CN219974012U - Assembled bathroom - Google Patents

Assembled bathroom Download PDF

Info

Publication number
CN219974012U
CN219974012U CN202223251688.XU CN202223251688U CN219974012U CN 219974012 U CN219974012 U CN 219974012U CN 202223251688 U CN202223251688 U CN 202223251688U CN 219974012 U CN219974012 U CN 219974012U
Authority
CN
China
Prior art keywords
groups
wallboards
keels
waterproof
wallboard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223251688.XU
Other languages
Chinese (zh)
Inventor
彭秀峰
广宇昊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Construction Engineering Yuyuan Architectural Decoration Co ltd
Original Assignee
Chongqing Construction Engineering Yuyuan Architectural Decoration Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Construction Engineering Yuyuan Architectural Decoration Co ltd filed Critical Chongqing Construction Engineering Yuyuan Architectural Decoration Co ltd
Priority to CN202223251688.XU priority Critical patent/CN219974012U/en
Application granted granted Critical
Publication of CN219974012U publication Critical patent/CN219974012U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Residential Or Office Buildings (AREA)

Abstract

The utility model relates to the technical field of toilets, in particular to an assembled bathroom, which comprises a waterproof chassis, wherein clamping strips are arranged at the positions, close to four sides, of the top end of the waterproof chassis, the four groups of clamping strips are movably clamped with corresponding wallboards through corresponding mounting clamping grooves, a reserved door slot is formed in the position, close to the middle, of the bottom end of one group of wallboards, and a plurality of groups of transverse keels and a plurality of groups of vertical keels are arranged on the outer surfaces of the four groups of wallboards. The aviation resin composite material is adopted to replace the traditional waterproof coiled material and paint wet operation, so that the efficacy and quality of waterproof construction are improved. The adopted aviation resin composite material has the advantages of light weight, toughness and durability, and the toilet chassis is firstly leveled and installed through the special regulator. The waterproof chassis is connected with the sewage drain pipe by installing the sewage drain flange. And ensure that the water outlet is tight and does not leak. And secondly, when the wallboard is installed, accurately positioning by adopting an infrared laser instrument, and checking the installation verticality of the wall body.

