CN202467149U - Special rigid integral combination platform system for bottom construction of high suspension building - Google Patents

Special rigid integral combination platform system for bottom construction of high suspension building Download PDF

Info

Publication number
CN202467149U
CN202467149U CN201220113337XU CN201220113337U CN202467149U CN 202467149 U CN202467149 U CN 202467149U CN 201220113337X U CN201220113337X U CN 201220113337XU CN 201220113337 U CN201220113337 U CN 201220113337U CN 202467149 U CN202467149 U CN 202467149U
Authority
CN
China
Prior art keywords
construction
platform system
wire rope
hanging basket
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201220113337XU
Other languages
Chinese (zh)
Inventor
齐宏
张帅
盛鹰
陈德学
罗祖泽
何志润
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JustReach Science & Technology Co., Ltd.(Chengdu)
Original Assignee
CHENGDU JUSTREACH METAL MANUFACTURING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHENGDU JUSTREACH METAL MANUFACTURING Co Ltd filed Critical CHENGDU JUSTREACH METAL MANUFACTURING Co Ltd
Priority to CN201220113337XU priority Critical patent/CN202467149U/en
Application granted granted Critical
Publication of CN202467149U publication Critical patent/CN202467149U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The utility model discloses a special rigid integral combination platform system for the bottom construction of a high suspension building. The special rigid integral combination platform system comprises a main hanging basket, wherein a first steel wire rope is connected onto the main hanging basket, one end of the first steel wire rope is fixed with the main hanging basket, and the other end of the first steel wire rope is fixedly arranged on an upper suspension system. The construction platform system has the advantages that the cost is low, the occupied construction field is small, the building period is short, the ascending and the descending of construction materials, construction tools and operators can be convenient, and the bottom decoration construction of building floors with complicated structures and with the construction surface net height higher than the maximum allowable building height can be met.

Description

A kind of rigid unitary combined platform system that is exclusively used in high unsettled construction bottom construction
Technical field
The utility model relates to the operation platform system, especially relates to a kind of rigid unitary combined platform system that is exclusively used in high unsettled construction bottom construction.
Background technology
Along with the continuous development of builing industry, building structure is complicated more, and highrise building is more and more, and high unsettled buildings such as the vestibule between the building, shelter bridge also increase day by day.Carrying out high unsettled building floor bottom decoration construction at present, mainly is to adopt the mode of setting up full hall steel pipe frame to construct.
The scheme that adopts at present is: the mode of setting up full hall steel pipe frame is carried out building floor bottom decoration construction.Promptly below working face, from ground or down the first floor plate begins to set up full hall steel pipe frame, about 1.8 meters of full hall steel pipe frame scope of operation height distance working face, and a full hall steel pipe frame need be abound with in the working face below.From ground or down the first floor plate is provided with and runs ladder to a full hall steel pipe frame scope of operation, and construction material, construction tool and operating personnel are through running the terraced upper and lower scope of operation.Carry out building floor bottom decoration construction and have a lot of defectives and set up full hall steel pipe frame, even can't satisfy complex structure, highly higher working face operation.
The utility model content
The purpose of the utility model is to overcome the shortcoming and defect of above-mentioned prior art, and a kind of rigid unitary combined platform system that is exclusively used in high unsettled construction bottom construction is provided, and this operation platform system cost is low; It is little to take the construction plant; The cycle of setting up is short; Be convenient to the upper and lower of construction material, construction tool and operating personnel; The building floor bottom decoration construction that can satisfy that structure is complicated, the working face headway is higher than the maximum height that full hall frame allows to set up.
The purpose of the utility model realizes through following technical proposals: a kind of rigid unitary combined platform system that is exclusively used in high unsettled construction bottom construction; Comprise main hanging basket; Be connected with wire rope one on the said main hanging basket; Said wire rope is held one by one with main hanging basket and is fixed, and the other end is fixed in the upper suspension system.
Connect with rigid connector between the said adjacent main hanging basket, constitute a rigid unitary platform.
Said rigid connector is provided with frame plate and forms operating platform.
Some independent stationary are installed in building structure in the top of said operating platform, and the wire rope two parallel with operation platform, and wire rope two has constituted the safeguard protection rope.
Guard rail is installed around the said operating platform, and protective screening is installed, constitute the device of a protection constructor safety at guard rail and operating platform bottom.
Some auxiliary hanging baskets are set on the sidewall of said operating platform.Be used for transportation to other subsequent material or personnel.
In sum, the beneficial effect of the utility model is: this operation platform system cost is low; It is little to take the construction plant; The cycle of setting up is short; Be convenient to the upper and lower of construction material, construction tool and operating personnel; The building floor bottom decoration construction that can satisfy that structure is complicated, the working face headway is higher than the maximum height that full hall frame allows to set up.
Description of drawings
Fig. 1 is the cross-sectional view of the utility model;
Fig. 2 is the plane structure sketch map of the utility model.
Mark and corresponding component title in the accompanying drawing: 1-main hanging basket; 2-auxiliary hanging basket; 3-upper suspension system; 4-rigid connector; 5-operating platform; 6-safeguard protection rope; 7-guard rail; 8-protective screening; 9-wire rope one; 10-decorative cover.
The specific embodiment
Below in conjunction with embodiment and accompanying drawing, the utility model is done further to specify, but the embodiment of the utility model is not limited only to this.
Embodiment:
Like Fig. 1, shown in Figure 2; A kind of rigid unitary combined platform system that is exclusively used in high unsettled construction bottom construction comprises main hanging basket 1, is connected with wire rope 1 on the said main hanging basket 1; Said wire rope one 9 one ends and main hanging basket 1 are fixing, and the other end is fixed in the upper suspension system 3.Assigned address bores several wire rope via holes on the working face floor, and each wire rope via hole should be aimed at dalle lattice seam, interferes when avoiding constructing.Several upper suspension systems 3 are installed above the working face floor.
Connect with rigid connector 4 between the said adjacent main hanging basket 1, constitute a rigid unitary platform.
Said rigid connector 4 is provided with frame plate and forms operating platform 5.
Some independent stationary are installed in building structure in the top of said operating platform 5, and the wire rope two parallel with operation platform, and wire rope two has constituted safeguard protection rope 6.The operating personnel is connected to safety belt lock catch on the safeguard protection rope 6 after getting into high-altitude rigid unitary combination construction plateform system.Between safeguard protection rope 6 and the floor is exactly decorative cover 10.
Around the said operating platform 5 guard rail 7 is installed, and protective screening 8 is installed at guard rail 7 and operating platform 5 bottoms.Guard rail 7 constitutes sealing integral body all around with protective screening 8, guarantees constructor's safety.
Some auxiliary hanging baskets 2 are set on the sidewall of said operating platform 5.Construction material, construction tool and operating personnel are transported on the operation platform by auxiliary hanging basket 2.
After high-altitude rigid unitary combination construction plateform system is removed, the wire rope that bores on the working face floor one 9 via holes are carried out shutoff.
Take aforesaid way, just can realize the utility model preferably.
Combine accompanying drawing that the embodiment of the utility model is described above, but the utility model is not limited to the above-mentioned specific embodiment, the above-mentioned specific embodiment only is schematically, rather than restrictive.Those of ordinary skill is under the enlightenment of the utility model; Do not breaking away under the scope situation that the utility model aim and claim protect; Also can make a lot of forms, utilization is to a lot of fields that comprise building, and these all belong within the protection of the utility model.

Claims (6)

1. one kind is exclusively used in the rigid unitary combined platform system that high unsettled construction bottom is constructed; Comprise main hanging basket (1); Be connected with wire rope one (9) on the said main hanging basket (1); It is characterized in that: said wire rope one (9) one end and main hanging basket (1) are fixing, and the other end is fixed in the upper suspension system (3).
2. a kind of rigid unitary combined platform system that is exclusively used in high unsettled construction bottom construction according to claim 1 is characterized in that: connect with rigid connector (4) between the said adjacent main hanging basket (1), constitute a rigid unitary platform.
3. a kind of rigid unitary combined platform system that is exclusively used in high unsettled construction bottom construction according to claim 2, it is characterized in that: said rigid connector (4) is provided with frame plate and forms operating platform (5).
4. a kind of rigid unitary combined platform system that is exclusively used in high unsettled construction bottom construction according to claim 3; It is characterized in that: some independent stationary are installed in building structure in the top of said operating platform (5); And the wire rope two parallel with operation platform, wire rope two have constituted safeguard protection rope (6).
5. a kind of rigid unitary combined platform system that is exclusively used in high unsettled construction bottom construction according to claim 3; It is characterized in that: guard rail (7) is installed around the said operating platform (5), and protective screening (8) is installed at guard rail (7) and operating platform (5) bottom.
6. a kind of rigid unitary combined platform system that is exclusively used in high unsettled construction bottom construction according to claim 3 is characterized in that: some auxiliary hanging baskets (2) are set on the sidewall of said operating platform (5).
CN201220113337XU 2012-03-23 2012-03-23 Special rigid integral combination platform system for bottom construction of high suspension building Expired - Fee Related CN202467149U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201220113337XU CN202467149U (en) 2012-03-23 2012-03-23 Special rigid integral combination platform system for bottom construction of high suspension building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201220113337XU CN202467149U (en) 2012-03-23 2012-03-23 Special rigid integral combination platform system for bottom construction of high suspension building

Publications (1)

Publication Number Publication Date
CN202467149U true CN202467149U (en) 2012-10-03

Family

ID=46915316

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201220113337XU Expired - Fee Related CN202467149U (en) 2012-03-23 2012-03-23 Special rigid integral combination platform system for bottom construction of high suspension building

Country Status (1)

Country Link
CN (1) CN202467149U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105839906A (en) * 2016-05-23 2016-08-10 王崇祥 Outer wall decoration lifting platform

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105839906A (en) * 2016-05-23 2016-08-10 王崇祥 Outer wall decoration lifting platform

Similar Documents

Publication Publication Date Title
CN202144437U (en) Standing type single-person hanging seat device
CN201268937Y (en) Double-layer hanging cradle for working aloft
CN206233102U (en) A kind of packaged type faces side operation work platform
CN206553923U (en) A kind of mobile platform device for being used to install Collison fence for bridge
CN107700719A (en) A kind of hanging method of high-rise building glass curtain wall
CN202359510U (en) Multi-functional working vehicle for concrete anti-collision guardrail of bridge
CN102691474A (en) Maintenance platform
CN202467149U (en) Special rigid integral combination platform system for bottom construction of high suspension building
CN202688879U (en) Arch steel tower coating platform running with arch
CN204418629U (en) A kind of integrated form climbing frame
CN204418013U (en) Bridge flange plate is constructed self-propelled cantilever hanging basket
CN201649654U (en) Discharging platform for high-rise building construction
CN205654127U (en) Portable operation protective platform of assembly type structure stairwell
CN205873594U (en) Special construction elevator of cooling tower section of thick bamboo wall
CN205000656U (en) From over -and -under type material cycling platform
CN205476381U (en) But material loading formula elevating gear for building
CN102587601A (en) Multistage connection cage-type staircase
CN205688820U (en) A kind of installation system of high-rise building large area cell cube curtain wall block
CN102807178A (en) Chamfered hanging basket device with slide rail
CN104278864A (en) Locomotive servicing work platform
CN202181898U (en) Special hanging scaffold for sheathing and building inner-layer well wall in vertical shaft sinking construction
CN101967903A (en) Basic guide rail for helicopter assembly transmission line iron tower leg section
CN102587276B (en) Multifunctional operating vehicle for concrete anti-collision guardrail of bridge and construction method realized by aid of multifunctional operating vehicle
CN201401000Y (en) Special hanging basket for installing noise barrier roof boards
CN203392657U (en) Machine maintenance platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHENGDU JUSTREACH SCIENCE + TECHNOLOGY CO., LTD.

Free format text: FORMER NAME: CHENGDU JUSTREACH METAL MANUFACTURING CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 610000, No. nine, 339 Peak Road, Industrial Development Zone, Qingbaijiang District, Sichuan, Chengdu

Patentee after: JustReach Science & Technology Co., Ltd.(Chengdu)

Address before: 610000, No. nine, 339 Peak Road, Industrial Development Zone, Qingbaijiang District, Sichuan, Chengdu

Patentee before: Chengdu Justreach Metal Manufacturing Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121003

Termination date: 20150323

EXPY Termination of patent right or utility model