
US5159993A (en) * 1991-10-15 1992-11-03 Gestion Des Brevets Fraco Limitee Self-raising work platform assembly

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT237875B (en) * 1962-06-01 1965-01-11 Giuseppe Pieri Dismountable framework

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102017109839A1 (en) * 2017-05-08 2018-12-20 Kewazo Gmbh Scaffold transport system, method for controlling a scaffold transport system and use of a scaffold transport system
US11821223B2 (en) 2017-05-08 2023-11-21 Kewazo Gmbh Scaffold transport system, method for controlling a scaffold transport system and use of a scaffold transport system

Also Published As

Publication number Publication date
DE59500425D1 (en) 1997-09-04
ATE156226T1 (en) 1997-08-15
CA2143813A1 (en) 1995-09-04
ES2107869T3 (en) 1997-12-01
JPH07259322A (en) 1995-10-09
EP0670399A1 (en) 1995-09-06
US5992565A (en) 1999-11-30
DE4406987C1 (en) 1995-07-06
KR950031861A (en) 1995-12-20

Similar Documents

Publication Publication Date Title
EP0670399B1 (en) Lifting scaffold platform
DE3935665C2 (en) Device for transporting a component
EP2052118B1 (en) Climbing formwork for concreting a wall of a structure
DE2622840A1 (en) CLIMBING SCAFFOLDING WITH APPROPRIATE FORMWORK
DE4009354C2 (en) Detachable track carrier bridge with a stem carrier arranged between the track carriers
DE2815898A1 (en) DEVICE FOR POSITIONING CEILING SUPPORT IN A TUNNEL
AT521858B1 (en) Mobile work hall
DE2050516A1 (en) Vertically adjustable platform for scaffolding
DE102005040733B4 (en) Device for a building and method for its installation
DD244274A3 (en) GERUEST FOR REPAIR WORK ON FACADES AND ROOF ROOFS
CH660895A5 (en) DEVICE FOR SETTING PILLARS, POLES OR SNOW BARS.
DE2542778B1 (en) PROCEDURE FOR MECHANIZED INSTALLATION OF ROAD CONSTRUCTION AND EQUIPMENT FOR CARRYING OUT THE PROCEDURE
EP0486456A1 (en) Railway switch transport wagon
DE3332227C2 (en) Bridge viewing device
DE19610440C2 (en) Device for assembling and laying track carrier and stem sections to form a bridge structure
DE19704967C2 (en) Gantry crane, in particular for the construction of buildings
DE102005014230B4 (en) Device for introducing holes in a slope
DE19545453A1 (en) Frame mast or moving platform for lift
AT237875B (en) Dismountable framework
EP0510528A2 (en) Lift for building materials and elements of trestle work
DE19730932C1 (en) Trolley for positioning ceiling panels for building
DE4217109C2 (en) Automatic car parking facility
EP0382083B1 (en) Rescue and/or work basket
DE202004011443U1 (en) Assembly to support a forward projecting load, at a self-propelled working platform or a crane, has hollow carriers with extending support carriers and adjustable end supports together with structured blocks to restrict their extension
DE3118340A1 (en) Mounting-aid unit for mounting ceiling structural parts

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE CH DE ES FR GB IT LI NL SE

17P Request for examination filed

Effective date: 19960305

GRAG Despatch of communication of intention to grant

Free format text: ORIGINAL CODE: EPIDOS AGRA

GRAH Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOS IGRA

17Q First examination report despatched

Effective date: 19960730

GRAH Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOS IGRA

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE CH DE ES FR GB IT LI NL SE

REF Corresponds to:

Ref document number: 156226

Country of ref document: AT

Date of ref document: 19970815

Kind code of ref document: T

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REF Corresponds to:

Ref document number: 59500425

Country of ref document: DE

Date of ref document: 19970904

ET Fr: translation filed
ITF It: translation for a ep patent filed

Owner name: ING. C. GREGORJ S.P.A.

REG Reference to a national code

Ref country code: CH

Ref legal event code: NV

Representative=s name: DR.-ING. ULRICH TIEMANN PATENTANWALT

REG Reference to a national code

Ref country code: ES

Ref legal event code: FG2A

Ref document number: 2107869

Country of ref document: ES

Kind code of ref document: T3

GBT Gb: translation of ep patent filed (gb section 77(6)(a)/1977)

Effective date: 19971218

PLBQ Unpublished change to opponent data

Free format text: ORIGINAL CODE: EPIDOS OPPO

PLBI Opposition filed

Free format text: ORIGINAL CODE: 0009260

PLBF Reply of patent proprietor to notice(s) of opposition

Free format text: ORIGINAL CODE: EPIDOS OBSO

26 Opposition filed

Opponent name: HEK MANUFACTURING B.V.

Effective date: 19980407

NLR1 Nl: opposition has been filed with the epo

Opponent name: HEK MANUFACTURING B.V.

PLBF Reply of patent proprietor to notice(s) of opposition

Free format text: ORIGINAL CODE: EPIDOS OBSO

PLBF Reply of patent proprietor to notice(s) of opposition

Free format text: ORIGINAL CODE: EPIDOS OBSO

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 19990304

Year of fee payment: 5

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20000229

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20000229

RDAH Patent revoked

Free format text: ORIGINAL CODE: EPIDOS REVO

APAC Appeal dossier modified

Free format text: ORIGINAL CODE: EPIDOS NOAPO

APAC Appeal dossier modified

Free format text: ORIGINAL CODE: EPIDOS NOAPO

APAE Appeal reference modified

Free format text: ORIGINAL CODE: EPIDOS REFNO

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

REG Reference to a national code

Ref country code: GB

Ref legal event code: IF02

RAP2 Party data changed (patent owner data changed or rights of a patent transferred)

Owner name: THEELEN, JOERG

RIN2 Information on inventor provided after grant (corrected)

Free format text: THEELEN, JOERG

NLT2 Nl: modifications (of names), taken from the european patent patent bulletin

Owner name: THEELEN, JOERG

APAC Appeal dossier modified

Free format text: ORIGINAL CODE: EPIDOS NOAPO

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: NL

Payment date: 20030224

Year of fee payment: 9

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20040128

Year of fee payment: 10

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: ES

Payment date: 20040210

Year of fee payment: 10

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20040219

Year of fee payment: 10

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: SE

Payment date: 20040220

Year of fee payment: 10

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: BE

Payment date: 20040223

Year of fee payment: 10

Ref country code: AT

Payment date: 20040223

Year of fee payment: 10

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20040310

Year of fee payment: 10

PLAY Examination report in opposition despatched + time limit

Free format text: ORIGINAL CODE: EPIDOSNORE2

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES;WARNING: LAPSES OF ITALIAN PATENTS WITH EFFECTIVE DATE BEFORE 2007 MAY HAVE OCCURRED AT ANY TIME BEFORE 2007. THE CORRECT EFFECTIVE DATE MAY BE DIFFERENT FROM THE ONE RECORDED.

Effective date: 20050221

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20050221

Ref country code: AT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20050221

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20050222

Ref country code: ES

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20050222

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20050228

PLBC Reply to examination report in opposition received

Free format text: ORIGINAL CODE: EPIDOSNORE3

BERE Be: lapsed

Owner name: *LINGEN PAUL

Effective date: 20050228

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20050901

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20050901

EUG Se: european patent has lapsed
APAH Appeal reference modified

Free format text: ORIGINAL CODE: EPIDOSCREFNO

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20050221

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20051031

NLV4 Nl: lapsed or anulled due to non-payment of the annual fee

Effective date: 20050901

REG Reference to a national code

Ref country code: FR

Ref legal event code: ST

Effective date: 20051031

REG Reference to a national code

Ref country code: ES

Ref legal event code: FD2A

Effective date: 20050222

RDAD Information modified related to despatch of communication that patent is revoked

Free format text: ORIGINAL CODE: EPIDOSCREV1

BERE Be: lapsed

Owner name: *LINGEN PAUL

Effective date: 20050228

PLAB Opposition data, opponent's data or that of the opponent's representative modified

Free format text: ORIGINAL CODE: 0009299OPPO

RDAG Patent revoked

Free format text: ORIGINAL CODE: 0009271

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: PATENT REVOKED

27W Patent revoked