Description

Assembled bathroom
Technical Field
The utility model relates to the technical field of toilets, in particular to an assembled toilet.
Background
The bathroom is a combination of a toilet, a bathroom and a bath pool, and the bathroom of a residence is generally divided into a special room and a public room, and the special room only serves a master bedroom; the public is connected with the public walkway, is public by other family members and guests, can be divided into three types of independent type, dual-purpose type and folding type according to the layout, can be divided into a semi-open type, an open type and a closed type according to the form, and the assembled bathroom is used more and more currently, namely the main body structure of the bathroom is prefabricated in advance, and finally the assembled bathroom is installed in a house, so that the assembled bathroom is very convenient to install.
The existing assembled bathroom has the problems that the bottom surface of the bathroom cannot be in a horizontal state due to the fact that the bottom surface of the bathroom is affected by the foundation easily during construction and installation, and normal use is affected, and meanwhile, the bottom surface of the bathroom cannot be perpendicular to the bottom surface of the bathroom during wallboard installation, and therefore the overall installation efficiency and the final overall quality are affected.
Disclosure of Invention
The present utility model is directed to an assembled toilet, which solves the above-mentioned problems.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides an assembled bathroom, includes waterproof chassis, the card strip is all installed to the top of waterproof chassis by the position of four sides, and four groups card strip are movable joint setting through corresponding installation draw-in groove and corresponding wallboard respectively, and one of them set of reserve the door pocket has been seted up to the bottom of wallboard by the position in the middle, four groups the surface of wallboard all is provided with a plurality of groups of horizontal fossil fragments and a plurality of groups of vertical fossil fragments, four groups the top of wallboard corresponds one side with the bottom of ceiling respectively and is fixed mutually.
Preferably, the bottom end of the waterproof chassis is provided with a plurality of groups of regulators, and the corresponding groups of regulators are respectively placed at corresponding positions of the foundation.
Preferably, the corresponding plurality of groups of transverse keels and the corresponding plurality of groups of vertical keels are uniformly distributed on the outer side surfaces of the corresponding wallboards, and the corresponding plurality of groups of transverse keels and the corresponding plurality of groups of vertical keels are arranged in a crisscross manner.
Preferably, the distance between the corresponding groups of transverse keels and the corresponding groups of vertical keels is larger than 1200mm, and the two groups of wallboards are fixed by using connecting fixture bolts.
Preferably, the two groups of wallboards are fixed through right angle boards, and a gap of 4-5 mm is kept between the two groups of wallboards at the corner of the wall, so that the length of the sealing strip for installing the sealing strip is consistent with that of the wallboard.
Preferably, the bottom ends of the plurality of groups of regulators are respectively arranged on the foundation of the bathroom through corresponding expansion bolts, and the plurality of groups of regulators are aligned by adopting an infrared level meter.
Compared with the prior art, the utility model has the beneficial effects that:
the aviation resin composite material is adopted to replace the traditional waterproof coiled material and paint wet operation, so that the efficacy and quality of waterproof construction are improved. The adopted aviation resin composite material has the advantages of light weight, toughness and durability, and the toilet chassis is firstly leveled and installed through the special regulator. The waterproof chassis is connected with the sewage drain pipe by installing the sewage drain flange. And ensure that the water outlet is tight and does not leak. And secondly, when the wallboard is installed, accurately positioning by adopting an infrared laser instrument, and checking the installation verticality of the wall body.
Drawings
Fig. 1 is a schematic perspective view of the structure of the main body of the present utility model.
Fig. 2 is an enlarged schematic view at a in fig. 1.
Fig. 3 is a schematic structural perspective view of the waterproof chassis of the present utility model.
In the figure: 1. a waterproof chassis; 11. an adjustor; 12. clamping strips; 2. a wallboard; 21. reserving a door slot; 22. installing a clamping groove; 23. a transverse keel; 24. a vertical keel; 3. and a ceiling.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1 to 3, the present utility model provides a technical solution: the utility model provides an assembled bathroom, including waterproof chassis 1, waterproof chassis 1's bottom is provided with a plurality of groups of regulator 11, and correspond a plurality of groups of regulator 11 and place respectively on the corresponding position of ground, a plurality of groups of regulator 11's bottom is installed on the bathroom ground through corresponding expansion bolts respectively, and correspond a plurality of groups of regulator 11 and adopt infrared ray spirit level to adjust, waterproof chassis 1's top is by the position of four sides all installing card strip 12, and four groups of card strip 12 are movable joint setting with corresponding wallboard 2 through corresponding installation draw-in groove 22 respectively, wherein reserve door groove 21 has been seted up to the bottom of a set of wallboard 2 by the position in the middle, four groups of wallboard 2's surface all is provided with a plurality of groups of horizontal fossil fragments 23 and a plurality of groups of vertical fossil fragments 24, correspond a plurality of groups of horizontal fossil fragments 23 and correspond a plurality of groups of vertical fossil fragments 24 evenly distributed on the outside surface of corresponding wallboard 2, and correspond a plurality of groups of horizontal fossil fragments 23 and correspond a plurality of groups of vertical fossil fragments 24 and be the setting of cross, correspond a plurality of groups of horizontal fossil fragments 23 and correspond a plurality of groups of vertical fossil fragments 24 and be the interval of vertical fossil fragments of vertical keel is greater than 1200mm, and the wallboard 2 is connected between the wallboard 2, and the wallboard 2 is fixed with the top of the wallboard 2 and the corresponding ceiling 3 is fixed with the corresponding bottom of a plurality of one side of the fixing clamp respectively.
The two groups of wallboards 2 are fixed through the right angle plates, and a gap of 4-5 mm is kept between the two groups of wallboards 2 at the corner of the wall, so that the length of the installation sealing strip of the sealing strip is consistent with that of the wallboards 2.
The scheme is an improvement innovation of the existing assembly type bathroom assembly technology, and aims at an integrated bathroom comprising a top, a bottom, walls and all bathroom facilities. The aviation resin composite material is adopted to replace the traditional waterproof coiled material and paint wet operation, so that the efficacy and quality of waterproof construction are improved. The adopted aviation resin composite material has the advantages of light weight, toughness and durability, the weight is less than one fifth of that of the ceramic tile, but the strength is greatly higher than that of the ceramic tile, the ceramic tile cannot crack, deform and fall off when cut, and the service life is as long as 20 years. Toilet products such as toilets, bathtubs, hand washing tables and the like are just like parts, and can be integrated into the whole body through assembly, so that the characteristics of attractive appearance, compactness, strong waterproofness and the like are achieved. First, the toilet pan is installed by leveling through the proprietary regulator 11. The waterproof chassis 1 is connected with a sewage drain pipe by installing a sewage drain flange. And ensure that the water outlet is tight and does not leak. And secondly, when the wallboard 2 is installed, accurately positioning by adopting an infrared laser instrument, and checking the installation verticality of the wall body. The vertical plates are connected by utilizing the reserved clamping grooves of the bottom plates, and the connection between the walls is connected by utilizing reserved connecting pieces. And finally, installing a top cover. After the integral toilet is installed, a layer of light steel keel and an Emmet board light partition wall is installed on the outer wall of the toilet for decoration and closing, the distance between the assembled integral toilet and the partition wall is kept at 3-4 cm, and the finished surface is flat with the wall surface in the suite. And keeps consistent with the decoration style of the wall surface of the suite, and the advantages of the external-installation integrated bathroom are highlighted. The application of the assembly engineering is of great significance.
