DD148800A5 - WATER-IMPROPER CONSTRUCTION - Google Patents

WATER-IMPROPER CONSTRUCTION Download PDF

Info

Publication number
DD148800A5
DD148800A5 DD21865680A DD21865680A DD148800A5 DD 148800 A5 DD148800 A5 DD 148800A5 DD 21865680 A DD21865680 A DD 21865680A DD 21865680 A DD21865680 A DD 21865680A DD 148800 A5 DD148800 A5 DD 148800A5
Authority
DD
German Democratic Republic
Prior art keywords
reinforced concrete
construction according
components
prefabricated
pig
Prior art date
Application number
DD21865680A
Other languages
German (de)
Inventor
Otto Pozsonyi
Original Assignee
Beton Es Vasbetonipari Muevek
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beton Es Vasbetonipari Muevek filed Critical Beton Es Vasbetonipari Muevek
Publication of DD148800A5 publication Critical patent/DD148800A5/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H4/00Swimming or splash baths or pools
    • E04H4/0075Swimming or splash baths or pools made of concrete
    • E04H4/0093Swimming or splash baths or pools made of concrete with walls and floor prefabricated
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H7/00Construction or assembling of bulk storage containers employing civil engineering techniques in situ or off the site
    • E04H7/02Containers for fluids or gases; Supports therefor
    • E04H7/18Containers for fluids or gases; Supports therefor mainly of concrete, e.g. reinforced concrete, or other stone-like material

Abstract

Die Erfindung bezieht sich auf eine Konstruktion zum Bau von Fluessigkeitsspeicherbecken, Schwimmbecken oder aehnlichen Bauwerken. Durch die Erfindung werden wesentliche Einsparungen an Material und Arbeitszeit erreicht, wobei unabhaengig von bestimmten zweckgebundenen Projekten, Bauwerke der eingangs genannten Art mit beliebig waehlbaren Grundrissen und Abmessungen errichtet werden koennen. Das Wesen der Erfindung besteht in der Verwendung und spezifischen Anordnung von vorgefertigten, plattenartigen Stahlbeton-Bauelementen, die mit Hohlraeumen zur Ableitung eventuell eindringenden Sickerwassers versehen sind u. zusammen mit vorgefertigten und/oder aus Monolitbeton hergestellten Stuetzpfeilern zu einem entsprechenden Bauwerk montiert werden.The invention relates to a construction for the construction of fluid storage tanks, swimming pools or similar structures. The invention achieves substantial savings in terms of material and working time, it being possible to construct structures of the type mentioned above with arbitrarily selectable floor plans and dimensions, independently of specific purpose-oriented projects. The essence of the invention is the use and specific arrangement of prefabricated, plate-like reinforced concrete components, which are provided with cavities for the discharge of any infiltration leachate u. assembled together with prefabricated and / or made of monolith concrete stanchions to a corresponding structure.

Description

2! 8 656 -"-2! 8 656 - "-

12 821 5612 821 56

Wasserundurchlässige BaukonstruktionWaterproof construction

Anwendungsgebiet der Erfindung:Field of application of the invention:

Die Erfindung besieht sich auf eine wasserundurchlässige Konstruktion zum Bau von Flüssigkeitsspeicherbecken, Schwimmbecken oder ähnlichen Bauwerken, wobei die Abgrenzungskonstruktionen wie Wände, Bodenplatten und Decken mindestens zum Teil - aus in V/asser sperrenden, aneinander angeschlossenen, plattenartig vorgefertigten Stahlbeton-Bauelementen hergestellt werden.The invention relates to a waterproof construction for the construction of liquid storage tanks, swimming pools or similar structures, the demarcation structures such as walls, floor slabs and ceilings are at least partially - made in V / asser blocking, connected to each other, plate-like prefabricated reinforced concrete components.

Charakteristik der bekannten technischen Lösungen;Characteristic of the known technical solutions;

Die Vorteile der unter Verwendung von vorgefertigten Beton- und Stahlbeton-Bauelementen erfolgenden Bauweise sind allgemein bekannt. Diese Bauweise hat sich im Hochbau ziemlich stark durchgesetzt und gewinnt auch auf gewissenThe advantages of using prefabricated concrete and reinforced concrete structural elements are well known. This construction has prevailed quite strong in building construction and also wins on certain

-Z--Z-

21 8 656 21 8656

Gebieten des Tiefbaues immer mehr an Bedeutung. Bisher konnte jedoch noch keine Lösung gefunden werden, die die Möglichkeit bietet, Tiebauobjekte, in denen Flüssigkeiten gespeichert v/erden sollen wie Wasserspeicherbecken, Schwimmbecken, Badebecken usw. - oder Tiefbauobjekte, in denen das '.Eindringen von Grundwasser oder fließendem V/asser von außen verhindert werden muß, in rationeller V/eise und bei Gewährleitung einer vollkommenen Flüs3igkeitsabsperrung aus vorgefertigten Stahlbeton-Bauelementen herzustellen.Areas of civil engineering are becoming increasingly important. So far, however, no solution has been found, which offers the possibility of Tiebau objects, in which liquids are stored such as water storage tanks, swimming pools, baths, etc. - or civil engineering objects, in which the '. Penetration of groundwater or flowing V / asser of It must be prevented on the outside, in a rational manner and with the guarantee of a perfect liquid barrier, from prefabricated reinforced concrete components.

Im Verlaufe ihrer auf die Lö3ung dieses Problems gerichteten Anstrengungen kamen die Fachleute höchstens bi3 zu dem Statium, daß sie Seitenwändc und Zwischenpfeiler und natürlich die Decke - aus vorgefertigten Elementen herstellten und diese auf eine gemeinsamen, auf der Baustelle hergestellten monolitischen Stahlbeton-Bodenplatte anordneten. Diese Bodenplatte diente ala'einheitliche Flachgründung des gesaraten Bauwerkes und war, da oie die vom Gewicht der Dachkonstruktion, der Pfeiler und der Seitenwände kommende Belastung .auf den Baugrund weiterleiten mußte, stets überdimensioniert. Die vorgefertigten Stahlbetonelemente der Seitenwände sind volle, flache oder stützbandartig ausgebildete Bauelemente, die mittels übergreifender Bewehrungen und durch Ausbetonieren auf der Baustelle einander angeschlossen werden (sogenannte reißverschlußartige monolitische Stahlbetonverbindung). Oftmals sind die Bauelemente auch mit einer Verzahnung versehen und werden durch Betonausfüllung mit Kunstharzbindung miteinander verbunden.In the course of their efforts aimed at solving this problem, the experts came at most to the Statium that they made sidewalls and interstices and, of course, the ceiling - from prefabricated elements and arranged them on a common monolithic reinforced concrete floor slab manufactured on site. This bottom plate served as a uniform flat foundation of the construction and, since the weight of the roof structure, the pillar and the side walls had to be passed on to the subsoil, it was always oversized. The prefabricated reinforced concrete elements of the side walls are full, flat or support band-like components, which are connected by means of cross-reinforcements and by concreting on the construction site each other (so-called zipper-like monolithic reinforced concrete connection). Often, the components are also provided with a toothing and are connected by concrete filling with synthetic resin bond.

Diese Lösungen sind jedoch von mehreren Gesichtspunkten aus gesehen mit Nachteilen behaftet. Das grundlegende Problem besteht darin, daß die aus einer monolitischen Stahlbeton-Bodenplatte und aus Seitenwänden aus vorgefertigten Bauelementen hergestellten Becken nur zum Teil wasserdicht sind.However, these solutions are disadvantageous from several points of view. The basic problem is that the basins made of a monolithic reinforced concrete floor slab and sidewalls of prefabricated building elements are only partially watertight.

21 8 65621 8656

Einerseits sind die. Bauelemente 'selbst und die Bodenplatte soweit sie niöht in unwirtschaftlicher Y/eiae über da3 atatisch erforderliche Maß liegend, dimensioniert wurden wasserdurchlässig; andererseits können die erwähnten Verbindungen auch bei größter Sorgfalt in der Bauausführung nicht als vollkommen betrachtet werden. So müssen die Bekken im Interesse der Wasaerundurchlässigkeit durch einen wasserdichten Verputz, einer Torkretschicht und jedem Falle durch einen Kunststoffanstrich bzw. -Überzug isoliert werden.On the one hand are the. Components themselves and the base plate, insofar as they do not lie in uneconomic position over and above the required dimensions, were permeable to water; On the other hand, the compounds mentioned can not be considered perfect, even with the greatest care in the construction. For example, in the interests of impermeability to water, the recesses must be insulated by a waterproof plaster, a Torkret layer and each trap with a plastic coating or coating.

Ein weiterer Nachteil besteht darin, daß die für die Seitenwände verwendeten, vorgefertigten Stahlbeton-Bauelemente stets Einzweckbauelemente, d.h. Gegenstände sind, die für ein bestimmtes Objekt separat projektiert wurden und demzufolge aus ihnen kein Becken mit anderen Abmessungen oder ein sonstiges Objekt bzw. Bauwerk gebaut werden kann. Dadurch überschreiten die Baukosten dieser Bauwerke die Kosten zu anderen vergleichbaren Bauwerken, die aus vorgefertigten Bauelementen aufgebaut wurden.Another disadvantage is that prefabricated reinforced concrete components used for the sidewalls are always single-purpose components, i. Objects are objects that have been projected separately for a particular object and therefore can not be used to build a pool of a different size or any other object or structure. As a result, the construction cost of these structures exceeds the cost of other comparable structures constructed from prefabricated building elements.

Ein anderer Nachteil ist der Umstand, daß die erwähnten bekannten Becken in ästhetischer Hinsicht unvertretbar sind, da diese im allgemeinen in den Erdboden eingesenkt werden. Bei hohem Grundwa3ser3tand 13t die3 natürlich mit einem wesentlichen Kostenmehraufwand verbunden, was anstelle der vorgefertigten Bauelemente die monolitischen Ausführungen (Kastenabsenkung) in den Vordergrund rückt. Als Ubergangslösung werden - irrt Interesse der Verminderung der für die Erdarbeiten und die Grundwasserabsenkung erforderlichen Aufwendungen - häufig nur halb in die Erde eingesenkte V/asserspeicherbecken gebaut und die ausgehobene Erde als äußere Aufschüttung verwendet. Dies ist aus ästhetischer Sicht immer eine Zwangslösung, auch wenn die Böschungen begrast oder mit einer Steinverkleidung versehenAnother disadvantage is the fact that the mentioned known basins are aesthetically unacceptable because they are generally sunk into the ground. Of course, in the case of a high basic heating station, there is a significant increase in cost, which, instead of the prefabricated components, brings the monolithic versions (box lowering) into the foreground. As a transitional solution, the interest in reducing the expenses required for earthworks and lowering the groundwater level is often built only with half of the reservoirs immersed in the ground, and the excavated soil used as an outer landfill. From an aesthetic point of view, this is always a compulsory solution, even if the slopes are buried or provided with a stone cladding

-♦- 21 S 656- ♦ - 21 S 656

werden. Die sich aus der natürlichen Umgebung ohne jeden Grund hervorhebenden Erhöhungen bzw. Hocker atb'ren die Einheit des Landschaftsbildes und erinnern mit ihren hervorstehenden Luftern, Abgängen usw. an militärische Bauwerke. Diese ästhetischen Nachteile sind insbesondere in Urlaubergegenden und in inneren Siedlungsgebieten schwerwiegend.become. The elevations and stools, which stand out from the natural environment for no reason atb'ren the unity of the landscape and remind with their protruding Lufter, departures, etc. to military structures. These aesthetic disadvantages are particularly serious in tourist areas and in inner settlement areas.

Nachteilig ist weiterhin der ungelöste Stand der Wärmeisolierung bei den zur Zeit bekannten Beckenkonstruktionen.Another disadvantage is the unresolved state of thermal insulation in the currently known pelvic constructions.

Auf Grund der aufgezählten Nachteile werden tfasaerapeich-erbecken und ähnliche Anlagen überwiegend einzeln projektiert und vollständig in monolitischen Stahlbeton-Konstruktionen erbaut, obwohl bereits Vorschläge für den Bau von Becken aus vorgefertigten Bauelemente vorliegen. Pur diese Becken werden einzeln projektierte Bauelemente empfohlen, spezielle Pugenausbildungen verwendet und überwiegend BeIcke η mit nachträglichem Spannen und in den Erdboden eingesenkter Ausführung gebaut.Due to the listed disadvantages tfasaerapeich-basin and similar systems are mainly individually designed and built entirely in monolithic reinforced concrete structures, although there are already proposals for the construction of basins made of prefabricated components. For these basins, individually designed components are recommended, special formations are used and predominantly cladding η with subsequent tensioning and construction recessed into the ground is built.

Nach der DE-PS 1 684 733 wurde z.B. die Seitenwand eines Beckens mit kreisförmigem Grundriß au3 vorgefertigten, bogenförmigen, vollen Bauelementen gebaut. Zum Nachspannen werden äußere Stahlbänder verwendet. Nachteile dieser Ausführung sind die einzelne und komplizierte Ausgestaltung der Elemente und Verbindungen, das ziemlich arbeitsaufwendige Nachspannen, die Gefahr der Zerstörung des Nachspanabandes durch Korrosion (was bei jedem äußeren Nachspannen Probleme bedeutet) sowie die grundrißbedingten Gebundenheit.According to DE-PS 1 684 733, e.g. built the side wall of a basin with a circular plan au3 prefabricated, arched, full building elements. For tensioning outer steel bands are used. Disadvantages of this design are the individual and complicated design of the elements and compounds, the laborious re-tensioning, the risk of destruction of Nachspanabandes by corrosion (which means problems with any external Nachspannen) and the Grundrißbedingten bondage.

Die Grundrißabmessungen eine3 Bauwerkes gemäß der DE-PS 1 559 174, ein der Kreisform nahekommendes Polygon, sind ebenfalls gebunden. Auch hier kommen Einzelbauelemente und spezielle Verbindungen zur Anwendung. Die in den senkrechtenThe ground plan dimensions of a building according to DE-PS 1 559 174, a polygon close to the circular shape, are also bound. Here, too, individual components and special connections are used. The in the vertical

-5- 2t8 6 56-5- 2t8 6 56

Fugen aufeinandertreffenden, seitlich herausragenden waagerechten Stahlbewehrungsteile werden durch gurtartige Elemente miteinander verbunden und hiernach die Fugen durch Monolitbeton ausgefüllt.Joints meeting side-by-side horizontal steel reinforcement sections are connected by belt-like elements and thereafter the joints are filled with monolithic concrete.

In den DE-PS1η 1 434 829 und 1 434 830 werden ebenfalls Becken beschrieben, die aus einzeln projektierten, vollen vorgefertigten Bauelementen hergestellt werden. Die Verbindungen sind auch hier kompliziert und - genau wie bei den vorgenannten Ausführungen - muß die Isolierung mit Hilfe einer zusätzlichen aufgetragenen Schicht gelöst werden.In the DE-PS 1 η 1 434 829 and 1 434 830 also pools are described, which are made of individually projected, full prefabricated components. The compounds are also complicated here and - just as in the aforementioned embodiments - the insulation must be solved by means of an additional applied layer.

Ziel der Erfindung: Aim of the invention:

Durch die Erfindung werden die aufgeführten Nachteile beseitigt und die Voraussetzung geschaffen, ein wasserundurchlässiges Bauwerk aus vorgefertigten, nicht an ein Einzelprodukt gebundenes Bauelement rationoll mit hohem ästhetischen V/ert zu errichten.By the invention, the disadvantages listed are eliminated and created the premise to build a waterproof construction of prefabricated, not bound to a single product component rationoll with high aesthetic V / ert.

.^ des V/eoens der Erfindung:of the invention:

Die Erfindung beruht auf der Erkenntnis, daß man in dem Falle, wenn man auch an sich V/asserundurchlässigkeit gewährleistende und gleichzeitig zur Aufnahme von durch auftretende Kräfte bewirkten Beanspruchungen geeignete vorgefertigte Bauelemente verwendet, rationall den in funktioneller Hinsicht an monolitische Beckon gestellten Anforderungen entsprechende Becken au3 vorgefertigten Bauelementen herstellen kann.The invention is based on the finding that in the case, when one also uses v / impermeability guaranteeing and at the same time for absorbing forces caused by occurring forces suitable prefabricated components, rationall the functional requirements of monolithic Beckon asked requirements corresponding basin au3 can manufacture prefabricated components.

Bei größeren Becken kann - in Abhängigkeit von den jeweiligen Bodengegebenheiten - eine Trennung der Gründungen für die verschiedenen Belastungen erforderlich werden, wo-For larger basins - depending on the particular soil conditions - a separation of the foundations for the different loads may be required, where

- 6 -  - 6 -

-6- 218 656-6- 218 656

durch Becken aufgebaut werden können, deren Grundplatte, Seitenwände und eventuell Zwiochenpfeiler als statisch selbständige Konstruktionen funktionieren, so daß ihre Verbindungen die bekannten v/esentlich unterschreitenden Beanspruchungen ausgesetzt sind» d,h. daß sie auch mit : geringerem Aufwand vollkommen wasserundurchlässig gemacht v/erden können. Die gegenseitigen Verbindungen, d.h. Anschlüsse der vorgefertigten Bauelemente hingegen 3ind so gelöst, daß das ganze Bauwerk durch eine rationelle Baumontage erstellt werden kann. Der Bedarf an Arbeitskräften macht etwa ein Viertel de3 Arbeitskräftebedarfes bei den bekannten monolitischen Ausführungen au3. Die Fertigstellung des die untere Abstützung der vorgefertigten Seitenwand gewährleistenden Baustellen-LIassenbetone kann ebenfalls schnell verwirklicht werden, da dieser (anstelle der Erdrückschüttung) zwischen den Erdböschungen eingearbeitet werden muß.can be constructed by basins whose base plate, side walls and possibly twin pillars function as statically independent constructions, so that their connections are exposed to the known and / or undershooting stresses »d, h. that they can also be made completely impermeable to water with less effort. The mutual connections, i. Connections of the prefabricated components, however, 3ind solved so that the whole structure can be created by a rational construction site. The need for manpower accounts for about a quarter of the labor demand in the known monolithic designs. The completion of the lower support of the prefabricated side wall ensuring building site LIassenbetone can also be realized quickly, since this must be incorporated (instead of Erdreckschungung) between the Erdböschungen.

Die gestellte Aufgabe wurde dadurch gelöst, daß im Inneren der vorgefertigten Stahlbeton-Bauelemente in vorteilhafter Weise miteinander in gleicher Richtung verlaufende, zur Ableitung und/oder Verdampfung der in das Innere des Bauelementes gelangenden Flüssigkeit geeignete Kanäle vorgesehen sind. Die plattenartig vorgefertigten Stahlbeton-Bauelemente können auf eine die Dichte und damit die V/asserundurchlässigkeit ihres Materials erhöhenden V/eise, vorteilhaft mindestens in der mit der Richtung ihrer Kanäle übereinstimmenden Richtung, gegebenenfalls in zwei zueinander senkrechten Richtungen vorgespannt werden. Bei größeren Becken sind die Gründungen der voneinander in unterschiedlichein Ausmaße belastenden Konstruktionen, z.B. der Seitenwände und der Bodenplatte und/oder Pfeiler des Beckens voneinander getrennt und zwischen diesen unterschiedlich belasteten Konstruktionen unterschiedliche Senkungen ermöglichende Dilatati'onsfugen vorgesehen. .The above object has been achieved in that in the interior of the prefabricated reinforced concrete components in an advantageous manner with each other in the same direction running, suitable for the discharge and / or evaporation of the liquid reaching into the interior of the device suitable channels are provided. The plate-like prefabricated reinforced concrete components can be biased to a density which increases the density and thus the impermeability of their material, advantageously at least in the direction coinciding with the direction of their channels, optionally in two mutually perpendicular directions. For larger basins, the foundations of constructions which are subject to different degrees of loading, e.g. the side walls and the bottom plate and / or pillar of the pelvis separated and provided between these differently loaded structures different sinking dilatation joints. ,

-7- 21 8 656-7- 21 8 656

In den Dilatationafugen iat elastisches wasserundurchlässiges -Material, z.B. Kunstharzkitt vorgesehen·In the dilatation membranes, elastic, water-impermeable material, e.g. Synthetic resin putty provided ·

Nach einem vorteilhaften Llerkwal dor Erfindung sind die Abgrensungckonotruktionen plnttenartige quader- oder im wesentlichen quaderförmig vorgefertigte Stahlbeton-Bauelemente, die entlang ihrer zu den längsverlaufenden Kanälen parallelen Kündern durch in die Anachlußfugen eingesetzte Betonstahlstäbe und durch eine vorteilhafterweise kunstharzgebundene Ivlonolitbetonausfüllung aneinander geführt werden.According to an advantageous Llerkwal dor invention, the Abgrensungckonotruktionen plnttenartige cuboid or substantially cuboid prefabricated reinforced concrete components, which are guided along their longitudinal channels to the parallel runners by inserted into the Anachlußfugen reinforcing steel bars and by an advantageously resin-bonded Ivlonolitbetonausfüllung to each other.

Bei einer weiteren Au3führungsform der Erfindung sind die die Seitenwände de3 Bau'.verkes bildenden, vorgefertigten Stahlbeton-Bauelemente - in ihrer eingebauten Lage - entlang ihrer LLingskanten durch Pfeiler abgestützte, in Querrichtung Ia3ttragende Elemente, wobei die Kanäle in der V/and im wesentlichen senkrecht verlaufen. Nach einem anderen Auoführung3beiapiol sind die die Seitenwände des Bauwerkes bildenden Stahlbeton-Bauelemente - .in ihrer eingebauten Lage - unten und oben eingespannte, in Längsrichtung lasttragende Elemente, wobei die Kanäle in der V/and im wesentlichen senkrecht angeordnet sind. Das Bauwerk kann auch so ausgelegt werden, daß die die Scitenwändo bildenden Bauelemente aufeinander gelegt angeordnet sind und die Kanäle in ihnen waagerecht verlaufen. Diese Lösung ist zweckmäßigerweise in dem Falle zu verwende, wenn das Bauwerk auf einem körnigen Boden angeordnet wird und der Baugrund eine Trennung der Gründung der Bodenplatte und der Seitenwände nicht erforderlich macht.In another embodiment of the invention, the prefabricated reinforced concrete elements forming the sidewalls of the building are - in their installed position - supported along their edges by pillars supported in the transverse direction, the channels being substantially vertical in the vertical direction run. According to another Auoführung3beiapiol are the side walls of the building forming reinforced concrete elements -. In its installed position - clamped down and up, longitudinally load-bearing elements, the channels are arranged in the V / and substantially perpendicular. The building can also be designed so that the Scitenwändo forming components are placed one above the other and run the channels in them horizontally. This solution is expediently to be used in the case when the building is placed on a granular ground and the ground does not require a separation of the foundation of the bottom plate and the side walls.

In anderen Fällen ist das Bauwerk zum Teil in den Erdboden eingesenkt, verfügt über eine Segmentseitenwand, einen auf der Erdböschung angestützten schrägen Abschnitt und eine waagerechte Bodenplatte,In other cases, the structure is partially sunk into the ground, has a segmental side wall, an inclined section supported on the embankment, and a horizontal floor slab.

~8' 218 656~ 8 '218 656

Nach einem weiteren Merkmal der-Erfindung sind die Kanäle der Abgrenzkonstruktion, insbesondere der Seitenwände und/oder der Bodenplatte mit Wasser- und/oder belüfteten Dunstableitungsrohren verbunden, wobei die in die Fortsetzungslinien voneinander fallenden Kanäle der benachbarten Stahlbeton-Bauelemente durch Gänge, z.B. durch Rohre miteinander verbunden sind.According to a further feature of the invention, the channels of the boundary structure, in particular of the side walls and / or the bottom plate are connected to water and / or ventilated fume extraction tubes, wherein the channels of the adjacent reinforced concrete components falling apart in the continuation lines through passages, e.g. connected by pipes.

Zweckdienlich ist eine Gründung vorgehen, bei der die Seitenwände auf die auch zur Gründung der vorgefertigten Pfeiler dienenden vorgefertigten Stahlbeton-Nestgründungen abgestützt sind und bei der der Bereich über den llestgründungen zu einem, die Seitenwand-Bauelemente und die Pfeiler zusammenfassenden, bandartigen, kombinierten Gründungskörper ausbetoniert ist.It is expedient to use a foundation in which the side walls are supported on prefabricated reinforced concrete foundations, which are also used for founding the prefabricated piers, and where the area above the foundations is concreted to form a band-like combined foundation body comprising the sidewall elements and the piers is.

Charakteristisch für eine weitere Ausführungaforrn der iürfindung ist, daß die vorgefertigten Stahlbeton-Bauelemente durch Kerne miteinander verbunden sind, die durch daa üinfließen des Monolitbeton beim Ausbetonieren der Fugen zwischen zwei benachbarten Bauelementen in die Randsonen dor Hohlräume und auch in den lindteil der Kanüle entstehen.It is characteristic of another embodiment of the invention that the prefabricated reinforced concrete elements are interconnected by cores which are formed by flowing the monolith concrete in concreting the joints between two adjacent structural elements into the rim areas of the cavities and also into the needle portion of the cannula.

Nach einem weiteren Merkmal der Erfindung i3t zwischen den aufeinanderliegenden Flächen der benachbarten Stahlbeton-Bauelemente ein zuoammendrückbares Llikrozellen-Gummiband und/oder ein Bleiblechstreifen eingelegt. Anstelle desselben oder neben diesem wird in den vorhandenen Fugen ein Gummiteil eingelegt. Das Gummiband und/oder der Bleiblechstreifen ist in den zur Flüssigkeit hin entgegengesetzten Randzonen des Bauelementes eingelegt. Der Raum zwischen dem Gummiband und/oder dem Bleiblech3treifen und/ oder dem Gummiteil und der an der Flüssigkeit angrenzenden Fläche der Fuge ist mit Monolitbeton ausgefüllt - zweckdienlicherweise mit Kunst3toffbeton - in der vorteilhafterweise zumindest ein Betonstahlstab eingeigt ist.According to a further feature of the invention, a compressible Llikrozellen rubber band and / or a Bleiblechstreifen inserted between the superposed surfaces of the adjacent reinforced concrete components. Instead of the same or next to this, a rubber part is inserted in the existing joints. The rubber band and / or the lead-sheet strip is inserted in the edge zones of the component which are opposite to the liquid. The space between the rubber band and / or the Bleiblech3treifen and / or the rubber part and the liquid adjacent surface of the joint is filled with monolith concrete - expediently with Kunst3toffbeton - in which advantageously at least one reinforcing steel bar is eingeigt.

218 6 56218 6 56

Die in den vorgefertigten Stahlbeton-Bauelemente eingebetteten vorgespannten Drähte sind ausschließlich oder zum größten Teil in den zur Flüssigkeit entgegengesetzten Bereich deö Bauelementes angeordnet. Dies ist aU3 Gründen des Korrosionsschutzes - wie später noch, erläutert wird - außerordentlich vorteilhaft.The prestressed wires embedded in the prefabricated reinforced concrete components are arranged exclusively or for the most part in the region of the component which is opposite to the liquid. This is aU3 reasons of corrosion protection - as will be explained later - extremely beneficial.

Bei einem nach der Erfindung errichteten Schwimmbecken bestehen die Seitenwände aus mehreren, zweckdienlicherweise aus zwei Reihen vorgefertigter plattenartiger und quaderförmigen Stahlbeton-Bauelemente, die im wesentlichen über waagerecht verlaufende Kanäle verfügen. Die Bauelemente der unteren Reihe sind jedoch breiter als die der der oberen Reihe (Reihen), so daß ein im Beckenraum hervorspringender zmlaufender Absatz entsteht, Um die obersten Kanäle in den Seitenwänden des Schwimmbeckens als Überlaufrinne zu nutzen, sind in den, die oberen waagerechten Kanäle begrenzenden Botonrippen Durchbräche vorgesehen, die den Eintritt des Y/assers in die oueraten Kanäle ermöglichen. Die so entstandene überlaufrinne lot an die Kanäle des Y/asserableitaystcns dor Seitcnwünde angeschlossen.In a swimming pool constructed according to the invention, the side walls consist of a plurality of, advantageously, two rows of prefabricated plate-like and parallelepipedic reinforced concrete building elements, which have substantially horizontally extending channels. However, the components of the lower row are wider than those of the upper row (rows), so that a cascading protruding pelvic floor is formed in the pelvic space. To use the uppermost channels in the side walls of the pool as an overflow channel are in the upper horizontal channels limiting Botonrippen breakthroughs that allow the entrance of the Yerser in the oueraten channels. The resulting overflow trough is connected to the channels of the Y / asserableitaystcns dor Seitcnwünde.

Nach einem anderen Ausführungsbeispiel ist das nach der Erfindung errichtete Bauwerk ein in den Erdboden eingesenktes Becken, bei dem zumindest entlang eines Teiles seiner Seitenwände ein Gang vorgesehen ist, der auf der zur Bockenwand entgegengesetzten Seite durch eine stabilisierende Erdböschung abgegrenzt wird. Der Gang ist durch eine Decke aus vorgefertigten Stahlbeton-Bauelementen abgedeckt, die einerseits auf einem in der Böschung auf Terrainniveau errichtetem Fundament und andererseits auf dem oberen Ringanker der Beckenwand aufliegen.According to another embodiment, the building constructed according to the invention is a sinking into the ground basin, wherein at least along a part of its side walls, a passage is provided which is delimited on the opposite side to the Bockenwand by a stabilizing Erdböschung. The corridor is covered by a ceiling of prefabricated reinforced concrete elements, which rest on the one hand on a built in the embankment at ground level foundation and on the other hand on the upper ring anchor the pool wall.

Einem weiteren Erfindungsmerkmai entsprechend sind dieAccording to another Erfindungsmerkmai according to the

- 10 -- 10 -

2ί β 656 2ί β 656

die Stahlbeton-Bauelemente der Seitenwand von außen abstützenden Pfeiler Stahlprofilträger, deren unteres und oberes Ende in monolytische Stahlbetonringanker eingespannt ist. Die Pfeiler sind beispielsweise U-Stahlprofile, die mit ihren U-Schenklen gegenüberliegend angeordnet sind. Zwischen diesen U-Profil3chenkeln verläuft auch die senkrechte jftige zweier benachbarter Bauelementreihen, wobei die U-Schenkel der Stahlprofile unter Zwischenfügung eines Mikrozellen-Gumminbandes an die Außenfläche der vorgefertigten Stahlbeton-Bauelemente gepreßt werden und der zwischen den U-Stahlprofilen vorhandene Raum, samt der senkrechten Fuge zwischen den Bauelementen, ausbetoniert ist. Das untere Ende der.Stahlprofilpfeiler kann mit einen in den Lagerbalken der Bodenplatte hineinreichenden, in diesen einbetonierten, im wesentlichen waagerechten Teil versehen sein. Die Llontage der vorgefertigten Stahlbeton-Bauelemente kann dadurch erleichtert werden, daß zwischen den unteren und oberen monoliti3chen Stahlbeton-Balken ein aua Stahl gefertigter an die Pfeiler befestigter dazwischenliegender Ringankor vorgesehen 13t. .the reinforced concrete elements of the sidewall supporting pillars made of steel profile beam whose lower and upper end is clamped in monolithic reinforced concrete ring anchors. The pillars are for example U-steel profiles, which are arranged opposite each other with their U-cycles. The vertical jftige two adjacent rows of components runs between these U-Profil3chenkeln, the U-legs of the steel profiles are pressed with the interposition of a micro-cell rubber tape to the outer surface of the prefabricated reinforced concrete components and existing between the U-steel profiles space, including the vertical Fugue between the components, is concreted. The lower end of .Steinprofilpfeiler may be provided with a in the bearing bar of the bottom plate extending into this concreted, substantially horizontal part. The Llontage the prefabricated reinforced concrete components can be facilitated by the fact that provided between the lower and upper monoliti3chen reinforced concrete beams a steel-made attached to the pillar interposed Ringankor 13t. ,

Nach einem anderen vorteilhaften Auoführungobeiopiel der Erfindung ist da3 Bauwerk auf Pfeilern über der Geländeebene angeordnet, wobei die Bodenplatte des Bauwerkes auf einem, den monoliti3chen oder/und vorgefertigten Hauptbalken ruht, au,£ den Pfeilern angeordnet ist. Oberhalb der Hauptbalken ist in der Bodenplatte ein monolitischer Stahlbeton-Lagerbalken vorgesehen, an den sich die in die Hohlräume der vorgefertigten Stahlbeton-Bauelemente hineinreichende Monolitbetonkerne anschließen, in die - zur Verhinderung der Endplattenverdrehung - zur Längsrichtung des Hauptbalkens querliegende und im monoliti3chen Stahlbeton-Lagerbalken quer hindurchgehende Stahlbeton-Stäbe eingelegt sind. Die Vorteile dieser Ausführung werden nachstehend dataillierter beschrieben.According to another advantageous Auoführungobeiopiel the invention da3 building is arranged on pillars above the ground level, the bottom plate of the building on one, the monoliti3chen and / or prefabricated main beam rests, au, the pillars is arranged. Above the main beams, a monolithic reinforced concrete bearing beam is provided in the floor slab, adjoining which are the monolithic concrete cores extending into the cavities of the prefabricated reinforced concrete elements, transverse to the longitudinal beam of the main beam and transverse to the monolithic reinforced concrete bearing beam to prevent end plate twisting passing reinforced concrete rods are inserted. The advantages of this embodiment will be described below in more detail.

- 11 -- 11 -

-11- 21 a 656 - 11 - 21 a 656

Schließlich sind nach einem weiteren Brfindungsmerkmal zwischen den vorgefertigten Stahlbeton-Bauelementen mindestens in der Bodenplatte, zweckdienlicherweise jedoch auch in den Seitenwänden breitere und schmalere Fugen vorgesehen, Durch Ausfüllen der breiteren Fugen mit Stahlbeton entstehen in der Bodenplatte Lagerbalken*Finally, according to another Brfindungsmerkmal between the prefabricated reinforced concrete elements at least in the bottom plate, but expediently also in the side walls wider and narrower joints provided by filling the wider joints with reinforced concrete arise in the bottom plate bearing beams *

Mit der Erfindung sind zahlreiche vorteilhafte und neuartige zusätzliche Y/irkungen verbunden, über die die zur Zeit bekannten Bauwerke dieser Art nicht verfügen.Numerous advantageous and novel additional effects are associated with the invention, which the currently known structures of this type do not have.

Durch die Erfindung werden erstmals Möglichkeiten vorgeschlagen, V/asserspeicherbecken und ähnliche Anlagen praktisch vollständig aus vorgefertigten Bauelementen aufzubauen und alle Elemente einer rationellen und moderen Bauweise weitestgehend auszunutzen. Darüberhinausgehend wird nicht mit einzeln projektierten, vorgefertigten Bauelenenten gearbeitet, die nur für ein bestimmtes Projekt verwendet werden können, sondern allgemein "durch Blindfertig-ung" hergestellte Bauelemente eingesetzt, aus denen praktisch jedes beliebige Bocken aufgebaut worden kann.For the first time, the invention proposes possibilities for constructing water reservoirs and similar systems practically completely from prefabricated components and making the most of all elements of a rational and modern design. In addition, it does not work with individually configured, prefabricated Bauenteenten that can be used only for a particular project, but in general used by "dummy production" manufactured components from which virtually any Bocken can be built.

Ein bedeutsamer wirtschaftlicher Faktor besteh't darin, daß die Kanäle etwa 50 c/a des Volumens der Bauelemente ausmachen, d.h. daß der LIaterialeinsatz minimal ist. So kann eine bedeutende Verminderung des Eigengewichtes erreicht werden, deren Vorteile insbesondere beim Transport, bei der Baumontage und bei den Baugründungen eintreten.A significant economic factor is that the channels make up about 50 c / a of the volume of the devices, that is, the material usage is minimal. Thus, a significant reduction in its own weight can be achieved, the advantages of which occur in particular during transport, during assembly and in the grounds.

Das erfindungsgemäße Becken kann wesentlich schneller und mit geringerem Aufwand an Kosten und manueller Arbeiten aufgebaut werden als die zur Zeit bekannten Anlagen. Die Effektivität dieser Faktoren wird durch den .Umstand weiter erhöht, daß das Becken nicht in den Erdboden eingesenkt werden muß, wodurch sich ein minmaler Bedarf an ErdarbeitThe basin according to the invention can be built much faster and with less effort in terms of costs and manual work than the plants currently known. The effectiveness of these factors is further increased by the circumstance that the basin does not have to be sunk into the ground, which results in a minimal need for earthwork

- 12 -- 12 -

-12~ 218 656- 12 ~ 218 656

ergibt und die Möglichkeit geboten wird, das Gründungsniveau der Becken oberhaöb des Grundwasserniveaus vorzusehen. So entfallen auch die Baugrubenontwässerungs- und V/asserhaltungsarbeiten. Die Becken können sogar auf Füße gestellt aufgebaut werden, was die Gründungskosten auf ein Mindestmaß reduziert. Muß hingegen ein unterirdisches oder ein unter dem Grundwasserspiegel befindliches Bauwerk, z.B. ein Tunnel gebaut werden, so können die Baugruben mittel Schrämtechnologie hergestellt und in diese, mit senkrechten Kanälen veeehene, vorgefertigte Bauelemente eingesenkt und die Fugen z.B. durch Unterwasserbetonierung abgeschlossen werden.and provides the opportunity to provide the founding level of the basins above groundwater level. This also eliminates the construction pit drainage and preservation work. The pools can even be set up on feet, which minimizes the founding costs. On the other hand, if a subterranean structure or a structure below the groundwater level, e.g. a tunnel can be built, so the excavations can be prepared by means of Schrämtechnologie and in this, with vertical channels veeehene, pre-fabricated components sunk and the joints, for example. be completed by underwater concrete.

Da die Seitenwand und die Grundplatten-Bauelemente jeweils über voneinander getrennte vollkommen wasserisolierende Eigenschaften verfugen, ist ein Auftragen von zusätzlichen Isolierschichten (Torkretieren, Kunststoffüberzug, wasserdichter Verputz usw.) nicht erforderlich.Since the side wall and the base plate components each have completely separate water-insulating properties from each other, it is not necessary to apply additional insulating layers (torketing, plastic coating, watertight plaster, etc.).

Erforderlichenfalls kann eine V/ämeisolierung, die zwischen den kürzeren Rippen vorgesehen wird, einfach und ästhetisch gelöst werden.If necessary, a thermal insulation provided between the shorter ribs can be easily and aesthetically solved.

Besonders hervorzuheben 3ind die ästhetischen Vorteile, die durch die Erfindung erzielt werden. Die Säulcntcilung und die Oberflächenausbildung ermöglichen die Ausgestaltung einer den modernen baulichen Grundsätzen entsprechenden Architektur. Bei den erfindungsgemäßen Flüssigkeitsspeicherbecken erscheint auch die kleinste Baueinheit selbständig und oaßt sich harmonisch in da3 jweilige Stadtbild bzw. in die natürliche Umgebung ein. Abschließend ist al3 ein wesentlicher Vorteil anzusehen, daß durch Aneinanderreihen der vorgefertigten Bauelemente, Becken oder sonstige Bauwerke mit theoretisch beliebigem Fassungsvermögen und beliebigem Grundriß hergestellt werden können, wobei·Of particular note are the aesthetic advantages achieved by the invention. The column and the surface training make it possible to design an architecture that conforms to modern building principles. In the case of the liquid storage tanks according to the invention, even the smallest building unit appears on its own and blends in harmoniously with the urban landscape or the natural environment. Finally, al3 is a significant advantage that can be made by juxtaposing the prefabricated components, basins or other structures with theoretically arbitrary capacity and any plan, wherein

- 13 -- 13 -

218 656218 656

auch die Dachkonstruktion aus dem gleichen Bauelement v/ie die Seitenwände und die Bodenplatten hergestellt werden·the roof construction is also made of the same building element as the side walls and the floor slabs ·

Ausfuhrunffsbe i ap i el:Export information:

Die Erfindung soll nachstehend an einem Ausführungsbeispiel näher erläutert werden· In den dazugehörigen Zeichnungen zeigen:The invention will be explained in more detail below using an exemplary embodiment. In the accompanying drawings:

Pig· 1: ein Detail eines Beckens im senkrechten Schnitt entsprechend der Linie I-I in Pig, 2, bei den die Kanäle der vorgefertigten plattenartigen Stahlbetonelemente senkrecht verlaufen, wobei bei jedem Bauelementanschluß ein Pfeiler zugeordnet ist und die Bauelemente in Querrichtung laottragend sind;Pig · 1: a detail of a basin in vertical section along the line I-I in Pig, 2, in which the channels of the prefabricated plate-like reinforced concrete elements are perpendicular, wherein each component connection is assigned a pillar and the components are transient in the transverse direction;

Pig. 2; einen Schnitt ge^niü dor Linie II-II in Pig· Ii ,Pig. 2; a section along line II-II in piglets,

pig. 2a: eine alternative Anachlußnüglichkeit der Bodenplatten-Bauelemente;pig. FIG. 2a shows an alternative accessibility of the floor panel components; FIG.

Pig» 3: ein Detail eines Beckens im SchnittPig »3: a detail of a basin in section

III-III nach Pig. 4, bei dem die quaderförmig η vorgefertigten Stahlbeton-Bauelemente in Längsrichtung lasstragend sind;III-III after Pig. 4, in which the cuboid η prefabricated reinforced concrete elements in the longitudinal direction are laser-bearing;

Pig. 4: den Schnitt IV-IV nach Pig. 3;Pig. 4: the section IV-IV after Pig. 3;

Pig, 5: den Teilschnitt durch ein kleines Becken entlang der Linie V-V in Pig. 6;Pig, 5: the partial section through a small basin along the line V-V in Pig. 6;

- 14 -- 14 -

-H--H-

2t 6 6562t 6 656

Pig. 6: einen Schnitt entlang der Linie VI-VI . in Pig. 5; Pig. 6: a section along the line VI-VI. in Pig. 5;

Pig. 7: das statische Verhalten der Beckenwand und 8: im Palle von quaderförmigen, in Querrichtung Ias3tragenden vorgefertigten Stahlbeton-Plattenbauelementen;Pig. 7: the static behavior of the pelvic wall and 8: in the palle of parallelepiped-shaped, prefabricated reinforced concrete slab elements in the transverse direction;

Pig. 9: eine Illustrierung des ästhetischen Vor- und 10; teils des erfindungsgemäßen Beckens;Pig. 9: an illustration of the aesthetic fore- and 10; partly of the basin according to the invention;

Pig. 11: einen senkrechten Teilschnitt eines Schv/immsportbeckens;Pig. 11: a vertical partial section of a swimming pool;

Pig. 12:, den Schnitt entlang der Linie VII-VII in Pig. 11;Pig. 12:, the section along the line VII-VII in Pig. 11;

Pig. 13: da3 Detail VIII auo Pig. 12 in vergrößertem Maßstab;Pig. 13: da3 detail VIII auo pig. 12 on an enlarged scale;

Pig. 14: einen schematischen Schnitt durch ein Plüssigkeitaopeicherbeckcn gemäß der Erfindung mit unterschiedlicher Tiefe;Pig. FIG. 14 is a schematic section through a plethora of aaaaaa of different depths according to the invention; FIG.

Pig. 15: den waagerechten Schnitt entlang der Linie VIII-VIII in Pig. 14;Pig. 15: the horizontal section along the line VIII-VIII in Pig. 14;

Pig. 16: das in Pig. 14 bezeichnete Detail XVI in größerem Maßstab;Pig. 16: that in Pig. 14 designated detail XVI on a larger scale;

Pig. 17: das in Pig. 15 bezeichnete Detail XVII in größerem Maßstab;Pig. 17: that in Pig. 15 designated detail XVII on a larger scale;

Pig, 18: ein nach Pig. Il ähnliches, jedoch aufPüße aufgestelltes Becken imPig, 18: one after Pig. Il similar, but at pots placed in the

- 15 -- 15 -

-15 - 218 6 5 6-15 - 218 6 5 6

waagerechten Schnitt;horizontal cut;

Fig. 19: den senkrechten Querschnitt entlang der Linie X-X in Pig. 18;Fig. 19: the vertical cross section along the line X-X in Pig. 18;

Pig. 20: den Längsschnitt entlang der Linie XI-XI in Pig. 18;Pig. Figure 20: the longitudinal section along the line XI-XI in Pig. 18;

Pig, 21: eine vorteilhafte Verbindung eines Zwischen-Tragpfeilers mit Beckenbodenplatte;Pig, 21: an advantageous connection of an intermediate support pillar with pelvic floor plate;

Pig. 22: einen Schnitt entlang der Linie .XII-XII in Pig. 21;Pig. 22: a section along the line .XII-XII in Pig. 21;

Pig. 23: einen senkrechten Schnitt entlang der Linie IX-IX in Pig. 17.Pig. Figure 23: a vertical section along the line IX-IX in Pig. 17th

Wie aus Pig. 1 und 2 ersichtlich, besteht die Seitenwand a und die Bodenplatte jb des Beckens aus plattonartig vorgefertigten otahlbeton-Bauelcmentcn 1, in denen kreisförmige-Kanüle 2 vorgesehen sind. Die einzelnen Bauolcaente 1 sind in der Draufsicht rechteckförmig und zumindest in der gleichen Richtung wie die Kanüle 2 - d.h. in der Längsrichtung - vorgespannt, wobei jedoch eine in zwei Richtungen erfolgende Vorspannung günstiger ist. Die Spanndrahte sind jeweils mit 3 bezeichnet.Like from Pig. 1 and 2, the side wall a and the bottom plate jb of the basin consist of plate-like prefabricated otahlbeton-Bauelcmentcn 1, in which circular cannula 2 are provided. The individual Bauolcaente 1 are rectangular in plan view and at least in the same direction as the cannula 2 -. in the longitudinal direction - biased, but a bi-directional bias is cheaper. The tension wires are each denoted by 3.

Bei dem Becken nach Pig. 1 und 2 sind die die Seitenwünde _jx bildenden Bauelemente 1 auf der kürzeren Seite gestellt angeordnet, d.h. die Kanäle 2 verlaufen senkrecht. Die Ka nüle 2 der Bauelemente 1 der Bodenplatte h verlaufen natürlich in waagerechter Richtung. Die die Seitenwände a bildenden Bauelemente 1 stehen auf einem Streifenfunda-At the pool after Pig. 1 and 2, the side walls _jx forming components 1 are placed on the shorter side, ie, the channels 2 are perpendicular. The Ka nüle 2 of the components 1 of the bottom plate h course in the horizontal direction. The components 1 forming the side walls a stand on a strip basis.

au~£ ment 4, Sas in der Beschreibung noch näher eingegangen v/ird. Zur Gründung der Bodenplatte Jd dient eine vom Strei4, which is described in more detail in the description. For the foundation of the base plate Jd serves one of the Strei

218 6 56218 6 56

fenfundament 4 getrennte dünne Stahlbeton-Platte 5« Zwischen dieser Platte und der Beckenbodenplatte b ist die Kunststoffolie 6 vorgesehen. Als alternative Lösung kann anstelle der Folie auf der Stahlbeton-Platte 5 auch eine Kunststoffüberzugsschicht aufgetragen werden. Unter der Bodenplatte b ist eine sandige Kiesschicht 7 vorgesehen.Fenfundament 4 separate thin reinforced concrete slab 5 «between this plate and the pelvic floor plate b, the plastic film 6 is provided. As an alternative solution, instead of the film on the reinforced concrete slab 5, a plastic coating layer can also be applied. Under the bottom plate b a sandy gravel layer 7 is provided.

An den Anschlußpunkten der die Seitenwände a bildenden Bauelemente 1 ist Je ein Pfeiler 8 angeordnet, an den sich die Längsseiten der Bauelemente 1 abstützen. Der untere Teil 8a jedes Pfeilers 8 ist mit einem zentralen Hohlraum versehen, während der Querschnitt des oberen Teiles 8b U-förmig ausgeführt ist. Die Pfeiler 8 sind in vorgefertigte liestgründungen 9, genauer in die in ihrem Zentrum liegende Rippe 9d eingepaßt, die auf dem Unterbeton 9b ruht. Die liestgründungen, die Pfeiler und die Bauelemente 1 werden durch den streifenämdamentartigen Llonolitkörper 9a zu einer einzingen kombinierten Grundkörpereinheit zusammengefaßt. Die Ilest^ründungen 9 liegen ebenfalls auf der Unterbetonschicht 9b. Aus Pig. 1 ist gut su seilen, daß die vorstehend detaillierte Gründung der Pfeiler S und der Seitenwand a von der Gründung der Bodenplatte b des Beckens getrennt ist, d.h. die unterschiedlich belasteten Konstruktionen sind voneinander vollkommen getrennt, so daß eine Senkung voneinander unabhängig ist.At the connection points of the side walls a forming components 1 Je a pillar 8 is arranged, to which the longitudinal sides of the components 1 are supported. The lower part 8a of each pillar 8 is provided with a central cavity, while the cross section of the upper part 8b is U-shaped. The pillars 8 are fitted in prefabricated reading foundations 9, more precisely in the rib 9d located in their center, which rests on the sub-concrete 9b. The reading foundations, the pillars and the structural elements 1 are combined by the strip-like amber Llonolitkörper 9 a to a single combined basic body unit. The nozzles 9 are also located on the sub-concrete layer 9b. From Pig. 1 is good to see that the above-detailed foundation of the pillars S and the side wall a is separated from the foundation of the bottom plate b of the basin, i. the differently loaded structures are completely separated from each other, so that a reduction is independent of each other.

Wie aus Pig. 1 und 2 ferner ersichtlich, belastet die an sich bekannte Deckenkonstruktion 10 nicht die Pfeiler 8. Neben dein umlaufenden Ringanker 11 wirkt lediglich die vom Wasserdruck herrührende Belastung über die Seitenwand auf die Pfeiler 8 ein.· Die von der Deckenkonstruktion 10 kommende Belastung wird durch die Stahlbeton-Bauelemente 1 über das kombinierte Streifenfundament 4 auf den Baugrund übertragen. Außerhalb der Beckenseitenwände a ist mit Hilfe der an die Pfeiler befestigten Versteifungsdrähte eine Y/är-Like from Pig. 1 and 2, the per se known ceiling construction 10 does not burden the pillars 8. Besides the circumferential ring anchor 11, only the load resulting from the water pressure acts on the pillars 8 via the side wall Reinforced concrete components 1 on the combined strip foundation 4 transferred to the ground. Outside the tank side walls a, a reinforcing wire is attached with the help of stiffening wires attached to the pillars.

- 17 -- 17 -

218 656218 656

meisolierschicht 12 angeordnet, die aus Schwannziegelplatten hergestellt werden kann. Zusammen mit der durch die Beckenwand a eingeschlossenen Luftschicht gewährleistet sie eine hervorragende Wärmeisolierung.meisolierschicht 12 which can be made of Schwannziegelplatten. Together with the trapped by the pool wall a layer of air ensures excellent thermal insulation.

Zum Sammeln und Ableiten des in die Kanäle 2 der Stahlbeton-Bauelemente 1 der Seitenwand a und der Bodenplatte Id einsickernden V/asser3 dient der in den kombinierten Grundkörper 4 eingebettete und zur Wand α parallel verlaufende Sojnmelkanal 13· Dieser Sammelkanal 13 wird beispielsweise durch ein Kunststoffrohr (Pla3trohr) gebildet. In diesen Kanal 13 münden die sich an die Kanäle 2 anschließenden Leitungen 13a und 13b. Anstelle der Rohr-Lösung kann natürlich auch ein Rinnensystem oder eine sonstige an sich bekannte Ausführung verwendet werden.For collection and discharge of the seep into the channels 2 of the reinforced concrete components 1 of the side wall a and the bottom plate Id V / asser3 embedded in the combined base body 4 and the wall α parallel running Sojnmelkanal 13 · This collecting channel 13 is for example by a plastic pipe (Pla3trohr) formed. In this channel 13 which are connected to the channels 2 lines 13a and 13b open. Of course, instead of the tube solution, a gutter system or any other known design can be used.

Zwischen dem kombinierten Streifenfundament 4 und der Bodenplatte b ist eine Dilatationsfuge 14 vorgesehen, in die eine Kunststoffkittausfüllung 14a eingebracht ist« Diese ermöglicht infolge ihrer elastischen Eigenschaften Gov/egungen, die aus den Senkungen der unterschiedlich belasteten Konstruktionen herrühren und gewährleistet gleichzeitig eine vollkommene Wasserabdichtung.Between the combined strip foundation 4 and the bottom plate b, a dilatation joint 14 is provided, in which a Kunststoffkittausfüllung 14 a is introduced "This allows due to their elastic properties Gov / educations, resulting from the subsidence of differently loaded structures while ensuring a perfect waterproofing.

Die Art und V/eise des Anschlusses der Längsseiten der quaderförmigen Stahlbeton-Bauelemente 1 zeigt Pig. 2. Die Stahlbeton-Bauelemente 1 sind an ihren Läng3kanten mit J3inschnitten 15b und Rippen 15a versehen. Beim Aneinanderfügen beider Bauelemente 7 entsteht zwischen ihnen ein im wesentlichen schwalbenschwanzartiger Hohlraum 15. In diese Hohlräume 15 wird je ein Betonstahlstab 16 eingesetzt und anschließend mit Honolitbeton 17 - vorteilhafterweise mit kunstharzgebundeneai Beton - ausgefüllt, wojrdurch eine wasserdichte Verbindung der Bauelemente entsteht.The type and connection of the connection of the longitudinal sides of the cuboidal reinforced concrete building elements 1 is shown by Pig. 2. The reinforced concrete components 1 are provided at their longitudinal edges with J3inschnitten 15 b and ribs 15 a. When joining both components 7 creates between them a substantially dovetail-like cavity 15. In these cavities 15 is ever a reinforcing steel rod 16 is inserted and then filled with Honolitbeton 17 - advantageously with kunstharzgebundeneai concrete - wojrdurch a waterproof connection of the components.

218 656218 656

Die Verbindung der Bauelemente 1*, die die Bodenplatte 8b bilden, d.h. v/o die Hohlräume 2 ineinander übergehen, ist dem rechtsseitigen Teil von Pig. 1 und Pig. 2a dargestellt. Gemäß der Variante in Pig. 1 ist die zwischen den benachbarten Bauelementen 1 vorhandene Puge der Breite £ mit Stahlbeton 2a ausgefüllt, der auch in die , in dieser Linie liegenden Kanäle 2 eindringen kann. Diese Lösung wird allgemein bei geringeren Belastungen gewählt. Bei größeren V/asserlaaten wird in die in eine Linie fallenden Kanäle 2 ein die Kontinuität gewährleistendes Rohrstück 2b eingesetzt und dann der Spalt mit der Breite £ unterhalb und oberhalb des Rohrstückes mit Kunststoffbeton 20 ausgefüllt.The connection of the components 1 * forming the bottom plate 8b, i. v / o the cavities 2 merge into each other, is the right-hand part of Pig. 1 and Pig. 2a shown. According to the variant in Pig. 1, the gap between the adjacent components 1 of width £ is filled with reinforced concrete 2a, which can also penetrate into the channels 2 lying in this line. This solution is generally chosen at lower loads. In the case of larger seedlings, a pipe section 2b ensuring continuity is inserted into the channels 2 falling in a line, and then the gap of width £ below and above the pipe section is filled with plastic concrete 20.

Gemäß Pig. 1 und Pig. 2 sind die durch Pfeiler abgestützen Y/andelernente in Querrichtung lasttragend und der obere Ringanker 11 nur in geringem LIaße belastet. Diese Beckenkonstruktion eignet sich zum Beispiel vorzüglich für. Trinkwasser-Speicher, da hinsichtlich der Gewährleistung der .V/ac scr undurchlässigkeit diese Abstützungsart die idealste ist.According to Pig. 1 and Pig. 2 are supported by pillars Y / andelernente in the transverse direction load-bearing and the upper ring anchor 11 loaded only in small LIaße. This pelvic construction is excellent for example. Drinking water storage, since this type of support is the most ideal in terms of ensuring .V / ac scr impermeability.

Die in Pig. 3 und 4 dargestellte Konstruktion sti;.:;'it ber:U.jlich der Bauelemente, die die ßeitenwände und den Beckenboden bilden, mit der Ausführung nach Pig. 1 und 2 überein, d.h. daß die Kanäle der Scitenwände auch hier eine senkrechte Lage aufweisen. Gleiche Konstruktionselemente sind mit den gleichen in Pig. 1 und 2 benutzten Bezugsnummern bezeichnet. Die Abweichung der Konstruktion nach Pig. 3 und 4 gegenüber der in Pig. 1 und 2 besteht darin, daß die Stahlbeton-Bauelemente 1 der Seitenwand a unten und oben eingespannt sind und als eine in Längsrichtung lasttragende Konstruktion angesehen werden können. Die Y/andelemente 1 sind unten im Streifenfundament 4a eingespannt, in dem auch der Sammelkanal in der Porm einer Rinne 13 ausgebildet ist. Oben ist der Ringanker 11a so ausgebildet, daß er zum Teil in die Kanäle 2 eingreift. Hier ist demgemäß der Ringanker 11a belastet. Bei der Ausgestaltung der Bodenplatte liegt kein Unterschied vor.The one in Pig. FIGS. 3 and 4 show the construction of the components forming the side walls and the pelvic floor, with the construction of Pig. 1 and 2, i. that the channels of the Scitenwände also have a vertical position here. Same construction elements are the same in Pig. 1 and 2 used reference numbers. The deviation of the construction according to Pig. 3 and 4 compared to the one in Pig. 1 and 2 is that the reinforced concrete components 1 of the side wall a are clamped at the top and bottom and can be regarded as a load-bearing design in the longitudinal direction. The Y / andelemente 1 are clamped at the bottom of the strip foundation 4a, in which the collecting channel is formed in the Porm a groove 13. Above the ring anchor 11a is formed so that it partially engages in the channels 2. Here, accordingly, the ring anchor 11a is loaded. In the design of the bottom plate there is no difference.

_ IO_ IO

218 656218 656

Als äußere Stützkonstruktion werden in den Ringanker 11a eingespannte raonolitische Pfeiler 8c verwendet, die jedoch nicht je Stahlbetonelement 1, sondern in wesentlich größeren Abständen angeordnet sind. Die Grundkörper der monolitischen Pfeiler wurden mit der Bezugsnummer 9a bezeichnet. Zur besseren Übersichtlichkeit wurde die Deckenkonstruktion nicht dargestellt.As an outer support structure in the ring anchor 11a clamped raonolitische pillar 8c are used, but not each reinforced concrete element 1, but at substantially greater intervals are arranged. The bodies of the monolithic pillars have been designated by the reference number 9a. For better clarity, the ceiling construction was not shown.

Auch bei dieser Lösung ist gut zu sehen, daß die Gründung der unterschiedlich belasteten Konstruktionsteile vollkommen voneinander getrennt sind.Even with this solution, it is easy to see that the foundation of the differently loaded construction parts are completely separated from each other.

Die Konstruktion nach Pig. 3 und 4 wird insbesondere zum Bau von V/aoserspoicherbecken eingesetzt, die in die Erde eingesenkt werden.The construction according to Pig. FIGS. 3 and 4 are used in particular for the construction of vaerosco tanks, which are sunk into the ground.

Bei der Ausführung nach Pig. 5 und 6 bestehen die Seitenwände ει wiederum aus quaderförmig vorgefertigten·Stahlbeton-Bauelementen 1, die jedoch mit ihrer Längsseite aufgelegt wurden. Die Ausbildung der Bodenplatte b bleibt unverändert. In der Seitenwand a haben domgemäß die Kanäle 2 im wesentlichen eine waagerechte Lage. Aus dem Grunde "im wesentlichen", da die Kanäle in einer Richtung mit einemgeringen, z.B. 1 Jeigen Gefälle verlaufen, um co einen ablauf der Sickerwasser zu gewährleisten. Demtentoprechend müssen bei dieser Ausführung in den I.Ionolitbetonpfeilern Se auch senkrechte Sammelrohre 13e zum Sammeln dc3 durchsickernden V/aasers vorgesehen werden, die an den im Grundkörper 4d vorgesehenen Sammelkanal 13d angeschlossen sind. Aus den Kanälen 2 der Bodenplatte b wird da3 durchsickernde V/asoer durch die Leitungen 13 g über die Sammelleitungen 13f abgeleitet, die ebenfalls an den Sammelkanal 13d angeschlossen sind. Die aus Plastrohren gefertigten Leitungen 13e, 13f und 13g werden durch die gestrichelt gezeichneten Pfeile dargestellt, die gleichzeitig die Stromungsrichtung anzeigen.In the execution of Pig. 5 and 6, the side walls ει again consist of cuboid prefabricated · reinforced concrete building elements 1, which, however, were placed with their longitudinal side. The formation of the bottom plate b remains unchanged. In the side wall a, domes 2, the channels have a substantially horizontal position. For the reason "substantially", since the channels are one-way with one, e.g. 1 gradient to ensure co-drainage of seepage water. Demtentoprechend must in this embodiment in the I.Ionolitbetonpfeilern Se also vertical manifolds 13e for collecting dc3 oozing V / aasers are provided, which are connected to the provided in the main body 4d collection channel 13d. From the channels 2 of the bottom plate b da3 seeping through v / asoer through the lines 13 g via the manifolds 13f derived, which are also connected to the collecting channel 13d. The pipes 13e, 13f and 13g made of plastic pipes are represented by the dashed arrows, which simultaneously indicate the direction of flow.

"20~ 218 656" 20 ~ 218 656

Die Bodenplatte b_ ruht auf der bewehrten Unterbetonplatte 5, und die Seitenwände a auf dem Streifenfundament 4b. Die vorgefertigten Bauelemente 1 der Seitenwand a sind an die monolitischen, einen T-Querschnitt aufweisenden Pfeiler 8e angeschlossen. Die Gründungen der Wände und des Bekkenboden3 sind auch in diesem Falle wieder voneinander getrennt. Die Konstruktion weicht von den vorgehenden dadurch ab, daß sie nicht abgedeckt ist und keinen Ringanker besitzt. Sie wird in erster Linie zum Bau von Badebecken verwendet.The bottom plate b_ rests on the reinforced base concrete plate 5, and the side walls a on the strip foundation 4b. The prefabricated components 1 of the side wall a are connected to the monolithic, a T-section having pillar 8e. The foundations of the walls and the Bekkenboden3 are again separated from each other in this case. The construction differs from the previous one in that it is not covered and has no ring anchor. It is used primarily for the construction of baths.

Im Sinne der Erfindung kann auch ein Becken mit einer Segmentseitenwand, einem sich an die Erdböschung abstützenden schrägeji Abschnitt und einer waagerechten Bodenplatte errichtet werden, das bis zur Hälfte in das Erdreich eingesenkt und insbesondere für Wasserspeicher mit größeren Abmessungen verwendet wird. Sowohl die Seitenwände al3 auch die Bodenplatte werden ebefnalls aus quaderförnigen vorgefertigten Stahlbetonbauelementen 1 hergestellt, Die sonstigen Detaillösungen 3ind mit den bereits beschriebenen indentisch.For the purposes of the invention, a basin with a segment side wall, a supported on the Erdböschung schrägeji section and a horizontal base plate can be built, which is half sunk into the ground and used in particular for water storage with larger dimensions. Both the side walls al3 and the bottom plate are ebefnalls made of cuboid prefabricated reinforced concrete elements 1, The other detail solutions are 3indent with the already described.

In Pig. 7 und 8 13t das Verhalten des unter Belastung (V/aaserdruck) stehenden, in Querrichtung lasttragenden vorgespannten Stahlbeton-Bauelementes 1 eines Beckens dargestellt. Der Wasserdruck wird durch den Pfeil X angezeigt. Unter der Wirkung dieses Druckes verformt sich das Stahlbeton-Bauelement 1 gemäß der unterbrochenen Linie la, d.h. daß die mit dem Wa3ser in Berührung kommende Pläche der Druckgurt, die äußere Pläche hingegen der Zuggurt des Bauelementes ist. Wird in diesem Druckbereich ein ausgewähltes Elementarteilchen v_ untersucht, so wirkt darauf aus der einen Richtung der aus der Wirkung der Kraft χ herrührende Druck P2, und aus der anderen Richtung der aus der zu den Kanälen 2 parallel gerichteten Vorspannung herrührende Druck p-^.In dessen Ergebnis steht der eben mitIn Pig. FIGS. 7 and 8 show the behavior of the load-bearing (V / aaserdruck), transversely load-bearing prestressed reinforced concrete structural element 1 of a basin. The water pressure is indicated by the arrow X. Under the effect of this pressure, the reinforced concrete element 1 deforms according to the broken line la, ie that the surfaces coming into contact with the wafer are the pressure belt, whereas the outer surface is the tension belt of the component. If a selected elementary particle v_ is examined in this pressure range, the pressure P 2 resulting from the action of the force χ acts on it from one direction, and the pressure p 2 resulting from the bias directed parallel to the channels 2 acts on the other direction. In the result of which is just with

- 21 -- 21 -

21" 21 8 656 21 "21 8 656

dem Wasser in Berührung stehende Oberflächenberexch der Seitenwand a des Beckens unter einem in zwei Richtungen wirkenden Druck, Demzufolge ist eine Bruchgefahr praktiach vollkommen ausgeschaltet. Der Bereich der inneren Fläche des Beckenwand ist maximal dicht, d.h. seine Wasserundurchlässigkeit optimal. Die eventuell durchsickernde geringe Wassermenge läuft durch die Kanäle 2 ab und erscheint demgemäß in keiner Weise, auf der Außenfläche. Daraus folgend sind keine weiteren zusätzlichen Wasserisolierungsmaßnahmen erforderlich.surface area of the side wall a of the tank in contact with the water under a bi-directional pressure. As a result, a risk of breakage is virtually eliminated. The area of the inner surface of the pelvic wall is maximally dense, i. its waterproofness optimal. The possibly seeping small amount of water passes through the channels 2 and thus appears in any way, on the outer surface. As a result, no further additional water insulation measures are required.

Es ist leicht einzusehen, daß bei jeder Ausführungsvariante - d.h. auch bei einer längsgerichteten Belastung der Bauelemente - die von der Vorspannung herrührende Beanspruchung in Abhängigkeit vom Wasserdruck so groß gewählt werden kann, daß eine Rißfreiheit auf der inneren, mit dem Wasser in Berührung koranenden Seite gesichert iat und das das in das Innere der Wand unter der Bodenplatte gelangende Wasser durch die Kanäle 2 frei ablaufen kann.It will be appreciated that in each embodiment - i. even with a longitudinal load of the components - the stress resulting from the bias depending on the water pressure can be chosen so large that a crack-free secured on the inner, koranenden with the water in contact side iat and that in the interior of the wall under the Bottom plate reaching water through the channels 2 can drain freely.

Der in Fig. 9 dargestellte perspektivische Aufriß zeigt,, welchen -hohen ästhetischen Anforderungen mit Hilfe der erfindungsgemäßen Lösung entsprochen werden kann.The perspective elevation shown in Fig. 9 shows, which -high aesthetic requirements can be met by means of the solution according to the invention.

Das in den Pig. 11 bis 13 dargestellte Becken besitzt mittelgroße Abmessungen (Tiefe 2,0 bi3 3,0 m/ und kann für Sportwettbewerbe eingesetzt werden. Die Seitenwände a und die Bodenplatte b_ des Beckens sind ebenfalls aus quaderförmigen,plattenartigen, vorgefertigten Stahlbeton-Bauelementen 1 aufgebaut, in denen in Längsrichtung Kanäle 20 verlaufen. Diese Kanäle haben einen eckigen Querschnitt, wodurch das Volumen der Kanäle größer wird und im Vergleich zu den Kanälen mit Kreisquerschnitt wesentliche Materialeinsparungen erzielt werden. In den Seitenwänden b_ verlaufen diese Kanäle 20 waagerecht. An jeder Anschlußstelle, wo zwischen zwei Stahlbeton-Bauelementen 1 eine senkrechteThat in the Pig. The basin shown in Figures 11 to 13 has a medium size (depth 2.0 to 3.0 m / ft) and can be used for sports competitions.The side walls a and the bottom plate b_ of the pool are also constructed of rectangular slab-like prefabricated reinforced concrete elements 1, These channels have a polygonal cross-section which increases the volume of the channels and achieves substantial material savings compared to the channels of circular cross-section, in the sidewalls b_ these channels 20 extend horizontally two reinforced concrete elements 1 a vertical

- 22 -- 22 -

218 656 218 656

Fuge entsteht, ist ein monolitischer Stahlbetonpfeiler vorgesehen, der die anliegenden Stahlbeton-Bauelemente 1 abstützt. Die Bauelemente 1 sind demzufolge in Längsrichtung lasttragend. Die gleiche Lage, wie die Kanäle 20, weisen auch die Spanndrähte 3 auf. In diesem Falle ist nur eine in einer Richtung erfolgende Spannung erforderlich. Die Spanndrähte 3 liegen in den Rippen des Bauelementes, d.h. daß sie eine größere Betondeckung als die Betondeckung der Spanndrähte anderer plattenartiger, vorgespannter, vorgefertigter Stahlbeton-Bauelemente aufweisen.Fugue is created, a monolithic reinforced concrete pillar is provided, which supports the adjoining reinforced concrete elements 1. The components 1 are therefore load-bearing in the longitudinal direction. The same position as the channels 20, also have the tension wires 3. In this case, only unidirectional tension is required. The tension wires 3 lie in the ribs of the component, i. that they have a greater concrete cover than the concrete cover of the tension wires of other plate-like, prestressed, prefabricated reinforced concrete components.

Der untere Teil der Seitenv/and a besteht aus breiteren Stahlbe.ton-Bau-elementen 2, wodurch im Becken ein rundum verlaufender Treppenabsatz 22 entsteht. Diese Anordnung ist konstruktiv günstiger, da die stärkeren, eine größere Tragfähigkeit besitzenden, Bauelemente unten, an den Stellen mit höherer Belastung liegen. Das Aufsetzen der Bauelemente auf die schmale Längsseite ist auch mit dem Vorteil verbunden, daß in den Scitcnwänden a weniger Fugen, entstehen, als wenn die Bauelemente mit ihrer schmaleren, kürzeren Seitenfläche aufgesetzt werden, d.h. die Kanäle 2 senkrecht verlaufen. Dadurch kann die Gefahr der '.7a3serdurchlässigkeit weiter verringert werden.The lower part of the Seitenv / and a consists of wider Stahlbe.ton-construction elements 2, whereby in the basin an all-round extending landing 22 is formed. This arrangement is structurally more favorable, since the stronger, a greater carrying capacity possessed, components below, in the places with higher load. The placement of the components on the narrow longitudinal side is also associated with the advantage that in the Scitcnwänden a fewer joints, arise than when the components are placed with their narrower, shorter side surface, i. the channels 2 are perpendicular. This can further reduce the danger of permeability.

Die monolitischen Stahlbetonpfeiler 80 besitzen einen T-förmigen Querschnitt und dienen zur Abstützung der benachbarten Bauelemente 2 entlang ihrer senkrechten Kanten. Gleichzeitig füllen sie die Fuge zwischen je zwei Stahlbetonbauelementen 2 aus. Ihre Innenfläche bildet mit der Innenfläche der Seitenwand-Bauelemente eine Linie. Ihre Außenfläche verläuft hingegen in- Fortsetzung der Außenkante des aus monolitischem Stahlbeton gefertigten Streifenfundamentes 40 siehe Fig. 12. Das Streifenfundament ist hier von der Bodenplatte nicht getrennt. Eine der-The monolithic reinforced concrete pillars 80 have a T-shaped cross-section and serve to support the adjacent components 2 along their vertical edges. At the same time they fill the gap between two reinforced concrete elements 2. Its inner surface forms a line with the inner surface of the sidewall components. On the other hand, its outer surface runs along the outer edge of the strip foundation 40 made of monolithic reinforced concrete, see FIG. 12. Here, the strip foundation is not separated from the base plate. One of the-

- 23 -- 23 -

218 656218 656

artige Konstruktion wird vorrangig bei günstigen Bodenverhältnissen eingesetzt, die gegebenenfalls auch durch einen Austausch des Bodens erreicht werden« Die am Rand liegenden -StahlbetonTBauelemente 1 der atatisch als Trägernetz funktionierenden Bodenplatte sind an der inneren Seite des Streifenfundemantes 40 angeschlossen, das gleichzeitig als unterer Ringanker dient, der durch die Pfeiler 8C versteift wird. Der Teil 80a (der Schenkel des T) des Stahlbetonpfeilers 80 reicht bis in die Breite c der Fuge zwischen zwei benachbarten Stahlbeton-Bauelementen 1 der Bodenplatte b_ hinein (Pig. 12) und geht durch das als Ringanker dienende Streifenfundament 40, In der Bodenplatte b laufen quer zur Längsrichtung der Kanäle 2 monolitische Stahlbetonbalken 2a, deren Beton beim Betonieren auf beiden Seiten auch in die Kanäle 2 der Bauelemente 1 hineinfließt wie da.s in Pig. 12 gut sichtbar ist. (Den gleichen Zusammenhang zeigt Pig. 2a in.einem anderen Schnitt). Die Gründung entspricht in den sonstigen Einzelheiten der gemäß Pig. 1, d.h. daß unter der Bodenplatte b und dem Streifenfundamont 40 das Stahlbeton-Unterbett 5 und unter diesem die oandige Kieaschicht 7 liegt. Zwischen dem Stahlbetonunterbett 5 und der Bodenplatte Ib ist eine Kunststoffolie vorgesehen.This construction is primarily used in favorable soil conditions, which may also be achieved by replacing the floor. "The peripheral steel concrete elements 1 of the bottom plate, functioning atomatically as a support net, are connected to the inner side of the strip foundation edge 40, which also serves as the lower ring anchor. which is stiffened by the pillars 8C. The part 80a (the leg of the T) of the reinforced concrete pillar 80 extends into the width c of the joint between two adjacent reinforced concrete components 1 of the bottom plate b_in (Pig. 12) and passes through the strip anchorage 40 serving as a ring anchor, In the bottom plate b Run transversely to the longitudinal direction of the channels 2 monolithic reinforced concrete beams 2a, the concrete in concreting on both sides also flows into the channels 2 of the components 1 as da.s in Pig. 12 is clearly visible. (The same relationship is shown in Fig. 2a in another section). The foundation corresponds in the other details according to the Pig. 1, that under the bottom plate b and the strip foundation 40, the reinforced concrete sub-bed 5 and below this the oandige Kieaschicht 7 lies. Between the reinforced concrete underbed 5 and the bottom plate Ib a plastic film is provided.

Ein Vorteil dieser Beckenausführungen besteht darin, daß sie erforderlichenfalls eine einfache Erweiterung des Bekkens ermöglicht.An advantage of this type of basin is that it allows, if necessary, a simple extension of the Bekkens.

In der Seitenwand und in der Bodenplatte liegen die Kanäle 2 in einer Linie und können so durch die in den Beton der Balken 2a bzw. de.r Pfeiler 80 eingebetteten Rohratücke 2b verbunden werden (Pig. 12). In den Pfeilern 80 sind senkrechte Sammelrohre 13e vorgesehen, An-das durch die Rohrstücke 2b, die Kanäle 2 und die Sammelrohre 13e gebildete System schließen sich die au3 einem oder mehreren Pfeilern 80 heraustretenden Lüftungsrohre 23 an. Das Kanalsystem derIn the side wall and in the bottom plate, the channels 2 are in line and can thus be connected by the tubular pieces 2b embedded in the concrete of the beams 2a and 80, respectively (Fig. 12). Vertical manifolds 13e are provided in the pillars 80. At the system formed by the pipe sections 2b, the ducts 2 and the manifolds 13e, the ventilation ducts 23 emerging from one or more pillars 80 join. The channel system of

21 8 65621 8656

Bodenplatte b wird durch die im Streifenfundament 40 vorgesehenen 'Lüftungsrohre 24 mit der äußeren Atmosphäre verbunden. Auf diese Weise wird eine entsprechende Belüftung gewährleistet. Da die Beckenhöhe größer ist, kommt auch die Schietwirkung zur Geltung. So ist die Belüftung vollständig.Base plate b is connected to the outside atmosphere by the venting tubes 40 provided in the strip foundation 40. In this way, a corresponding ventilation is ensured. Since the pelvic height is greater, the Schiet effect also comes into its own. So the ventilation is complete.

Die in den vorgefertigten Stahlbeton-Bauelemente 1 waagerecht verlaufenden obersten Kanäle 20 können als Rinnen entlang deroberen Ränder ausgebildet werden. Dazu wird die oberste Rippe der Stahlbeton-Bauelemente 1 stellenweise a.B. alle 3 bis 4 m auf einem höchstens 40 cm langen Abschnitt durchgebrochen - die Durchbrüche sind mit der Bezugsnummer 25 bezeichnet - (Pig. 11). Haben die Kanäle einen Kreisquerschnitt, so ist eine Abänderung nicht erforderlich. Im Falle de3 Beispiels gemäß Pig. Il wird jedoch in den obersten Kanal 20, der einen vieleckförraigen Querschnitt besitzt, ein Kunststoffrohr 26 eingelegt. Da3 durch die Durchbrüche 25 in die Rinne 27 eindringende V/asser kann mittels eines nicht dargestellten RohranschlU3se3 in den Ausgleichsbehälter geleitet werden, der mit dem Becken zusammengebaut ist. Die durch die Durchbrüche gebildeten Öffnungen werden von einem (nicht dargestellten) Gitter abgedeckt. Dao Gitter 1st an die Kunststeinverkleidung angeschlossen, die an die Rander des Durchbruches 24 vorgesehen ist und bei einer entsprechenden Profilge3taltung den gespannten Wasserspiegel im Bekken sichert. Bei den herkömmlichen Ausführungen war die Fertigstellung der Rinne ziemlich arbeitsaufwendig.The uppermost channels 20 running horizontally in the prefabricated reinforced concrete building elements 1 can be formed as channels along the upper edges. For this purpose, the uppermost rib of the reinforced concrete elements 1 is broken in places every 3 to 4 m on a section of at most 40 cm long - the openings are designated with reference numeral 25 - (Pig. 11). If the channels have a circular cross-section, then a modification is not required. In the case of the example according to Pig. Il, however, a plastic tube 26 is inserted into the uppermost channel 20, which has a vieleckförraigen cross-section. The water entering the channel 27 through the apertures 25 can be directed by means of a pipe connection 3, not shown, into the expansion tank, which is assembled with the tank. The openings formed by the apertures are covered by a grid (not shown). Dao 1st grid connected to the artificial stone panel, which is provided on the rims of the opening 24, and secures the tensioned water level at a corresponding Profilge3taltung in Bekken. In the conventional designs, the completion of the gutter was quite laborious.

Muß auf Grund der betrieblichen Anforderungen entlang der Außenseite der Beckenwände ein Gang ausgebaut werden, so kann diese Aufgabe verhältnismäßig einfach gelöst werden.Must be expanded due to the operational requirements along the outside of the pool walls a gear, so this task can be solved relatively easily.

- 25 -- 25 -

-25- 21 8 656-25- 21 8 656

Bei einem in das Erdreich eingesenkten Becken wird die Stahlbeton-Platte 5 über das Streifenfundament 40 hinaus ausgebaut (Pig, 11), die dann den Boden des Kontrollganges 28 bildet. An dem Außenrand der Platte 5a schließt sich eine stabilisierende Erdböschung 28 an, die mit einem monolytischen Stahlbeton-Ringanker 21 abschließt. Am oberen Ende der Pfeiler 80 ist ebenfalls ein aus monolytischem Stahlbeton gefertigter Ringanker 11 vorgesehen, der diese Pfeiler zusammenhält. Die Ringanker 11 und 21 werden durch die Decke 10 überbrückt, die einerseits den Kontrollgang 28 von oben abschließt, andererseits neben dem Becken als Gehsteig dient. Die Decke 10 kann au3 den gleichen Stahlbeton-Bauelementen 20 hergestellt werden, aus denen die Bodenplatte b bzw. die Wände a gefertigt vmrden.In a basin lowered into the ground, the reinforced concrete slab 5 is removed beyond the strip foundation 40 (Pig, 11), which then forms the bottom of the inspection passageway 28. At the outer edge of the plate 5 a is followed by a stabilizing Erdböschung 28, which terminates with a monolithic reinforced concrete ring anchor 21. At the upper end of the pillar 80 also made of monolithic reinforced concrete ring anchor 11 is provided which holds these pillars together. The ring anchors 11 and 21 are bridged by the ceiling 10, which on the one hand completes the inspection passage 28 from above, on the other hand serves as a sidewalk next to the pool. The ceiling 10 can be made of the same reinforced concrete building elements 20 from which the floor slab b or walls a are made.

Bei einem auf Terrainniveau aufgebauten Sehwimmbecken ergibt sich unter dem Gehsteig eine Höhe von etwa 2,6 m, go daß in den neben den SoitenwUnden entlanglaufenden Räumen Ankleide- und Sizialräumc sowie für die Unterbringung der maschinellen Einrichtungen geeignete Kammern usw. ausgebildet werden können. Der Gehsteig ist dann natürlich entsprechend abzustützen und zu verglasen. Der Vorteil einer Anordnung auf Torrainniveau besteht in einem minimalen Aufwand für Erdarbeiten, dem Wegfall der Entwässerung und der eventuellen Auslösung der öffentlichen Werke sowie in der von der Erdoberfläche aus vornehmbaren Bauausführung.In a built-up to Terrainniveau swimming pool results under the sidewalk, a height of about 2.6 m, go that in the running along the SoitenwUnden rooms dressing and Sizialräumc as well as for the accommodation of the machinery suitable chambers etc. can be formed. Of course, the sidewalk should be supported and glazed accordingly. The advantage of an arrangement at Torrainniveau consists in a minimum effort for earthworks, the elimination of drainage and the eventual triggering of the public works and in the vornehmbaren from the earth's surface construction.

Die Ausführung der waagerechten Fugen in den Seitenwänden 9 ist in einem größeren Maßstab in Pig. 13 zu sehen. In die Puge wird von der Außenseite das Hikrozellengummiband 30 eingelegt. Weiter innen ist die Betonausfüllung 31 vorgesehen, die gleichzeitig auch den Treppenabsatz 22 bildet. Der zum 'Ausfüllen benutzte monolitische Beton hat bei-The execution of the horizontal joints in the side walls 9 is on a larger scale in Pig. 13 to see. In the Puge from the outside of the Hikrozellengummiband 30 is inserted. Further inside, the concrete filling 31 is provided, which also forms the landing 22 at the same time. The monolithic concrete used for filling has

21 β 65621β656

spieloweise die Qualität B28O. in den Beton ist in Längsrichtung ein umlaufender Bestonstahl 32 eingelegt, der den vollständigen Zusammenhalt der übereinander angeordneten Stahlbeton-Bauelemente 1 in der gleichen Weise fördert, v/ie die an den beiden Rändern vorgesehenen Rippen 33 und 34, zwischen denen sich die Betonausfüllung 31 (Betonkern) befindet. Da3 Mikrozellengummiband 30 wird durch die oberen Stahlbeton-Bauelemente 1 zusammengedrückt, wodurch seine Dichte und demzufolge seine V/aaaorundurchlässigkeit weiter ansteigt. Anstelle des Mikrozellengummibandes kann auch ein Bleiblechstreifen verwendet werden.playfully the quality B28O. into the concrete a circumferential Bestonstahl 32 is inserted in the longitudinal direction, which promotes the complete cohesion of stacked reinforced concrete components 1 in the same way, v / ie provided on the two edges ribs 33 and 34, between which the concrete filling 31 (FIGS. Concrete core) is located. The microcellular rubber band 30 is compressed by the upper reinforced concrete components 1, whereby its density and, consequently, its v / aaaorundurchlässigkeit further increases. Instead of the microcellular rubber band, a lead-sheet strip can also be used.

In den Pig. 14 bis 17 sind Flüssigkeitsspeicherbecken größerer Tiefe dargestellt, bei denen die Stahlbeton-Bauelemente 1 der Seitenwände a auf ihrer schmalen Längsseite aufliegen, d.h. in der Längsrichtung lasstragend sind. Die Kanäle 2 verlaufen waagerecht, Auf der linken und rechten Seite der Fig. 14 und 15 sind voneinander abweichende Ausführungsvarianten au sehen. Bei.der linksseitigen Variante ist bei der senkrechten Fuge jedes Seitenv;and-3auelementanochlusseo von außen ein monolitischer Stahlbetonpfeiler 80 angeordnet, wobei die Pfeiler im Streifenfundament 40 verankert sind. Diese Konstruktion ist mit der in Fig. 11 und 12 bereits beschrieben identisch. Die Zwischenpfeiler 80 sowie die Eckpfeiler 35 sind oben durch einen Ringanker 11 miteinander verbunden. Die Bodenplatte b ist auch wie vom Fundament 40 nicht getrennt. Eine Abweichung stellt die Anordnung eines zwi3chenliegcnden Ringankers 11a dar, der zusammen mit den Pfeilern 80, dem oberen Ringanker 11 und das al3 unteren Ringanker dienende Streifenfundament 40 ein monoliti3ches Stahlbeton-Trägernetz bildet, das die aus vorgefertigten Stahlbeton-Bauelementen 1 bestehenden Seitenwände a. und Bodenplatte Jb des Beckens wie ein geschlossener Rahmen umfaßt. Der Zwischenringanker und/oder die Pfeiler können auch au3 vorgefertigten Stahlbeton- oder Stahlbalsiken bestehen.In the pig. 14-17, liquid storage tanks of greater depth are shown in which the reinforced concrete building elements 1 of the side walls a rest on their narrow longitudinal side, i. are laser-bearing in the longitudinal direction. The channels 2 are horizontal, on the left and right side of Figs. 14 and 15 are different embodiments see au. In the case of the left-hand variant, a monolithic reinforced concrete pillar 80 is arranged on the outside of the vertical joint of each side wall and the exterior, whereby the pillars are anchored in the strip foundation 40. This construction is identical to that already described in FIGS. 11 and 12. The intermediate piers 80 and the corner posts 35 are connected to each other at the top by a ring anchor 11. The bottom plate b is also not separated from the foundation 40. One variation is the arrangement of a two-way ring anchor 11a which, together with the posts 80, upper ring anchor 11 and strip anchor 40 serving as the lower ring anchor, forms a monolithic reinforced concrete girder net constituting the prefabricated reinforced concrete elements 1 side walls a. and bottom plate Jb of the pelvis as a closed frame. The intermediate ring anchor and / or the pillars may also consist of pre-fabricated reinforced concrete or steel balers.

. - 27 -, - 27 -

21 8 65621 8656

Der obere Ringanker und das Streifenfundament müssen jedoch wegen der Zusammenarbeit aus monolitischem Stahlbeton gefertigt werden. Zu erwähnen ist noch, daß die un- · teren - waagerecht nach innen gehenden - Teile der Pfeiler 80 (siehe auch die Pig. 11 und 12) auch in die Bodenplatte b_; hineinreichen, d.h. die Pfeiler in die Bodenplatte einspannen und die auf den am meisten belasteten unteren Ringankern entfallende Belastung dadurch vermindern, daß sie seine Spannweite herabsetzen. Diese Konstruktion ist zweckmäßigerweioe dann zu verwenden, wenn das Becken auf einem gut belastbaren, eine gleichmäßige Körnung aufweisenden Boden errichtet wird. Seine 7/ände sind höchstens 3 bis 4 Bauelenente hoch» Da3 Becken ist etwa 3>0 bis 4,0 m tief.However, the upper ring anchor and the strip foundation must be made because of the cooperation of monolithic reinforced concrete. It should also be mentioned that the lower-horizontally inward-going parts of the pillars 80 (see also the Pig. 11 and 12) are also in the bottom plate b_; extend, i. Clamp the pillars into the bottom plate and reduce the load on the most loaded lower ring anchors by reducing its span. This construction is suitably used when the basin is built on a well-loadable, even-grained soil. Its 7 walls are at most 3 to 4 construction elements high »Da3 basin is about 3> 0 to 4.0 m deep.

Da das auf der rechten Seite von Pig. 14 und 15 dargestellte Becken funktionell zur Belüftung von Abwasser dient, sind in der Linie jeder zweiten senkrechten Puge zur Seitenwand o, nach innen reichende lcitwlindo 3>G angeschlossen, die in der vollen Tiefe des Beckens oder in einem Toil derselben vorlaufen und so den Aufenthalt (den Strömungsweg) dc3 V/asscro im Beckon verlängern« Anstelle der Leitwündo 36 - oder neben diesen - können über die gesamte Breite des Beckens verlaufende Trennwände vorgesehen werden. Die Bauelemente dieser Trennwände werden in die monolitischen Stahlbeton-Balken 2a der Bodenplatte b eingebettet oder zwischen den in den Pigen eingesetzten Stahlbewehrungen, ind die Teile 80a der Pfeiler-80 (siehe Pig. 12) bzw. in die die Breite C- aufweisenden Stahlbetonbalken 2a der Bodenplatte b_ eingespannt - Pig. 12 -. In sonstiger Hinsicht stimmt das Becken mit den früher beschriebenen vollkommen überein (z.B. Belüftungssystem), so daß die bereits beschriebenen Konstruktionsbauelemente mit den früher bereits verwendeten Bezugsnummern bezeichnet wurden.Since this is on the right side of Pig. 14 and 15 is functionally used for the aeration of waste water, are connected in the line of every other vertical Puge to the side wall o, inward lcitwlindo 3> G , which run in the full depth of the basin or in a Toil of the same and so stay extend the flow path dc3 v / asscro in the Beckon "Instead of the Leitwündo 36 - or in addition to these - over the entire width of the basin extending partitions can be provided. The components of these partitions are embedded in the monolithic reinforced concrete beam 2a of the base plate B, or between the inserted into the Pigen steel reinforcements, ind the parts 80a of the pillar 80 and in which the width C (see Pig. 12) - having reinforced concrete beams 2a the base plate b_ clamped - Pig. 12 -. In other respects, the basin is in perfect agreement with those previously described (eg ventilation system), so that the construction elements already described have been designated with the reference numbers previously used.

- 28 -- 28 -

-28- 21 8 656 -28- 21 8 656

In Pig. 16 vfird ähnlich wie in Fig. 13 eine Ausführung der waagerechten Fugendichtung dargestellt. (Detail XVI ind Fig. I1J), In den gegenüberliegenden schmalen Längsseitenflächen der Stahlbeton-Bauelemente 1 sind die Rippen 33 und 34 vorgesehen, die einen 3ägezahnförmigen Raum ergeben. In der äußersten, nicht dem Wasser'zuliegenden Seite, ist zwischen den Rippen 34 ein Mikrozellengummiband 30 oder ein Bleiblech3treifen eingelegt. Von der anderen Seite ist vor dem Ausbetonieren ein Gunmiseil 37 in die zwischen den Bauelementen 1 befindliche waagerechte Fuge eingetrieben und anschließend die Fuge mit einem Monolitbetonkern 17 ausgefüllt worden. Diese Lösung erhöht die Sicherheit der Wasserundurchläosigkeit.In Pig. 16 vfird similar to Fig. 13 shows an embodiment of the horizontal joint seal. (Detail XVI in Fig. I 1 J), In the opposite narrow longitudinal side surfaces of the reinforced concrete components 1, the ribs 33 and 34 are provided, which give a 3ägezahnförmigen space. In the outermost, not the Wasser'zuliegenden side, between the ribs 34, a micro-cell rubber band 30 or a Bleiblech3treifen inserted. From the other side, a gunmileil 37 is driven into the horizontal joint between the components 1 prior to concreting, and then the joint has been filled with a monolith concrete core 17. This solution increases the safety of water impermeability.

Die auf der rechten Seite von Fig. 14 und 15 zu sehende Beckenkonatruktion wird dann angewandt, wenn auf Grund schwieriger Bodenverhältnisse ein ungleichmäßigen Sinsinken zu erwarten ist oder, wenn die Höhe der Beckenwand a. 4,0 bis 6,0 m überschreitet. Im letzten Fall ist die von der Gründung aufzunehmende Belastung bereits sehr bedeutend. Die Gründungen, der Seitenwinde α und der Bodenplatte 6 sind daher durch eine Dilatationüfuge 14 voneinander getrennt, wie das bereite bei dor Beckenkonstruktion gemäß Fig. 1 und 5 geschehen int. Dio Fuge wird mit Kunststoffkitt ausgefüllt. Die au3 vorgefertigten Stahlbeton-Bauelemente 1 aufgebauten Wände und die Bodenplatte werden wiederum durch ein äußerea Trägernetz versteift·(linke Seite von Fig. 14 und 15), wobei das Trägernetz nicht aus monolitischem Stahlbeton, sondern zum Teil aus Stahlbalken hergestellt ist. Das Lastspiel desselben ist mit dem vorstehend beschriebenen übereinstimmend. Das kombinierte Streifenfundament aus monolitischeiii Stahlbeton entspricht dem in Fig. 1 und 2 und dient gleichzeitig als unterer Ringanker. Der obere Ringanker 11 wird ebenfalls aus monolitiochera Stahl-The pelvic reconstruction seen on the right side of Figs. 14 and 15 is used when uneven sinking is to be expected due to difficult soil conditions, or when the height of the pelvic wall is a. Exceeds 4.0 to 6.0 m. In the latter case, the burden to be borne by the foundation is already very significant. The foundations, the crosswinds α and the bottom plate 6 are therefore separated from each other by a Dilatationüfuge 14, as the ready done in dor pelvic construction of FIG. 1 and 5 int. Dio joint is filled with plastic putty. The walls and the floor slab constructed of prefabricated reinforced concrete building elements 1 are in turn stiffened by an external support network (left side of FIGS. 14 and 15), the support network being made not of monolithic reinforced concrete but partly of steel beams. The load cycle thereof is consistent with that described above. The combined strip foundation of monolithic reinforced concrete corresponds to that in FIGS. 1 and 2 and at the same time serves as a lower ring anchor. The upper ring anchor 11 is also made of monolitiochera steel

- 29 -- 29 -

-29~ 21 8 656- 29 ~ 21 8 656

beton hergestellt. Die Zwischenpfeiler 39 und die Eckpfeiler 39a können z.B. aus U- oder I-Profilstahlbalken oder mit einer Kombination von solchen aufgebaut werden, z.B; mit geschweißten und/oder genieteten und/oder geschraubten Verbindungen. Der Zwiachenringanker 11b iat ebenfalls aus Stahl gefertigt. Die durch den Zwischenringanker und durch die Pfeiler gebildete Stahlstützkonstruktion kann bei der Montage der vorgefertigten Stahlbetonbaueleraente 1 als Hilfskonstruktion benutzt werden. Die Pfeiler 39 und 39a sind unten in das kombinierte Streifenfundament 4, oben in den Ringanker 11 eingespannt. Das Becken wird durch eine Deckenkonstruktion 10 abgedeckt. Die vorgesehene Abstützung ergibt einen Rahmen, der den. Bau eines Beckens mit einer Wandhöhe von 7,0 m ermöglicht. Die übrigen Konstruktionsmerkmale wie Wasserableitung, Belüftung, Einzelheiten der Gründung usw. entsprechen den vorstehenden Darlegungen.made of concrete. The intermediate posts 39 and the corner posts 39a may e.g. be constructed of U- or I-section steel beams or with a combination of such, e.g. with welded and / or riveted and / or bolted connections. The Zwiachenringanker 11b iat also made of steel. The steel support structure formed by the intermediate ring anchor and by the pillars can be used as an auxiliary construction during assembly of the prefabricated reinforced concrete building elements 1. The pillars 39 and 39 a are clamped at the bottom in the combined strip foundation 4, at the top in the ring anchor 11. The basin is covered by a ceiling construction 10. The proposed support results in a frame that the. Construction of a basin with a wall height of 7.0 m possible. The other design features such as water drainage, ventilation, details of the foundation, etc. are as described above.

Pig. 17 zeigt das in Pig. 15 bezeichnete Detail ICVII in vergrößertem Maßstab. Der Pfeiler 39 besteht aus zwei mit ihren Schenkeln gegenüberliegenden U-Stahlprafilo An den äußeren Seitenflächen der Schenkel liegen unter Zwischenfügung dos Uikrozellengummibaiides 30 die. Bauelemente der Seitenwand an. Die Kanäle 20 in den Bauelementen verlaufen wiederum waagerecht, wobei da3 die Verbindung zwischen den benachbarten Kanälen sichernde Rohr 2b in Pig. 17 ebenfalls gut zu sehen ist. Die Stahlbalken 41 werden mit Hilfe der Obergurte,42a, 42b und der Spannschrauben 43 an das Mikrozellengummiband gepreßt, wodurch einerseits die Wasserundurchläsaigkeit und andererseits eine gute Befestigung der Bauelemente gesichert wird. Der innere Gurt 42b liegt an der inneren Y/andfläche der Kanäle 20 zweier benachbarter Stahlbeton-Bauelemente an. Die V/asserundurchlässigkoit der Puge kann noch dadurch erhöht werden, wenn unter, das Mikrozellengummiband 30Pig. 17 shows this in Pig. 15 designated detail ICVII on an enlarged scale. The pillar 39 consists of two opposite with their thighs U-Stahlprafilo At the outer side surfaces of the legs lie with the interposition dos Uikrozellengummibaiides 30 the. Components of the side wall on. The channels 20 in the components in turn extend horizontally, where da3 the connection between the adjacent channels securing tube 2b in Pig. 17 is also good to see. The steel beams 41 are pressed by means of the upper belts, 42a, 42b and the clamping screws 43 to the microcellular rubber band, which on the one hand the Wasserundurchläsaigkeit and on the other hand, a good attachment of the components is secured. The inner belt 42b abuts the inner Y / and surface of the channels 20 of two adjacent reinforced concrete components. The water permeability of the puck can still be increased if, below, the microcell rubber band 30

- 30 -.- 30 -.

" 30 " 218 6 56" 30 " 218 6 56

von außen eine elastische Kittdichtung in die Fuge eingebracht und der durch die Stahlbalken 41 (teilweise) abgegrenzten Raum mit Mo noli tb et on 44 ausgefüllt v/ird.From the outside, an elastic putty seal is introduced into the joint and the space (partially) delimited by the steel beams 41 is filled with monolayer 44.

Fig. 17 zeigt.sehr gut, daß in die breite Puge der Seitenwand sowie in den eine Breite von £ aufweisenden Lager- und Deckenbalken die innere Wand 45 konstruktiv eingebaut ist. Die Decke 10, die Seitenwände, b und die Innenwände 45 übertragen ihre Belastungen über da3 Streif en-.fundament 4 und den Verbindungs3treifen 2a euf den Baugrund unabhängig von der Bodenplatte b_. In Fig. 17 wurde übrigens die IJeigungsrichtung der Kanäle 20 in den Seitenwänden a bzw. in der Bodenplatte b mit den Pfeilern e, bezeichnet. Dqr ITeigungswert, d.h. das Gefälle kann z.B. ca. 1 fo betragen.Fig. 17 shows very well that in the wide Puge the side wall and in the width of £ having bearing and ceiling beams, the inner wall 45 is structurally installed. The ceiling 10, the side walls, b and the inner walls 45 transmit their loads over the strip foundation 4 and the connecting strip 2a to the ground independently of the floor plate b_. Incidentally, in FIG. 17, the direction of inclination of the channels 20 in the side walls a and in the bottom plate b is indicated by the pillars e. Dqr ITeigungswert, ie the slope may be, for example, about 1 fo .

Die Ausbildung der Dilatationsfuge des Beckens nach Pig. 14 und 15 ist in Pig. 23 dargestellt, die den Schnitt entlang der in Pig. 17 bezeichneten Linie IX-IX zeigt. In Pig. 23 sind mehrere unterschiedliche Stahlbeton-Bauelemente 1 und zwei verschiedene Dilatationsfugenfomen dargestellt. In beide Dilatationsfugen 14 werden Guromiseile 17 eingetrieben und der darüber befindliche Spalt wird mit wasserdichten Llürtel ausgegossen. Das eingetriebene Gummiseil 37 ermöglicht eine Bewegung und verhindert ein Durchsickern des Wassers, wobei der ausgegossene Mörtel einen weiteren Schutz sichert.The formation of the dilatation joint of the pelvis after Pig. 14 and 15 is in Pig. 23, which shows the section along that in Pig. 17 designated line IX-IX shows. In Pig. 23, a plurality of different reinforced concrete building elements 1 and two different dilatation joints are shown. In both dilatation joints 14 Guromiseile 17 are driven and the gap above it is filled with watertight Llürtel. The driven rubber cord 37 allows movement and prevents seepage of the water, the poured mortar ensures further protection.

Bei der Verwendung der U-Profilbalken 41 als Montagegerüst ist es zweckmäßig, den unteren ca. 1,0 m langen Abschnitt erst dann mit Beton auszufüllen, wenn die Betonierung des Streifenfundamentes 2a der Bodenplatte b, vorgenommen wird. Dadurch wird erreicht, daß die Balken 41 im Verlaufe der Montage unbeweglich 3ind und feststehen.When using the U-profile beam 41 as a mounting frame, it is expedient to fill the lower approximately 1.0 m long section only with concrete when the concreting of the strip foundation 2a of the bottom plate b, made. This ensures that the bars 41 are immovable in the course of assembly and are fixed.

-31 --31 -

218 656218 656

Die Fig. 18 bis 20 zeigen ein auf 2 zueinander parallel verlaufende Säulenreihen gestelltes Becken mit einer geringeren Grundfläche. Die Säulen tragen das Bezug3zeichen 47. Die in den Pig. 19 und 20 sichtbaren linksseitigen Säulen 47 sind in vorgefertigten Stahlbeton-Nestfundamenten 48 eingesetzt, die rechtsseitigen Säulen 47 sind hingegen in einen monolitischen Stahlbetongrundkörper 49 eingegossen, deren Form der Form des Grundkörpers 48 entspricht. Die Säulen können übrigens auch aus vorgefertigten Stahlbeton-Bauelementen bestehen. Die in jeder Längsreihe stehenden Säulen 47 ruhen auf einem geraeinsamen raonolitischen Stahlbeton-Streifen 50, der die Säulen 47 jeder Reihe zusammenfaßt. Am oberen linde der Säulen 47 der einzelnen Säulenreihen ist ein Hauptbalken vorgesehen. Auf der linken Seite der Fig. 19 ist ein vorgefertigter Stahlbeton-Hauptbalken 51» auf der rechten Seite ein Stahlbetonhauptbalken 52 zu sehen.FIGS. 18 to 20 show a basin with a smaller footprint placed on two parallel rows of columns. The pillars bear the reference sign 47. The in the Pig. 19 and 20 visible left-side columns 47 are used in prefabricated reinforced concrete nest foundations 48, the right-side columns 47, however, are cast in a monolithic reinforced concrete base body 49, whose shape corresponds to the shape of the base 48. Incidentally, the columns can also consist of prefabricated reinforced concrete components. The columns 47 standing in each longitudinal row rest on a single raonolithic reinforced concrete strip 50, which groups together the columns 47 of each row. At the upper linden of the columns 47 of the individual rows of columns, a main beam is provided. On the left side of FIG. 19, a prefabricated reinforced concrete main beam 51 'on the right side of a reinforced concrete main beam 52 can be seen.

Im Falle eines auf Füßen (Säulen) aufgestellton Beckons. sind die Vorteile der mit vorgefertigten Bauelementen erfolgenden Bauweise noch offensichtlicher. Von der Gründung angefangen bi3 zum Aufbau der Konstruktion ist dan gesamte Bauwerk au3 Bauelementen zusammenateilbar. Der Bedarf an monolitischeni Beton macht nur einen unwesentlichen Anteil der gesamten Bauarbeit aus. Die Erdarbeit ist noch geringer als im Falle eines auf Terrainniveau errichteten Beckens, da eine echte Erdarbeit nur an den Stellen der liestfundament erforderlich ist» Das beschriebene Pfeilergerüstsystem kann mit jedem beliebigen Grundriß und - abweichend von der in Fig. 18 bis 20 gezeigten Konstruktion mit zwei Säulenreihen, aus mehreren Säulenreihen bestehen. In Fig. 21 sind eine zwischenstehende Säule 47 und ein mit einer Konsole versehener monolitischer Stahlbetonbalken 52 sowie der Anachlußknotenpunkt der Bodenplatte b_ in einem größeren LIaßstab zu sehen. Die beiden benachbarten Stahlbeton-Bauelemente 1 liegen auf dem Hauptbalken 52 auf,In the case of Beckon set up on feet (pillars). the advantages of prefabricated construction are even more obvious. Starting with the foundation from the foundation to the construction of the construction, the entire structure can be divided into three components. The demand for monolithic concrete accounts for only insignificant proportions of the total construction work. The earthwork is even lower than in the case of a ground level pelvis, since a true earthwork is required only at the points of the read foundation. "The described pillar scaffold system can be constructed with any plan and, deviating from the construction shown in Figs Column rows, consisting of several rows of columns. In Fig. 21, an intermediate column 47 and a monolithic monolithic concrete beam 52 provided with a bracket, and the approach node of the floor slab b_ are seen on a larger scale. The two adjacent reinforced concrete components 1 rest on the main beam 52,

- 32- 21 8 6 56- 32- 21 8 6 56

wobei zwischen ihnen eine Fuge mit einer Breite £ vorhanden ist. Bis in diese Fuge reichen die Stahlbewehrungen 53 der Säule 47 hinein, die auch durch den Hauptbalken 52 hindurchgeführt sind. Beim Ausbetonieren dieses Zwischenraumes in der vorstehend beschriebenen Y/eise erhält man den Stahlbetonbalken 2a, dessen Beton auch in die Kanäle 2 der Bauelemente 1 hineindringt, wodurch die Betonkerne 2d entstehen. Bei diesem Ausführungsbeispiel sind auch die beidseitig in die Betonkerne 2d hineinreichenden, in Querrichtung angeordneten Stahleinlagen 54 in die Balken 2a eingebettet, die zur Minderung der Endplattenverdrehung dienen. Durch Rohre 2b wird die Verbindung zwischen den Kanälen 20 in den Stahlbeton-Bauelementen 1 hergestellt. Auf die obere Fläche des Hauptbalkens 52 wird wasserdichter Verlegemortel (,Cunstatoffinörtel) 55 aufgetragen und an beiden oberen Rändern de3 Balkens längsvorlaufende Streifen I.Iikrozellengummibänder 30 oder Bleiblechstreifen eingelegt, die unter den Druck der Stahlbeton-Bauelemente 1 zusammengepreßt werden und eine vollständige Y/asserundurchlässigkeit gewährleisten.there is a gap between them with a width £. The steel reinforcements 53 of the column 47, which are also guided through the main beam 52, extend into this joint. When concreting this gap in the above-described Y / eise obtained the reinforced concrete beam 2a, the concrete penetrates into the channels 2 of the components 1, whereby the concrete cores 2d arise. In this embodiment, the steel inserts 2 extending into the concrete cores 2d on both sides and arranged transversely are also embedded in the beams 2a, which serve to reduce the end plate twisting. Through pipes 2b, the connection between the channels 20 in the reinforced concrete components 1 is produced. On the upper surface of the main beam 52 watertight installation turf (Cunstatoffinörtel) 55 is applied and inserted at both upper edges of the beam longitudinally leading strip I.Iikrozellengummibänder 30 or Bleibelchstreifen that are pressed together under the pressure of reinforced concrete components 1 and a complete Y / apererdurchlässigkeit guarantee.

Fig. 22 zeigt den Schnitt XII-XII aus Fig. 21. Zwischen den Längsrändern der benachbarten Ctahlbcton-Bauelcmente l'.dst eine kleine Fuge mit einer Breite £ vorhanden, die mit Kunststoffbeton 20 ausgefüllt ist. Die Abmessung f ist wesentlich kleiner, al3 die die Abmessung £ (Fig. 21), In den Kunststoffbeton 20 ist ein Betonbewehrungsstahl 5β eingelegt. Zwischen don Rippen 34 der Bauelemente 1 ist genauso wie unter den Bauelementen ein Liikrozellengummiband 30 oder ein Bleiblechstreifen eingelegt. In linksseitigen Bauelement 1 wird der Kommunikationsgang durch die Kunststoffrohre 2b und im rechtsseitigen Bauelement durch die unten vorgesehenen Gänge 2f gesichert.Fig. 22 shows the section XII-XII of Fig. 21. Between the longitudinal edges of the adjacent Ctahlbcton-Bauelcmente l'.dst a small gap with a width £ present, which is filled with plastic concrete 20. The dimension f is substantially smaller than the dimension ε (Fig. 21). In the plastic concrete 20, a concrete reinforcing steel 5β is inserted. Between don ribs 34 of the components 1 as well as under the components a Liikrozellengummiband 30 or a lead sheet strip is inserted. In the left-side component 1, the communication passage is secured by the plastic pipes 2b and in the right-hand component by the gears 2f provided below.

- 33 -- 33 -

-33- 21 8 656-33- 21 8 656

Die zwischen den Stahlbeton-Bauelementen 1 vorliegenden waagerechten Fugen können sowohl in den Seitenwänden a als auch in der Bodenplatte b in der V/eise wie bei Pig. 13 oder 16 beschrieben und in Abhängigkeit davon, abgedichtet v/erden, ob in den Bauelementen Kanäle 2 mit Kreisquerschnitt oder Kanäle 20 mit eckigem Querschnitt vorgesehen sind.The horizontal joints present between the reinforced concrete building elements 1 may be in the sidewalls a as well as in the floor slab b in the manner of Pig. 13 or 16 described and depending on whether sealed v / earth, whether in the components channels 2 are provided with circular cross-section or channels 20 with polygonal cross-section.

Bei einem auf Füßen errichteten Becken kann der unter der Bodenplatte 8b befindliche Raum zu beliebigen Zwecken benutzt werden. Im Falle eines Schwimmbeckens können hier z.B. die Umkleideräume, Maschinenräume usw. vorgesehen werden, wobei die den Raum von oben abgrenzende Decke durch die Bodenplatte selbst gebildet wird. Da das Becken auch durch Hauptbalken mit Konsolen abgestützt ist (Fig. 20), kann unmittelbar neben dem Becken auch ein anderes Gebäude- errichtet werden, ohne daß die beiden benachbarten, voneinander unabhängigen, jedoch konstruktionanäasig gleichen Fundament einander 3toren wurden. Ein weiterer Vorteil der Anordnung des Beckens auf Füßen besteht darin, daß die dein Y/aooer gegenüberliegende Doitc den Beckenwänden in keine Berührung mit dera Boden konunt, d.h. daß kein Bodendunst bzw. keine Bodenfeuchtigkeit die vorgefertigten Bauelenente erreicht. Dies ist aus dem Grunde von Bedeutung, da zu den in der Nachbarschaft dieser Flächen auf der gezogenen Seite befindlichen Betonbewehrungsstähle weder von außen noch von innen Feuchtigkeit gelangt, weil diese durch die Kanäle abgeleitet wird.In a basin built on feet, the space under the floor panel 8b can be used for any purpose. In the case of a swimming pool, here e.g. the changing rooms, machine rooms, etc. are provided, wherein the space delimiting the space from above ceiling is formed by the bottom plate itself. Since the basin is also supported by main beams with brackets (FIG. 20), another building can be erected immediately adjacent to the pool without the two adjacent, mutually independent but construction-like foundations being the same. Another advantage of the placement of the pelvis on feet is that the doublet facing your yaw ace does not contact the pelvic walls with any contact with the floor, i. that no soil vapor or soil moisture reaches the prefabricated Bauenteente. This is important because concrete reinforcement steels located on the drawn side in the vicinity of these surfaces do not get moisture either from the outside or from the inside because it is discharged through the channels.

In der Decke und in den Seitenwänden der Becken nach Fig. 11 bis 23 sind gespannte Drähte 3 nur auf der gezogenen, d.h. der den mit dem Y/aaaer in Berührung kommenden Flächen entgegengesetzten Seite vorhanden. Dies bedeutet, daß die Ausführung, da auf der durchnäßten Seite kein Konstruktionsstahl vorhanden ist, vom Gesichtspunkt des Korrosionsschutzes aus gesehen außerordentlich vorteilhaft ist,In the ceiling and in the side walls of the basins of Figs. 11 to 23 are tensioned wires 3 only on the towed, i. the opposite side to the surfaces coming into contact with the Y / aaaer. This means that the embodiment, since there is no structural steel on the wetted side, is extremely advantageous from the point of view of corrosion protection.

- 34 -- 34 -

218 656218 656

da das durchsickernde Wasser durch die Kanäle abläuft, bevor es zu den Spanndrähten gelangt· d.h. daß ihre Umgebung trocken bleibt.since the seepage water drains through the channels before it reaches the tension wires. that their environment stays dry.

Die Erfindung beschränkt sich natürlich nicht nur auf die vorstehend beschriebenen Ausführungsbeispiele, sondern kann innerhalb des durch die Erfindungsansprüche definierten Schutzumfanges in zahlreichen Varianten verwirklicht werden. In erster Linie soll betont werden, daß sich die Erfindung nicht nur auf Y/aeserspeicherbecken, sondern auf sämtliche Bauwerke bezieht, deren Münde und/ oder - Decken und/oder Bodenplatten - flüssigkeitsundurchlässig sein müssen. Dies gilt sowohl für von außen in das Bauwerk eindringendes V/asse.r als auch für V/as3er, das aus dem -umbauten Raum ausfließen kann. Gegenstand der Erfindung können demgemäß zum Beispiel die Ernpfangsetagen von hohen Paneelhäusern; unterirdische Kommunikationsgänge, Tunnelbauten öffentlicher Gebäude oder sonstige Tunnelkonatruktionen; Auf Grundwasser errichtete Ingenieurbauten, z.B. Brückenpfeiler, Schleusenkammern usw. sein. Aus vorstehendem folgt, daß sowohl im Quer- · schnitt'als auch im Grundriß bogenförmige Bauwerke nach der erfindungsgemäßen Llethode errichtet werden können, da die vorgefertigten Stahlbeton-Bauelemente eine beliebige Form und al30 auch eine Bogenform haben können.Of course, the invention is not limited to the embodiments described above, but can be embodied in numerous variants within the scope of protection defined by the claims of the invention. In the first place, it should be emphasized that the invention relates not only to storage tanks but to all structures whose mouth and / or ceiling and / or floor slabs must be impermeable to liquids. This applies both to V / asse.r entering from outside the building and to V / as3er, which can flow out of the rebuilt space. The subject matter of the invention can accordingly be, for example, the food racks of tall panel houses; underground communications, tunnels of public buildings or other tunnel constructions; Engineering structures erected on groundwater, eg bridge piers, lock chambers etc. It follows from the above that arcuate structures can be erected according to the method according to the invention both in the transverse section and in the plan, since the prefabricated reinforced concrete elements can have any shape and also an arch shape.

Das erfindungsgemäße Bauwerk kann z.B. auch ein Unterfluttunnel oder ein ähnliches Bauwerk mit geschlossenem Profil sein. Zur Herstellung von solchen oder ähnlichen Bauwerken kann auch die Schrämtechnologie angewandt werden. In den entsprechend vorbereiteten und ausgebildeten Baugruben werden zuerst durch Unterwasserbetonierung längsverlaufende Hauptbalken hergestellt und in diese noch vor Verfestigung des Monolitbetons - die vorgefertigten Stahlbeton- Hohlbauelemente'so eingesenkt, daßThe building according to the invention can e.g. also a sub-channel tunnel or a similar structure with a closed profile. For the production of such or similar structures also the Schrämtechnologie can be applied. In the appropriately prepared and trained excavations are first made by underwater concrete longitudinal main beam and in this before solidification of Monolith concrete - the prefabricated reinforced concrete Hohlbauelemente'so sunk that

- 35 -- 35 -

218 656218 656

die Hohlräume in aufrechter, im*wesentlichen senkrechter Stellung bleiben. Die Fugen zwischen den vorgefertigten Bauelementen sowie die einzelnen Hohlräume werden mit Monolitbeton ausgefüllt und ind die säulenartigen Monolitbetonkerne der Hohlräume Stahlbewehrungen eingesetzt. Dadurch werden in den V/andkonstruktionen Stahlbetonoäulcn ausgebildet, deren Eisenarmierung nach oben aua der V/and hervoreteht und in die ein ein oben auf den Y/änden entlanglaufender monolitischer Stahlbeton-Ringanker angeordnet, der vorteilhafterweise auch in Längslagerbalken eingespannt wird. Werden die Säulen bzw. Pfeiler in den parallel zueinander verlaufenden V/änden aneinander gegenüberliegend angeordnet, 30 können sie mit ebenfalls aus monoliti3chem Stahlbeton gefertigten Querbalken verbunden werden^ so daß rahnenartige Konstruktionen entstehen. Nach der Entwässerung kann die Bodenplatte sowohl aus monolitischern Stahlbeton als auch - in der bereits beschriebenen V/eise - aus Stahlbeton-Bauelementen mit Hohlräumen aufgebaut werden. Auch die Deckenplatte kann aua Stahlbeton-Bauelementen mit Holhräumen bestehen, z.3. zwischen den erwähnten Querveroteifunrrjbalken oder - in Palle eines Pehlens von solchen - den zwischen den beiden. Seitenwänden liegenden Raum - zusammenhängend abdeckend, wobei jedoch die Deckenplatte auch als monoliticche Gtahlbetonkonstruktion hergestellt werden kann.the cavities remain in an upright, substantially vertical position. The joints between the prefabricated components and the individual cavities are filled with monolithic concrete and used in the columnar Monolitbetonkerne the cavities steel reinforcements. As a result, reinforced concrete columns are formed in the wall constructions whose iron reinforcement protrudes upward from the wall and into which a monolithic reinforced concrete ring anchor running along the top of the wall is advantageously arranged, which is also clamped in longitudinal bearing beams. If the columns or pillars are placed opposite one another in the mutually parallel walls, they can be connected with cross beams also made of monolithic reinforced concrete, so that the structures of a ridge are formed. After drainage, the floor slab can be constructed from monolithic reinforced concrete as well as - as already described - from reinforced concrete elements with cavities. The ceiling slab may also consist of reinforced concrete elements with hollows, z.3. between the mentioned cross-verifier bars or - in the palle of a penny of such - the one between the two. Side walls lying space - covering contiguous, but the ceiling plate can also be made as a monolithic Gtahlbetonkonstruktion.

V/ird die Bodenplatte aus vorgefertigten, Hohlräume aufweisenden Stahlbeton-Bauelementen gefertigt, so ist es zweckmäßig auch in der Bodenplatte monolitische Stahlbeton-Querbalken an den Stellen vorzusehen, wo durch die Hohlräume in den aneinanderliegenden' Bauelementen Säulenpaare entstehen. Der Monolitbeton der Balken dringt in die Hohlräume der Bauelemente ein und kann auch bewehrt werden, z.B. auf der in Pig. 21 gezeigten V/eise. Dadurch wird die Starrheit der Konstruktion weiter erhöht. Kuß mit einem bedeutenden äußeren V/as3erdruck gerechnet werden, der vonIf the floor slab is made of prefabricated reinforced concrete structural elements having cavities, it is also expedient to provide monolithic reinforced concrete crossbeams in the floor slab at the points where column pairs are created by the cavities in the adjoining building elements. The monolithic concrete of the beams penetrates into the cavities of the components and can also be reinforced, e.g. on the in Pig. 21 shown. This further increases the rigidity of the construction. Kiss can be counted on a significant external pressure, which is derived from

- 36 -- 36 -

- 36 - 21 8-656- 36 - 21 8-656

unten auf die Bodenplatte einwirkt, so ist es zweckdienlich, die Bodenplatte aus zwei Schichten vorgefertigter Stahlbeton-Bauelemente mit Hohlräumen herzustellen, zwischen denen eine wasserundurchlässige Liörtelschicht aufgetragen wird. Auch in diesem Falle können in der Bodenplatte die in Querrichtung zur Versteifung dienenden Lagerbalken ausgebildet werden, deren Höhe der zweifachen Bauelementenstärke entspricht, wobei die in die Hohlräume einfließenden - eventuelle bewehrten - Monolitbetonkerne auf je zwei Stellen in verschiedenen Höhen entstehen. Die beiden Bodenplatten-Baueleraente-Schichten können auch so angeordnet werden, daß die Hohlräume in den einzelnen Schichten zueinander senkrecht verlaufen. Bei zwei Bauelemente-Reihen kann dadurch erreicht werden, daß der Wasserdruck durch das Eindringen in die Hohlräume der unteren Reihe bereits weitgehend vermindert wird und' aus den Kohlräumen der oberen Reihe die eventuell eingedrungene kleine Y/asserrnenge leicht abgeleitet werden kann*acting bottom of the bottom plate, it is useful to make the bottom plate of two layers of prefabricated reinforced concrete elements with cavities, between which a water-impermeable Liörtelschicht is applied. Also in this case can be formed in the bottom plate serving in the transverse direction for stiffening bearing beams, the height of which corresponds to twice the component thickness, wherein the inflowing into the cavities - possibly reinforced - Monolitbetonkerne arise in two places at different heights. The two bottom plate Baueleraente layers can also be arranged so that the cavities in the individual layers are perpendicular to each other. With two rows of components can be achieved by the fact that the water pressure is already largely reduced by the penetration of the cavities of the lower row and 'from the cabbage rooms of the upper row, the possibly penetrated small Y / asserrnenge can be easily derived *

Abschließend ist zu bemerken, daß - in erster Linie bei Becken geringerer Höhe, wo die Kanäle in den Seitenwändcn waagerecht verlaufen - .außerhalb dor './andcbene angeordnete Pfeiler oder Säulen nicht unbedingt erforderlich sind, sondern daß diese Konstruktionen in der wand selbst in einer mit der V/andbreite gleichen Breite ausgebildet werden können. In diesem Falle ist es zweckdienlich, die Pugenbreite größer als üblich zu wählen. Dabei dringt dor Monolibeton der Säule beiderseits in die einander gegenüberliegenden Hohlräume ein und kann an diesen Stelleniivie'in Pig* 21 dargestellt- durch querliegendc Stähle bewehrt werden. Die senkrechten Säulenbewehrungen oder zumindest der größere Teil derselben ist auf der gezogenen Seite - d.h. z.B. bei Flüssigkeitsspeicherbecken auf der dem Flüssigkeitsraum entgegengesetzten Seite - anzuordnen. In einer Linie mit den Säulen werden in die BodenplatteIn conclusion, it should be noted that - in the case of basins of lesser height, where the channels run horizontally in the lateral walls - pillars or pillars arranged outside the wall are not absolutely necessary, but that in the wall itself, these constructions are required can be formed with the V / andbreite same width. In this case, it is expedient to choose the Pugenbreite larger than usual. In this case, the monoli- ketone penetrates the column on both sides into the cavities lying opposite one another and can be reinforced by transverse steels at these locations in Pig * 21. The vertical column reinforcements, or at least the greater part of them, are on the drawn side - i. e.g. at liquid storage tank on the opposite side of the liquid space - to order. In a line with the columns are in the bottom plate

- 37 -- 37 -

-37- 21 8 656-37- 21 8 656

sich an die Säulen anschließende, die gleiche Breite wie diese aufweisende monolitische Stahlbeton-Lagerbalken angeordnet, wodurch sich die·erwähnte U-förmige Verstärkungskonstruktion ergibt.arranged on the columns, the same width as this having monolithic reinforced concrete bearing beams, resulting in the mentioned U-shaped reinforcing construction.

- 38 -- 38 -

Claims (21)

- 38 - 218 6 56- 38 - 218 6 56 Erfindungsanspruchinvention claim 1. Wasserundurchlässige Baukonstruktion für Flüssigkeitsspeicherbecken, Schwimmbecken oder ähnliche Bauwerke, dessen Seitenwände und/oder Bodenplatte mindestens zum Teil aus vorgefertigten, wasserundurchlässigen, plattenartigen Bauelementen hergestellt sind, gekennzeichnet dadurch, daß im Inneren der vorteilhafterweise vorgespannten, vorgefertigten Stahlbeton-Bauelemente (l) in gleicher Richtung verlaufende, zur Ableitung und/oder Verdampfung der in das I nere des Bauelementes (1) gelangenden Flüssigkeit geeignet Kanäle (20; 20) vorgesehen sind,1. Waterproof construction for liquid storage tanks, swimming pools or similar structures, the side walls and / or bottom plate are made at least in part of prefabricated, water-impermeable, plate-like components, characterized in that inside the advantageously prestressed, prefabricated reinforced concrete elements (l) in the same Direction extending, suitable for the discharge and / or evaporation of the in the I nere of the component (1) liquid reaching channels (20; 20) are provided, 2. Baukonstruktion nach Punkt 1, gekennzeichnet dadurch, daß die Gründungen der in unterschiedlichem I.Iaße belasteten Konstruktionsteile, z.B. der Seitenwändc (a) und der Bodenplatte (b) und/oder der Säulen (3; 8a; 8c; 8e; 80) voneinander getrennt sind und zwischen diene:] Gründungen eine Dilatationsfuge (14) vorgesehen ist, die eine unterschiedliche Senkung gestattet und mit einen elastischen wasserundurchlässigen Material, z.B. ICunstharzkitt (14a) ausgefüllt ist.2. Construction according to item 1, characterized in that the foundations of the structural parts loaded in different I.Iaße, e.g. the side walls (a) and the bottom plate (b) and / or the columns (3; 8a; 8c; 8e; 80) are separated from one another and between:] a dilation joint (14) is provided which allows different countersinking and with an elastic water-impermeable material, eg ICunstharzkitt (14a) is filled. 3. Baukonstruktion nach Punkt 1 oder 2, gekennzeichnet dadurch, daß die Abgrenzungskonstruktionen plattenartige, quader- oder im wesentlichen quaderförmige vorgefertigte Stahlbeton-Bauelemente (1) enthalten, die entlang ihrer zu den Iäng3 verlaufenden Kanälen parallelen Rändern mittels in den Anschlußfugen eingesetzten Betonstahlstäben (l6) und durch eine vorteilhafterweise kunstharzgebundene I.Ionolitbetonau3füllung (17) miteinander verbunden sind.3. Construction according to item 1 or 2, characterized in that the demarcation constructions plate-like, cuboid or substantially cuboid prefabricated reinforced concrete components (1) containing along their parallel to the Iäng3 channels edges by means inserted in the connecting rods reinforcing steel bars (l6 ) and are connected by an advantageously resin-bound I.Ionolitbetonau3füllung (17). 21S 65621S 656 4· Baukonstruktion nach einen der 'Punkte 1 bis 3, gekennzeichnet dadurch, daß die die Seitenwände (a) des Bauwerkes bildenden, quader- oder im wesentlichen quaderförmigen vorgefertigten Stahlbeton-Bauelemente (I)-in ihrer eingebauten Lage - entalng ihrer Längskanten durch Säulen/Pfeiler (8) abgestützte, in der Querrichtung lasttragende Elemente sind, wobei die Kanäle (2) in der V/and (a) im wesentlichen senkrecht angeordnet sind.4 · Building construction according to one of the 'points 1 to 3, characterized in that the prefabricated reinforced concrete building elements (I) forming the sidewalls (a) of the building, rectangular or substantially cuboid prefabricated reinforced concrete elements (i) - in their installed position - entalng their longitudinal edges by columns / Pillars (8) supported in the transverse direction load-bearing elements, wherein the channels (2) in the V / and (a) are arranged substantially vertically. 5# Baukonstruktion nach einem der Punkte 1 bis 3, gekennzeichnet dadurch, daß die die Seitemvände (a) des Bauwerkes bildenden, quader- oder im wesentlichen quaderförmigen vorgefertigten Stahlbeton-Bauelemente (l) - in ihrer eingebauten Lage - unten und oben eingespannte, in Längsrichtung Ia3ttragende Bauelemente sind, wobei die Kanäle (2) in der V/and (a) im wesentlichen senkrecht angeordnet sind.5 # Construction according to one of the items 1 to 3, characterized in that the side walls (a) of the building, cuboid or substantially cuboid prefabricated reinforced concrete elements (l) - in their installed position - clamped at the top and bottom, in Longitudinally carrying components are, wherein the channels (2) in the V / and (a) are arranged substantially vertically. 6» Baukonstruktion nach einem der Punkte 1 bis 3, gekennzeichnet dadurch, daß die die Seitenwinde (a) den Bauwerkes 'bildenden plattenartigcn, quader- oder'im wesentlichen quaderfürmigen vorgefertigten Stahlbeton-Bauelemente (l) aufeinanderliegend angeordnet 3ind und die Kanäle (2, 20) im wesentlichen waagerecht verlaufen.6 »Building construction according to one of the items 1 to 3, characterized in that the crosswinds (a) of the building 'forming plate-like, cuboid or'im substantially cuboid prefabricated reinforced concrete elements (l) are arranged one above the other 3ind and the channels (2, 20) extend substantially horizontally. 7. Baukonstruktion nach einem der Punkte 1 bis 3, gekennzeichnet dadurch, daß das Bauwerk zum Teil in den Erdboden eingesenkt ist und über eine Segmentseitenwand einen auf der Erdböschung abgestützten schrägen Abschnitt und über eine waagerechte Bodenplatte verfügt.7. Construction according to one of the items 1 to 3, characterized in that the building is partially sunk into the ground and has a segment side wall supported on the Erdböschung oblique section and a horizontal base plate. 8, Baukonstruktion nach einem der Punkte 1 bis 7t gekennzeichnet dadurch, daß die Kanäle (2, 20) in den Seitenwand- (a) und/oder der Bodenplattenelemente (b) mit Wasser und/oder belüfteten Dunstableitungsrohren (13> 13a -8, building construction according to one of the points 1 to 7 t characterized in that the channels (2, 20) in the side wall (a) and / or the bottom plate elements (b) with water and / or ventilated fume extraction pipes (13> 13a - - AO -- AO - 218 656218 656 13f) verbunden sind, wobei die Kanäle (2,. 20) der aneinanderliegenden benachbarten Stehlbeton-Bauelemente (1) durch Gänge, z.B. Rohre (2b) miteinander verbunden sind.13f), wherein the channels (2, 20) of the adjoining adjacent stacked concrete building elements (1) are connected by passages, e.g. Tubes (2b) are interconnected. 9. Baukonstruktion nach einem der Punkte 1 bis 4, gekennzeichnet dadurch, daß die Seitenwände (a) auf die auch zur Gründung der vorgefertigten Säulen/Pfeiler (8) dienenden vorgefertigten Stahlbeton-Nestgründungen (9) ab-· gestützt sind und der Bereich über den ITestgründungen (9) zu einem die Seitenwand-Bauelemente (1) und die Säulen/Pfeiler )8) ζusammeηfassenden, streifenartigen, kombinierten Fundament (4) ausbetoniert ist (Pig. I).9. Construction according to one of the items 1 to 4, characterized in that the side walls (a) on the also for the founding of the prefabricated columns / pillars (8) serving pre-fabricated reinforced concrete nest foundations (9) are supported and the area over the ITestgründungen (9) to a sidewall components (1) and the columns / pillars) 8) ammeusammeηfassenden, strip-like, combined foundation (4) is concreted (Pig I). 10. Baukonstruktion nach einem der Punkte 1 bi3 9, gekennzeichnet dadurch, daß die vorgefertigten Stahlbeton-Bauelemente (1) durch die in den entlang ihrer die I.Iündungsöffnungen der Kanüle (2; 20) enthaltenden Handflachen laufenden Fugen ausgebildeten und auch die den ündtoile der Kanäle (2; 20) ausfüllenden Kerne (2d) enthaltenden I.Ionolitbetoribalken. (2a) aneinander befestigt sind (Pig.· 2a).10. Construction according to one of the points 1 bi3 9, characterized in that the prefabricated reinforced concrete components (1) formed by the in their along the I.Iündungsöffnungen of the cannula (2, 20) containing surfaces running joints and also the ündtoile of the channels (2; 20) filling nuclei (2d) containing I.Ionolitbetoribalken. (2a) are attached to each other (Pig. * 2a). 11« Baukonstruktion nach einem der Punkte 1 bis 10, gekennzeichnet dadurch, daß zwischen den aufeinanderliegenden Stahlbeton-Bauelementen (l) ein durch das Gewicht der Bauelemente zusammengedrücktes Llikrozellengumniband (30) und/oder ein Bleiblechstreifen eingelegt ist (Pig. 13, 16, 21, 22 und 23).11 «Building construction according to one of the points 1 to 10, characterized in that between the superimposed reinforced concrete components (l) a compressed by the weight of the components Llikrozellengumniband (30) and / or a Bleiblechstreifen is inserted (Pig. 13, 16, 21 , 22 and 23). 12« Baukonstruktion nach einem der Punkte 1 bis 11, gekennzeichnet dadurch, daß in den Fugen benachbarter Stahlbeton-Bauelemente (1) ein Liikroz.ellengummiseil (37) eingetrieben ist (Pig. l6).12 «Construction according to one of the items 1 to 11, characterized in that in the joints of adjacent reinforced concrete components (1) a Liikroz.ellengummiseil (37) is driven (Pig. L6). 2ί 8 656 2ί 8 656 13. Baukonstruktion nach Punkt 11, 'gekennzeichnet dadurch, daß das Gummiband (30) und/oder der Bleiblechatreifen in der zu:" Flüssigkeit hin abgewandten Randzone der Fuge zwischen zwei benachbarten Bauelementen (l) der Abgrenzkonstruktion- angeordnet ist.13. Construction according to item 11, 'characterized in that the rubber band (30) and / or the lead-wire tires in the facing away to: liquid edge zone of the joint between two adjacent components (l) Abgrenzkonstruktion- is arranged. 1,4. Baukonstruktion nach einem der Punkte 11 bis 13,-gekennzeichnet dadurch, daß in dor zwischen den Stahlbeton-Baualementen(l) verlaufenden Fuge vom Gummiband (30) und/oder Blechstreifen und/oder Gummiseil (37) zur Flüssigkeit hin eine I.Ionolitbetonausfüllung - zweckdienlicherweise eines Kunststoffbetonausfüllung - vorgesehen ist, in der vorteilhafterweise zumindest ein Beton3tahlotab (32) eingelegt iot.1.4. Construction according to any one of items 11 to 13, characterized in that in the gap between the reinforced concrete structural elements (1) extending from the rubber band (30) and / or sheet metal strip and / or rubber rope (37) to the liquid I.Ionolitbetonfüllung - expediently a plastic concrete filling - is provided, in the advantageously at least one Beton3tahlotab (32) inserted iot. 15. Baukonstruktion nach einem der Punkte 1 bis 14, gekennzeichnet dadurch, daß die in den vorgefertigten Stahlbeton-Bauelementen (1) vorgespannte Drähte (3).ausschließlich oder ziuTi grüßten Teil in den zur ?lüsnigkeit hin entgegengesetzten Handzonen angeordnet sind.15. Construction according to one of the items 1 to 14, characterized in that in the prefabricated reinforced concrete structural elements (1) prestressed wires (3) are arranged exclusively or ziuTi grüßten part in the lüsnigkeit towards opposite hand zones. 16. Baukonstruktion nach einem der Punkte 1 bis 15, gekennzeichnet dadurch, daß das Bauwerk-ein Schwimmbecken ist, dessen Seitenwände (a) aus mehreren, sv/eckdienlichorv/eise in zwei Reihen angeordnete, plattenarige, qiiaderförmige, über waagerecht verlaufende Kanüle (20) verfügende vorgefertigte Stahlbeton-Bauelemente (1) aufgebaut sind, wobei die Bauelemente der untersten Reihe breiter als die der oberen Reihe (Reihen) sind und im Vergleich zu den Bauelementen der oberen Reihe in Richtung zum Beckenraum hervorspringen und dadurch einen umlaufenden Treppenabsatz (22) bilden (Pig. Il bis 13).16. Construction according to one of the items 1 to 15, characterized in that the building is a swimming pool whose side walls (a) of several, sv / eckdienlichorv / iron arranged in two rows, plate-like, qiiaderförmige, over horizontally extending cannula (20 ) prefabricated reinforced concrete components (1) are constructed, wherein the components of the bottom row are wider than those of the upper row (rows) and in comparison to the components of the upper row in the direction of the pelvic space and thereby protrude a circumferential landing (22) form (Pig. Il to 13). 17. Baukonstruktion nach einem der Punkte 1 bis 16, gekennzeichnet dadurch, daß das Bauwerk ein Schwimmbecken ist,17. Construction according to one of the items 1 to 16, characterized in that the building is a swimming pool, - 42 -- 42 - 21 8 65621 8656 in dessen Seitenwinden (a) in den obersten Randzonen Durchbrüche (25) vorgesehen sind, die das Eintreten des Wassers in die obersten Kanäle (20, 2) ermöglichen, wodurch die obersten, zweckdienlicherweise an das Y/asserableitsystem (13a bis 13g) der Seitenwände (a) angeschlossenen Kanäle Überlaufrinnen bilden (Pig. 11).in whose side winches (a) openings (25) are provided in the uppermost marginal zones, which allow the water to enter the uppermost channels (20, 2), whereby the uppermost, expediently, to the side walls (13a to 13g) (a) connected channels form overflow channels (Pig. 11). 18, Baukonstruktion nach einem der Punkte 1 bis 17, gekenn., zeichnet dadurch, daß das Bauwerk ein in den Erdböden eingesenktes Becken ist, bei dem zumindest entlang eines Teiler der Seitenwände (a) ein Gang (28) vorgesehen ist, der auf der der Beckenwand (a) entgegengesetzten Seite durch eine stabilisierende Erdböschung (29) abgegrenzt wird, und der .zweckdienlicherweise durch eine aus vorgefertigten Stahlbeton-Bauelenenten (1) bestehende De like (10) abgedeckt ist, die einerseits auf einen in die Böschung (29) in Höhe des Geländenivcaus errichteten Fundament (21) und andererseits auf den'Ringanker (11) der Beckenwand (a) abgestützt ist.(Pig. 11).18, building construction according to one of the items 1 to 17, characterized, characterized in that the building is a sunk in the ground basin, in which at least along a divider of the side walls (a) a passage (28) is provided which on the the basin wall (a) opposite side by a stabilizing Erdböschung (29) is demarcated, and the. Zweckdienlicherweise by a prefabricated reinforced concrete Bauelenenten (1) existing De like (10) is covered, on the one hand in the embankment (29) Supported at the level of Geländivcaus foundation (21) and on the other hand on den'Ringanker (11) of the pelvic wall (a) is supported. (Pig 11). 19e Baukonstruktion nach einem der Punkte 1 bis 17, gekennzeichnet dadurch, daß die die -Stahlbeton-Bauelemente (1) der Seitenwand (a) von außen abstützenden Säulen (39) Stahlprofile sind, deren unteres und oberes I^nde in mo~ nolitischen Stahlbeton-Ringankern (11, 4) eingespannt ist (Pig. 15, 17).19e Building construction according to one of the items 1 to 17, characterized in that the steel-concrete structural elements (1) of the side wall (a) are supported by columns (39) on the outside of steel profiles whose lower and upper walls are in monolithic reinforced concrete Ring anchors (11, 4) is clamped (Pig 15, 17). 20. Baukonstruktion nach Punkt 19, gekennzeichnet dadurch, daß die Säulen (39) U-Stahlprofile (41) sind, die mit ihren U-Schenkeln gegenüberliegen, wobei die zwischen zwei vorgefertigten Stahlbeton-Bauelementreihen (1) entstehende senkrechte Fuge zwischen diesen U-Schenkeln verläuft und die Bauelemente (1) unter Zwischenfügung eines Mikrozellen-Gummibandea- (30) an die Außenfläche der U-Schenkel angepreßt sind, während der zwischen den U-ßtahl-20. Construction according to item 19, characterized in that the columns (39) are U-steel profiles (41) which are opposite with their U-legs, whereby the vertical joint between two prefabricated reinforced concrete component rows (1) between these U- Legs runs and the components (1) with the interposition of a Mikrozellen-Gummibandea- (30) are pressed against the outer surface of the U-legs, while the between the U-ßahl- - 43- 43 218 656218 656 profilen (41) vorhandene Raum samt der senkrechten Fuge zwischen den Bauelementen (1) ausbetoniert ist (Pig. 17).Profiles (41) existing space including the vertical joint between the components (1) is concreted (Pig. 17). 21· Baukonstruktion nach Punkt 19 oder 20, gekennzeichnet dadurch, daß das untere Ende der aua Stahl hergestellten Säulen (39) einen in da3 Fundament (2a) der Bodenplatte (b) hineinreichenden, in diesen einbetonierten, im wesentlichen waagerechten Teil (41a) besitzt (Pig. 14).21 · Building construction according to item 19 or 20, characterized in that the lower end of the columns (39) made of steel has a substantially horizontal part (41a) extending into da3 foundation (2a) of the base plate (b) (Pig. 14). 22. Baukonstruktion nach den Punkten 19 bis 21m gekennzeichnet dadurch, daß zwischen den unteren und oberen monolitiachen Stahlbetonringanker (11, 4) ein- aus Stahl gefertigter, an die Säulen (39) befestigter dazwischenliegender Ringanker (lib) vorgesehen i3t (Pig. 14).22. Building construction according to items 19 to 21m, characterized in that between the lower and upper monolithic reinforced concrete ring anchors (11, 4) one intermediate ring anchor (lib) made of steel attached to the columns (39) is provided (Pig. 14). , 23. Baukonstruktion nach einem der Punkte 1 bis 22, gekennzeichnet dadurch, daß das Bauwerk auf Säulen (47) oberhalb dor Geländcebene angeordnet ist, wobei die Bodenplatte des Bauwerkes auf einem, auf den Säulen (47) angeordneten monolitischen oder/und vorgefertigten ilauptbalken ruht (Pig. 19). 23. Construction according to one of the items 1 to 22, characterized in that the building is arranged on columns (47) above dor terrain level, wherein the bottom plate of the building on a, on the columns (47) arranged monolithic and / or prefabricated ilauptbalken rests (Pig.19). 24. Baukonstruktion nach Punkt 23, gekennzeichnet dadurch, daß oberhalb der Hauptbalken (51, 52) in der Bodenplatte (b) ein monolitischer Stahlbeton-Oagerbalken (2a) vorgesehen ist, an den sich in die Hohlräume (2, 20) der vorgefertigten Stahlbeton-Bauelenente (l) hineinreichende Monolitbetonkerne (2d) anschließen, in die - zur Verhinderung der Sndplattenverdrehung - zur Längsrichtung des Hauptbalkens querliegende und im monolitischen Stahlbeton-Lagerbalken (2a) quer hindurchgehende Betonstahlstäbe (54) eingelegt sind (Pig. 21).24. Construction according to item 23, characterized in that above the main beam (51, 52) in the bottom plate (b) a monolithic reinforced concrete Oagerbalken (2 a) is provided at the in the cavities (2, 20) of the prefabricated reinforced concrete -Construction elements (l) connect monolith concrete cores (2d) which extend into them and into which are inserted reinforcing steel bars (54) which are transverse to the longitudinal direction of the main beam and which transversely penetrate the monolitic reinforced concrete bearing beam (2a) (Pig. 21). - 44 -- 44 - 21 β 65621β656 25. Baukonstruktion nach einem der Tunkte 1 big 24, gekennzeichnet dadurch, daß in den Wänden und/oder in der Bodenplatte zwischen den vorgefertigten Stahlbeton-Bauele- menten (l) wasserundurchlässig ausgefüllte, schmalere oder breitere Fugen vorhanden sind und die Ausfüllung der letzteren in der Bodenplatte (b) monolitische Stahlbeton-Lagerbalken, in den Seitenwänden (a) hingegen, sich an die abstützenden Pfeiler anschließende monolitische Stahlbetonkörper ergeben, wobei die Lagerbalken und/oder die sich an die Pfeiler anschließenden Körper in den von ihnen auf beiden Seiten liegenden Hohlräume ausgebildete Llonolitbetonkerne besitzen, in denen durch die Lagerbalken bzw. die Körper ebenfalls durchgehende, in Querrichtung angeordnete Betonstähle vorgesehen sind und die Lagerbalken'vorteilhafterweise mit je zwei Pfeilern bzw. sich an diese anschließenden mit den in den V/änden ausgebildeten monolitischen Stahlbotonkorpcrn verbunden sind und einen U-förnigen Rahmen bilden.25. Building construction according to one of the points 1 big 24, characterized in that in the walls and / or in the bottom plate between the prefabricated reinforced concrete building elements (l) water-impermeable filled, narrower or wider joints are present and the filling of the latter in the bottom plate (b) monolithic reinforced concrete bearing beams, in the side walls (a), on the supporting pillars adjoining monolithic reinforced concrete bodies, the bearing beams and / or adjoining the pillar body in lying on both sides of the cavities have trained Llonolitbetonkerne in which are provided by the bearing bar or the body also continuous, arranged in the transverse direction of reinforcing bars and the Lagerbalken'vorteilhafterweise with two pillars or connected to these subsequent with the V / änder monolithic Stahlbotonkorpcrn are connected and a U-shaped frame bil the. 26. Baukonstruktion nach einem der Punkte 1 bis 25, gekennzeichnet dadurch, daß die V/änuo clorj Bair.vcrlcoo in der durch Schrämtechnologie hergestellten Baugruben aus Hohlräume enthaltende vorgefertigte Gtahlbeton-Br.uelemente zusammengesetzt sind, in denen die·Hohlräume aufrecht- zweckdienlicherweisG senkrecht vorlaufen - und die Bauelemente mit ihrem untereniindo in einen durch Unterwasserbetonierung gefertigten, in Längsrichtung verlaufenden monolitischen Stahlbeton-Lagerbalkcn; ihre oberen 2nd en hingegen in einen monolitischen iJtahlbeton-Ringanker eingespannt sind, wobei ein Teil der Hohlräume durch I.ionolitbeton ausgefüllt ist, und in diese säulenartige llonolitbetonkerne Stahlbewehrungen eingelegt sind, die mindestens in den oberen Ringanker, vorteilhafterweise auch in den längsliegenden Lagerbalken hineinreichön, während die zwischen den vorgefertigten Bauelementen vor-26. A building structure according to any one of items 1 to 25, characterized in that the V / ñuo clorj Bair.vcrlcoo in the excavation-type excavation pits are composed of cavities containing prefabricated Gtahlbeton Br.uelemente in which the cavities uprightapproximately G perpendicular precursors - and the components with their lower sides into a longitudinal monolithic reinforced concrete bearing beam made by underwater concreting; their upper 2nd s are, however, clamped in a monolithic iJtahlbeton ring anchor, wherein a portion of the cavities is filled by I.ionolitbeton, and in these columnar llonolitbetonkerne steel reinforcements are inserted, at least in the upper ring anchor, advantageously also in the longitudinal bearing beam reaching, while those between the prefabricated components 21 8 65621 8656 handenen senkrechten Fugen mindestens zum Teil durch Unterwasserbetonierung abgedichtet sind.existing vertical joints are at least partially sealed by underwater concreting. 27. Baukonstruktion nach Punkt 26, gekennzeichnet dadurch, daß das 'Bauwerk ein Linienbauwerk mit geschlossenem Profil, insbesondere ein Unterpflastertunnel ist, in dessen parallel zueinanderliegenden Wänden die in je einem Hohlraum ausgebildeten monolitiachen Stahlbeton-Säulen einander gegenüber angeordnet sind und paarweise unten und/oder oben durch einen monolitischen Stahlbeton-Querbalken miteinander verbunden sind.27. Construction according to item 26, characterized in that the 'structure is a linear structure with a closed profile, in particular a sub-pavement tunnel, in whose mutually parallel walls each formed in a cavity monolithic reinforced concrete columns are arranged opposite each other and in pairs below and / or are interconnected above by a monolithic reinforced concrete crossbeam. 28, Baukonstruktion nach Punkt 27, gekennzeichnet dadurch, daß die Bodenplatte und/oder die Deckenplatte aus monolitischem Stahlbeton und/oder aus vorgefertigten Bauelementen mit Hohlräumen besteht.28, building construction according to item 27, characterized in that the bottom plate and / or the ceiling plate consists of monolithic reinforced concrete and / or prefabricated components with cavities. 29. Baukonstruktion nach einen der Punkte 1 bi3 2G, gekennzeichnet dadurch, daß die Bodenplatte aus mehreren, vorteilhafterweise aus zwei mit Hohlr'iunen versehenen, vorgefertigten Stahlboton-Bauelernentcrcihcn .bestehen und zwischen den beiden Reihen, -wasserdichter I.Iortel eingebracht ist.29. Building construction according to one of the points 1 bi3 2G, characterized in that the bottom plate of several, advantageously from two Hohlr'iunen provided, prefabricated Stahlboton Bauelernentcrcihcn .bestehen and between the two rows, watertight I.Iortel is introduced. 30. Baukonstruktion nach Punkt 29, gekennzeichnet dadurch, daß in den beiden Reihen die Hohlräume quer zueinander verlaufen.30. Construction according to item 29, characterized in that in the two rows, the cavities extend transversely to each other. 31. Baukonstruktion nach einem der Punkte 27 bis 30, gekennzeichnet dadurch, daß die monolitischen Stahlbeton-Lagerbalken an den Pugen zwischen den vorgefertigten Bauelementen in der V/eise ausgebildet sind, daß durch den Monolitbeton des Lagerbalkens auch die Bereiche der Hohlraumenden gefüllt werden und in die so entstehenden Betonkerne bzw. an diesen Stellen zur Längsrichtung der31. The construction according to any one of items 27 to 30, characterized in that the monolithic reinforced concrete bearing beams are formed on the Pugen between the prefabricated components in the V / eise that are filled by the monolithic concrete of the bearing bar, the areas of the cavity ends and in the resulting concrete cores or at these points to the longitudinal direction of " 4 " 21 8 656" 4 " 21 8 656 Querbalken quer liegende, auch 'in die Kerne hineinreichende Stahlbewehrungen in die Lagerbalken eingelegt sind.Crossbeams transverse, also 'in' the cores extending into steel reinforcements are inserted into the bearing beams. 32. Baukonstruktion nach Punkt 1 bis 31, gekennzeichnet dadurch, daß zur Verstärkung der Münde und zur Verbindung der benachbarten Stahlbeton-Bauelemente, in denen die Hohlräume liegend bzw. waagerecht.verlaufen, der Wandstärke in ihrer (Breite gleiche monoli tische Stahlbetonpfeiler in der V/eise ausgeführt sind, daß aus dem I.Ionolitbeton der Pfeiler in die Hohlräume der V/andelemente hineinreichende Kerne bzw. Ansätze ausgebildet sind und in diesen Kernen zur Längsrichtung der Pfeiler quorliegende und durch die Pfeiler hindurchgehende Bewehrungsstähle vorgesehen sind. 32. Building construction according to item 1 to 31, characterized in that for reinforcing the mouth and for connecting the adjacent reinforced concrete components in which the cavities horizontally or horizontally .verlaufen, the wall thickness in their ( width same monoli tables reinforced concrete pillars in the V / Eise are carried out that are formed from the I.Ionolitbeton the pillar in the cavities of V / andelemente in reaching cores or lugs and are provided in these cores to the longitudinal direction of the pillar quorliegende and passing through the pillars reinforcing bars. 33« Baukonstruktion nach Punkt 32, gekennzeichnet dadurch, daß die in Längsrichtung verlaufenden Betoncrfcahleinsätze des Pfeilers oder ein Großteil derselben auf der gezogenen, d.h. auf der mit der Flüssigkeit nicht in Berührung, kommenden Fläche vorgesehen ist«33 "Construction according to item 32, characterized in that the longitudinally extending concrete crimp inserts of the pillar or a large part thereof on the towed, i. on which the surface is not in contact with the liquid " 34» Baukonstruktion nach Punkt 32 oder 33, gekennzeichnet dadurch, daß on den zueinander parallel verlaufenden V/änden einander gegenüberstehende Säulen ausgebildet sind und zwischen den Säulen Je eines Säulenpaares auch in der aus Hohlräume enthaltenden vorgefertigten Stahlbeton-Bauelementen bestehenden Bodenplatte ein derartiger monolitischer Stahlbeton-Lagerbalken ausgebildet und an die Säulen angeschlossen ist, der über in die Hohlräume der Bauelemente hineinriechonde Ilonolitbetonkerne verfügt, und in diesen zur Längsrichtung des Lagerbalkens querverlaufende und durch diesen hindurchgeführte Stahleinlagen vorgesehen sind.34 »Building construction according to item 32 or 33, characterized in that on the mutually parallel V / änden opposing columns are formed and between the columns of each pair of columns in the existing of cavities prefabricated reinforced concrete elements floor plate such a monolithic reinforced concrete A bearing bar is formed and connected to the columns, which has in the cavities of the components hineinriechonde Ilonolitbetonkerne, and are provided in this transverse to the longitudinal direction of the bearing bar and guided through this steel inserts. .!!.....Seiten Zeichnungen. !! ..... pages drawings
DD21865680A 1979-07-30 1980-01-25 WATER-IMPROPER CONSTRUCTION DD148800A5 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
HUPO000531 HU176862B (en) 1979-07-30 1979-07-30 Construction limited by wqter-tight structures particularly basin,e.g. fluid storing basin.swimming pool or similar

Publications (1)

Publication Number Publication Date
DD148800A5 true DD148800A5 (en) 1981-06-10

Family

ID=11000573

Family Applications (1)

Application Number Title Priority Date Filing Date
DD21865680A DD148800A5 (en) 1979-07-30 1980-01-25 WATER-IMPROPER CONSTRUCTION

Country Status (7)

Country Link
CS (1) CS233714B2 (en)
DD (1) DD148800A5 (en)
DE (1) DE3002739C2 (en)
FR (1) FR2462532A1 (en)
HU (1) HU176862B (en)
PL (1) PL125175B1 (en)
YU (1) YU41903B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2689552A1 (en) * 1992-04-03 1993-10-08 Andrei Gerard Construction system for swimming pool with liner - uses sectional reinforced base components with sloping edges and walls made from hollow blocks filled with concrete after inserting reinforcing steel rods
FR2850997B1 (en) * 2003-02-10 2006-01-13 Jean Lermite MODULAR SWIMMING POOL
ES2298037B1 (en) * 2006-05-23 2009-07-21 Ceramica Sugrañes, S.A. POOL AND PROCEDURE FOR CONSTRUCTION.

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH23514A (en) * 1901-04-01 1902-07-31 C Butticaz Tank with drainage device
US2157290A (en) * 1939-02-13 1939-05-09 William P Witherow Drain for foundation walls
FR1014520A (en) * 1942-02-09 1952-08-18 Haes Ets Improvements made to tanks, in reinforced concrete, for liquids or finely divided materials
CH348370A (en) * 1956-11-19 1960-08-15 Hartmann Julius Process for the production of a sewage treatment plant and sewage treatment plant produced according to this process
DE1434605A1 (en) * 1960-03-04 1969-03-13 Babcock & Wilcox Dampfkessel W Liquid container with double wall
GB894105A (en) * 1960-04-07 1962-04-18 Michael Dermot Solon Improvements in or relating to cylindrical water tanks, silos and the like large containers
US3287866A (en) * 1963-10-23 1966-11-29 Robert J Rider Foundation and wall drainage system
FR1500859A (en) * 1966-06-16 1967-11-10 Commerciales Et De Sciences Ap Foundations for pools especially
FR2148899A5 (en) * 1971-08-03 1973-03-23 Carles Yvan
US3852925A (en) * 1973-06-25 1974-12-10 J Gazzo Method and means for maintaining a dry basement
US4015783A (en) * 1975-07-10 1977-04-05 American Pulverizer Company Reversible grate bar and support for crushers

Also Published As

Publication number Publication date
PL221594A1 (en) 1981-01-30
YU41903B (en) 1988-02-29
YU19680A (en) 1984-02-29
FR2462532B1 (en) 1983-12-30
CS233714B2 (en) 1985-03-14
FR2462532A1 (en) 1981-02-13
DE3002739A1 (en) 1981-02-05
DE3002739C2 (en) 1983-09-08
PL125175B1 (en) 1983-04-30
HU176862B (en) 1981-05-28

Similar Documents

Publication Publication Date Title
DE69926791T2 (en) STAUDAMM AND SEALING METHOD
DE4024176A1 (en) Covered drain channel system - is made up of precast concrete components having sides and cover in one piece
DE3708081A1 (en) METHOD FOR BUILDING SEEDER PLANTS
EP0322667B1 (en) Method for building a wall, construction element and connection slab for applying the method, and wall built by the method
EP0322668A1 (en) Building blocks for wall constructions, and wall built with the building blocks
EP1267035B1 (en) Method for constructing underground waterproof tunnels with a concrete inner shell
DE202021105799U1 (en) Protective construction for high incline embankments in layered sloping soils in the coal mine
CH610966A5 (en) Rock or slope revetment and method of constructing it
DE1811682C3 (en) Lost formwork for a retaining wall
DD148800A5 (en) WATER-IMPROPER CONSTRUCTION
DE2917994C2 (en) Process for the production of a construction pit sheeting or retaining wall made of reinforced concrete for terrain cuts
EP1426495A2 (en) Method and device for the construction of a tunnel or a trench
DE102005013993B3 (en) Foundation for a flood protection
DE1634589B2 (en) PILE GRATING MADE FROM CONCRETE PILES
EP1067243B1 (en) Catchment basin for above ground water and construction method thereof
DE20219139U1 (en) Infiltration and retention system for rainwater
DE3727752C2 (en)
DE2803860C2 (en) Method of making a retaining wall
WO2004044334A1 (en) Floodwater protection system
AT317092B (en) Process for the production of a trough arranged in the ground below the groundwater level and for this purpose prefabricated reinforced concrete girders for their production
DE315867C (en)
DE3514333A1 (en) Method of producing a concrete structure, preferably a tunnel tube
AT271552B (en) Tunnel body for underground railways and process for its manufacture
DE3210659A1 (en) Sheeting, in particular for formwork
DE3214648A1 (en) Method of producing foundations for shell-shaped containers