CN211689728U - Assembled temporary road - Google Patents

Assembled temporary road Download PDF

Info

Publication number
CN211689728U
CN211689728U CN201921882599.0U CN201921882599U CN211689728U CN 211689728 U CN211689728 U CN 211689728U CN 201921882599 U CN201921882599 U CN 201921882599U CN 211689728 U CN211689728 U CN 211689728U
Authority
CN
China
Prior art keywords
noise reduction
temporary road
layer
steel plate
prefabricated steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921882599.0U
Other languages
Chinese (zh)
Inventor
郝孟辉
刘洁
梅世浩
刘保珠
冯禄卿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Provincial Communication Planning and Design Institute Co Ltd
Original Assignee
Henan Provincial Communication Planning and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Provincial Communication Planning and Design Institute Co Ltd filed Critical Henan Provincial Communication Planning and Design Institute Co Ltd
Priority to CN201921882599.0U priority Critical patent/CN211689728U/en
Application granted granted Critical
Publication of CN211689728U publication Critical patent/CN211689728U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

An assembled temporary road comprises a steel plate surface layer, a honeycomb noise reduction layer, a gravel cushion layer and a soil layer which are sequentially arranged from top to bottom; the steel plate surface layer comprises a plurality of prefabricated steel plates, and the adjacent prefabricated steel plates are connected through connecting pieces; the honeycomb noise reduction layer comprises a precast block, noise reduction holes which penetrate through the precast block in the thickness direction are distributed in the precast block, a drainage channel is connected between the adjacent noise reduction holes, and the drainage channel is arranged inside the precast block. The utility model discloses an assembled temporary road, this road simple structure, construction convenience, but reuse, energy-concerving and environment-protective in job site temporary road of the same type, has extensive using value and market prospect.