The floor surface of the integrated toilet is required to be flat, water accumulation and sand dust free, the floor surface of the original toilet is found to be horizontal (+ -5 mm), and the elevation of the toilet is unified. Checking whether the flatness of the ground meets the installation requirements of the horizontal waterproof chassis 1 and the vertical waterproof chassis 1, leveling by using a round special adjuster 11 instead of a traditional foundation bolt, then fixedly installing the round adjuster 11 by adopting an expansion bolt, ensuring the level of the waterproof chassis 1, aligning by adopting an infrared level meter when the waterproof chassis 1 is installed, and ensuring the level of the waterproof chassis 1.
The back edge of the wallboard 2 is reinforced by adopting transverse and vertical steel keels on the basis of the original aviation resin composite material, the distance between the keels is not more than 1200mm, and the reinforced keels are fixed by connecting fixture bolts. The integral rigidity and stability of the wallboard 2 are improved, and when the wallboard 2 is installed, the infrared laser instrument is adopted for accurate positioning, and the installation verticality of the wall body is checked in the whole installation process. The back of riser is connected with the reserved draw-in groove of bottom plate, and the connection between the wall is connected with the connecting piece of reservation, before wallboard 2 is assembled, need take off 5cm to the protection film from wallboard 2 edge to avoid the protection film to press from both sides between two wallboards 2, hardly take off afterwards. The square steel screw at the corner of the wall needs to be provided with at least 3 to 4 self-tapping screws, one screw is arranged at the upper part and the lower part, and the middle two screws are arranged at the middle part, and when the wallboard 2 is installed, an infrared laser instrument is adopted for accurate positioning, and the installation verticality of the wall is checked. The back of the vertical plate is connected by utilizing a reserved clamping groove of the bottom plate, the wall plate is connected with the waterproof chassis 1, and after the wall plate 2 is assembled, a gap of 4-5 mm is kept between the two wall plates 2 at the corner of the wall, so that the length of the installation sealing strip of the sealing strip is kept consistent with that of the wall plates 2, and the tightness of the integrated bathroom is ensured.
When the ceiling 3 is installed, dust and sundries at the upper end of the wallboard 2 are removed completely, so that the ceiling 3 falls into the upper end face of the wallboard 2 all around, the periphery is uniformly overlapped with the wallboard 2, then the fixing bolts are fixed, the fixing bolts are firmly installed, gaskets are required to be additionally installed at two sides, and all reserved holes are required to be fixed by bolts.
The method for closing the decorative outer wall of the bathroom is to adopt a light steel keel and an Eastet plate light partition wall to close the outer side of the bathroom. Namely, a layer of light steel keel Earthward light partition wall is arranged on the outer wall of the bathroom, the distance between the assembled bathroom and the partition wall is kept between 3 and 4cm, and the finished surface is flat with the wall surface in the suite. And keeps consistent with the decoration style of the wall surface of the suite, and the advantages of the external integrated bathroom are highlighted.
The drain flange is arranged to connect the drain pan with the drain pipe. After the waterproof disc is put in, the center of the outer drain pipe is required to be aligned with the drain hole of the waterproof disc. And uniformly coating glass cement on the lower surface of the pollution discharge flange, and coating PVC (polyvinyl chloride) cement on the joint of the pipe fittings. The drain flange is buckled into the drain hole, a circle of sealant is coated around the drain flange and is trowelled, the metal hose connector is necessarily parallel to the centers of the connectors, rubber sealing rings are required to be arranged, the insertion depth of the joint part of each pipe fitting is required to reach the maximum value, the pipe fitting is properly rotated by a certain angle after being inserted in place, PVC (polyvinyl chloride) glue at the connector is uniformly distributed, the construction side is required to ensure 2% of gradient when carrying out external drain pipe operation, and the drain pipe is required to ensure 1.5% of gradient.
Finally, the test is needed checking and accepting,
1. Pressurized test of water supply system
Firstly, the water in the pipe must be slowly filled, and the water filling point is at the lowest point, so that the air is conveniently discharged. After the pipes are filled with water, each pipe and its joint are checked under static pressure to see if water leaks. The pipeline is slowly boosted by a water pump for at least 10 minutes, and the minimum pipeline pressure is required to be at least 0.6Mpa. After the pressure was raised to a predetermined test pressure, the pressure was stabilized for 1 hour, and each joint was checked for water leakage.
2. Irrigation test
And (3) performing a water filling test after the assembly of the integrated toilet, filling the installed pipeline with water, wherein the water filling height of the integrated toilet is not lower than the height of the upper edge or the chassis surface of the bottom-layer sanitary ware. The chassis should also be used for a water filling test, and the floor drain is filled with water 5-10 cm above the surface of the chassis after being plugged.
The drainage pipeline is filled with water, and water is added to the raw water surface if the water surface is lowered after 1h until the water surface is not lowered, and meanwhile, the detection pipeline and the interface are qualified in terms of no seepage and no leakage, and the test meets the requirements of the building water supply and drainage and heating engineering construction quality acceptance Specification GB 50242-2002. 1h after the chassis is irrigated to a specified height, the water surface is not lowered, and the chassis is qualified in terms of no seepage and no leakage.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. Assembled bathroom, including waterproof chassis (1), its characterized in that: clamping strips (12) are arranged at the top end of the waterproof chassis (1) near the positions of four sides, and four groups of clamping strips (12) are movably clamped with corresponding wallboards (2) through corresponding mounting clamping grooves (22), wherein a group of clamping strips are arranged at the bottom end of each wallboard (2) near the middle position, reserved door grooves (21) are formed in the positions near the middle, a plurality of groups of transverse keels (23) and a plurality of groups of vertical keels (24) are arranged on the outer surface of each wallboard (2), and the top ends of the wallboards (2) are fixed with one corresponding side of the bottom end of a ceiling (3) respectively.
2. A fabricated toilet as claimed in claim 1, wherein: the bottom end of the waterproof chassis (1) is provided with a plurality of groups of regulators (11), and the corresponding groups of regulators (11) are respectively placed at corresponding positions of the foundation.
3. A fabricated toilet as claimed in claim 1, wherein: the corresponding groups of transverse keels (23) and the corresponding groups of vertical keels (24) are uniformly distributed on the outer side surfaces of the corresponding wallboards (2), and the corresponding groups of transverse keels (23) and the corresponding groups of vertical keels (24) are arranged in a crisscross manner.
4. A fabricated toilet as claimed in claim 1, wherein: the distance between the corresponding groups of transverse keels (23) and the corresponding groups of vertical keels (24) is larger than 1200mm, and the two groups of wallboards (2) are fixed by connecting fixture bolts.
5. A fabricated toilet as claimed in claim 1, wherein: the two groups of wallboards (2) are fixed through right angle boards, and a gap of 4-5 mm is kept between the two groups of wallboards (2) at the corner of the wall, so that the length of the mounting sealing strip of the sealing strip is consistent with that of the wallboards (2).
6. A fabricated toilet as claimed in claim 2, wherein: the bottom ends of the plurality of groups of regulators (11) are respectively arranged on the foundation of the bathroom through corresponding expansion bolts, and the corresponding plurality of groups of regulators (11) are aligned by adopting an infrared level meter.
CN202223251688.XU 2022-11-30 2022-11-30 Assembled bathroom Active CN219974012U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223251688.XU CN219974012U (en) 2022-11-30 2022-11-30 Assembled bathroom

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223251688.XU CN219974012U (en) 2022-11-30 2022-11-30 Assembled bathroom

Publications (1)

Publication Number Publication Date
CN219974012U true CN219974012U (en) 2023-11-07

Family

ID=88583812

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223251688.XU Active CN219974012U (en) 2022-11-30 2022-11-30 Assembled bathroom

Country Status (1)

Country Link
CN (1) CN219974012U (en)

Similar Documents

Publication Publication Date Title
CA2514275C (en) Shower receptor
CN103397790A (en) Assembled bathroom and installation process
CN106836516B (en) A kind of integrated water-proof chassis of toilet pipeline
CN101363244A (en) Inner wall board system and mounting method thereof
CN112240108A (en) Construction method of assembly type building integrated bathroom system
CN210508509U (en) Same-floor drainage assembly type waterproof toilet system
CN212613960U (en) Assembled bathroom system
CN203394108U (en) Fabricated bathroom
AU2020256635A1 (en) Panel and panel assembly for modular wet area construction
CN219974012U (en) Assembled bathroom
CN204627039U (en) A kind of integral vacuum toilet
CN110644814A (en) Integrated bathroom and assembling method thereof
CN213773708U (en) Wall side floor drain installation watertight fittings
CN206625609U (en) Quick decoration system
CN205024824U (en) Bathroom mounting structure
CN114176439A (en) Assembled barrier-free integrated bathroom chassis and installation method thereof
CN201276755Y (en) Major structure of combined house
CN106499221A (en) Quick decoration system
CN206554180U (en) A kind of integrated water-proof chassis of toilet pipeline
CN208105948U (en) A kind of shower house preventing water leakage back board fixing device
CN214615662U (en) Integrally-assembled waterproof shower room
CN104790472A (en) Same floor drainage structure of toilet
CN117468767A (en) Construction method of assembled building integrated bathroom system
CN216076098U (en) Mounting structure on waterproof ground of assembled
CN103982042A (en) Split mounting technique of quick home-decoration split mounting engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant