CN105220595A - A kind of construction work temporary road structure and construction method thereof - Google Patents
A kind of construction work temporary road structure and construction method thereof Download PDFInfo
- Publication number
- CN105220595A CN105220595A CN201510692400.8A CN201510692400A CN105220595A CN 105220595 A CN105220595 A CN 105220595A CN 201510692400 A CN201510692400 A CN 201510692400A CN 105220595 A CN105220595 A CN 105220595A
- Authority
- CN
- China
- Prior art keywords
- layer
- steel plate
- construction
- rubble
- construction work
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Road Paving Structures (AREA)
Abstract
The invention discloses a kind of construction work temporary road structure and construction method thereof, first on road foundation, lay one deck miscellaneous fill path layer, one deck rubble or old concrete layer is laid above miscellaneous fill path layer, rubble or old concrete layer are laid handling layer, the rhone that handling layer is arranged is connected with the gutter of road foundation both sides, and the present invention uses standardization prefabricated steel, can have enough to meet the need use, site machineryization is assembled, quick and convenient; Directly can come into operation after construction, not need schedule delays; Use material for recyclable material, do not produce building waste, pollution-free, energy-conserving and environment-protective; Steel plate long service life, can have enough to meet the need repeatedly, cost is low, and steel plate stress performance is good, is not easy to destroy.
Description
Technical field
Patent of the present invention relates to a kind of construction work temporary road structure and construction method thereof, belongs to technical field of building construction.
Background technology
At present, need to adopt cast-in-situ concrete to realize road surface sclerosis in the construction of construction work tradition temporary road, after concrete reaches requirement of strength, just can come into operation, but such construction method not only can affect the duration, and need to abolish after the use of rigid pavement, produce a large amount of building wastes, not only contaminated environment but also waste material, increase cost, do not meet the principle of green construction material-saving environmental, so existing construction work tradition temporary road construction method is still perfect not.
Summary of the invention
The object of the invention is: a kind of construction work temporary road structure and construction method thereof are provided, the method adopts the standardization steel plate splicing that can have enough to meet the need use to form, pollution-free, intensity is high, the life-span is long, use can be had enough to meet the need, can reduce costs, temporary road structure installment is quick and easy, can save the duration, steel plate road, road foundation and gutter form construction work temporary road structure, are conducive to draining the water away.
The present invention is achieved in that a kind of construction method of construction work temporary road, first on road foundation, lay one deck miscellaneous fill path layer, one deck rubble or old concrete layer is laid above miscellaneous fill path layer, rubble or old concrete layer are laid handling layer, and the rhone that handling layer is arranged is connected with the gutter of road foundation both sides.
Described handling layer is connected to form by steel plate, is connected to form between steel plate by bolt cover plate, being provided with between steel plate can the rhone of draining.
A kind of construction work temporary road, comprise road foundation, it is characterized in that: on road foundation, be equipped with miscellaneous fill path layer, miscellaneous fill path layer is equipped with rubble or old concrete layer, rubble or old concrete layer are equipped with handling layer, on road foundation and handling layer both sides be provided with gutter.
Described handling layer is connected to form by steel plate, is interconnected, between adjacent two steel plates, is provided with rhone between two adjacent steel plates by bolt cover plate.
Described steel plate is connected by bolt with bolt cover plate.
Steel plate is provided with bolt hole.
Owing to have employed technique scheme, compared with prior art, the present invention is applicable to the way of construction work temporary road, first on road foundation, lay one deck miscellaneous fill path layer, one deck rubble or old concrete layer is laid above miscellaneous fill path layer, then utilizing bolt cover plate to be spliced into handling layer after being holed by steel plate covers on roadbed, and both sides are provided with gutter, ensure that ponding can be discharged smoothly.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is the sectional view of Fig. 1;
Fig. 3 is the structural representation of steel plate;
Description of reference numerals 1-road foundation, 2-miscellaneous fill path layer, 3-rubble or old concrete layer, 4-loads and unloads layer, 5-gutter, 6-steel plate, 7-bolt cover plate, 8-rhone, 9-bolt, 10-bolt hole.
Detailed description of the invention
Below in conjunction with drawings and Examples, the present invention is described in further detail, but not as limitation of the present invention.
Embodiments of the invention: a kind of construction method of construction work temporary road, first on road foundation, lay one deck miscellaneous fill path layer, one deck rubble or old concrete layer is laid above miscellaneous fill path layer, rubble or old concrete layer are laid handling layer, and the rhone that handling layer is arranged is connected with the gutter of road foundation both sides.
Described handling layer is connected to form by steel plate, is connected to form between steel plate by bolt cover plate, being provided with between steel plate can the rhone of draining.
