CN205873594U - Special construction elevator of cooling tower section of thick bamboo wall - Google Patents

Special construction elevator of cooling tower section of thick bamboo wall Download PDF

Info

Publication number
CN205873594U
CN205873594U CN201620646157.6U CN201620646157U CN205873594U CN 205873594 U CN205873594 U CN 205873594U CN 201620646157 U CN201620646157 U CN 201620646157U CN 205873594 U CN205873594 U CN 205873594U
Authority
CN
China
Prior art keywords
bearing frame
cage
cooling tower
link
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620646157.6U
Other languages
Chinese (zh)
Inventor
徐西兴
葛涛
姚磊
刘亚芬
刘克勇
张卫星
李启忠
杨明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chinese Energy Construction Group Anhui Electric Power Builds Second Engineering Co Ltd
Original Assignee
Chinese Energy Construction Group Anhui Electric Power Builds Second Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chinese Energy Construction Group Anhui Electric Power Builds Second Engineering Co Ltd filed Critical Chinese Energy Construction Group Anhui Electric Power Builds Second Engineering Co Ltd
Priority to CN201620646157.6U priority Critical patent/CN205873594U/en
Application granted granted Critical
Publication of CN205873594U publication Critical patent/CN205873594U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Types And Forms Of Lifts (AREA)

Abstract

The utility model discloses a special construction elevator of cooling tower section of thick bamboo wall, including the bearing frame, one side even interval ground in the vertical direction of bearing frame sets firmly the support that adheres to that is used for with cooling tower wall connection, lie in keep away from adhere to support one side the bearing frame upward swing joint have the cage, the cage passes through the levelling device and is connected with the bearing frame, the levelling device include with the same link of bearing frame inclination, the bottom and the cage fixed connection of link, the top and the centre of link are connected with the link through the towline respectively, the individual direction rack that is equipped with of lateral wall of bearing frame, the link pass through the gear with the direction rack is connected to remove along the direction rack. Make the outer wall of bearing frame laminating cooling tower in vertical orientation, the cage is connected to the rethread levelling device, and messenger's cage under the horizontality, operates steadily all the time, and stable in structure.

Description

A kind of special building hoist of Cooling Tower Wall
Technical field
This utility model relates to building hoist field, particularly relates to a kind of special building hoist of Cooling Tower Wall.
Background technology
Building hoist is manned, loading construction machinery commonly used in building, is mainly used in the inside and outside of skyscraper The construction of the building such as finishing, bridge, owing to the body structure of its uniqueness allows workmen take the most comfortable but also safety, makes to execute The application in engineering construction of the work elevator is more and more extensive.But the operation principle of current existing building hoist is linear type Ascending, descending, it is applicable in the structure that outer wall is vertical-horizontal use, and the outer wall of cooling tower is usually up-small and down-big shaped form , cause existing building hoist can not be suitable for the operating mode of this curve construction, so it is the safest but also steady that one is presently required The special building hoist of fixed cooling tower.
Utility model content
The purpose of this utility model is to provide a kind of special building hoist of Cooling Tower Wall, solves present stage shortage cooling The problem of the special building hoist of this curve of tower wall construction operating mode.
For solving above-mentioned technical problem, this utility model adopts the following technical scheme that
A kind of special building hoist of Cooling Tower Wall, including bearing frame, the side of described bearing frame is in vertical direction It is evenly spaced apart to be installed with the steel framework for being connected with cooling tower outer wall, is located remotely from the bearing frame of steel framework side It is connected with cage;Described cage is connected with bearing frame by levelling device, and described levelling device includes and described bearing frame The link that angle of inclination is identical, the bottom of described link is fixing with cage to be connected, and top and the centre of link lead to respectively Cross hoist ropes to be connected with link;The sidewall of described bearing frame is provided with guiding tooth bar, and described link passes through gear with described Guiding tooth bar connects, and moves along guiding tooth bar.
Scheme, described link is installed with driving machine and traction sheave further, and described hoist ropes end is wrapped in traction It is connected with link again on wheel;The output shaft of described driving machine is connected with described traction sheave, drives cage to hang down along bearing frame Nogata moving up and down upwards.
Scheme further, the bottom of described bearing frame is detachable with the ground of concreting to be connected;The end of bearing frame End outside is provided with end guardrail, and the top of bearing frame is provided with pillory cage.
Scheme further, the distance between adjacent two steel frameworks is 6 meters.
Scheme further, described cage is provided with boom hoisting.
Scheme further, described bearing frame is to be connected in sequence by multiple standard knots head and the tail, and described guiding tooth bar is arranged On the intermediate standard joint in addition to each joint standard knot in two ends.
Scheme further, is additionally provided with the cable drum putting the cable connecting driving machine for volume, and described bearing frame is spaced Being disposed with cable saddle, described cable is connected to driving machine by cable saddle after cable drum is released.
Compared with prior art, Advantageous Effects of the present utility model is as follows:
Adpting flange is built on ground by concrete, then by bolt by bearing frame bottom be connected acting flange Connect fixing, bearing frame is played fixing effect and is then connected on the outer wall of cooling tower by steel framework, make bearing frame The outer wall of in the vertical direction laminating cooling tower is obliquely installed, then connects cage by levelling device, makes cage all the time in level Under state, operate steadily, and Stability Analysis of Structures.
Accompanying drawing explanation
The utility model is described in further detail in explanation below in conjunction with the accompanying drawings.
Fig. 1 is axonometric chart of the present utility model;
Fig. 2 is partial side view of the present utility model;
In figure: 1, bearing frame, 101, standard knot;2, steel framework;3, cage;4, levelling device, 401, hoist ropes, 402, Traction sheave, 403, link;5, machine is driven;6, tooth bar is guided;7, end guardrail;8, pillory cage;9, boom hoisting, 10, cable drum; 11, cable saddle;12, gear.
Detailed description of the invention
As shown in Figure 1, 2, a kind of special building hoist of Cooling Tower Wall, including bearing frame 1, the one of described bearing frame 1 Side is evenly spaced apart to be installed with the steel framework 2 for being connected with cooling tower outer wall in vertical direction, is located remotely from attachment It is connected with cage 3 on the bearing frame 1 of frame 2 side;Described cage 3 is connected with bearing frame 1 by levelling device 4, described tune Leveling device 4 includes the link 403 identical with described bearing frame 1 angle of inclination, and the bottom of described link 403 is solid with cage 3 Fixed connection, the top of link 403 and centre are connected with link 403 by hoist ropes 401 respectively;The side of described bearing frame 1 Wall is provided with guiding tooth bar 6, and described link 403 is connected with described guiding tooth bar 6 by gear 12, and along guiding tooth bar 6 Mobile.
Scheme, described link 403 is installed with driving machine 5 and traction sheave 402, the end of described hoist ropes 401 further Portion is wrapped on traction sheave 402 and is connected with link 403;The output shaft of described driving machine 5 is connected with described traction sheave 402, Cage 3 is driven to carry out moving up and down in vertical direction along bearing frame 1.
Scheme further, the bottom of described bearing frame 1 is detachable with the ground of concreting to be connected;Bearing frame 1 Bottom periphery encloses and is provided with end guardrail 7, prevents layman from arbitrarily entering this region, causes personal injury;The top of bearing frame 1 It is provided with pillory cage 8, is convenient for people to requirements of one's work on bearing frame 1 top.
Scheme further, the distance between adjacent two steel frameworks 2 is 6 meters.
Scheme further, described cage 3 is provided with boom hoisting 9, facilitates the lifting of cage internal objects.
Scheme further, described bearing frame 1 is to be connected in sequence by multiple standard knots 101 head and the tail, described guiding tooth bar 6 It is arranged on the intermediate standard joint in addition to each joint standard knot in two ends.
Scheme further, is additionally provided with the cable drum 10 putting the cable connecting driving machine 5 for volume, on described bearing frame 1 Interval is disposed with cable saddle 11, and described cable is connected to driving machine 5 by cable saddle 11 after cable drum 10 is released, Make cable smooth and easy, will not tie a knot.
In this device, the bottom of bearing frame 1 removably connects with the ground of concreting, as mixed in passed through by adpting flange Solidifying soil is built on ground, is then bolt-connected to bearing frame bottom, and bearing frame plays fixing effect;Described load-bearing Frame 1 is connected on the outer wall of cooling tower by steel framework 2, in order to strengthen the steadiness of connection, is evenly spaced apart to arrange several more Individual steel framework 2, specifically the distance with two adjacent steel frameworks 2 is 6 meters, makes bearing frame 1 cooling tower outer wall of fitting exist Shape on vertical direction, its outline is curved;Described bearing frame 1 is connected with cage 3 by levelling device 4, described Cage 3 is located remotely from described steel framework 2 side;Make no matter cage can keep level on the bearing frame that slope is how many; Being driven traction sheave 402 to rotate by driving machine 5, the friction produced between traction sheave 402 and hoist ropes 401 produces leading cage 3 Gravitation, cage 3 is moved along the guiding tooth bar 6 on bearing frame 1 by the gear 12 on link 403, it is achieved cage 3 exists Moving up and down on bearing frame 1, gear ratio is more stable, makes cage run more steady.
Described bearing frame 1 is connected in sequence by multiple standard knots 101 head and the tail, both convenient dismounting, again convenient laminating cooling The curvilinear structures of tower wall.Topmost it is not provided with guiding on a described standard knot of joint 101 and a bottom described standard knot 101 of joint Tooth bar 6, remaining described standard knot 101 is respectively provided with tooth bar 6, saves, due to the space of cage based on a bottom joint standard knot Relation, drives machine 5 will not contact with this joint standard knot, so not setting tooth bar;Topmost arrange spacing below a joint standard knot Device, prevents cage from deviating from track.
Embodiment described above is only to be described optimal way of the present utility model, not to of the present utility model Scope is defined, and on the premise of without departing from this utility model design spirit, those of ordinary skill in the art are new to this practicality Various deformation that the technical scheme of type is made and improvement, all should fall into the protection domain that this utility model claims determine In.

Claims (7)

1. the special building hoist of Cooling Tower Wall, including bearing frame (1), it is characterised in that: the one of described bearing frame (1) Side is evenly spaced apart the steel framework (2) being installed with for being connected with cooling tower outer wall in vertical direction, is located remotely from attachment It is connected with cage (3) on the bearing frame (1) of support (2) side;Described cage (3) passes through levelling device (4) and bearing frame (1) connecting, described levelling device (4) includes the link (403) identical with described bearing frame (1) angle of inclination, described connection The bottom of frame (403) is fixing with cage (3) to be connected, and the top of link (403) and centre are passed through hoist ropes (401) respectively and connected Connect frame (403) to connect;The sidewall of described bearing frame (1) is provided with guiding tooth bar (6), and described link (403) passes through gear (12) it is connected with described guiding tooth bar (6), and mobile along guiding tooth bar (6).
The special building hoist of Cooling Tower Wall the most according to claim 1, it is characterised in that: described link (403) On be installed with driving machine (5) and traction sheave (402), described hoist ropes (401) end be wrapped on traction sheave (402) again be connected Frame (403) connects;The output shaft of described driving machine (5) is connected with described traction sheave (402), drives cage (3) along bearing frame (1) Carry out moving up and down in vertical direction.
The special building hoist of Cooling Tower Wall the most according to claim 1, it is characterised in that: described bearing frame (1) Bottom is detachable with the ground of concreting to be connected;The bottom periphery of bearing frame (1) encloses and is provided with end guardrail (7), bearing frame (1) top is provided with pillory cage (8).
The special building hoist of Cooling Tower Wall the most according to claim 1, it is characterised in that: adjacent two steel frameworks (2) distance between is 6 meters.
The special building hoist of Cooling Tower Wall the most according to claim 1, it is characterised in that: described cage sets on (3) There is boom hoisting (9).
The special building hoist of Cooling Tower Wall the most according to claim 1, it is characterised in that: described bearing frame (1) is Being connected in sequence by multiple standard knots (101) head and the tail, described guiding tooth bar (6) is arranged in addition to each joint standard knot in two ends On intermediate standard joint.
The special building hoist of Cooling Tower Wall the most according to claim 1, it is characterised in that: it is additionally provided with for the volume company of putting Connecing the cable drum (10) of the cable of driving machine (5), the upper interval of described bearing frame (1) is disposed with cable saddle (11), described electricity Cable is connected to driving machine (5) by cable saddle (11) after cable drum (10) is released.
CN201620646157.6U 2016-06-27 2016-06-27 Special construction elevator of cooling tower section of thick bamboo wall Expired - Fee Related CN205873594U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620646157.6U CN205873594U (en) 2016-06-27 2016-06-27 Special construction elevator of cooling tower section of thick bamboo wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620646157.6U CN205873594U (en) 2016-06-27 2016-06-27 Special construction elevator of cooling tower section of thick bamboo wall

Publications (1)

Publication Number Publication Date
CN205873594U true CN205873594U (en) 2017-01-11

Family

ID=57692636

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620646157.6U Expired - Fee Related CN205873594U (en) 2016-06-27 2016-06-27 Special construction elevator of cooling tower section of thick bamboo wall

Country Status (1)

Country Link
CN (1) CN205873594U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110422722A (en) * 2019-08-12 2019-11-08 廊坊凯博建设机械科技有限公司 A kind of mechanical self-level(l)ing device and method
CN114368664A (en) * 2021-12-30 2022-04-19 江苏省送变电有限公司 Inclined construction elevator cage
CN114394499A (en) * 2021-12-30 2022-04-26 国网江苏省电力有限公司建设分公司 Safety monitoring system and monitoring method for angle-adjustable suspension cage

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110422722A (en) * 2019-08-12 2019-11-08 廊坊凯博建设机械科技有限公司 A kind of mechanical self-level(l)ing device and method
CN114368664A (en) * 2021-12-30 2022-04-19 江苏省送变电有限公司 Inclined construction elevator cage
CN114394499A (en) * 2021-12-30 2022-04-26 国网江苏省电力有限公司建设分公司 Safety monitoring system and monitoring method for angle-adjustable suspension cage
CN114368664B (en) * 2021-12-30 2024-04-26 江苏省送变电有限公司 Inclined construction elevator cage
CN114394499B (en) * 2021-12-30 2024-05-17 国网江苏省电力有限公司建设分公司 Safety monitoring system and monitoring method for angle-adjustable suspension cage

Similar Documents

Publication Publication Date Title
CN101514586B (en) Hanger rail type electric hanging boat and construction method thereof
CN105000482B (en) Tower crane with walking mechanism
CN101537976B (en) Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof
CN205873594U (en) Special construction elevator of cooling tower section of thick bamboo wall
CN205387439U (en) Mast hoisting accessory
CN201376848Y (en) Large-scale double-tower automatic-elevation hoisting equipment
CN106698208A (en) Hoisting equipment and hoisting method for external transportation of super high-rise building
CN205294665U (en) Jack -up tower crane based on engineering mechanics
CN103274315B (en) Installing and hoisting device for side plate and upright of gas chamber
CN101863405A (en) Traction elevator with counterweight of double cars in single hoistway
CN216341336U (en) Adjustable inverted frame structure of 750 x 750mm cross-section holding rod system
CN206562264U (en) A kind of hanging device for transport outside high-rise building
CN210084788U (en) Tower crane for building
CN2923635Y (en) Single-column towing type elevator
CN103306218B (en) Bottom width overhaul hanging basket of bridge
CN107476195A (en) A kind of suspension bridge transports the fortune beam tackle system of stiff girder
CN201507112U (en) Sliding template system
CN201325826Y (en) Rock anchor beam hoisting device for underground power house
CN203257106U (en) Multifunctional power-driven walking type walking system
CN201762053U (en) Simple automatic hoisting rod
CN206109992U (en) Bridge bottom surface construction platform
CN205591115U (en) Suspension type catwalk veil installing the system
CN209567730U (en) A kind of small-sized lattice dead man steel construction
CN204938801U (en) The tower crane that is connected can be realized with building
CN2703832Y (en) Elevator well creeping formwork hoisting frame

Legal Events

Date Code Title Description
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170111

Termination date: 20210627