A kind of assembled architecture staircase movable type operation protective platform
Technical field
This utility model relates to building field, a kind of assembled operating platform being suitable for reserved staircase.
Background technology
Precast reinforced concrete structure is one of important directions of China's building structure development, and it is conducive to China to build
Industrialized development, improves production efficiency and saves the energy, develops Green environmental-protection building, and is conducive to improving and ensure building work
Cheng Zhiliang.
And assembled stair are as one of first-selected assembled designed component, most assembled architecture all has construction.But
Assembled stair often lag behind the construction of one layer of main body floor, cause staircase to there is adjacent side hole potential safety hazard, and staircase
This layer of template construction is without operating platform.According to existing job site Normal practice, after lifting for stair each time, set up operation foot
Hand cradle and adjacent side protection, carry out again this operation scaffold and the dismounting work of adjacent side protection in time need to carrying out stair lifting, and make
Industry workman up to work layer also needs additionally to set up stair frame, also affects site operation and enter while Normal practice repetition and waste is artificial
Degree.
Utility model content
For solving the problems referred to above, this utility model provides a kind of assembled architecture staircase movable type operation and protection flat
Platform, this platform can replace conventional stair frame, and the advantage using flexibly, can be recycled.
For achieving the above object, the technical solution adopted in the utility model is: a kind of assembled architecture staircase is portable
Operation protective platform, as the interface channel between architecture storey, it is characterised in that: include being positioned at bottom the first operation layer,
Be positioned at the 3rd operation layer above the first operation layer and with for the fixing vertical rod being connected the first operation layer and the 3rd operation layer,
And the spacing between described first operation layer and the 3rd operation layer and architecture storey matches, described 3rd operation layer has the 3rd
Break oral area, described first operation layer is provided with and tiltedly runs stair, and this tiltedly runs entry to the stair and is positioned at the first operation layer, Xie Pao building
Exporting close 3rd operation layer and being positioned at the lower section of third layer notch part of ladder, tiltedly runs outlet and the superstructure floor phase of stair
Right.
Further, described assembled architecture staircase movable type operation protective platform farther includes to be positioned at the first operation
The second operation layer between layer and the 3rd operation layer, described second operation layer has second layer notch part, and described oblique race stair
Stage casing through described second layer notch part.
Further, described second operation layer includes second layer longitudinal beam, second layer transverse beam, second layer inboard beams and
Two layers of square tube, two described second layer longitudinal beams and two described second layer transverse beam first places are connected to form for enclosing the second behaviour
Make the rectangular frame at layer edge;Two described second layer inboard beams is parallel with described second layer longitudinal beam and end is arranged on second
Layer transverse beam on, described oblique race stair be mounted laterally protective frame and protective frame is fixedly mounted on second layer longitudinal beam, institute
State and multiple second layer square tube is installed between second layer longitudinal beam and second layer inboard beams, and second layer square tube upper berth is equipped with carrying
Plate;A part and the second layer longitudinal beam of described second layer transverse beam enclose second layer notch part.
Further, described first operation layer includes ground floor longitudinal beam, ground floor transverse beam, ground floor inboard beams and
One layer of square tube, two described ground floor longitudinal beams and two described ground floor transverse beam first places are connected to form for enclosing the first behaviour
Make the rectangular frame at layer edge;Two described ground floor inboard beams is parallel with described ground floor longitudinal beam and end is arranged on first
In layer transverse beam, and ground floor inboard beams is as the support member tiltedly running stair.
Further, multiple ground floor square tube, and are installed between described ground floor longitudinal beam and ground floor inboard beams
One layer of square tube upper berth is equipped with loading plate.
Further, described 3rd operation layer includes third layer longitudinal beam, third layer transverse beam, third layer square tube and the 3rd
Layer inboard beams, two described third layer longitudinal beams and two described third layer transverse beam first places are connected to form for enclosing the 3rd behaviour
Make the rectangular frame at layer edge;Two described third layer inboard beams is parallel with described third layer longitudinal beam and end is arranged on the 3rd
Layer transverse beam on, described oblique race stair be mounted laterally protective frame and protective frame is fixedly mounted on third layer longitudinal beam, institute
State and multiple third layer square tube is installed between third layer longitudinal beam and third layer inboard beams, and third layer square tube upper berth is equipped with carrying
Plate.
Further, the edge of described first operation layer has the connection assembly for docking with architecture storey, described
Connect assembly and include the mobile jib extended by the first operation layer and the external connecting rods being connected with described mobile jib by rotating shaft, described assembled
When between architectural stair, portable operation protective platform docks with architecture storey, described external connecting rods is parallel also with described first operation layer
It is overlapped on architecture storey.
Further, described assembled architecture staircase movable type operation protective platform also includes multiple foot that hangs, and described
Hang foot and be positioned at the edge of described second operation layer.
Further, the angle between stair face and the horizontal plane of described oblique race stair is between 35 °-40 °.
Further, described first operation layer, the second operation layer, the 3rd operation layer and the oblique edge running stair are provided with
Vertical protective frame.
Use the beneficial effects of the utility model are: this operation protective platform by the first operation layer and the 3rd operation layer with
Architecture storey docks, and by tiltedly running the stair passage as two floors of connection, facilitates workman to walk at upper and lower floor gap.This
Operation protective platform can replace conventional stair frame, and can be recycled.
Accompanying drawing explanation
Fig. 1 is the overall structure schematic diagram of this utility model assembled architecture staircase movable type operation protective platform.
Fig. 2 is that the first operation layer of this utility model assembled architecture staircase movable type operation protective platform overlooks signal
Figure.
Fig. 3 is that the second operation layer of this utility model assembled architecture staircase movable type operation protective platform overlooks signal
Figure.
Fig. 4 is that the 3rd operation layer of this utility model assembled architecture staircase movable type operation protective platform overlooks signal
Figure.
Fig. 5 is the connecting component structure signal of this utility model assembled architecture staircase movable type operation protective platform
Figure.
Fig. 6 is to connect under another state of assembly in this utility model assembled architecture staircase movable type operation protective platform
Structural representation.
Reference includes:
100-the first operation layer 110-ground floor longitudinal beam 120-ground floor transverse beam
130-ground floor inboard beams 140-ground floor square tube 150-connects assembly
151-mobile jib 152-external connecting rods 153-rotating shaft
160-ground floor notch part
200-the second operation layer 210-second layer longitudinal beam 220-second layer transverse beam
230-second layer inboard beams 240-second layer square tube 250-hangs foot
260-second layer protective frame 270-second layer notch part 300-the 3rd operation layer
310-third layer longitudinal beam 320-third layer transverse beam 330-third layer square tube
340-third layer inboard beams 350-third layer protective frame 360-third layer notch part
400-tiltedly runs stair 500-vertical rod 600-vertical reinforced bar
Detailed description of the invention
Below in conjunction with accompanying drawing, this utility model is described in detail.
As shown in figs 1 to 6, the utility model proposes a kind of assembled architecture staircase movable type operation protective platform, make
For the interface channel between architecture storey, it is characterised in that: include being positioned at the first operation layer 100 of bottom, being positioned at the first operation
The 3rd operation layer 300 above layer 100 and be connected the first operation layer 100 and vertical rod of the 3rd operation layer 300 with for fixing
Spacing between 500, and the first operation layer 100 and the 3rd operation layer 300 and architecture storey matches, and the 3rd operation layer 300 has
There is third layer notch part 360, the first operation layer 100 is provided with and tiltedly runs stair 400, and this tiltedly runs stair 400 entrance and is positioned at the
One operation layer 100, tiltedly runs close 3rd operation layer 300 of outlet of stair 400 and is positioned at the lower section of third layer notch part 360, tiltedly
The outlet running stair 400 is relative with superstructure floor.
Concrete, in this operating platform, the first operation layer 100 docks with substrustion floor, and the 3rd operation layer 300 is with upper
Layer architecture storey docking, it is possible to understand that the first operation layer 100 and spacing between the 3rd operation layer 300 and architecture storey mutually
Join.Tiltedly run stair 400 to make as the walking passageway between the first operation layer 100 and the 3rd operation layer 300, the first operation layer 100
The operating platform of template is removed and transmits for staircase operator.3rd operation layer 300 is installed as staircase operator
During template and artificial abortion is positioned at the ceiling protective platform of this movable operation platform.
Above 3rd operation layer 300, there is third layer notch part 360, when workman is when tiltedly running walking on stair 400, workman
May pass through third layer notch part 360, and head will not bump against the 3rd operation layer 300.
As it is shown in figure 1, assembled architecture staircase movable type operation protective platform farther includes to be positioned at the first operation layer
100 and the 3rd the second operation layers 200 between operation layer 300, the second operation layer 200 has second layer notch part 270, and tiltedly runs
The stage casing of stair 400 passes second layer notch part 270.
Second operation layer 200, as the operating platform of staircase operator's installation form, has in the middle of the second operation layer 200
There is second layer notch part 270, same, when workman is when tiltedly running walking on stair 400, and workman may pass through second layer notch part
270, and head will not bump against the second operation layer 200.
Vertical reinforced bar 600 is as reinforcing the first operation layer 100 and fixing stiffening device of the second operation layer 200, vertically
Bracing piece 600 shares top gravity.
As it is shown on figure 3, the second operation layer 200 includes inside second layer longitudinal beam 210, second layer transverse beam 220, the second layer
Beam 230 and second layer square tube 240, two second layer longitudinal beams 210 and two second layer transverse beams 220 join end to end composition for
Enclose the rectangular frame at the second operation layer 200 edge;Two second layer inboard beams 230 are parallel with second layer longitudinal beam 210 and end
Portion is arranged in second layer transverse beam 220, tiltedly run stair 400 be mounted laterally protective frame and protective frame is fixedly mounted on second
Inside Ceng on cant beam 230, multiple second layer square tube 240 is installed between second layer longitudinal beam 210 and second layer inboard beams 230,
And second layer square tube 240 upper berth is equipped with loading plate;A part and the second layer longitudinal beam 210 of second layer transverse beam 220 enclose
Become second layer notch part 270.
Concrete, second layer longitudinal beam 210, second layer transverse beam 220, second layer inboard beams 230 and second layer square tube 240
All using the material such as steel pipe or steel square tube to make, both are material common in construction site, to facilitate temporary weld to assemble.
Multiple ground floor square tube 140 is installed between ground floor longitudinal beam 110 and ground floor inboard beams 130, and on ground floor square tube 140
Mat formation and have loading plate.Loading plate forms plane firm when workman walks.
As described in Figure 2, similar with the second operation layer 200, the first operation layer 100 includes ground floor longitudinal beam 110, ground floor
Transverse beam 120, ground floor inboard beams 130 and ground floor square tube 140, two ground floor longitudinal beams 110 and two ground floors are horizontal
Beam 120 joins end to end composition for the rectangular frame enclosing the first operation layer frontside edge;Two ground floor inboard beams 130 and
One layer longitudinal beam 110 is parallel and end is arranged in ground floor transverse beam 120, and ground floor inboard beams 130 is as tiltedly running stair
The support member of 400.First operation layer 100 is that personnel enter the passage of this movable operation platform, ground floor from bottom stair
Notch part 160 docks with stair passway, bottom, arranges in diagonal.When workman enters movable operation platform from lower floor
Time, workman may pass through ground floor notch part 160, and head will not bump against the first operation layer 100.
As described in Figure 4, similar with the second operation layer 200, the 3rd operation layer 300 includes third layer longitudinal beam 310, third layer
Transverse beam 320, third layer square tube 330 and third layer inboard beams 340, two third layer longitudinal beams 310 and two third layer are horizontal
Beam 320 joins end to end composition for the rectangular frame enclosing the 3rd operation layer 300 edge;Two third layer inboard beams 340 and
Three layers longitudinal beam 310 is parallel and end is arranged in third layer transverse beam 320, and that tiltedly runs stair 400 has been mounted laterally protective frame
And protective frame is fixedly mounted on inside third layer on cant beam 340, pacify between third layer longitudinal beam 310 and third layer inboard beams 340
Equipped with multiple third layer square tubes 330, and third layer square tube 330 upper berth is equipped with loading plate.
As shown in Figure 5, Figure 6, the edge of the first operation layer 100 has the connection assembly for docking with architecture storey
150, outside connection assembly 150 is included the mobile jib 151 extended by the first operation layer 100 and is connected with mobile jib 151 by rotating shaft 153
Extension bar 152, when assembled architecture staircase movable type operation protective platform docks with architecture storey, external connecting rods 152 and the first behaviour
Make layer 100 parallel and be overlapped on architecture storey.When lifting this platform, rotating shaft 153 of checking card, now external connecting rods 152 is according to certainly
Heavy sensation of the body power turns to the state vertical with mobile jib 151, such as Fig. 6, to facilitate this platform of slinging.When this platform docks with architecture storey
Time, external connecting rods 152 rotate and with mobile jib 151 level, this platform can be realized and be overlapped on architectural so that this platform firm with
Building connects installs.
As preferably, assembled architecture staircase movable type operation protective platform also includes multiple hanging foot 250, and hangs foot
250 edges being positioned at the second operation layer 200.Lift this platform to be sling this platform through the form hanging foot 250 by cable wire.
As preferably, tiltedly run the angle between stair face and the horizontal plane of stair 400 between 35 °-45 °.In this reality
Executing in example, the angle tiltedly run between stair face and the horizontal plane of stair 400 is 38 °.
As preferably, first operation layer the 100, second operation layer the 200, the 3rd operation layer 300 and tiltedly run stair 400
Edge is provided with vertical protective frame.Specifically, the first operation layer 100 surrounding installs ground floor protective frame, the second operation layer 200
Around installing second layer protective frame 260, the 3rd operation layer 300 surrounding installs third layer protective frame 350, tiltedly runs around stair 400
Corresponding handrail is installed.
Above content is only preferred embodiment of the present utility model, for those of ordinary skill in the art, according to this reality
By novel thought, may be made that many changes in specific embodiments and applications, as long as these changes are without departing from this
The design of utility model, belongs to protection domain of the present utility model.