CN206109992U - Bridge bottom surface construction platform - Google Patents

Bridge bottom surface construction platform Download PDF

Info

Publication number
CN206109992U
CN206109992U CN201621139998.4U CN201621139998U CN206109992U CN 206109992 U CN206109992 U CN 206109992U CN 201621139998 U CN201621139998 U CN 201621139998U CN 206109992 U CN206109992 U CN 206109992U
Authority
CN
China
Prior art keywords
girder
construction
basketry
cat ladder
track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621139998.4U
Other languages
Chinese (zh)
Inventor
孙有竹
沈新铭
柴建军
姜军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG XINGTU BRIDGE SPECIAL EQUIPMENT MANUFACTURING Co Ltd
Original Assignee
ZHEJIANG XINGTU BRIDGE SPECIAL EQUIPMENT MANUFACTURING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG XINGTU BRIDGE SPECIAL EQUIPMENT MANUFACTURING Co Ltd filed Critical ZHEJIANG XINGTU BRIDGE SPECIAL EQUIPMENT MANUFACTURING Co Ltd
Priority to CN201621139998.4U priority Critical patent/CN206109992U/en
Application granted granted Critical
Publication of CN206109992U publication Critical patent/CN206109992U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

Bridge bottom surface construction platform is including girder, construction basket, gyro wheel, lay at the track of bridge floor, hang mechanism and cat ladder, the girder below is equipped with the gyro wheel, and the gyro wheel can be followed the track and extend to the slip with track cooperation installation, gyro wheel, the construction basket is established in the girder below, and the girder is connected by the girder bearing through hanging the mechanism to the construction basket, hang the mechanism including connecting cable and elevating gear, connect the cable and connect elevating gear, distance between elevating gear adjustment construction basket and the girder, the cat ladder extends to construction basket, cat ladder and girder relatively fixed from the girder.

Description

Bridge bottom surface operation platform
Technical field
This utility model is related to bridge bottom surface operation platform.
Background technology
During bridge construction, need to construct bridge bottom surface, the bottom surface of usual bridge is arc, to bridge bottom During surface construction, timely adjustment construction height is needed, in the hope of reaching optimal construction location.And current bridge bottom surface operation platform Suitable construction location cannot be adjusted to, and overall construction design is not ideal enough, security performance is relatively low.
Utility model content
It is to solve the problems, such as prior art that the purpose of this utility model is, there is provided one kind movement is flexibly, suitably not With the bridge bottom surface operation platform of construction environment.
The technical solution adopted in the utility model is as follows:Bridge bottom surface operation platform, including girder, construction basketry, roller, It is laid on track, hanging mechanism and the cat ladder of bridge floor;The girder lower section is provided with roller, and roller coordinates with track to be installed, roller Can extend to slide along track;Construction basketry is located at girder lower section, and construction basketry connects girder and held by girder by hanging mechanism Weight;Hanging mechanism includes connecting strand and lowering or hoisting gear, connecting strand connection lowering or hoisting gear, lowering or hoisting gear adjustment construction basketry and girder The distance between, the cat ladder extends to construction basketry from girder, and cat ladder is relatively fixed with girder.
Lowering or hoisting gear described in the utility model is electric block or chain block.
Track described in the utility model is channel-section steel, and upwards, roller falls and slided in channel-section steel the notch of channel-section steel.
Girder described in the utility model includes two crossbeams, the connecting rod of two crossbeams of anchor ear device and connection, the crossbeam bag Two I-steel are included, two I-steel are set up in parallel and are fixedly connected by contiguous block, there is clearance distance between two I-steel;Anchor ear Device includes upper boom, lower beam and threaded rod, and upper boom, lower beam distribution are arranged on crossbeam upper and lower, and upper boom, lower beam are by threaded rod Lower screw-threaded coupling;Connecting rod is erected on two crossbeams, and connection bridge two ends are fixedly connected respectively with two crossbeams.
This utility model also includes guard rail, and guard rail is arranged on cat ladder periphery and is fixedly connected with cat ladder.
This utility model is had the advantage that compared to existing technology:This utility model has construction safety reliability, operative employee Convenient construction is flexible, the bridge bottom surface operation platform of the suitable construction height of scalable.
Description of the drawings
Fig. 1 is the structural representation of embodiment described in the utility model.
Fig. 2 is the partial enlargement structural representation of A portions shown in Fig. 1.
Specific embodiment
Embodiment 1
As shown in Figure 1 to Figure 2, bridge bottom surface operation platform described in the present embodiment, including girder 1, construction basketry 2, roller 3rd, track 4, hanging mechanism 5 and the cat ladder 6 of bridge floor are laid on;The lower section of the girder 1 is provided with roller 3, and roller 3 coordinates with track 4 Install, roller 3 can extend to slide along track 4;Construction basketry 2 is located at the lower section of girder 1, and construction basketry 2 is connected by hanging mechanism 5 Girder 1 is connect by the load-bearing of girder 1;Hanging mechanism 5 includes connecting strand 51 and lowering or hoisting gear 52, and connecting strand 51 connects lowering or hoisting gear 52, The distance between the adjustment of lowering or hoisting gear 52 construction basketry 2 and girder 1, the cat ladder 6 extends to construction basketry 2, cat ladder from girder 1 6 are relatively fixed with girder 1., across bridge two ends, the two ends of girder 1 are by the connection construction basketry 2 of hanging mechanism 5, construction basket for girder 1 Basket 2 is the frame structure being built into using shape, and walkway board is equipped with frame structure, and builder can be in construction basketry 2 Interior walking.
Lowering or hoisting gear 52 described in the present embodiment is electric block or chain block.The connecting strand 51 being connected with lowering or hoisting gear 52 Construction basketry 2 is hung, by the lifting for operating the controllable construction basketry 2 of lowering or hoisting gear 52.
Track 4 described in the present embodiment is channel-section steel, and upwards, roller 3 falls and slided in channel-section steel the notch of channel-section steel.
Girder 1 described in the present embodiment includes two crossbeams 11, the connecting rod 13 of two crossbeams 11 of anchor ear device 12 and connection, described Crossbeam 11 includes two I-steel 111, and two I-steel 111 are set up in parallel and are fixedly connected by contiguous block, between two I-steel 111 With clearance distance;Anchor ear device 12 includes upper boom 121, lower beam 122 and threaded rod 123, and upper boom 121, the distribution of lower beam 122 are arranged In the upper and lower of crossbeam 11, threaded rod 123 penetrates upper boom 121, lower beam 122 by threaded rod screw-threaded coupling about 123;Connecting rod 13 It is erected on two crossbeams 11, the frame two ends of connecting rod 13 are fixedly connected respectively with two crossbeams 11.
Also include guard rail 7 described in the present embodiment, guard rail 7 is arranged on the periphery of cat ladder 6 and is fixedly connected with cat ladder 6.
Specific embodiment of the utility model is described above.It is to be appreciated that this utility model not office It is limited to above-mentioned particular implementation, those skilled in the art can within the scope of the claims make various modifications or modification, This has no effect on flesh and blood of the present utility model.

Claims (5)

1. bridge bottom surface operation platform, is characterized in that:Including girder, construction basketry, roller, the track for being laid on bridge floor, hanging Mechanism and cat ladder;The girder lower section is provided with roller, and roller coordinates with track to be installed, and roller can extend to slide along track;Apply Work basketry is located at girder lower section, and construction basketry connects girder by girder load-bearing by hanging mechanism;Hanging mechanism includes connecting strand And lowering or hoisting gear, connecting strand connection lowering or hoisting gear, the distance between lowering or hoisting gear adjustment construction basketry and girder, the cat ladder from Girder extends to construction basketry, and cat ladder is relatively fixed with girder.
2. bridge bottom surface as claimed in claim 1 operation platform, is characterized in that:The lowering or hoisting gear is electric block or pulls Calabash.
3. bridge bottom surface as claimed in claim 1 operation platform, is characterized in that:The track is channel-section steel, the notch of channel-section steel to On, roller falls and is slided in channel-section steel.
4. bridge bottom surface as claimed in claim 1 operation platform, is characterized in that:The girder includes two crossbeams, anchor ear device With connection two crossbeams connecting rod, the crossbeam include two I-steel, two I-steel be set up in parallel and by contiguous block fix connect Connect, there is clearance distance between two I-steel;Anchor ear device includes upper boom, lower beam and threaded rod, and upper boom, lower beam distribution are arranged on Crossbeam upper and lower, upper boom, lower beam pass through the upper and lower screw-threaded coupling of threaded rod;Connecting rod is erected on two crossbeams, connection bridge two ends It is fixedly connected with two crossbeams respectively.
5. bridge bottom surface as claimed in claim 1 operation platform, is characterized in that:Also include guard rail, guard rail is arranged on climbs Terraced periphery is fixedly connected with cat ladder.
CN201621139998.4U 2016-10-20 2016-10-20 Bridge bottom surface construction platform Active CN206109992U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621139998.4U CN206109992U (en) 2016-10-20 2016-10-20 Bridge bottom surface construction platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621139998.4U CN206109992U (en) 2016-10-20 2016-10-20 Bridge bottom surface construction platform

Publications (1)

Publication Number Publication Date
CN206109992U true CN206109992U (en) 2017-04-19

Family

ID=58527621

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621139998.4U Active CN206109992U (en) 2016-10-20 2016-10-20 Bridge bottom surface construction platform

Country Status (1)

Country Link
CN (1) CN206109992U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107178033A (en) * 2017-06-01 2017-09-19 黄河交通学院 It is a kind of to be used for the mobile device of bridge machinery and reinforcing
CN107858924A (en) * 2017-10-26 2018-03-30 中铁大桥局集团第八工程有限公司 Extension type construction platform and the bridge for being provided with the construction platform

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107178033A (en) * 2017-06-01 2017-09-19 黄河交通学院 It is a kind of to be used for the mobile device of bridge machinery and reinforcing
CN107858924A (en) * 2017-10-26 2018-03-30 中铁大桥局集团第八工程有限公司 Extension type construction platform and the bridge for being provided with the construction platform
CN107858924B (en) * 2017-10-26 2023-12-12 中铁大桥局集团第八工程有限公司 Bridge provided with telescopic construction platform

Similar Documents

Publication Publication Date Title
CN104632088B (en) Oil-well rig derrick set assembly/installation method
CN103882811A (en) Bridge floor crane for cable-stayed bridge
CN105002831A (en) Wheel-rail type loading and traveling cable crane
CN103352559A (en) Hanging type movable working platform for storage tank maintenance
CN206109992U (en) Bridge bottom surface construction platform
CN104453201A (en) Automatic ascending and descending type material platform
CN205973518U (en) Track portal jib crane
CN103306218B (en) Bottom width overhaul hanging basket of bridge
CN103147404B (en) System and method for hanging stay cable at tower end of height limiting cable-stayed bridge
CN202298476U (en) Bridge variable cross-section box girder surface operation trolley
CN206051300U (en) A kind of gantry crane's supporting legs structure
CN202390116U (en) High-intensity small-tonnage hoist
CN207017153U (en) Main push-towing rope inspection trolley lifting device
CN209010984U (en) A kind of Bridge Erector hoisting system and Bridge Erector suitable for low headroom condition
CN205873594U (en) Special construction elevator of cooling tower section of thick bamboo wall
CN205275061U (en) Semi -portal crane
CN209618693U (en) A kind of encircling type single-beam operation trolley
CN205407131U (en) Cable laying device
CN205275058U (en) Monospar gantry crane
CN204530513U (en) The manned maintenance Hanging Basket of suspension cable
CN105317031B (en) A kind of ship lift main equipment room bridge main beam hanging method
CN211006334U (en) Maintenance equipment for inner side surface of inverted Y-shaped tower column of three-way movable cable-stayed bridge
CN203998745U (en) The tower machine suspension hook disconnected rope anti-drop device of rushing to summit
CN112012103A (en) Suspension bridge main push-towing rope overhauls device
CN205187694U (en) Novel tower crane equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant