Prior art keywords
well
cover plate
seat
drainage inspection
chamber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2012201135074U
Other languages
Chinese (zh)
Inventor
马微
龙浩
李盛涛
杨卫
李量
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHONGSHE ENGINEERING CONSULTING (CHONGQING) Co.,Ltd.
Original Assignee
CHONGQING ZHONGSHE ENGINEERING DESIGN Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING ZHONGSHE ENGINEERING DESIGN Co Ltd filed Critical CHONGQING ZHONGSHE ENGINEERING DESIGN Co Ltd
Priority to CN2012201135074U priority Critical patent/CN202492917U/en
Application granted granted Critical
Publication of CN202492917U publication Critical patent/CN202492917U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a drainage inspection well, which comprises a well cover and well seat (1), a well room (2) and a drainage pipe (3), wherein the well room (3) is piled by concrete building blocks, the drainage pipe (3) is connected with the well room (2), a mounting cover board (4) is fixedly arranged at the top of the well room (2), a round hole (4a) is arranged in the middle of the mounting cover board (4), the well cover and well seat (1) is supported on the mounting cover board (4) and is limited by the round hole (4a) in the middle of the mounting cover board (4). According to the structure, through adding the mounting cover board, which is larger than the building blocks, at the top of the well room, the subsidence phenomenon of the well cover and the well seat in a long-time using process can be effectively avoided, and the drainage inspection well has the advantages of simple structure and durable service.

Description

Drainage inspection well
Technical field
The utility model belongs to the water supply and sewage work technical field, relates in particular to a kind of drainage inspection well.
Background technology
Drainage inspection well as shown in Figure 1 is made up of well lid well seat 1, well chamber 2 and gutter 3.Well lid well seat 1 is a composite member, and well lid is generally the plectane that has reinforcing rib, and the well seat is the annulus on edge in having, and well lid is supported by the interior edge of well seat, and well lid well seat 1 is installed in 2 tops, well chamber, and gutter 3 is arranged on 2 bottoms, well chamber and is connected with well chamber 2.The upper surface of well lid well seat 1 flushes with road end face 5, because well chamber 2 is piled up by concrete block and formed, durability is bad, and in use, well lid well seat 1 is prone to downward depression, makes troubles to the pedestrian, also influences city look and feel simultaneously.
The utility model content
The utility model carries out structure optimization to the problems referred to above that prior art exists, and intending provides the not drainage inspection well of depression downwards of a kind of good endurance, well lid well seat.
For reaching above-mentioned purpose; The technical scheme that the utility model adopted: a kind of drainage inspection well, comprise well lid well seat, well chamber and gutter, said well chamber is piled up by concrete block and is formed; Said gutter and well chamber are connected; Key is: the top of said well chamber is installed with the installation cover plate, and said installation cover plate middle part has circular hole, and said well lid well seat is bearing on the installation cover plate also spacing through the circular hole that the cover plate middle part is installed.
Said installation cover plate is a steel concrete, or cast iron, or the composite construction of cast iron and steel concrete.
As preferably, said installation cover plate is square, and the length of side is more than or equal to 1.4 meters, and thickness is 150 ± 20 millimeters.
The utility model is novel, design is ingenious, increases the installation cover plate bigger than building block size through the top in the well chamber, has effectively avoided the phenomenon of well lid well seat generation depression in long-time use, and is simple in structure and durable in use.
Description of drawings
Fig. 1 is the structural representation before improving.
Fig. 2 is the structural representation after improving.
Fig. 3 is the structure chart that cover plate is installed among Fig. 2.
The specific embodiment
Below in conjunction with accompanying drawing and embodiment the utility model is described further:
As Fig. 2 shown in drainage inspection well, by well lid well seat 1, well chamber 2, gutter 3, cover plate 4 is installed is formed.Well lid well seat 1 is a composite member, is made up of well lid and well seat two parts, and well lid is generally the plectane that has reinforcing rib, and the well seat is the annulus on edge in having, and well lid is supported by the interior edge of well seat.The upper surface of well lid well seat 1 flushes with road end face 5, and well chamber 2 is piled up by concrete block and formed, and in well chamber 2, is provided with cat ladder 7, and gutter 3 is arranged on 2 bottoms, well chamber and is connected with well chamber 2, and gutter 3 is installed on the concrete foundation 6.The top of well chamber 2 is installed with installs cover plate 4, can know in conjunction with Fig. 3, and installation cover plate 4 middle parts have circular hole 4a and are used for well lid well seat 1 spacing.Well lid well seat 1 is bearing on the installation cover plate 4 also spacing through the circular hole 4a that cover plate 4 middle parts are installed.
It is reinforced concrete structure that installation cover plate 4 can make, and also can be cast iron, perhaps the composite construction of cast iron and steel concrete.Installation cover plate 4 preferably is fixed on the top of well chamber 2 through cement mortar.
As preferably, it is square that cover plate 4 is installed, and the length of side is more than or equal to 1.4 meters, and thickness is 150 ± 20 millimeters, to guarantee enough bearing strengths.

Claims (4)

1. drainage inspection well; Comprise well lid well seat (1), well chamber (2) and gutter (3); Said well chamber (2) is piled up by concrete block and formed, and said gutter (3) is connected with well chamber (2), it is characterized in that: the top of said well chamber (2) is installed with installs cover plate (4); Said installation cover plate (4) middle part has circular hole (4a), and said well lid well seat (1) is bearing in installs that cover plate (4) is gone up and spacing through the circular hole (4a) that cover plate (4) middle part is installed.
2. according to the described drainage inspection well of claim 1, it is characterized in that: said installation cover plate (4) is a steel concrete, or cast iron, or the composite construction of cast iron and steel concrete.
3. according to claim 1 or 2 described drainage inspection wells, it is characterized in that: said installation cover plate (4) is fixed on the top of well chamber (2) through cement mortar.
4. according to the described drainage inspection well of claim 3, it is characterized in that: said installation cover plate (4) is for square, and the length of side is more than or equal to 1.4 meters, and thickness is 150 ± 20 millimeters.
CN2012201135074U 2012-03-23 2012-03-23 Drainage inspection well Expired - Lifetime CN202492917U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012201135074U CN202492917U (en) 2012-03-23 2012-03-23 Drainage inspection well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012201135074U CN202492917U (en) 2012-03-23 2012-03-23 Drainage inspection well

Publications (1)

Publication Number Publication Date
CN202492917U true CN202492917U (en) 2012-10-17

Family

ID=46999152

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012201135074U Expired - Lifetime CN202492917U (en) 2012-03-23 2012-03-23 Drainage inspection well

Country Status (1)

Country Link
CN (1) CN202492917U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107489423A (en) * 2017-10-20 2017-12-19 中冶建工集团有限公司 A kind of construction method of assembled concrete square frame vertical shaft

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107489423A (en) * 2017-10-20 2017-12-19 中冶建工集团有限公司 A kind of construction method of assembled concrete square frame vertical shaft

Similar Documents

Publication Publication Date Title
CN205530344U (en) Utility tunnel is pour to split type no mould
CN203569579U (en) Building foundation
CN209099601U (en) A kind of UHPC ultra-high performance concrete steel bar girder laminated floor slab
CN105220595A (en) A kind of construction work temporary road structure and construction method thereof
CN105971007A (en) Split type non-formwork pouring underground comprehensive pipe gallery
CN204456218U (en) A kind of municipal manhole is mated formation well lid
CN102367735B (en) Back-to-back waterstop installation equipment for tunnel construction joint
CN201933751U (en) Novel metal floor tile
CN202492917U (en) Drainage inspection well
CN202450558U (en) Basement waterproof structure based on application of dewatering board
CN206267169U (en) A kind of split blade type prestressing force anchor slab
CN103046664A (en) Energy-saving wall with connecting keys and recycled concrete wall panels holding insulation block masonry, and manufacturing method of energy-saving wall
CN202081434U (en) Prefabricated pipe shaft
CN102296633A (en) Prefabricating pipe shaft
CN203394019U (en) Frame type template structure for placing of concrete
CN103541435B (en) With the cross node of full assembling of steel plate concrete Cantilever Beams
CN202849893U (en) Concrete slab pavement structure
CN103437349B (en) The construction method of steel concrete perfusion shaped pile
CN201538974U (en) Well cover seat
CN208267067U (en) A kind of building basement bottom plate catch pit
CN202672331U (en) Prefabricated reinforced concrete circular grit well
CN202000463U (en) Prefabricated reinforced concrete drainage inspection well
CN201850655U (en) T-shaped connector for new and old buildings
CN202689365U (en) Prefabricated reinforced concrete roof gutter
CN207003738U (en) A kind of prefabricated steel faced wall with stirrup

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: The five store five road, Jiangbei District of Chongqing City No. 18 400023

Patentee after: ZHONGSHE ENGINEERING CONSULTING (CHONGQING) Co.,Ltd.

Address before: The five store five road, Jiangbei District of Chongqing City No. 18 400023

Patentee before: CHONGQING ZHONGSHE ENGINEERING DESIGN Co.,Ltd.

CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 400023 Jiangbei District, Chongqing port 2, two, road 2, building 3-1

Patentee after: ZHONGSHE ENGINEERING CONSULTING (CHONGQING) Co.,Ltd.

Address before: The five store five road, Jiangbei District of Chongqing City No. 18 400023

Patentee before: ZHONGSHE ENGINEERING CONSULTING (CHONGQING) Co.,Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20121017