Description

Assembled temporary road
Technical Field
The utility model belongs to assembled road field especially relates to an assembled temporary road.
Background
In the construction process of modern buildings, temporary roads in project sites are often hardened in order to meet the traffic needs and the purposes of preventing and controlling dust in the project sites and meet the requirements of construction civilization and construction specifications.
At present, temporary road hardening is commonly adopted as follows: after the cast-in-place concrete structure and the cast-in-place concrete pavement structure are poured, long-time moisture preservation and maintenance are needed, the construction period is prolonged, and the construction progress is influenced. Meanwhile, after rolling of a large truck on a construction site, a pavement structure is easy to damage, and pavement repair is time-consuming and labor-consuming. In addition, after the construction is finished, the temporary road of the construction site is generally subjected to removal treatment, so that a great deal of waste of manpower, material resources and financial resources is caused, a great deal of construction waste is generated, the environment is harmed, and the requirements of green construction, energy conservation and environmental protection advocated by the state are not met.
In recent years, with the improvement of enterprise cost saving consciousness and energy-saving and environment-friendly consciousness, some cities and construction units begin the research of prefabricated assembled modular roads.
The assembled steel plate temporary road has the advantages of high structural strength, high construction speed, low maintenance cost, reusability and the like, and is popularized and applied in part of domestic construction units at present.
However, as the application becomes widespread, the assembled steel plate pavement gradually exposes some disadvantages:
1, when rolling by a vehicle, the steel plate can vibrate to generate larger noise;
2 the vehicle is when business turn over job site, all need wash, and the sewage after washing can't in time be discharged, can cause the large tracts of land ponding on job site road surface, and can cause the road surface to skid, influences driving safety, can pollute the job site in addition.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing an implement convenient, excellent in use effect's assembled temporary road.
In order to solve the technical problem, the utility model provides a following technical scheme: an assembled temporary road comprises a steel plate surface layer, a honeycomb noise reduction layer, a gravel cushion layer and a soil layer which are sequentially arranged from top to bottom; the steel plate surface layer comprises a plurality of prefabricated steel plates, and the adjacent prefabricated steel plates are connected through connecting pieces; the honeycomb noise reduction layer comprises precast blocks, noise reduction holes penetrating in the thickness direction of the precast blocks are distributed in the precast blocks, a drainage channel is connected between every two adjacent noise reduction holes, and the width and the height of each drainage channel are 30-50 mm; the drainage channel is arranged inside the precast block.
The connecting piece comprises a connecting plate, wherein 4 connecting holes are distributed in the connecting plate, and the connecting line of the 4 connecting holes is rectangular; 4 prefabricated holes are distributed on the prefabricated steel plate and are arranged close to the included angle of the prefabricated steel plate; 4 connecting holes on the same connecting plate are respectively connected with the prefabricated holes of 4 prefabricated steel plates.
A drainage ditch is reserved between the adjacent prefabricated steel plates.
The cross section of the noise reduction hole is hexagonal.
The gravel cushion layer is composed of stones, and the particle size of the stones is 5-30 mm.
The thickness of the gravel cushion layer is 100-300 mm.
The aperture of the noise reduction hole is 80-100 mm.
And anti-rust layers are arranged on the surfaces of the prefabricated steel plate and the honeycomb noise reduction layer.
The prefabricated steel plate is 1000mm multiplied by 1000mm in size and 15 mm-25 mm in thickness.
Through the technical scheme, the beneficial effects of the utility model are that: (1) the steel plate surface layer and the honeycomb noise reduction layer can be prefabricated, the construction period is shortened, and the traffic is opened quickly. (2) Set up drainage channel between the hole of making an uproar falls in the honeycomb, can effectively improve drainage efficiency, prevent that temporary road surface ponding is too much, guarantee driving safety. (3) The noise reduction holes can effectively reduce the automobile noise and achieve the aim of civilized construction. (4) The prefabricated steel plates are connected through the connecting pieces, so that the size between the adjacent prefabricated steel plates can be effectively controlled, and the purposes of attractiveness and practicability are achieved.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural diagram of a steel plate surface layer;
FIG. 3 is an enlarged view of portion A of FIG. 2;
fig. 4 is a schematic diagram of a honeycomb noise reduction layer structure.
Detailed Description
An assembled temporary road comprises a steel plate surface layer 1, a honeycomb noise reduction layer 2, a gravel cushion layer 3 and a soil layer 4 which are sequentially arranged from top to bottom as shown in figure 1.
The soil layer 4 is positioned at the bottommost part and is used as a foundation of the whole temporary road; the soil layer 4 is here tamped.
The gravel cushion layer 3 is located on the soil layer 4, waste stones can be directly used on the construction site and serve as secondary support, and the thickness of the gravel cushion layer 3 is 100-300 mm. In the embodiment, the broken stone cushion layer 3 consists of stones, wherein the particle size of the stones is 5-30 mm; the stones with the particle size range are convenient to implement, the road stability is higher, and meanwhile, the effects of noise reduction and drainage can be achieved to a certain extent.
The honeycomb noise reduction layer 2 is used for reducing noise and simultaneously realizing drainage. Wherein, the honeycomb noise reduction layer 2 comprises precast blocks, and the construction period can be shortened by selecting the precast blocks, so that the traffic is opened rapidly. The precast block is also made of steel. An anti-rust layer is arranged on the outer surface of the precast block, so that the service time of the temporary road is prolonged. Evenly distributed has the hole 9 of making an uproar that falls that runs through the setting along prefabricated section thickness direction on the prefabricated section, and the cross section of the hole 9 of making an uproar that falls is personally submitted the hexagon, and the aperture of the hole 9 of making an uproar that falls is 80~100mm, and heavy road surface aperture can set up a little more, and medium-sized road surface is inferior, and light road surface aperture can set up a little to satisfy the intensity requirement. The noise reduction holes 9 can effectively reduce the noise of the automobile and achieve the aim of civilized construction.
And a drainage channel 10 is connected between the adjacent noise reduction holes 9, the drainage channel 10 is arranged in parallel to the precast block, and in addition, the drainage channel 10 is arranged inside the precast block. Size of cross section of the drain passage 10: the width and the height are both 30-50 mm. The size of the drainage channel 10 is limited because the too narrow noise reduction holes 9 are likely to cause clogging of sand and mud during drainage, which affects the drainage effect. The drainage channel 10 can effectively improve drainage efficiency, prevent that temporary road surface ponding is too much, guarantee driving safety.
The steel plate surface course 1 has a certain strength, and a vehicle can run on the steel plate surface course.
The steel plate surface layer 1 comprises a plurality of prefabricated steel plates 5, the construction period can be shortened through the prefabricated steel plates 5, the size of each prefabricated steel plate 5 is 1000mm multiplied by 1000mm, and the thickness of each prefabricated steel plate is 15 mm-25 mm. An anti-rust layer is arranged on the surface of the prefabricated steel plate 5, so that the service time of the steel plate surface layer 1 is prolonged.
A drainage ditch 8 is reserved between the adjacent prefabricated steel plates 5, so that water on the road surface can be drained in time, and the construction environment is prevented from being influenced by accumulated water.
The adjacent prefabricated steel plates 5 are connected through a connecting piece, wherein the connecting piece comprises a connecting plate 7, 4 connecting holes are distributed in the connecting plate 7, and connecting lines of the 4 connecting holes are rectangular. 4 prefabricated holes 6 are distributed on the prefabricated steel plate 5, and the prefabricated holes 6 are arranged close to the included angle of the prefabricated steel plate 5; the 4 connecting holes on the same connecting plate 7 are respectively connected with the prefabricated holes 6 of the 4 prefabricated steel plates 5, so that the 4 prefabricated steel plates 5 are connected through the 4 connecting holes. The connecting mode of the connecting hole and the prefabricated hole 6 is in threaded connection, and the connecting mode is simple to install and convenient to detach.
In this embodiment, couple together adjacent prefabricated steel sheet 5 through the connecting piece can be better control the clearance between the adjacent prefabricated steel sheet 5, 8 width unanimity in the escape canal groove of whole steel sheet surface course 1, improve road quality.
The installation steps of this embodiment are:
(1) the prefabricated steel plate of the steel plate surface layer is manufactured in advance, and the prefabricated block of the honeycomb layer is also manufactured;
(2) marking the edge line of the width of the pavement with lime;
(3) tamping the soil foundation, then paving a gravel cushion layer on the soil foundation, paving the gravel cushion layer to a thickness of 100-300 mm according to the specific situation on site, and then uniformly tamping the gravel cushion layer by using a small tamper;
(4) laying a noise reduction layer on the gravel cushion layer;
(5) and (3) paving prefabricated steel plates from the edge of the road, connecting the adjacent prefabricated steel plates with the help of a connecting plate and a bolt, and paving the prefabricated steel plates in sequence until the whole road is paved.
The utility model discloses an assembled temporary road, this road simple structure, construction convenience, but reuse, energy-concerving and environment-protective has the better noise reduction and drainage effect, in the temporary road of job site of the same type, has extensive using value and market prospect.

Claims (9)

1. An assembled temporary road, characterized in that: the honeycomb noise reduction structure comprises a steel plate surface layer, a honeycomb noise reduction layer, a gravel cushion layer and a soil layer which are sequentially arranged from top to bottom; the steel plate surface layer comprises a plurality of prefabricated steel plates, and the adjacent prefabricated steel plates are connected through connecting pieces; the honeycomb noise reduction layer comprises precast blocks, noise reduction holes penetrating in the thickness direction of the precast blocks are distributed in the precast blocks, a drainage channel is connected between every two adjacent noise reduction holes, and the width and the height of each drainage channel are 30-50 mm; the drainage channel is arranged inside the precast block.
2. The fabricated temporary road of claim 1, wherein: the connecting piece comprises a connecting plate, wherein 4 connecting holes are distributed in the connecting plate, and the connecting line of the 4 connecting holes is rectangular; 4 prefabricated holes are distributed on the prefabricated steel plate and are arranged close to the included angle of the prefabricated steel plate; 4 connecting holes on the same connecting plate are respectively connected with the prefabricated holes of 4 prefabricated steel plates.
3. The fabricated temporary road of claim 2, wherein: a drainage ditch is reserved between the adjacent prefabricated steel plates.
4. The fabricated temporary road of claim 3, wherein: the cross section of the noise reduction hole is hexagonal.
5. The fabricated temporary road of any one of claims 1 to 4, wherein: the gravel cushion layer is composed of stones, and the particle size of the stones is 5-30 mm.
6. The fabricated temporary road of claim 5, wherein: the thickness of the gravel cushion layer is 100-300 mm.
7. The fabricated temporary road of claim 1 or 6, wherein: the aperture of the noise reduction hole is 80-100 mm.
8. The fabricated temporary road of claim 7, wherein: and anti-rust layers are arranged on the surfaces of the prefabricated steel plate and the honeycomb noise reduction layer.
9. The fabricated temporary road of claim 8, wherein: the prefabricated steel plate is 1000mm multiplied by 1000mm in size and 15 mm-25 mm in thickness.
CN201921882599.0U 2019-11-04 2019-11-04 Assembled temporary road Active CN211689728U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921882599.0U CN211689728U (en) 2019-11-04 2019-11-04 Assembled temporary road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921882599.0U CN211689728U (en) 2019-11-04 2019-11-04 Assembled temporary road

Publications (1)

Publication Number Publication Date
CN211689728U true CN211689728U (en) 2020-10-16

Family

ID=72786203

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921882599.0U Active CN211689728U (en) 2019-11-04 2019-11-04 Assembled temporary road

Country Status (1)

Country Link
CN (1) CN211689728U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114086443A (en) * 2021-11-30 2022-02-25 二十二冶集团天津建设有限公司 Prefabricated temporary road
CN114622454A (en) * 2022-02-15 2022-06-14 中国一冶集团有限公司 Heavy-load steel plate combined construction access road filled with waste pile heads and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114086443A (en) * 2021-11-30 2022-02-25 二十二冶集团天津建设有限公司 Prefabricated temporary road
CN114622454A (en) * 2022-02-15 2022-06-14 中国一冶集团有限公司 Heavy-load steel plate combined construction access road filled with waste pile heads and construction method

Similar Documents

Publication Publication Date Title
CN211689728U (en) Assembled temporary road
CN110747711B (en) Assembled temporary road and manufacturing method thereof
CN106758637A (en) A kind of road and its construction method for having enough to meet the need quick-assembling
CN105220595A (en) A kind of construction work temporary road structure and construction method thereof
CN104763017A (en) Ground permeating rainwater recovery system utilizing building waste materials and construction method of ground permeating rainwater recovery system
CN213417462U (en) Novel assembled road
CN201553962U (en) U-shaped filter tank type curb stone made of reinforced concrete or natural stones
CN211734908U (en) Assembled temporary concrete pavement slab
CN204491342U (en) A kind of prefabricated concrete road plate
CN202450558U (en) Basement waterproof structure based on application of dewatering board
CN206428547U (en) A kind of road for having enough to meet the need quick-assembling
CN214992802U (en) Asphalt pavement pit repairing structure
CN213538588U (en) Municipal works antidetonation road surface structure
CN211571230U (en) Assembled parking area
CN214301067U (en) Novel sand temporary construction road plate
CN110552546B (en) Method for building underground parking lot waterproof facility by using tower crane
CN209602904U (en) A kind of steel plate turnover road surface
CN206529668U (en) The recyclable assembled pavement structure of no-dig technique
CN203373635U (en) Prefabricated hollow reinforced concrete wearproof pavement slab
CN217536556U (en) Assembly type construction terrace capable of being recycled
CN109868702A (en) Prefabricated Steel Fibre Concrete Pavements
CN204590158U (en) Utilize the ground infiltration system for reclaiming rainwater of construction waste material
CN216193749U (en) Assembly type road structure for construction site
CN218147580U (en) Solidified building muck road structure
CN212742062U (en) Structure for removing interlayer water in cement pavement reconstruction and pavement applying same

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant