CN205688820U - A kind of installation system of high-rise building large area cell cube curtain wall block - Google Patents
A kind of installation system of high-rise building large area cell cube curtain wall block Download PDFInfo
- Publication number
- CN205688820U CN205688820U CN201620342868.4U CN201620342868U CN205688820U CN 205688820 U CN205688820 U CN 205688820U CN 201620342868 U CN201620342868 U CN 201620342868U CN 205688820 U CN205688820 U CN 205688820U
- Authority
- CN
- China
- Prior art keywords
- curtain wall
- vertical
- large area
- wall block
- cell cube
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000009434 installation Methods 0.000 title claims abstract description 16
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 12
- 239000010959 steel Substances 0.000 claims abstract description 12
- 230000032258 transport Effects 0.000 claims description 4
- 238000010276 construction Methods 0.000 abstract description 6
- 238000011900 installation process Methods 0.000 abstract description 2
- 238000005516 engineering process Methods 0.000 description 3
- 230000007812 deficiency Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000002420 orchard Substances 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses the installation system of a kind of high-rise building large area cell cube curtain wall block, device is allocated and transported including vertical-lifting device and level, described vertical-lifting device includes the vertical guide being arranged on outside high-rise building and the vertical-lifting equipment being arranged on vertical guide top floor, and large area cell cube curtain wall block is placed between vertical guide and is carried by allocation and transportation and steel wire rope is connected with vertical-lifting equipment;Described level allocation and transportation device includes the horizontal rail being arranged on vertical guide top floor and the lifting means of certainly walking being arranged in horizontal rail.This utility model is changed curtain wall the handling of into track restrained property by traditional outside handling, even if still can install at strong wind weather, installation process is avoided to be affected by upper air current, the outside installation of curtain wall is changed into installing at interior of building by this utility model simultaneously, greatly improve operational security and production efficiency, construction safety and construction speed are effectively ensured.
Description
Technical field
This utility model relates to the installation system of a kind of high-rise building large area cell cube curtain wall block, belongs to building curtain wall
Technical field of construction.
Background technology
When large area cell cube curtain wall block installed by the high-rise building high more than 300m, due to curtain wall block area mistake
Greatly, use elevator cannot to be loaded and transport, and when using tower crane handling, it is impossible to curtain wall block is hoisted in floor, simultaneously
Curtain wall block is easily subject to upper air current impact during handling, causes curtain wall block using tower crane handling and outside hanging basket to install
During cause and significantly swing, not only affect installation, and there is potential safety hazard.
Utility model content
The purpose of this utility model is: provide simple in construction, easy for installation, safe and reliable high-rise building large area
The installation system of cell cube curtain wall block, to overcome the deficiencies in the prior art.
The technical solution of the utility model: the installation system of a kind of high-rise building large area cell cube curtain wall block, including
Vertical-lifting device and level allocation and transportation device, it is vertical that described vertical-lifting device includes being arranged on outside high-rise building
Guide rail and the vertical-lifting equipment being arranged on vertical guide top floor, large area cell cube curtain wall block is placed in vertical guide
Between and carried by allocation and transportation and steel wire rope is connected with vertical-lifting equipment;Described level allocation and transportation device includes being arranged on vertically
Horizontal rail on rail crown floor and the lifting means of certainly walking being arranged in horizontal rail, described lifting of certainly walking
Equipment include can in horizontal rail the walking dolly of walking in a horizontal state, walking dolly is provided with strand electric block and electricity
Dynamic main frame, strand electric block is connected with large area cell cube curtain wall block by steel wire rope.
Described vertical-lifting device also includes the joist being connected with allocation and transportation band or steel wire rope, is provided with at the two ends of joist
The bearing that can slide in vertical guide, the bottom of large area cell cube curtain wall block is fixed on joist.
The vertical elongated layout of 500mm outside described vertical guide distance high-rise building, and between vertical guide between
Away from the width more than large area cell cube curtain wall block.
Compared with prior art, the utility model has the advantage of: large area cell cube curtain wall block is put by this utility model
Between vertical guide and by vertical-lifting equipment, be promoted to designated floor, the most again by horizontal rail voluntarily
Walk lifting means by large area cell cube curtain wall block level allocate and transport to designated mounting position, then by workmen inside floor complete
Become the installment work of large area cell cube curtain wall block, thus changed large area cell cube curtain wall into track by traditional outside handling
Restrictive handling, even if still can install at strong wind weather, it is to avoid installation process is affected by upper air current, simultaneously this reality
Change into installing at interior of building by outside installation of large area cell cube curtain wall with novel, greatly improve operational security and
Production efficiency, is effectively ensured construction safety and construction speed.Therefore, this utility model not only has safe and reliable, good stability
Advantage, but also have that technology is simple, establish one's own system, onsite application efficiency is high, labor intensive is low, be not take up elevator or tower
The advantages such as transporting equipment capacity such as hang.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the structural representation of vertical-lifting device in this utility model;
Fig. 3 is the structural representation of level allocation and transportation device in this utility model.
Description of reference numerals: 1-large area cell cube curtain wall block, 2-vertical guide, 3-joist, 4-horizontal rail, 5-is vertical
Lifting means, 6-steel wire rope, 7-allocates and transports band, 8-high-strength bolt, 9-high-rise building, 10-strand electric block, and 11-walks
Dolly, the electronic main frame of 12-, 13-track bolt.
Detailed description of the invention
In order to make this utility model purpose, technical scheme and advantage clearer, below in conjunction with the accompanying drawings with embodiment to this
Utility model is described in further detail.
Embodiment of the present utility model: the structural representation of the installation system of high-rise building large area cell cube curtain wall block
As shown in Figures 1 to 3, allocating and transporting device including vertical-lifting device and level, described vertical-lifting device includes being arranged on super
Vertical guide 2 outside skyscraper 9 and be arranged on the vertical-lifting equipment 5 on vertical guide 2 top floor, vertical-lifting
Equipment 5 can be selected for JK3T type hoist engine, is then fixed on the floor of high-rise building 9 by high-strength bolt 8;Described is perpendicular
The vertical elongated layout of direction guiding rail 2 500mm outside high-rise building 9, and the spacing between vertical guide 2 is more than large area list
The width of unit's body curtain wall block 1;Large area cell cube curtain wall block 1 is placed between vertical guide 2 and by allocation and transportation band 7 and steel wire rope
6 are connected with vertical-lifting equipment 5;Described level allocation and transportation device includes the horizontal rail being arranged on vertical guide 2 top floor
Road 4 and the lifting means of certainly walking being arranged in horizontal rail 4, horizontal rail 4 uses track bolt 13 to be fixed on Super High
On the floor of building 9, described includes walking little by the DPC-03 type of walking in a horizontal state in horizontal rail 4 from walking lifting means
Car 11, is provided with HSY03-01 type strand electric block 10 and electronic main frame 12, strand electric block on walking dolly 11
10 are connected with large area cell cube curtain wall block 1 by steel wire rope 6.Described vertical-lifting device also includes and allocation and transportation band 7 or steel
The joist 3 that cord 6 connects, is provided with the bearing that can slide in vertical guide 2, large area cell cube curtain at the two ends of joist 3
The bottom of wall block 1 is fixed on joist 3.
Above-mentioned large area cell cube curtain wall block 1 refers to a width of more than 1.8m, a length of cell cube curtain wall block more than 4m.?
Carry out large area cell cube curtain wall block 1 on high-rise building when installing, large area cell cube curtain wall block 1 is placed in vertical guide 2
Between, the bottom of large area cell cube curtain wall block 1 is fixed on joist 3 simultaneously, then will by allocation and transportation band 7 or steel wire rope 6
Large area cell cube curtain wall block 1 and joist 3 are connected with vertical-lifting equipment 5, the most just can be by vertical-lifting equipment 5 by big
Surface elemant body curtain wall block 1 is promoted to designated floor, the most again by the lifting means of walking certainly in horizontal rail 4 by large area
Cell cube curtain wall block 1 level is allocated and transported to designated mounting position, then is completed inside the floor of high-rise building 9 greatly by workmen
The installment work of surface elemant body curtain wall block 1.
System of the present utility model is carried out checking in the gardens and orchards Petronas Towers project building course of Kweiyang, and completes
The installation task of large area cell cube curtain wall block high for 300m, proves in implementation process that native system has safe and reliable, stability
The advantage good, work efficiency is high, and this utility model also has that technology is simple, onsite application efficiency is high, labor intensive is low,
It is not take up tower crane, elevator capacity, strong wind weather and still can carry out the advantages such as installation.
Claims (3)
1. an installation system for high-rise building large area cell cube curtain wall block, allocates and transports including vertical-lifting device and level
Device, it is characterised in that: described vertical-lifting device include being arranged on the vertical guide (2) in high-rise building (9) outside with
And the vertical-lifting equipment (5) being arranged on vertical guide (2) top floor, large area cell cube curtain wall block (1) is placed in vertically
It is connected with vertical-lifting equipment (5) between guide rail (2) and by allocation and transportation band (7) and steel wire rope (6);Described level allocation and transportation dress
Put the horizontal rail (4) including being arranged on vertical guide (2) top floor and the walking certainly being arranged in horizontal rail (4)
Lifting means, described includes to be expert at the walking dolly (11) of the upper walking in a horizontal state of horizontal rail (4) from walking lifting means
Walking to be provided with on dolly (11) strand electric block (10) and electronic main frame (12), strand electric block (10) passes through steel wire rope
(6) it is connected with large area cell cube curtain wall block (1).
The installation system of high-rise building large area cell cube curtain wall block the most according to claim 1, it is characterised in that: institute
The vertical-lifting device stated also includes the joist (3) being connected with allocation and transportation band (7) or steel wire rope (6), arranges at the two ends of joist (3)
Having can be at the upper bearing slided of vertical guide (2), and the bottom of large area cell cube curtain wall block (1) is fixed on joist (3).
The installation system of high-rise building large area cell cube curtain wall block the most according to claim 1, it is characterised in that: institute
Vertical guide (2) distance high-rise building (9) the outside vertical elongated layout of 500mm stated, and the spacing between vertical guide (2)
Width more than large area cell cube curtain wall block (1).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201620342868.4U CN205688820U (en) | 2016-04-22 | 2016-04-22 | A kind of installation system of high-rise building large area cell cube curtain wall block |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201620342868.4U CN205688820U (en) | 2016-04-22 | 2016-04-22 | A kind of installation system of high-rise building large area cell cube curtain wall block |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN205688820U true CN205688820U (en) | 2016-11-16 |
Family
ID=57265145
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201620342868.4U Expired - Fee Related CN205688820U (en) | 2016-04-22 | 2016-04-22 | A kind of installation system of high-rise building large area cell cube curtain wall block |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN205688820U (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107700854A (en) * | 2017-07-05 | 2018-02-16 | 中国建筑第八工程局有限公司 | The steel plate wall sliding erecting device and installation method of a kind of Super High Core Walls Structure |
| CN110030836A (en) * | 2018-07-17 | 2019-07-19 | 柳州钢铁股份有限公司 | The method and track-type facilities of sintering pallet safe and highly efficient operation in hole for hoist |
| CN115711023A (en) * | 2022-11-10 | 2023-02-24 | 上海建工五建集团有限公司 | Window wiping and replacing auxiliary equipment of glass curtain wall of super high-rise building with glass plank road |
-
2016
- 2016-04-22 CN CN201620342868.4U patent/CN205688820U/en not_active Expired - Fee Related
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107700854A (en) * | 2017-07-05 | 2018-02-16 | 中国建筑第八工程局有限公司 | The steel plate wall sliding erecting device and installation method of a kind of Super High Core Walls Structure |
| CN110030836A (en) * | 2018-07-17 | 2019-07-19 | 柳州钢铁股份有限公司 | The method and track-type facilities of sintering pallet safe and highly efficient operation in hole for hoist |
| CN115711023A (en) * | 2022-11-10 | 2023-02-24 | 上海建工五建集团有限公司 | Window wiping and replacing auxiliary equipment of glass curtain wall of super high-rise building with glass plank road |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107304631A (en) | The installation method and system of a kind of high-rise building large area cell cube curtain wall block | |
| CN205955236U (en) | Container formula of taking pulley platform of unloading of encorbelmenting | |
| CN103043526A (en) | Integral hoisting device and method for super-long steel reinforcement cage of underground continuous wall | |
| CN204689430U (en) | To Construction of Silo movable hoisting device | |
| CN201809077U (en) | Portable curtain wall material lifting device | |
| CN205688820U (en) | A kind of installation system of high-rise building large area cell cube curtain wall block | |
| CN104495632A (en) | Expanded type suspension rope lifting and hoisting system | |
| CN203794533U (en) | Light portable mobile lifting equipment | |
| CN102777048A (en) | Vertical transportation device | |
| CN204022201U (en) | A kind of weight-lifting equipment for vertical transport | |
| CN107190991A (en) | The special-shaped curtain wall vertical lifting system of glass plate | |
| CN102807178A (en) | Chamfered hanging basket device with slide rail | |
| CN104612391A (en) | Protection construction platform for high-rise building | |
| CN103626086A (en) | Chamfer wall construction basket | |
| CN204609308U (en) | A kind of passage limited position concrete rail transporter | |
| CN202139834U (en) | Chamfer wall surface construction hanging basket | |
| CN110593582A (en) | High-rise curtain wall installation auxiliary assembly with safety facility | |
| CN105152034B (en) | For the cableway Lift-on/Lift-off System of pitched roof curtain wall | |
| CN205527413U (en) | Hang cantilever crane | |
| CN206051300U (en) | A kind of gantry crane's supporting legs structure | |
| CN205873714U (en) | Aquatic gravity type gallows frame mounting structure | |
| CN206219113U (en) | One kind lifting chassis | |
| CN212771963U (en) | Movable suspension operation platform | |
| CN103362076A (en) | Extensible hanging basket for bridge | |
| CN203555689U (en) | Electric hanging basket for vertical shaft |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161116 Termination date: 20200422 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |