CN205742249U - A kind of prestressed concrete back cover cushion cap template - Google Patents

A kind of prestressed concrete back cover cushion cap template Download PDF

Info

Publication number
CN205742249U
CN205742249U CN201620465396.1U CN201620465396U CN205742249U CN 205742249 U CN205742249 U CN 205742249U CN 201620465396 U CN201620465396 U CN 201620465396U CN 205742249 U CN205742249 U CN 205742249U
Authority
CN
China
Prior art keywords
back cover
prestressed concrete
template
steel
concrete back
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620465396.1U
Other languages
Chinese (zh)
Inventor
冷平
毛以雷
刘春�
吴承恩
李瑞明
王纯生
赵东雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GENERAL CONTRACTING BRANCH Co OF CCCC FIRST HARBOR ENGINEERING Co Ltd
CCCC First Harbor Engineering Co Ltd
Original Assignee
GENERAL CONTRACTING BRANCH Co OF CCCC FIRST HARBOR ENGINEERING Co Ltd
CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GENERAL CONTRACTING BRANCH Co OF CCCC FIRST HARBOR ENGINEERING Co Ltd, CCCC First Harbor Engineering Co Ltd filed Critical GENERAL CONTRACTING BRANCH Co OF CCCC FIRST HARBOR ENGINEERING Co Ltd
Priority to CN201620465396.1U priority Critical patent/CN205742249U/en
Application granted granted Critical
Publication of CN205742249U publication Critical patent/CN205742249U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

This utility model relates to a kind of prestressed concrete back cover cushion cap template, it is characterized in that, described template is concrete sealing bottom type cushion cap template, described template is the circular frame of steel prestressed reinforced concrete combination, including prestressed concrete back cover (2), side template (3) and support type girder steel (4);Deformed bar, and the reserved hole corresponding with steel-pipe pile (1) it is evenly arranged with in described prestressed concrete back cover (2);Described side template (3) is formed a fixed connection with prestressed concrete back cover (2) by the barb type round platform nut being embedded in prestressed concrete back cover (2);Decreasing Jobs on the sea amount, efficiency of construction is higher, and land fabrication quality easily ensures.

Description

A kind of prestressed concrete back cover cushion cap template
Technical field
This utility model relates to a kind of offshore wind farm unit high-rise pile cap formula foundation construction facility field, particularly to one Prestressed concrete back cover cushion cap template.
Background technology
At present, in China's Oversea wind power generation engineering, high-rise pile cap formula basis be Wind turbines main foundation pattern it One.High-Rise Pile Cap Foundation needs marine Casting in-place Mass Concrete, therefore requires higher to cushion cap template.Compare tradition cap mold Plate construction technology, prestressed concrete back cover cushion cap template is owing to decreasing working procedure, and operation on the sea amount is little, construction period The features such as relatively short, cost is low, quality easily guarantee can be widely applied to the High-Rise Pile Cap Foundation of Oversea wind power generation engineering and execute In work.
Wind turbines High-Rise Pile Cap Foundation structure due between pile foundation span relatively big, and cushion cap volume of concrete is big, makes bed die Moment of flexure suffered by plate center position is the biggest.The steel bed die that the base plate employing shaped steel of conventional steel casing cushion cap template is strengthened, but steel Bed die intensity still is not enough to support the deadweight during cushion cap concreting of top, need to after model sheetinstallat first marine cast-in-place about 1m The bottom concrete of thickness, thus support the deadweight of superstructure concrete.Marine cast-in-place bottom concrete causes working procedure Too much, long construction period, construction cost is too high.
Therefore, how reasonable arrangement working procedure, reduce Jobs on the sea amount and the cushion cap end template of sufficient intensity is set, The deadweight supporting top cast-in-place structural concrete is an important step in bearing platform construction.
Utility model content
The purpose of this utility model is aiming at existing cushion cap template and there is working procedure too much, long construction period, construction The shortcoming of high cost, it is provided that a kind of prestressed concrete back cover cushion cap template.
The technical solution of the utility model is: a kind of offshore wind farm unit high-rise pile cap formula foundation construction template, template is The circular frame of steel-prestressed reinforced concrete combination, including prestressed concrete back cover, side template and support type girder steel;
Deformed bar, and the reserved hole corresponding with steel-pipe pile it is evenly arranged with in prestressed concrete back cover;
Side template is by the barb type round platform nut being embedded in prestressed concrete back cover and prestressed concrete back cover Form a fixed connection;
Support type girder steel divides upper and lower two parts, and top half is " well " character form structure, is connected by pin with side template; The latter half is " door " character form structure, is embedded in prestressed concrete back cover, erects on steel-pipe pile 1 top during installation;Up and down Two parts are connected by vertical girder steel.
Specifically optimize as this utility model scheme, prestressed concrete back cover generally circular in shape.
Specifically optimize as this utility model scheme, side template be shaped as arc or fan-shaped steel form, quantity is 4 Or 8.
This utility model compared with prior art, has the advantage that as follows:
(1) land fabrication bottom concrete, decreases Jobs on the sea amount, and efficiency of construction is higher, and land fabrication quality is easy Ensure;
(2) prestressing force bottom concrete intensity is higher, can bear bigger construction time load, and safety coefficient is greatly improved;
(3) bottom concrete directly serves as end template, saves the rolled steel dosage of original end template;
(4) working procedure is more reasonable, and construction period shortens, and ship machine equipment demand is little, greatly reduces construction cost.
Accompanying drawing explanation
Fig. 1 is land fabrication assembled formwork schematic diagram of the present utility model;
Fig. 2 is model sheetinstallat leveling schematic diagram of the present utility model;
Fig. 3 is formwork reinforcement sealing of hole schematic diagram of the present utility model;
Fig. 4 is the final schematic diagram in place of template of the present utility model;
Symbol description: 1, steel-pipe pile, 2, prestressed concrete back cover, 3, side template, 4, temporary support section steel beam, 5, husky Case, 6, reinforced steel, 7, rear pouring concrete.
Detailed description of the invention
Below in conjunction with accompanying drawing, embodiments herein is described in detail, but the application can be defined by the claims Implement with the multitude of different ways covered.The accompanying drawing of the part constituting the application is used for providing the further reason to the application Solving, the schematic description and description of the application is used for explaining the application, is not intended that the improper restriction to the application.
A kind of offshore wind farm unit high-rise pile cap formula foundation construction template, template is steel-prestressed reinforced concrete combination Circular frame, including prestressed concrete back cover 2, side template 3 and support type girder steel 4;In prestressed concrete back cover 2 uniformly It is provided with deformed bar, and the reserved hole corresponding with steel-pipe pile 1;Side template 3 is by being embedded in prestressed concrete grave Barb type round platform nut at the end 2 forms a fixed connection with prestressed concrete back cover 2;Upper and lower two of 4 points of support type girder steel Point, top half is " well " character form structure, is connected by pin with side template 3;The latter half is " door " character form structure, is embedded in In prestressed concrete back cover 2, erect on steel-pipe pile 1 top during installation;Two parts are connected by vertical girder steel up and down.
Specifically optimize as this utility model scheme, prestressed concrete back cover 2 generally circular in shape.
Specifically optimize as this utility model scheme, side template 3 be shaped as arc or fan-shaped steel form, quantity is 4 Sheet or 8.
For processing step of the present utility model, feature and effect can be further appreciated that, in conjunction with accompanying drawing 1-4, new to this practicality Type is further described.
Embodiment 1
A kind of prestressed concrete back cover cushion cap template, including prestressed concrete back cover 2, side template 3, temporary support Section steel beam 4 and rear pouring concrete 7 etc..Prestressed concrete back cover 2 is the one of the hole of land fabrication, reserved corresponding steel-pipe pile Circular prestressed reinforced concrete construction, serves as cushion cap concrete bottom template, arranges deformed bar, thus strengthen end template inside it Intensity.Hole location determines according to reality measurement after pile sinking completes.Deformed bar can use pre-tensioning system, it is possible to use Post stretching.Side template 3 is arc or sector, if being divided into dry tablet to surround circle, by spiral shell pre-buried in prestressed concrete back cover 2 Bolt makes bed die, side form form a fixed connection.This bolt can be round platform nut, it is also possible to be the bolt of other forms.Interim Depending on support section steel beam 4 concrete structure is according to pile foundation radical, upper and lower two parts can be divided into.Top half is crossbeam and vertical beam composition Reticular pattern girder steel, is connected with side template, and connected mode can be being that pin connection, anchor connection, welding or other modes connect;Under Half part is " door " shaped girder steel, is embedded in prestressed concrete back cover 2;Top and the bottom are connected by vertical shaped steel.In advance should Power concrete sealing bottom 2, side template 3, temporary support section steel beam 4 carry out assembly by land, as it is shown in figure 1, whole Transporting is to marine Job site.Integral mold plate is arranged on several steel-pipe pile, and this steel-pipe pile can be straight stake or taper pile.Before installation, in advance at steel pipe Suitable sandbox 5 is placed on stake top, during installation, as in figure 2 it is shown, hole reserved in prestressed concrete back cover is through steel-pipe pile, Sandbox contacts with temporary support section steel beam, and the stress becoming whole template supports.Integral mold plate can by sandbox carry out absolute altitude and The regulation of levelness.Integral mold plate is installed after meeting the requirements, by reinforced steel 6 pre-buried in prestressed concrete back cover 2 and steel Pile tube welds, and reinforced steel radical is drawn by Force Calculation.After reinforced steel welds with steel-pipe pile, to prestressed concrete grave Reserved hole blocks at the end 2, material selection and the concrete of prestressed concrete back cover 2 same model, waters coagulation the most afterwards Soil 7, as shown in Figure 3.After rear pouring concrete 7 reaches respective strengths, i.e. complete stress system conversion, temporary support type can be cut off Girder steel 4, removes stake top sandbox 5, and carries out reinforcing bar binding in template and pour the subsequent construction such as cushion cap concrete, such as Fig. 4 institute Show.After pouring cushion cap concrete maintenance, remove side template 3, side template reusable edible.
The foregoing is only the preferred embodiment of the application, be not limited to the application, for the skill of this area For art personnel, the application can have various modifications and variations.All within spirit herein and principle, that is made any repaiies Change, equivalent, improvement etc., within should be included in the protection domain of the application.

Claims (3)

1. a prestressed concrete back cover cushion cap template, it is characterised in that described template is steel-prestressed reinforced concrete The circular frame of combination, including prestressed concrete back cover (2), side template (3) and support type girder steel (4);
Deformed bar, and the reserved hole corresponding with steel-pipe pile (1) it is evenly arranged with in described prestressed concrete back cover (2) Hole;
Described side template (3) is by the barb type round platform nut being embedded in prestressed concrete back cover (2) and prestressed concrete At the bottom of grave, (2) form a fixed connection;
The upper and lower two parts of described support type girder steel (4) point, top half is " well " character form structure, passes through pin with side template (3) Connect;The latter half is " door " character form structure, is embedded in prestressed concrete back cover (2), erects in steel-pipe pile (1) during installation Stake top;Two parts are connected by vertical girder steel up and down.
A kind of prestressed concrete back cover cushion cap template the most according to claim 1, it is characterised in that described prestressing force Concrete sealing bottom (2) generally circular in shape.
A kind of prestressed concrete back cover cushion cap template the most according to claim 1, it is characterised in that described side template (3) be shaped as arc or fan-shaped steel form, quantity is 4 or 8.
CN201620465396.1U 2016-05-23 2016-05-23 A kind of prestressed concrete back cover cushion cap template Expired - Fee Related CN205742249U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620465396.1U CN205742249U (en) 2016-05-23 2016-05-23 A kind of prestressed concrete back cover cushion cap template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620465396.1U CN205742249U (en) 2016-05-23 2016-05-23 A kind of prestressed concrete back cover cushion cap template

Publications (1)

Publication Number Publication Date
CN205742249U true CN205742249U (en) 2016-11-30

Family

ID=57361585

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620465396.1U Expired - Fee Related CN205742249U (en) 2016-05-23 2016-05-23 A kind of prestressed concrete back cover cushion cap template

Country Status (1)

Country Link
CN (1) CN205742249U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107152032A (en) * 2017-05-23 2017-09-12 中能电力科技开发有限公司 The template system and the construction method of cushion cap of a kind of bearing platform construction for offshore wind farm

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107152032A (en) * 2017-05-23 2017-09-12 中能电力科技开发有限公司 The template system and the construction method of cushion cap of a kind of bearing platform construction for offshore wind farm

Similar Documents

Publication Publication Date Title
CN104746422B (en) A kind of hollow pier stud delay-pour joint structure of bridge prefabrication and construction method
CN105113389B (en) Assembled type bridge pier column member with steel-concrete composite structure
CN104790424B (en) The hardened system on generation power foundation of wind power ring basis and reinforcement means thereof
CN103225304B (en) A kind of marine foundation supporting structure and construction method thereof
CN104963289A (en) Integral one-time pouring construction method of large-volume concrete for special-shaped pier stud
CN105544593A (en) Wind power generation tower foundation with prefabricated foundation prestressed beams and slab
CN105863042A (en) All-steel structure building and construction method thereof
CN103912007A (en) Prefabricated concrete cushion cap preserved with foundation ring hole and pile recess ring hole and mounting method of assembly type multi-pile foundation based on cushion cap
CN106836463A (en) The constructing device and construction method of cushion cap and ground girder construction
CN109440634A (en) The prefabricated high strength concrete hollow bent cap structure that internal model can be taken off
CN207047881U (en) The prefabricated cushion cap of core is filled with joint bar
CN104612120A (en) Integrated construction method related to in-water steel pipe pile establishing platform
CN204097864U (en) A kind of bridge prefabrication hollow pier stud delay-pour joint structure
CN206408657U (en) Integrated bored concrete pile for static test
CN103938871B (en) A kind of construction method adopting the steel core concrete column bonded prestress frame beam structure of reinforced concrete ring beam joint
CN205636516U (en) Convertible template system of hollow concrete leaning tower
CN104929047A (en) V-shaped pier outer support construction method
CN208472757U (en) A kind of precast prestressed board-like generation power foundation of wind power
CN205742249U (en) A kind of prestressed concrete back cover cushion cap template
CN106381810B (en) With the cast-in-place outstanding method for filling beam of beam-column type bracket
CN102691267A (en) High pier construction method for external whole operation platform
CN204780635U (en) Super wide nonprismatic continuous beam 0# piece concreties and relieves construction structures
CN208650086U (en) A kind of movable type streetlamp foundation
CN114277672B (en) Large-span prestressed concrete bent cap structure and construction method thereof
CN206529881U (en) The constructing device of cushion cap and ground girder construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161130