CN110552546B - Method for building underground parking lot waterproof facility by using tower crane - Google Patents

Method for building underground parking lot waterproof facility by using tower crane Download PDF

Info

Publication number
CN110552546B
CN110552546B CN201910878914.0A CN201910878914A CN110552546B CN 110552546 B CN110552546 B CN 110552546B CN 201910878914 A CN201910878914 A CN 201910878914A CN 110552546 B CN110552546 B CN 110552546B
Authority
CN
China
Prior art keywords
tower crane
foundation
post
constructing
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910878914.0A
Other languages
Chinese (zh)
Other versions
CN110552546A (en
Inventor
王永泽
程旭升
曹准
彭彪
董琼
陈前
刘泽宇
王林明
王玉双
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN201910878914.0A priority Critical patent/CN110552546B/en
Publication of CN110552546A publication Critical patent/CN110552546A/en
Application granted granted Critical
Publication of CN110552546B publication Critical patent/CN110552546B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/34Foundations for sinking or earthquake territories
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/36Bearings or like supports allowing movement
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/98Protection against other undesired influences or dangers against vibrations or shocks; against mechanical destruction, e.g. by air-raids
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/22Sockets or holders for poles or posts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/22Sockets or holders for poles or posts
    • E04H12/2207Sockets or holders for poles or posts not used
    • E04H12/2215Sockets or holders for poles or posts not used driven into the ground
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/22Sockets or holders for poles or posts
    • E04H12/2292Holders used for protection, repair or reinforcement of the post or pole
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a method for building a waterproof facility of an underground parking lot by using a tower crane. The method is characterized in that the tower crane body is dismantled and moved to the place away from the wall type lining building after the building is finished, vibration generated in the working process of the tower crane body is absorbed by constructing a sulfur concrete temporary support between the tower crane foundation and the independent foundation in advance, and vibration damage is prevented from being damaged on the sulfur concrete temporary support, so that the unstable support of the damaged sulfur concrete temporary support on the independent foundation can be removed by using a concrete permanent support in a mode of removing the sulfur concrete temporary support after post-pouring, and the energy of the tower crane can be better utilized under the condition of ensuring the basic foundation strength requirement and the waterproof requirement of an underground garage, and the purposes of energy conservation and emission reduction are achieved.

Description

Method for building underground parking lot waterproof facility by using tower crane
Technical Field
The invention belongs to the technical field of energy-saving and environment-friendly building construction, and particularly relates to a method for building a waterproof facility of an underground parking lot by using a tower crane.
Background
With the rapid development of economic construction in China, an overground parking lot cannot meet the use requirement, all high-rise residential building groups are provided with underground garages, and in the construction process of the residential building groups, the determination of the tower crane construction scheme is a key construction technology in the whole building construction, so that the safety, the cost and the construction period are directly influenced. The position of the tower crane foundation can only be located in an underground garage, and the construction difficulty is increased along with the position. At present, the tower crane foundation is set by adopting the following two methods in construction sites:
firstly, a tower crane foundation is arranged below a water-resistant plate and forms a whole with the water-resistant plate, the method is simple to arrange, but the tower crane foundation is often higher than the water-resistant plate and needs to lie down on a part of the tower crane foundation, the area forms a strong support area, the periphery of the area is easy to be sheared and damaged under the action of the reaction force of the foundation to form cracks from bottom to top, underground capillary water goes upwards along crack channels to cause leakage at the cracks and corrosion of reinforcing steel bars around the parts below the cracks to cause structural damage, and the leakage and the cracks cannot be fundamentally remedied;
and secondly, directly arranging the tower crane foundation in a water-resistant plate, and issuing a scheme by a design institute to enlarge the cross section area and the reinforcing bars of the tower crane foundation. According to the method, a post-cast strip is not needed to be arranged in a tower foundation area, but the concrete in the area is easily cracked by vibration load generated in the tower crane construction process, so that later-stage cracks and leakage phenomena are caused. The two methods can form cracking and leakage in the tower crane foundation area at the later stage, so that how to fundamentally solve the problem that the tower crane foundation area does not crack or leak to form a construction pain point, the cracking reason is that overlarge tensile stress or shearing damage occurs in concrete, the concrete is pulled to crack or cut, and the leakage is that the waterproof layer is pulled to crack and loses the waterproof function. The method radically solves the following problems by eliminating cracking and leakage from the source: 1) the counter force of the substrate is uniformly stressed, and stress concentration is not generated; 2) the vibration load can not generate tensile stress to the area when the tower crane is constructed; 3) the waterproof layer cannot be deactivated.
The prior patent CN201811635193.2 discloses an anti-cracking and anti-seepage construction method for arranging a tower crane foundation under an independent foundation of an underground garage, which comprises the following steps: positioning a tower foundation and excavating earthwork → constructing a tower crane foundation cushion layer and a brick mold → constructing reinforcing steel bars, embedded parts and concrete of the tower crane foundation → installing the tower crane → constructing a retaining brick wall → backfilling the outer side of the retaining brick wall → paving an extruded polystyrene board → reserving a water-resistant board and a cushion layer construction seam → casting the cushion layer concrete outside a post-cast area → constructing a foundation waterproof layer and waterproofing treatment of the post-cast area → reinforcing steel bars outside the post-cast area of the water-resistant board, constructing the concrete → demolishing the tower crane after construction → demolishing the retaining brick wall and backfilling → casting the cushion layer concrete of the post-cast area → constructing the waterproof layer of the post-cast area → lapping the reinforcing steel bars of the water-resistant board in the post-cast area. The quality problem that the later stage of the tower crane foundation part is easy to crack and leak is solved.
However, as the waterproof measures of the underground garage are increasingly implemented by adopting off-wall lining, after the ground foundation of the underground garage is treated, lining materials such as various waterproof coiled materials, reinforcing steel bars and the like need to be hoisted into the space of the underground garage, and the lining materials need to be moved into the space of the underground garage after the ground foundation is made, and the construction method needs to be dismantled before the ground foundation of the underground garage is made, so that the hoisting capacity of a tower crane cannot be utilized to the maximum extent, the operation cost of waterproof construction of the underground garage is increased, and material and force are wasted.
Disclosure of Invention
The invention aims to provide a method for building underground parking lot waterproof facilities by using a tower crane, which improves the utilization efficiency of the tower crane and adopts the following technical scheme:
the method for building the underground parking lot waterproof facility by using the tower crane comprises the following steps:
1) installing a tower crane: constructing a tower crane foundation on a ground foundation, and installing a tower crane body on the tower crane foundation;
2) constructing a shock insulation belt on the tower crane foundation: reserving a tower crane body on a tower crane foundation, wherein the area where the tower crane body is located is a post-pouring area, constructing a sulfur concrete temporary support and a concrete body permanent support at the periphery of the post-pouring area, the sulfur concrete temporary support is higher than the concrete body permanent support, reserving a horizontally through post-pouring channel on the concrete body permanent support, and embedding an electric heating body in the sulfur concrete temporary support;
3) laying an extruded polystyrene board: an extruded polystyrene board is erected on the top of the temporary sulfur concrete support;
4) constructing an independent foundation: constructing an independent foundation above the extruded polystyrene board and keeping the post-pouring area;
5) constructing an off-wall lining: hoisting the building materials required by the off-wall lining to an independent foundation by using a tower crane body, and building the off-wall lining;
6) dismantling the tower crane body;
7) and (3) removing the temporary support of the sulfur concrete: electrifying an electric heating body in the sulfur concrete temporary support to remove the sulfur concrete temporary support;
8) and (3) post-cast area cast-in-place construction: and (3) overlapping steel bars in the post-cast area, and casting concrete in situ, wherein a post-cast channel in the permanent concrete support is filled with the area between the extruded polystyrene board and the tower crane foundation.
Preferably, the temporary sulfur concrete support and the permanent concrete support are spliced closely and adjacently to form a post-cast buffer module, one part of the post-cast buffer module is positioned in a seam allowance area arranged on the periphery of the tower crane foundation, the other part of the post-cast buffer module is positioned in the ground foundation, and a post-cast seam communicated with the post-cast area is reserved between the extruded polystyrene board and the tower crane foundation.
Preferably, between steps 3) and 4),
building a retaining brick wall on the extruded polystyrene board: building a retaining brick wall on one side edge of the extruded polystyrene board close to the center of the tower crane foundation;
between the steps 6) and 7),
and (5) removing and backfilling the retaining brick wall.
Preferably, between steps 5) and 6),
constructing an independent strut: constructing an independent pillar on an independent foundation;
constructing a garage ceiling: erecting a garage ceiling on the independent support column by using the tower crane body, and reserving a skylight area where the tower crane body is located;
between the steps 6) and 7),
constructing a ceiling skylight: and installing a ceiling skylight in the skylight area.
Compared with the prior art, the invention has the following beneficial effects:
according to the invention, the tower crane body is removed and moved to the place away from the wall type lining building after the building is finished, and the vibration generated in the working process of the tower crane body is absorbed by constructing the sulfur concrete temporary support between the tower crane foundation and the independent foundation in advance, so that the vibration damage is prevented from being damaged on the sulfur concrete temporary support, and therefore, the unstable support of the damaged sulfur concrete temporary support on the independent foundation can be removed in a way of removing the sulfur concrete temporary support and realizing the permanent support after post-pouring by using the concrete permanent support, so that the energy transportation of the tower crane can be better utilized under the condition of ensuring the basic foundation strength requirement and the waterproof requirement of an underground garage, and the purposes of energy conservation and emission reduction are realized.
Drawings
Fig. 1 is a schematic view of the construction structure of the garage foundation of the present invention.
Detailed Description
In order to make the technical purpose, technical solutions and advantages of the present invention clearer, the technical solutions of the present invention are further described below with reference to the accompanying drawings and specific embodiments.
As shown in fig. 1, the method for building the waterproof facility of the underground parking lot by using the tower crane in the embodiment comprises the following steps:
1. installing a tower crane: a tower crane foundation 2 is built on a ground foundation 1, a tower crane body 8 is installed on the tower crane foundation 2, the tower crane foundation 2 can be built in a cast-in-place mode or a direct installation mode after prefabrication, but the size of the tower crane foundation 2 is required to be ensured to be larger than the clear distance of an independent foundation 3, and the specific size and the building process are consistent with the construction method for arranging the tower crane foundation under the independent foundation of an underground garage for crack prevention and seepage prevention in the prior patent CN 201811635193.2.
2. Constructing a shock insulation belt on a tower crane foundation 2: the area where the tower crane body 8 is reserved on the tower crane foundation 2 is a post-pouring area, a sulfur concrete temporary support 4 and a concrete body permanent support 5 are constructed on the periphery of the post-pouring area, the sulfur concrete temporary support 4 is higher than the concrete body permanent support 5, a horizontally through post-pouring channel is reserved on the concrete body permanent support 5, and an electric heating body is pre-buried in the sulfur concrete temporary support 4. The sulfur concrete temporary support 4 and the concrete permanent support 5 are spliced closely and adjacently to form a post-cast buffer module, one part of the post-cast buffer module is positioned in a spigot area arranged on the periphery of the tower crane foundation, the other part of the post-cast buffer module is positioned in the ground foundation 1, and a post-cast seam communicated with a post-cast area is reserved between the extruded polystyrene board and the tower crane foundation 2. The sulfur concrete temporary support 4 comprises a sulfur mortar interlayer positioned in the middle, the bottom layer and the top layer of the sulfur mortar interlayer are concrete pouring layers, heating pipes are arranged in the sulfur mortar interlayer, more than 2 longitudinally-arranged sulfur mortar interlayers are arranged on the electrothermal pipes, the specific size is 1200cm in length, 80cm in width, 79.5cm in height, the height is 35cm of concrete, 10cm of sulfur mortar and 34.5cm of concrete, and the concrete label is C55. When the temporary sulfur concrete support 4 is constructed, the plane position of the temporary cushion block is measured, a D10 steel mesh layer is laid, a concrete cushion block with the thickness of 35cm at the bottom layer is firstly poured, 4 electric heating tubes with the thickness of 2KW are laid on a sulfur mortar layer or the number of the electric heating tubes is set according to the actual use requirement, a bamboo plywood with the thickness of 1.8cm is laid on a 10 multiplied by 10cm square wood frame to serve as a side template, the sulfur mortar cushion block is poured, finally, a D10 steel mesh layer 6 is laid, and a top concrete cushion block is poured.
3. Laying an extruded polystyrene board 6: an extruded polystyrene board 6 is erected on the top of the temporary sulfur concrete support 4.
4. The extruded polystyrene board 6 is provided with a retaining brick wall 7: and a retaining brick wall 7 is built on one side edge of the extruded polystyrene board 6 close to the center of the tower crane foundation 2.
5. Constructing an independent foundation 3: a separate foundation 3 is constructed over the extruded polystyrene board 6 and the post-cast zone is left behind.
6. Constructing an off-wall lining: and hoisting the building materials required by the off-wall lining to the independent foundation 3 by using the tower crane body 8, and building the off-wall lining.
7. Constructing an independent strut: and constructing an independent pillar on the independent foundation 3.
8. Constructing a garage ceiling: and erecting a garage ceiling on the independent support column by using the tower crane body 8, and reserving a skylight area where the tower crane body 8 is located.
9. And (4) dismantling the tower crane body 8.
10. The retaining brick wall 7 is removed and backfilled.
11. Constructing a ceiling skylight: and installing a ceiling skylight in the skylight area.
12. And (4) removing the temporary support 4 of the sulfur concrete: and electrifying the electric heating body in the sulfur concrete temporary support 4 to remove the sulfur concrete temporary support 4.
13. And (3) post-cast area cast-in-place construction: and (3) overlapping steel bars in the post-cast area, and casting concrete in situ, wherein a post-cast channel in the permanent concrete support 5 is filled with the area between the extruded polystyrene board 6 and the tower crane foundation 2.
Finally, it should be noted that: the above embodiments are merely illustrative and not restrictive of the technical solutions of the present invention, and any equivalent substitutions and modifications or partial substitutions made without departing from the spirit and scope of the present invention should be included in the scope of the claims of the present invention.

Claims (4)

1. The method for building the underground parking lot waterproof facility by using the tower crane comprises the following steps:
1) installing a tower crane: constructing a tower crane foundation on a ground foundation, and installing a tower crane body on the tower crane foundation;
it is characterized in that the preparation method is characterized in that,
2) constructing a shock insulation belt on the tower crane foundation: reserving a tower crane body on a tower crane foundation, wherein the area where the tower crane body is located is a post-pouring area, constructing a sulfur concrete temporary support and a concrete body permanent support at the periphery of the post-pouring area, the sulfur concrete temporary support is higher than the concrete body permanent support, reserving a horizontally through post-pouring channel on the concrete body permanent support, and embedding an electric heating body in the sulfur concrete temporary support;
3) laying an extruded polystyrene board: an extruded polystyrene board is erected on the top of the temporary sulfur concrete support;
4) constructing an independent foundation: constructing an independent foundation above the extruded polystyrene board and keeping the post-pouring area;
5) constructing an off-wall lining: hoisting the building materials required by the off-wall lining to an independent foundation by using a tower crane body, and building the off-wall lining;
6) dismantling the tower crane body;
7) and (3) removing the temporary support of the sulfur concrete: electrifying an electric heating body in the sulfur concrete temporary support to remove the sulfur concrete temporary support;
8) and (3) post-cast area cast-in-place construction: and (3) overlapping steel bars in the post-cast area, and casting concrete in situ, wherein a post-cast channel in the permanent concrete support is filled with the area between the extruded polystyrene board and the tower crane foundation.
2. The method for building the underground parking lot waterproof facility by using the tower crane as claimed in claim 1, wherein the sulfur concrete temporary support and the concrete permanent support are spliced closely and adjacently to form a post-cast buffer module, one part of the post-cast buffer module is positioned in a spigot area arranged on the periphery of the tower crane foundation, the other part of the post-cast buffer module is positioned in the ground foundation, and a post-cast seam communicated with the post-cast area is reserved between the extruded polystyrene board and the tower crane foundation.
3. The method for building an underground parking lot waterproof facility by using the tower crane according to claim 2, wherein, between the steps 3) and 4),
building a retaining brick wall on the extruded polystyrene board: building a retaining brick wall on one side edge of the extruded polystyrene board close to the center of the tower crane foundation;
between the steps 6) and 7),
and (5) removing and backfilling the retaining brick wall.
4. The method for constructing an underground parking lot waterproof facility by using the tower crane according to claim 1, 2 or 3, wherein, between the steps 5) and 6),
constructing an independent strut: constructing an independent pillar on an independent foundation;
constructing a garage ceiling: erecting a garage ceiling on the independent support column by using the tower crane body, and reserving a skylight area where the tower crane body is located;
between the steps 6) and 7),
constructing a ceiling skylight: and installing a ceiling skylight in the skylight area.
CN201910878914.0A 2019-09-18 2019-09-18 Method for building underground parking lot waterproof facility by using tower crane Active CN110552546B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910878914.0A CN110552546B (en) 2019-09-18 2019-09-18 Method for building underground parking lot waterproof facility by using tower crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910878914.0A CN110552546B (en) 2019-09-18 2019-09-18 Method for building underground parking lot waterproof facility by using tower crane

Publications (2)

Publication Number Publication Date
CN110552546A CN110552546A (en) 2019-12-10
CN110552546B true CN110552546B (en) 2020-11-10

Family

ID=68740641

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910878914.0A Active CN110552546B (en) 2019-09-18 2019-09-18 Method for building underground parking lot waterproof facility by using tower crane

Country Status (1)

Country Link
CN (1) CN110552546B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114164769B (en) * 2021-12-28 2023-04-14 招商局重庆交通科研设计院有限公司 Temporary support for bridge construction

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2455157C2 (en) * 2010-08-31 2012-07-10 Общество с ограниченной ответственностью "Научно-исследовательский институт природных газов и газовых технологий - Газпром ВНИИГАЗ" Method of moulding articles from sulfur concrete
CN202865751U (en) * 2012-11-07 2013-04-10 江苏省交通工程集团有限公司 Temporary support for sulphur-bonded mortar
CN103437369A (en) * 2013-08-30 2013-12-11 上海建工二建集团有限公司 Deep foundation pit support and removing method thereof
CN103643749A (en) * 2013-12-13 2014-03-19 刘浩琳 Combined shock-insulation support of high-rise building
CN105463985A (en) * 2016-01-14 2016-04-06 中铁七局集团第三工程有限公司 Temporary support for continuous rigid-frame bridge

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2455157C2 (en) * 2010-08-31 2012-07-10 Общество с ограниченной ответственностью "Научно-исследовательский институт природных газов и газовых технологий - Газпром ВНИИГАЗ" Method of moulding articles from sulfur concrete
CN202865751U (en) * 2012-11-07 2013-04-10 江苏省交通工程集团有限公司 Temporary support for sulphur-bonded mortar
CN103437369A (en) * 2013-08-30 2013-12-11 上海建工二建集团有限公司 Deep foundation pit support and removing method thereof
CN103643749A (en) * 2013-12-13 2014-03-19 刘浩琳 Combined shock-insulation support of high-rise building
CN105463985A (en) * 2016-01-14 2016-04-06 中铁七局集团第三工程有限公司 Temporary support for continuous rigid-frame bridge

Also Published As

Publication number Publication date
CN110552546A (en) 2019-12-10

Similar Documents

Publication Publication Date Title
CN104805866B (en) Prefabricated pipe gallery and construction method
CN105862873A (en) Construction method of underground water prevention and exterior wall structures of narrow space of deep foundation pit
CN110747899A (en) Basement waterproof construction method
CN113668612A (en) Modular combined prefabricated electric power working well and construction method thereof
CN109914644A (en) A kind of assembled heat insulation masonry wall and preparation method thereof
CN110552546B (en) Method for building underground parking lot waterproof facility by using tower crane
CN205224332U (en) Prefabricated wall body and prefabricated wallboard
CN211115052U (en) Shaft type underground stereo garage structure
CN112112295A (en) Reinforcing construction method for post-cast strip of post-sealed outer wall
CN111877626A (en) Overhead laminated slab construction structure and construction method
CN204645093U (en) Poured band of outer wall of basement advanced processing constructs
CN111827705A (en) Method for expanding well barrel-shaped underground garage in existing underground garage
CN109137984A (en) Assembled integral mixes prefabricated pipe gallery
CN214090002U (en) Basement outer wall post-cast strip is enclosed construction in advance
CN115387393A (en) Post-cast strip pre-sealing quick construction method
CN111576658B (en) Construction method of post-cast strip protection wall of assembled basement outer wall
CN211200460U (en) Assembled integral underground space foundation member
CN107268617A (en) Construction technology and device after a kind of anti-float anchor rod
CN209975560U (en) Prefabricated waterproof retaining wall plate structure
CN211900603U (en) Face combination shield structure hole of hoist enclosed construction forever
CN210104806U (en) Basement outer wall post-cast strip closed in advance
CN109667278B (en) Anti-cracking and anti-seepage construction method for arranging tower crane foundation under independent foundation of underground garage
CN110578413A (en) Shaft type underground stereo garage structure
CN106088762A (en) The prefabricated assembled circular underground granary of a kind of insertion slot type encased steel plate
CN110821021A (en) Floor slab capable of being installed rapidly

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant