CN202073110U - Concrete pile and bearing platform connecting structure - Google Patents

Concrete pile and bearing platform connecting structure Download PDF

Info

Publication number
CN202073110U
CN202073110U CN2011201365512U CN201120136551U CN202073110U CN 202073110 U CN202073110 U CN 202073110U CN 2011201365512 U CN2011201365512 U CN 2011201365512U CN 201120136551 U CN201120136551 U CN 201120136551U CN 202073110 U CN202073110 U CN 202073110U
Authority
CN
China
Prior art keywords
concrete
pile
concrete pile
end plate
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011201365512U
Other languages
Chinese (zh)
Inventor
陈芳斌
陈巧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jianhua Construction Materials China Co Ltd
Original Assignee
Jiangsu Builds China Pipe Pile Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Builds China Pipe Pile Co Ltd filed Critical Jiangsu Builds China Pipe Pile Co Ltd
Priority to CN2011201365512U priority Critical patent/CN202073110U/en
Application granted granted Critical
Publication of CN202073110U publication Critical patent/CN202073110U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model provides a concrete pile and bearing platform connecting structure, which comprises a concrete pile, a foundation bearing platform, a plurality of combined connecting holes, an end plate, a steel bar, a reinforcement stirrup and a steel bar upset head. The top part of the concrete pile is connected with the foundation bearing platform, the steel bar is arranged in the body of the concrete pile, the upper end of the steel bar extends out of the upper end face of concrete in the body of the concrete pile, the end plate is arranged on the steel bar upset head of the steel bar, the reinforcement stirrup used for fixing the end plate is arranged under the end plate, and the end face of the end plate is uniformly provided with a plurality of combined connecting holes for connection of the steel bar. The structure can be used when the actual elevation of the top part of the completed concrete pile is higher than the design elevation and is suitable for all tubular concrete piles, square concrete piles, precast concrete piles, cast-in-place concrete piles, solid concrete piles and hollow concrete piles.

Description

The syndeton of concrete pile and cushion cap
Technical field
The utility model relates to a kind of construction technology of building pile foundation engineering, is specifically related to the syndeton of a kind of concrete pile and cushion cap.
Background technology
Along with the raising of the significance level of modern building and the continuous increase of building height, the supporting capacity of ground is had higher requirement.The concrete pile foundation of building construction in the past mainly bears the vertical compression load, but present many pile foundations then will be born vertical compression load and vertical tension load simultaneously.More existing in recent years engineerings require to reduce under the pressure promotion of construction costs the investor, and concrete pile is applied in the anti-floating engineering, use as uplift pile.Stake has been made clear and definite regulation with being connected of cushion cap when only concrete pile being made compressive pile or pressure bearing pile on prior art rules or the atlas, but does not make clear and definite regulation when the uplift pile yet for concrete pile.At present when stake top mark height is higher than design elevation, the method of attachment that is used for the concrete pile of resistance to plucking engineering and cushion cap mainly is to go into the core concrete of filling out that concrete that reinforcing cage waters certain volume simultaneously forms certain-length after the stake again toward stake interpolation chamber by with saw stake device pile body simply being cut, be connected with cushion cap and realize being connected of stake and cushion cap by filling out core concrete and stake bonding of inwall and reinforcing bar, realize that the basic while of preformed pile stake top and cushion cap is stressed.But there is more problem in this method, as: only dependence is filled out core concrete and is born uplift resistance, and job site environment more complicated even more abominable sometimes, can cause an inner cavity water accumulation serious, inwall mud can't be cleaned out, it is wayward that construction trouble causes filling out the core concrete construction quality, core concrete often occurs filling out and be pulled out and influence the resistance to plucking quality and cause engineering problem etc.
Summary of the invention
The purpose of this utility model is to overcome the deficiencies in the prior art, and a kind of simple in structure, safe and reliable, convenient and quick construction, the concrete pile of saving construction costs and the syndeton of cushion cap are provided.
The technical solution of the utility model is: the syndeton of a kind of concrete pile and cushion cap, comprise concrete pile, foundation platform, the hole that is connected, end plate, reinforcing bar, reinforcing stirrup and reinforcing bar heading, the stake top of described concrete pile is connected with foundation platform, be provided with reinforcing bar in the described concrete pile pile body, the upper surface of concrete pile pile concrete is stretched out in the upper end of reinforcing bar, described end plate is installed in the reinforcing bar heading place of reinforcing bar, be provided with the reinforcing stirrup that is used for fixing end plate below the end plate, be evenly equipped with a plurality of holes that are connected that are used for connecting reinforcement on the end face of end plate.
As preferably, the described hole that is connected comprises stretching screw hole and heavy muscle hole, is provided with the muscle groove between described stretching screw hole and the heavy muscle hole, and described reinforcing bar inserts the stretching screw orifice ring and is connected after passing the muscle groove on the heavy muscle hole.
As preferably, when described concrete pile is hollow pile, the utility model syndeton also comprises reinforcing cage and fills out core concrete, described reinforcing cage is arranged in the cavity of concrete pile, reinforcing cage is made up of the thin steel supporting plate of vertical muscle (promptly filling out core concrete interpolation reinforcing bar), stirrup and circle, the thin steel supporting plate of circle is connected the bottom of vertical muscle, has built in the cavity of the concrete pile of the thin steel supporting plate of circle top and has filled out core concrete, and the end face of end plate is stretched out in the upper end of described vertical muscle.
As preferably, the described core concrete of filling out adopts slightly expanded concrete, and filling out core concrete intensity is C10 ~ C80, fills out core length and be pile tube stake footpath or side's stake length of side of 0.5 times pile tube stake footpath or the stake length of side ~ 20, side times, and fills out core length and be not less than 0.5m.
As preferably, the diameter of the thin steel supporting plate of described circle is less than or equal to the length of side of diameter or side's stake inner chamber of pile tube inner chamber, and the thin steel supporting plate thickness of circle is not less than 2mm.The length of described vertical muscle upper end is determined that by design hoop " ┐ " shape or vertical configuration outwardly is processed on vertical muscle top, and the quantity of vertical muscle is 4 ~ 30, and diameter is 6mm ~ 50mm, and the diameter of described stirrup is more than or equal to 3mm, and the spacing of stirrup is 40mm ~ 400mm.
The utility model structure is applicable to when concrete pile construction is finished stake top, a back actual elevation and is higher than design elevation, and scope comprises all concrete tubular piles and side, concrete precast pile and castinplace pile, concrete solid pile and hollow pile.
Job practices of the present utility model is: need cut stake when at first stake top actual elevation is higher than design elevation after construction is finished, cut the stake back and keep original reinforcing bar of pile body and end plate, the end plate of concrete pile is installed in the heading place of reinforcing bar, and with reinforcing stirrup with its fixed-site, realize being connected once more of end plate and reinforcing bar, the reinforcing cage that will be welded with the thin steel supporting plate of circle is then put in the inner chamber of concrete pile, pours into a mould slightly expanded concrete at last to the inner chamber of stake, forms reinforcing bar and fills out core concrete; Core concrete to be filled out is poured into a mould ordinary concrete to the cushion cap basis that is connected with stake after reaching certain intensity again, thus final the realization being connected of stake and cushion cap basis.
The beneficial effects of the utility model are: 1, guaranteed being connected between concrete pile and the cushion cap, and more safe and reliable.Abandon to only depend in the past and fill out core concrete and bear uplift resistance, adopt outside reinforcing bar to be connected once more and fill out the system that the interpolation reinforcing bar in the core concrete forms and bear uplift resistance jointly, make that the building foundation is stable more, safety with end plate.
2, simple in structure, save engineering comprehensive and cause.Do not waste pile body is cut reinforcing bar and end plate after the stake, and realize utilizing once more.
3, improved the concrete pile foundation construction quality, reduced the phenomenon that causes cushion cap to separate because of buoyancy is excessive, effectively avoided the generation of engineering safety accident, significantly reduced engineering safety hidden danger with stake.
4, applied widely.Applicable to the bigger more piece stake of anti-pulling capacity, also be applicable to the single-unit stake that uplift resistance is less.
Description of drawings
Fig. 1 is a structural representation of the present utility model;
Fig. 2 is an AA overlooking surface schematic diagram among Fig. 1;
Fig. 3 is a BB overlooking surface schematic diagram among Fig. 1.
The specific embodiment
The utility model is described in further detail below in conjunction with the drawings and specific embodiments:
As Fig. 1, shown in 2 and 3: the syndeton of a kind of concrete pile and cushion cap, comprise concrete pile 1, foundation platform 2, hole 4 is connected, end plate 6, reinforcing bar 8, reinforce stirrup 9 and reinforcing bar heading 10, the stake top of described concrete pile 1 is connected with foundation platform 2, be provided with reinforcing bar 8 in described concrete pile 1 pile body, the upper surface of concrete pile 1 pile concrete is stretched out in the upper end of reinforcing bar 8, described end plate 6 is installed in reinforcing bar heading 10 places of reinforcing bar 8, be provided with the reinforcing stirrup 9 that is used for fixing end plate 6 below the end plate 6, be evenly equipped with a plurality of holes 4 that are connected that are used for connecting reinforcement 8 on the end face of end plate 6.
The described hole 4 that is connected comprises stretching screw hole 41 and heavy muscle hole 42, is provided with muscle groove 43 between described stretching screw hole 41 and the heavy muscle hole 42, and described reinforcing bar 8 inserts and was connected on the heavy muscle hole 42 after stretching screw hole 41 hoops passed muscle groove 43.
Described concrete pile 1 is a hollow pile, the utility model syndeton also comprises reinforcing cage 3 and fills out core concrete 7, described reinforcing cage 3 is arranged in the cavity of concrete pile 1, reinforcing cage 3 is made up of the thin steel supporting plate 5 of vertical muscle 32, stirrup 31 and circle, the thin steel supporting plate 5 of circle is connected the bottom of vertical muscle 32, built in the cavity of the concrete pile 1 of thin steel supporting plate 5 tops of circle and filled out core concrete 7, the end face of end plate 6 is stretched out in the upper end of described vertical muscle 32.
Cut-off footpath 500mm, wall thickness 100mm, 10 of the quantity of prestressed reinforcement, diameter is that the precast concrete resistance to plucking pile tube of 10.7mm is connected with foundation platform.
Described reinforcing cage 3 diameters are 230mm, and the length of the vertical muscle 32 of this reinforcing cage 3 is that 3.6m, diameter are 12mm, and quantity is 8; The diameter of stirrup 31 is 6mm, and stirrup spacing is 100mm, and hoop " ┐ " outwardly is processed on vertical muscle 32 tops; Described circle approaches the thick 4 ~ 5mm of being of steel supporting plate, diameter is 298 ~ 300mm
Describedly fill out core concrete 7 to adopt intensity be the C40 slightly expanded concrete, filling out core length is 3m.

Claims (6)

1. the syndeton of concrete pile and cushion cap, it is characterized in that: comprise concrete pile (1), foundation platform (2), hole (4) is connected, end plate (6), reinforcing bar (8), reinforce stirrup (9) and reinforcing bar heading (10), the stake top of described concrete pile (1) is connected with foundation platform (2), be provided with reinforcing bar (8) in described concrete pile (1) pile body, the upper surface of concrete pile (1) pile concrete is stretched out in the upper end of reinforcing bar (8), described end plate (6) is installed in the reinforcing bar heading (10) of reinforcing bar (8) and locates, be provided with the reinforcing stirrup (9) that is used for fixing end plate (6) below the end plate (6), be evenly equipped with a plurality of holes that are connected (4) that are used for connecting reinforcement on the end face of end plate (6).
2. the syndeton of concrete pile according to claim 1 and cushion cap, it is characterized in that: the described hole that is connected (4) comprises stretching screw hole (41) and heavy muscle hole (42), be provided with muscle groove (43) between described stretching screw hole (41) and the heavy muscle hole (42), described reinforcing bar (8) inserts and was connected on the heavy muscle hole (42) after stretching screw hole (41) hoop passed muscle groove (43).
3. the syndeton of concrete pile according to claim 1 and cushion cap, it is characterized in that: described concrete pile (1) is a hollow pile, the syndeton of described concrete pile and cushion cap also comprises reinforcing cage (3) and fills out core concrete (7), described reinforcing cage (3) is arranged in the cavity of concrete pile (1), reinforcing cage (3) is by vertical muscle (32), the thin steel supporting plate (5) of stirrup (31) and circle is formed, the thin steel supporting plate (5) of circle is connected the bottom of vertical muscle (32), built in the cavity of the concrete pile (1) of the thin steel supporting plate (5) of circle top and filled out core concrete (7), the end face of end plate (6) is stretched out in the upper end of described vertical muscle (32).
4. the syndeton of concrete pile according to claim 3 and cushion cap, it is characterized in that: the described core concrete (7) of filling out adopts slightly expanded concrete, filling out core concrete (7) intensity is C10 ~ C80, fill out core length and be pile tube stake footpath or side's stake length of side of 0.5 times pile tube stake footpath or the stake length of side ~ 20, side times, and fill out core length and be not less than 0.5m.
5. the syndeton of concrete pile according to claim 3 and cushion cap is characterized in that: the diameter of the thin steel supporting plate (5) of described circle is less than or equal to the length of side of diameter or side's stake inner chamber of pile tube inner chamber, and thin steel supporting plate 5 thickness of circle are not less than 2mm.
6. the syndeton of concrete pile according to claim 3 and cushion cap, it is characterized in that: hoop " ┐ " shape or vertical configuration outwardly is processed on described vertical muscle (32) top, the quantity of vertical muscle (32) is 4 ~ 30, diameter is 6mm ~ 50mm, the diameter of described stirrup (31) is more than or equal to 3mm, and the spacing of stirrup (31) is 40mm ~ 400mm.
CN2011201365512U 2011-05-04 2011-05-04 Concrete pile and bearing platform connecting structure Expired - Lifetime CN202073110U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201365512U CN202073110U (en) 2011-05-04 2011-05-04 Concrete pile and bearing platform connecting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201365512U CN202073110U (en) 2011-05-04 2011-05-04 Concrete pile and bearing platform connecting structure

Publications (1)

Publication Number Publication Date
CN202073110U true CN202073110U (en) 2011-12-14

Family

ID=45111213

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201365512U Expired - Lifetime CN202073110U (en) 2011-05-04 2011-05-04 Concrete pile and bearing platform connecting structure

Country Status (1)

Country Link
CN (1) CN202073110U (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102518080A (en) * 2011-12-15 2012-06-27 中交第三航务工程勘察设计院有限公司 Pile-top hinge structure of high-pile wharf
CN102720206A (en) * 2012-07-16 2012-10-10 南京工业大学 Novel connecting structure of prestressed concrete pile and cushion cap
CN103590414A (en) * 2013-11-19 2014-02-19 中铁第四勘察设计院集团有限公司 Structure for connecting concrete tubular pile with bearing platform
CN103938644A (en) * 2014-03-14 2014-07-23 中国水电顾问集团西北勘测设计研究院有限公司 Prefabricated concrete bearing platform with reserved pile nest holes and fabricated multi-pile foundation installation method based on prefabricated concrete bearing platform with reserved pile nest holes
CN103953054A (en) * 2014-04-01 2014-07-30 中铁大桥局集团第一工程有限公司 Dry-sealed concrete pile foundation for protecting pile head reinforcement and construction method thereof
CN104110039A (en) * 2014-06-25 2014-10-22 中国电建集团华东勘测设计研究院有限公司 Fan base with pressure dispersed type arrangement high-strength pre-stressed anchor rods (cables)
CN104404869A (en) * 2014-11-26 2015-03-11 天津港航工程有限公司 Pile column type concrete hollow pile pier structure
CN104594371A (en) * 2015-01-23 2015-05-06 上海建工二建集团有限公司 Reinforcing structure of existing foundation bottom plate and construction method thereof
CN104695459A (en) * 2013-12-10 2015-06-10 江苏建华管桩有限公司 Connection method of concrete precast pile and pile foundation cap
CN105257015A (en) * 2015-09-11 2016-01-20 浙江理工大学 Construction method of bearing platform-beam column joint replacement advance reinforcement hoop structure
CN106320327A (en) * 2016-09-18 2017-01-11 中船第九设计研究院工程有限公司 Uplift pipe pile and connection method for uplift pipe pile and foundation bottom plate
CN106869121A (en) * 2017-02-21 2017-06-20 南昌大学 A kind of FRP pipes cast-in-place with half half prefabricated regeneration concrete prestressing force overlapping pile foundation and preparation method
CN108797627A (en) * 2018-06-05 2018-11-13 江苏地基工程有限公司 A kind of pulling-resistant type PHC pile piles being connect with cushion cap
CN109113058A (en) * 2018-08-15 2019-01-01 绿山高科建设科技有限公司 A kind of new type cement soil composite pile
CN109537614A (en) * 2018-12-29 2019-03-29 深圳供电局有限公司 Bored concrete pile and its forming method
CN109629559A (en) * 2019-01-17 2019-04-16 江西联保工程咨询有限公司 The integrally formed integrated basis of a kind of platform
CN110258608A (en) * 2019-06-12 2019-09-20 南通大学 A kind of new device that prestressed pile is connect with cushion cap or bottom plate
CN110700300A (en) * 2019-09-25 2020-01-17 安徽省建筑科学研究设计院 Connecting structure of precast pile and bearing platform and construction method

Cited By (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102518080B (en) * 2011-12-15 2013-11-13 中交第三航务工程勘察设计院有限公司 Pile-top hinge structure of high-pile wharf
CN102518080A (en) * 2011-12-15 2012-06-27 中交第三航务工程勘察设计院有限公司 Pile-top hinge structure of high-pile wharf
CN102720206A (en) * 2012-07-16 2012-10-10 南京工业大学 Novel connecting structure of prestressed concrete pile and cushion cap
CN103590414A (en) * 2013-11-19 2014-02-19 中铁第四勘察设计院集团有限公司 Structure for connecting concrete tubular pile with bearing platform
CN103590414B (en) * 2013-11-19 2016-06-29 中铁第四勘察设计院集团有限公司 A kind of attachment structure of concrete tubular pile and cushion cap
CN104695459A (en) * 2013-12-10 2015-06-10 江苏建华管桩有限公司 Connection method of concrete precast pile and pile foundation cap
CN103938644A (en) * 2014-03-14 2014-07-23 中国水电顾问集团西北勘测设计研究院有限公司 Prefabricated concrete bearing platform with reserved pile nest holes and fabricated multi-pile foundation installation method based on prefabricated concrete bearing platform with reserved pile nest holes
CN103938644B (en) * 2014-03-14 2015-10-28 中国电建集团西北勘测设计研究院有限公司 The reserved precast concrete cushion cap of stake socket bore and the assembling many pile foundations mounting method based on this cushion cap
CN103953054A (en) * 2014-04-01 2014-07-30 中铁大桥局集团第一工程有限公司 Dry-sealed concrete pile foundation for protecting pile head reinforcement and construction method thereof
CN103953054B (en) * 2014-04-01 2016-01-20 中铁大桥局集团第一工程有限公司 A kind of dry sealing concrete pile foundation and construction method thereof protecting pile crown reinforcing bar
CN104110039A (en) * 2014-06-25 2014-10-22 中国电建集团华东勘测设计研究院有限公司 Fan base with pressure dispersed type arrangement high-strength pre-stressed anchor rods (cables)
CN104110039B (en) * 2014-06-25 2016-08-31 中国电建集团华东勘测设计研究院有限公司 There is pressure dispersing type and arrange the blower foundation of high-strength prestressed anchor pole (rope)
CN104404869A (en) * 2014-11-26 2015-03-11 天津港航工程有限公司 Pile column type concrete hollow pile pier structure
CN104594371A (en) * 2015-01-23 2015-05-06 上海建工二建集团有限公司 Reinforcing structure of existing foundation bottom plate and construction method thereof
CN105257015A (en) * 2015-09-11 2016-01-20 浙江理工大学 Construction method of bearing platform-beam column joint replacement advance reinforcement hoop structure
CN106320327A (en) * 2016-09-18 2017-01-11 中船第九设计研究院工程有限公司 Uplift pipe pile and connection method for uplift pipe pile and foundation bottom plate
CN106869121A (en) * 2017-02-21 2017-06-20 南昌大学 A kind of FRP pipes cast-in-place with half half prefabricated regeneration concrete prestressing force overlapping pile foundation and preparation method
CN108797627A (en) * 2018-06-05 2018-11-13 江苏地基工程有限公司 A kind of pulling-resistant type PHC pile piles being connect with cushion cap
CN109113058A (en) * 2018-08-15 2019-01-01 绿山高科建设科技有限公司 A kind of new type cement soil composite pile
CN109537614A (en) * 2018-12-29 2019-03-29 深圳供电局有限公司 Bored concrete pile and its forming method
CN109629559A (en) * 2019-01-17 2019-04-16 江西联保工程咨询有限公司 The integrally formed integrated basis of a kind of platform
CN110258608A (en) * 2019-06-12 2019-09-20 南通大学 A kind of new device that prestressed pile is connect with cushion cap or bottom plate
CN110700300A (en) * 2019-09-25 2020-01-17 安徽省建筑科学研究设计院 Connecting structure of precast pile and bearing platform and construction method

Similar Documents

Publication Publication Date Title
CN202073110U (en) Concrete pile and bearing platform connecting structure
CN102127913B (en) Method for connecting concrete pile and bearing platform
CN202073111U (en) Connection structure of a concrete pile and a bearing platform
CN204112354U (en) The syndeton of concrete precast pile and pile foundation support table
CN204456162U (en) A kind of pulling-resistant type prefabricated tubular pile be connected with cushion cap
CN101220593A (en) Fastening method of post-treating pipe pile break with pre-stress pipe pile construction
CN103866761A (en) Mechanical connection pile head using repetitively used precast concrete pile as end plate and manufacturing method of mechanical connection pile head
CN205954656U (en) Double -layer steel manages cement pipe column foundation
CN203320539U (en) Steel structural connection element used for connecting pipe pile and bearing platform
CN106626032A (en) Integral type inner protrusion hollow uplift pile and preparation method thereof
CN203200771U (en) Connection structure for pile extension top and bearing platform
CN104314075A (en) Conical concrete pile tip, tubular pile provided with pile tip and production method of tubular pile
CN202299410U (en) Supporting structure of lower conical shell moldboard for large-tonnage inverted cone water tower water tank
CN209556197U (en) A kind of thin-walled square chest hollow floor
CN203755302U (en) Pre-tensioned pre-stressed concrete pile
CN203768893U (en) End plate-reusable mechanical connecting pile head of prefabricated concrete pile
CN205205847U (en) Frame construction of stake cushion cap
CN202108039U (en) Cylindrical compound concrete macadam placepile
CN104264659A (en) Prefabricated hollow uplift pile and preparation method thereof
CN205614821U (en) Core concrete member is irritated in prefabrication of PHC tubular pile
CN204080791U (en) A kind of precast hollow uplift pile
CN203924047U (en) Antidetonation rural area sectionalized house foundation pile
CN208733866U (en) A kind of connection structure of the wall up and down of precast shear wall
CN208328914U (en) A kind of prestressed concrete pipe pile
CN207131088U (en) A kind of shear wall support component

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 212413 Jiangsu Jianhua pipe pile Co., Ltd. of Zhenjiang Town, Jurong City, Jiangsu Province

Patentee after: Jianhua building materials (Jiangsu) Co., Ltd.

Address before: 212413 Jiangsu Jianhua pipe pile Co., Ltd. of Zhenjiang Town, Jurong City, Jiangsu Province

Patentee before: Jiangsu builds China pipe pile Co., Ltd.

CP03 Change of name, title or address

Address after: 212413 the development zone along the Yangtze River in Xia Shu Town, Jurong City, Zhenjiang, Jiangsu

Patentee after: Jianhua building materials (China) Co., Ltd.

Address before: 212413 Jianjiang pipe pile Co., Ltd., Jiangsu, Jiangsu, Zhenjiang, Jurong

Patentee before: Jianhua building materials (Jiangsu) Co., Ltd.

CP03 Change of name, title or address
CX01 Expiry of patent term

Granted publication date: 20111214

CX01 Expiry of patent term