CN202055516U - 竖井整体提升模板系统 - Google Patents

竖井整体提升模板系统 Download PDF

Info

Publication number
CN202055516U
CN202055516U CN2011201214279U CN201120121427U CN202055516U CN 202055516 U CN202055516 U CN 202055516U CN 2011201214279 U CN2011201214279 U CN 2011201214279U CN 201120121427 U CN201120121427 U CN 201120121427U CN 202055516 U CN202055516 U CN 202055516U
Authority
CN
China
Prior art keywords
template
mold board
vertical shaft
construction
mould roller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2011201214279U
Other languages
English (en)
Inventor
周厚贵
戴志清
刘晓华
孙昌忠
杨志书
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Co Ltd
Original Assignee
China Gezhouba Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Co Ltd filed Critical China Gezhouba Group Co Ltd
Priority to CN2011201214279U priority Critical patent/CN202055516U/zh
Application granted granted Critical
Publication of CN202055516U publication Critical patent/CN202055516U/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

一种竖井整体提升模板系统,竖井整体提升模板系统包括定型大模版,爬架系统、退模滚轮装置,定型大模版通过调节丝杆与立杆连接。本实用新型由于模板采用整体大模板,混凝土表面成形效果好;三层工作平台以及模板调节丝杆的设计,提高了人员施工的安全性和施工的便捷性;模板和爬架形成整体单元后,很容易通过吊车吊装就位,施工操作简单安全,施工效率高。同时本新型技术结构设计受力明确,荷载传力路线清晰,设计安全可靠。

Description

竖井整体提升模板系统
技术领域
本实用新型涉及建筑工程用模板技术领域,具体涉及一种竖井整体提升模板系统。 
背景技术
在建筑施工中,经常遇到竖井结构,其封闭的小空间内,模板操作施工非常不方便。目前常用的竖井模板方案大多采用木模板、组合小钢模散装等散拼的施工方式,该方式缺点如下:立模、拆模、模板调节以及模板板面清理不方便;现场施工人员没有一个安全可靠的操作平台;施工效率低、施工进度慢;竖井施工质量难以控制、外观质量差。 
发明内容
本实用新型要解决的技术问题是提供一种竖井整体提升模板系统,该系统在竖井内退模后,模板及爬架通过吊车一次提升就位,模板操作方便、人员施工安全、竖井混凝土施工质量优良以及竖井施工效率高的标准,适用于深度大的薄壁混凝土竖井施工时,模板需要多次周转的工况。
本实用新型的目的是这样实现的:一种竖井整体提升模板系统,竖井整体提升模板系统包括定型大模版,爬架系统、退模滚轮装置,定型大模版通过调节丝杆与立杆连接。
定型大模版包括平面模板、转角模板和拼缝模板,处于转角两侧的平面模板通过对角支撑连接。
吊装爬架系统包括爬架主梁,立杆和吊杆与爬架主梁连接,模板操作平台安装在爬架主梁上,混凝土浇筑平台与立杆连接,在吊装爬架系统下部还设有混凝土修补平台。
退模滚轮装置包括退模滚轮、悬挂板、螺杆和行走轨道,退模滚轮安装在行走轨道上,行走轨道固定在混凝土浇筑平台上。
本实用新型提供的竖井整体提升模板系统,由于模板采用整体大模板,混凝土表面成形效果好。三层工作平台以及模板调节丝杆的设计,提高了人员施工的安全性和施工的便捷性。模板和爬架形成整体单元后,很容易通过吊车吊装就位,施工操作简单安全,施工效率高。同时本新型技术结构设计受力明确,荷载传力路线清晰,设计安全可靠。
附图说明
下面结合附图和实施例对本实用新型作进一步说明。
图1是本实用新型的结构示意图。
图2是本实用新型的平面图。
图3是本实用新型模板工作状态图。
图4图5是本实用新型退模滚轮示意图。
图6是本实用新型吊装示意图。
具体实施方式
如图1-图6所示,竖井整体提升模板系统包括定型大模版1,爬架系统、退模滚轮装置3,定型大模版1通过调节丝杆4与立杆9连接。
定型大模版1包括平面模板1-1、转角模板1-2和拼缝模板1-3,处于转角两侧的平面模板1-1通过对角支撑1-4连接。
吊装爬架系统包括爬架主梁2,立杆9和吊杆8与爬架主梁2连接,模板操作平台6安装在爬架主梁2上,混凝土浇筑平台10与立杆9连接,在吊装爬架系统下部还设有混凝土修补平台7。
退模滚轮装置3包括退模滚轮3-1、悬挂板3-2、螺杆3-3和行走轨道5,退模滚轮3-1安装在行走轨道5上,行走轨道5固定在混凝土浇筑平台10上。
本实用新型中,如图3所示,为方便模板拆除,定型大模板1设计成由平面模板1-1、转角模板1-2、拼缝模板1-3和对角支撑1-4组成的一个完整的模板体系。
爬架系统2设计成由爬架主梁2、立杆9和吊杆8及工作平台模板操作平台6、混凝土修补平台7和混凝土浇筑平台10组成的一个整体单元。
图4和图5为退模滚轮示意图,退模滚轮3主要功能是方便模板后退,离开混凝土面一定距离,为模板板面清理以及预埋件的安装提供足够空间,组成部件包括退模滚轮3-1、悬挂板3-2、高强螺杆3-3及行走轨道5。
本实用新型的工作过程如下:
竖井首层混凝土浇筑完成后,本实用新型即可吊装就位投入使用,具体安装流程如下:
1.如图1所示,将凝土修补平台7和吊杆8提前放入竖井结构内后,吊装爬架主梁2和模板操作平台6就位并固定在预埋好的锚固点11上;
2.安装爬架系统立杆9,并用脚手架钢管将其固定形成整体;
3. 定型大模版1吊入竖井,并靠墙放置在模板操作平台6上;
4.安装混凝土浇筑平台10;
5.退模滚轮装置3在行走轨道5上安装好后,将行走轨道5固定在混凝土浇筑平台10的主梁上;
6.将定型大模版1吊起与退模滚轮装置3的高强螺杆3-3部件固定,见图4图5;
7.本实用新型浇筑第二层并周转至第三层后,可后续安装吊杆8和-1平台7。
至此本实用新型安装完毕,进入正常的使用阶段,具体的施工流程如下:
1、 操作调节丝杆4可调节模板垂直度并使模板靠近结构面;操作转角丝杆1-4,调节模板就位后,安装拼缝模板1-3;安装模板上部预埋锥,上紧对拉杆后,开始浇筑混凝土;
2、 混凝土达到设计强度后,松开对拉杆、断开调节丝杆4和模板1的连接,操作转角丝杆1-4,使模板1脱离混凝土面后,短边模板绕转角模板1-2轴转动回收;
3、 后拉模板1,退模滚轮装置3沿行走轨道5后退,带动整个长边模板后退;
4、 清理模板1板面、涂刷脱模剂;
5、 吊车钩住本新型实用设计的吊点位置,将模板1、爬架2整体提升至下一仓位,进入下一仓的竖井混凝土的施工。 

Claims (4)

1.一种竖井整体提升模板系统,其特征在于:竖井整体提升模板系统包括定型大模版(1),爬架系统、退模滚轮装置(3),定型大模版(1)通过调节丝杆(4)与立杆(9)连接。
2.根据权利要求1所述的竖井整体提升模板系统,其特征在于:定型大模版(1)包括平面模板(1-1)、转角模板(1-2)和拼缝模板(1-3),处于转角两侧的平面模板(1-1)通过对角支撑(1-4)连接。
3.根据权利要求1所述的竖井整体提升模板系统,其特征在于:吊装爬架系统包括爬架主梁(2),立杆(9)和吊杆(8)与爬架主梁(2)连接,模板操作平台(6)安装在爬架主梁(2)上,混凝土浇筑平台(10)与立杆(9)连接,在吊装爬架系统下部还设有混凝土修补平台(7)。
4.根据权利要求1所述的竖井整体提升模板系统,其特征在于:退模滚轮装置(3)包括退模滚轮(3-1)、悬挂板(3-2)、螺杆(3-3)和行走轨道(5),退模滚轮(3-1)安装在行走轨道(5)上,行走轨道(5)固定在混凝土浇筑平台(10)上。
CN2011201214279U 2011-04-22 2011-04-22 竖井整体提升模板系统 Expired - Fee Related CN202055516U (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011201214279U CN202055516U (zh) 2011-04-22 2011-04-22 竖井整体提升模板系统

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011201214279U CN202055516U (zh) 2011-04-22 2011-04-22 竖井整体提升模板系统

Publications (1)

Publication Number Publication Date
CN202055516U true CN202055516U (zh) 2011-11-30

Family

ID=45015492

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011201214279U Expired - Fee Related CN202055516U (zh) 2011-04-22 2011-04-22 竖井整体提升模板系统

Country Status (1)

Country Link
CN (1) CN202055516U (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536249A (zh) * 2012-02-23 2012-07-04 中煤第五建设有限公司 井塔提升系统快速施工方法
CN102704674A (zh) * 2012-05-03 2012-10-03 中国葛洲坝集团股份有限公司 竖井液压自升模板及施工方法
CN102777186A (zh) * 2012-08-03 2012-11-14 中煤矿山建设集团有限责任公司 立井砌壁全液压自移式模板装置
CN103334584A (zh) * 2013-07-29 2013-10-02 中国化学工程第三建设有限公司 一种滑模系统的模板调节系统
CN110284703A (zh) * 2019-07-26 2019-09-27 广西路桥工程集团有限公司 一种丝杆提升轻型爬模系统
CN110593555A (zh) * 2019-10-16 2019-12-20 四川省第六建筑有限公司 一种装配式提模
CN112962956A (zh) * 2021-02-03 2021-06-15 七冶安装工程有限责任公司 一种混凝土滑模施工方法和装置
CN113309147A (zh) * 2021-06-04 2021-08-27 中国水利水电第三工程局有限公司 一种矩形竖向井孔混凝土施工方法

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536249A (zh) * 2012-02-23 2012-07-04 中煤第五建设有限公司 井塔提升系统快速施工方法
CN102704674A (zh) * 2012-05-03 2012-10-03 中国葛洲坝集团股份有限公司 竖井液压自升模板及施工方法
CN102704674B (zh) * 2012-05-03 2015-10-21 中国葛洲坝集团股份有限公司 竖井液压自升模板及施工方法
CN102777186A (zh) * 2012-08-03 2012-11-14 中煤矿山建设集团有限责任公司 立井砌壁全液压自移式模板装置
CN102777186B (zh) * 2012-08-03 2014-08-20 中煤矿山建设集团有限责任公司 立井砌壁全液压自移式模板装置
CN103334584A (zh) * 2013-07-29 2013-10-02 中国化学工程第三建设有限公司 一种滑模系统的模板调节系统
CN103334584B (zh) * 2013-07-29 2015-07-08 中国化学工程第三建设有限公司 一种滑模系统的模板调节系统
CN110284703A (zh) * 2019-07-26 2019-09-27 广西路桥工程集团有限公司 一种丝杆提升轻型爬模系统
CN110593555A (zh) * 2019-10-16 2019-12-20 四川省第六建筑有限公司 一种装配式提模
CN112962956A (zh) * 2021-02-03 2021-06-15 七冶安装工程有限责任公司 一种混凝土滑模施工方法和装置
CN113309147A (zh) * 2021-06-04 2021-08-27 中国水利水电第三工程局有限公司 一种矩形竖向井孔混凝土施工方法

Similar Documents

Publication Publication Date Title
CN202055516U (zh) 竖井整体提升模板系统
WO2013185277A1 (zh) 高层钢结构建筑钢筋砼筒体的施工方法
CN204266590U (zh) 集水坑、电梯井模板底模抗浮装置
CN202090591U (zh) 一种建筑施工升降式爬升模板
CN102704674B (zh) 竖井液压自升模板及施工方法
WO2013120419A1 (zh) 液压顶升自爬模板系统
CN201962944U (zh) 一种建筑施工液压爬升模板
CN109356382B (zh) 抽拉式变形缝支模体系及施工方法
CN103938880A (zh) 大跨度异形空间网格管桁架整体滑移施工方法
CN103485574B (zh) 一种造粒塔塔顶钢筋混凝土结构施工方法
CN102733608B (zh) 一种造粒塔喷头层施工方法
CN205296803U (zh) 电梯自动提升操作台
CN205314542U (zh) 一种建筑施工液压模板爬升装置
CN112360469A (zh) 一种超深竖井顺作衬砌单侧支模提升模架及施工方法
CN103774841A (zh) 轨道式滑模装置
CN103669872B (zh) 一种筑墙方法和筑墙设备
CN203113793U (zh) 一种倾斜结构大模板安装系统
CN202064281U (zh) 一种滑模模架
CN203755173U (zh) 用于桥梁高墩液压爬升的模板装置
CN102777026A (zh) 一种贝雷架构建超长后浇板支撑体系的方法
CN204173804U (zh) 一种结构梁承载式的内爬塔吊安装及顶升结构
CN105863261A (zh) 一种万向可调式悬挂模板系统
CN206693614U (zh) 一种单面液压滑模装置
CN203113226U (zh) 高耸悬挑不对称混凝土结构模板支架体系
CN201539097U (zh) 全液压爬升模板

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111130

Termination date: 20180422

CF01 Termination of patent right due to non-payment of annual fee