A kind of construction work temporary road, comprise road foundation 1, it is characterized in that: on road foundation 1, be equipped with miscellaneous fill path layer 2, miscellaneous fill path layer 2 is equipped with rubble or old concrete layer 3, rubble or old concrete layer 3 are equipped with handling layer 4, on road foundation 1 and handling layer 4 both sides be provided with gutter 5.
Described handling layer 4 is connected to form by steel plate 6, is interconnected, between adjacent two steel plates 6, is provided with rhone 8 between two adjacent steel plates 6 by bolt cover plate 7.
Described steel plate 6 is connected by bolt 9 with bolt cover plate 7.
Steel plate 6 is provided with bolt hole 10.
Steel plate 6 of the present invention adopts existing model to be Q235 steel plate, and thickness is 20mm, is of a size of 2m × 2m, and steel plate is drilled with bolt hole 10,1, every angular bit hole, aperture 24 ㎜, pitch-row 75mm, back gauge steel plate edge, hole 25mm.
15mm steel plate selected by described bolt cover plate 7, one, every angular bit hole, aperture 26mm, spacing 80mm, distance edges of boards 40mm.
The present invention uses standardization prefabricated steel, and can have enough to meet the need use, site machineryization is assembled, quick and convenient; Directly can come into operation after construction, not need schedule delays; Use material for recyclable material, do not produce building waste, pollution-free, energy-conserving and environment-protective; Steel plate long service life, can have enough to meet the need repeatedly, cost is low, and steel plate stress performance is good, is not easy to destroy.
Claims (6)
1. the construction method of a construction work temporary road, it is characterized in that: on road foundation, first lay one deck miscellaneous fill path layer, one deck rubble or old concrete layer is laid above miscellaneous fill path layer, rubble or old concrete layer are laid handling layer, and the rhone that handling layer is arranged is connected with the gutter of road foundation both sides.
2. the construction method of construction work temporary road according to claim 1, is characterized in that: described handling layer is connected to form by steel plate, is connected to form between steel plate by bolt cover plate, being provided with between steel plate can the rhone of draining.
3. a construction work temporary road, comprise road foundation (1), it is characterized in that: on road foundation (1), be equipped with miscellaneous fill path layer (2), miscellaneous fill path layer (2) is equipped with rubble or old concrete layer (3), rubble or old concrete layer (3) are equipped with handling layer (4), go up at road foundation (1) and the both sides of handling layer (4) are provided with gutter (5).
4. construction work temporary road according to claim 3, it is characterized in that: described handling layer (4) is connected to form by steel plate (6), be interconnected by bolt cover plate (7) between two adjacent steel plates (6), between adjacent two steel plates (6), be provided with rhone (8).
5. construction work temporary road according to claim 3, is characterized in that: described steel plate (6) is connected by bolt (9) with bolt cover plate (7).
6. construction work temporary road according to claim 3, is characterized in that: on steel plate (6), be provided with bolt hole (10).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510692400.8A CN105220595A (en) | 2015-10-23 | 2015-10-23 | A kind of construction work temporary road structure and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510692400.8A CN105220595A (en) | 2015-10-23 | 2015-10-23 | A kind of construction work temporary road structure and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105220595A true CN105220595A (en) | 2016-01-06 |
Family
ID=54989830
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510692400.8A Pending CN105220595A (en) | 2015-10-23 | 2015-10-23 | A kind of construction work temporary road structure and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105220595A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106012749A (en) * | 2016-08-08 | 2016-10-12 | 中国建筑土木建设有限公司 | Cement-bound building slag composite board pavement and construction method thereof |
CN106245485A (en) * | 2016-08-08 | 2016-12-21 | 中国建筑土木建设有限公司 | Sand real estate feed bin stockyard and method of construction thereof |
CN106758637A (en) * | 2016-12-30 | 2017-05-31 | 中建八局第建设有限公司 | A kind of road and its construction method for having enough to meet the need quick-assembling |
CN106812042A (en) * | 2017-03-09 | 2017-06-09 | 陕西建工第五建设集团有限公司 | A kind of assembling steel plate road structure and construction method |
CN112962386A (en) * | 2021-02-10 | 2021-06-15 | 索新科技(北京)有限公司 | ADG steel floor unit and laying method thereof |
CN114622454A (en) * | 2022-02-15 | 2022-06-14 | 中国一冶集团有限公司 | Heavy-load steel plate combined construction access road filled with waste pile heads and construction method |
CN116537188A (en) * | 2023-05-24 | 2023-08-04 | 中国十七冶集团有限公司 | Construction method for removing steel sheet piles for excavation and support of drift sand stratum grooves |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09221707A (en) * | 1996-02-15 | 1997-08-26 | Oyo Corp | Movable temporary road surface structure and method for installation and removal thereof |
CN204435153U (en) * | 2015-01-14 | 2015-07-01 | 中建八局第一建设有限公司 | A kind of assembled steel plate construction road |
CN204715148U (en) * | 2015-05-22 | 2015-10-21 | 中建三局第二建设工程有限责任公司 | A kind of Simple mounting temporary construction steel plate pavement system |
CN205259023U (en) * | 2015-10-23 | 2016-05-25 | 中建四局第一建筑工程有限公司 | Building engineering temporary road |
-
2015
- 2015-10-23 CN CN201510692400.8A patent/CN105220595A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09221707A (en) * | 1996-02-15 | 1997-08-26 | Oyo Corp | Movable temporary road surface structure and method for installation and removal thereof |
CN204435153U (en) * | 2015-01-14 | 2015-07-01 | 中建八局第一建设有限公司 | A kind of assembled steel plate construction road |
CN204715148U (en) * | 2015-05-22 | 2015-10-21 | 中建三局第二建设工程有限责任公司 | A kind of Simple mounting temporary construction steel plate pavement system |
CN205259023U (en) * | 2015-10-23 | 2016-05-25 | 中建四局第一建筑工程有限公司 | Building engineering temporary road |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106012749A (en) * | 2016-08-08 | 2016-10-12 | 中国建筑土木建设有限公司 | Cement-bound building slag composite board pavement and construction method thereof |
CN106245485A (en) * | 2016-08-08 | 2016-12-21 | 中国建筑土木建设有限公司 | Sand real estate feed bin stockyard and method of construction thereof |
CN106758637A (en) * | 2016-12-30 | 2017-05-31 | 中建八局第建设有限公司 | A kind of road and its construction method for having enough to meet the need quick-assembling |
CN106812042A (en) * | 2017-03-09 | 2017-06-09 | 陕西建工第五建设集团有限公司 | A kind of assembling steel plate road structure and construction method |
CN112962386A (en) * | 2021-02-10 | 2021-06-15 | 索新科技(北京)有限公司 | ADG steel floor unit and laying method thereof |
CN114622454A (en) * | 2022-02-15 | 2022-06-14 | 中国一冶集团有限公司 | Heavy-load steel plate combined construction access road filled with waste pile heads and construction method |
CN114622454B (en) * | 2022-02-15 | 2023-05-16 | 中国一冶集团有限公司 | Heavy-load steel plate combined construction pavement filled with abandoned pile heads and construction method |
CN116537188A (en) * | 2023-05-24 | 2023-08-04 | 中国十七冶集团有限公司 | Construction method for removing steel sheet piles for excavation and support of drift sand stratum grooves |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105220595A (en) | A kind of construction work temporary road structure and construction method thereof | |
CN104863274B (en) | Building dilatation joint waterproof structure | |
CN203961012U (en) | A kind of prefabricated housing element of construction that is applied to big-and-middle-sized building | |
CN204024206U (en) | A kind of precast prestressed concrete Assembled enclosing wall | |
CN107059946A (en) | A kind of basement drain plate and its construction | |
CN112593644B (en) | Prefabricated assembly type shear wall vertical joint connecting structure and construction method thereof | |
CN204435153U (en) | A kind of assembled steel plate construction road | |
CN202577087U (en) | Road prefabricated slab | |
CN209099601U (en) | A kind of UHPC ultra-high performance concrete steel bar girder laminated floor slab | |
CN202450558U (en) | Basement waterproof structure based on application of dewatering board | |
CN211689728U (en) | Assembled temporary road | |
CN205259023U (en) | Building engineering temporary road | |
KR102072273B1 (en) | Construction Method of Water Proof Sheet Having Elasticity | |
CN105986539A (en) | Assembled temporary pavement | |
CN210288620U (en) | Prefabricated resin concrete escape canal | |
CN205443897U (en) | Reinforced concrete T beam bridge | |
CN212103531U (en) | Environment-friendly temporary road system | |
CN204023774U (en) | A kind of assembling composite construction seismic structural wall, earthquake resistant wall | |
CN203700899U (en) | Steel tool-type temporary construction road | |
CN207092154U (en) | A kind of basement drain plate | |
CN206189594U (en) | Shake to decrease and to replace steel beam structure | |
CN106948461B (en) | Integrated wellhead module device and modular multifunctional inspection well | |
CN201850655U (en) | T-shaped connector for new and old buildings | |
CN205046436U (en) | Wear -resisting construction road of assembled prestressing force cavity | |
CN202492917U (en) | Drainage inspection well |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160106 |
|
RJ01 | Rejection of invention patent application after publication |