CN201330609Y - 浅埋暗挖大洞室洞内钢支撑机械化吊运装置 - Google Patents
浅埋暗挖大洞室洞内钢支撑机械化吊运装置 Download PDFInfo
- Publication number
- CN201330609Y CN201330609Y CNU200820233638XU CN200820233638U CN201330609Y CN 201330609 Y CN201330609 Y CN 201330609Y CN U200820233638X U CNU200820233638X U CN U200820233638XU CN 200820233638 U CN200820233638 U CN 200820233638U CN 201330609 Y CN201330609 Y CN 201330609Y
- Authority
- CN
- China
- Prior art keywords
- cavern
- arch
- big
- hole
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本实用新型属于城市地铁车站浅埋暗挖大洞室物件输送装置。特别涉及一种浅埋暗挖大洞室洞内钢支撑机械化吊运装置。在洞内围护桩上面的桩顶冠梁上,支持大洞室拱部初支结构和固定大洞室拱部二衬结构;大洞室拱部二衬结构上固定工字钢锚固件,工字钢锚固件与单轨运行起重系统连接;在洞内围护桩下部连接大洞室下部二衬与中板结构。本实用新型适合于各类应用洞桩法施工技术的工程施工;优化了钢支撑、腰梁等钢构件的洞内吊装运输,从根本上解决了暗挖洞室内钢支撑等钢构件的吊装运输难题,施工更为安全、工效大大提高,同时也将使完善了的洞桩法施工技术的应用更为科学、更为广泛。
Description
技术领域
本实用新型属于城市地铁车站浅埋暗挖大洞室物件输送装置。特别涉及一种浅埋暗挖大洞室洞内钢支撑机械化吊运装置。适合于各类应用洞桩法施工技术的工程施工;优化了钢支撑、腰梁等钢构件的洞内吊装运输,从根本上解决了暗挖洞室内钢支撑等钢构件的吊装运输难题,施工更为安全、工效大大提高,同时也将使完善了的洞桩法施工技术的应用更为科学、更为广泛。
背景技术
目前,洞桩法施工技术已在城市地铁车站的设计和施工中得到了广泛的应用。但是,由于车站洞室较大,浅埋暗挖施工安全风险较大,特别是钢支撑和腰梁的洞内吊装和运输难度很大、工效很低;而往往采取将大洞室分割为小洞室的“多洞室”施工。这样,不仅导致洞桩法施工技术的优势并未得到充分发挥,更重要的是工程与施工成本、施工难度、施工安全、施工工期等各方面均受到了很大的制约。
发明内容
本实用新型的目的是针对现有技术的车站洞室较大,浅埋暗挖施工安全风险较大,特别是钢支撑和腰梁的洞内吊装和运输难度很大、工效很低;而往往采取将大洞室分割为小洞室的“多洞室”施工,不仅导致洞桩法施工技术的优势并未得到充分发挥的不足而提供一种浅埋暗挖大洞室洞内钢支撑机械化吊运装置。其特征在于,在洞内围护桩3上面的桩顶冠梁7上,支持大洞室拱部初支结构5,在大洞室拱部初支结构5下面固定大洞室拱部二衬结构6;大洞室拱部二衬结构6上固定.工字钢锚固件1,工字钢锚固件1与单轨运行起重系统2连接;在洞内围护桩3下部连接大洞室下部二衬与中板结构8。
所述单轨运行起重系统2为电葫芦自动运行系统。
所述大洞室拱部二衬结构6为单轨运行起重系统2的行车梁。
所述大洞室内包含上中下三层台阶大断面土方9。
本实用新型的有益效果是该浅埋暗挖大洞室洞内钢支撑机械化吊运装置从根本上解决了钢支撑和腰梁等较大构件的洞内运输。使洞内吊运吊装方法简单,安全、方便、快速。工程与施工成本低、施工难度大大降低,进而使得洞桩法施工技术的优势得到了更好的发挥。
附图说明
图1为大洞室内钢支撑机械化吊运装置结构示意图。
图2单轨运行起重系统示意图。
图中:1.工字钢锚固件,2.单轨运行起重系统,3.洞桩围护4.钢支撑与腰梁,5.大洞室拱部初支结构,6.大洞室拱部二衬结构,7.冠梁,8.大洞室下部二衬与中板结构.9.大洞室内三层大断面土方。
具体实施方式
本实用新型提供一种浅埋暗挖大洞室洞内钢支撑机械化吊运装置。下面结合附图对本本实用新型予以说明。在图1为大洞室内钢支撑机械化吊运装置结构示意图中,在洞内围护桩3上面固定桩顶冠梁7,桩顶冠梁7支持大洞室拱部初支结构5和大洞室拱部二衬结构6,工字钢锚固件1通过锚固钢筋锚固在大洞室拱部二衬结构6内,工字钢锚固件1与单轨运行起重系统2连接(如图2所示);单轨运行起重系统是由5t电葫芦自动运行系统,根据计划的施工流水和施工节拍,将单轨(工字钢)运行起重系统锚固在先行施工的洞室拱部二衬结构上,大洞室拱部二衬结构6作为单轨运行起重系统2的行车梁,随着下部土方的开挖,进行钢管支撑和型钢腰梁的洞内吊运、配合安装。
Claims (4)
1.一种浅埋暗挖大洞室洞内钢支撑机械化吊运装置,其特征在于,在洞内围护桩(3)上面的桩顶冠梁(7)上,支持大洞室拱部初支结构(5),在大洞室拱部初支结构(5)下面固定大洞室拱部二衬结构(6);大洞室拱部二衬结构(6)上固定工字钢锚固件(1),工字钢锚固件(1)与单轨运行起重系统(2)连接;在洞内围护桩(3)下部连接大洞室下部二衬与中板结构(8)。
2.根据权利要求1所述浅埋暗挖大洞室洞内钢支撑机械化吊运装置,其特征在于,所述单轨运行起重系统(2)为电葫芦自动运行系统。
3.根据权利要求1所述浅埋暗挖大洞室洞内钢支撑机械化吊运装置,其特征在于,所述大洞室拱部二衬结构(6)为单轨运行起重系统(2)的行车梁。
4.根据权利要求1所述浅埋暗挖大洞室洞内钢支撑机械化吊运装置,其特征在于,所述大洞室内包括上中下三层台阶大断面土方(9)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU200820233638XU CN201330609Y (zh) | 2008-12-22 | 2008-12-22 | 浅埋暗挖大洞室洞内钢支撑机械化吊运装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU200820233638XU CN201330609Y (zh) | 2008-12-22 | 2008-12-22 | 浅埋暗挖大洞室洞内钢支撑机械化吊运装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201330609Y true CN201330609Y (zh) | 2009-10-21 |
Family
ID=41223987
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNU200820233638XU Expired - Fee Related CN201330609Y (zh) | 2008-12-22 | 2008-12-22 | 浅埋暗挖大洞室洞内钢支撑机械化吊运装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201330609Y (zh) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102061927A (zh) * | 2010-12-10 | 2011-05-18 | 中铁隧道集团有限公司 | 隧道防水材料铺设装置及其铺设方法 |
CN102061928A (zh) * | 2010-12-26 | 2011-05-18 | 广州广船国际股份有限公司 | 一种盾构机管片吊运装置 |
CN102296986A (zh) * | 2011-07-29 | 2011-12-28 | 中铁一局集团有限公司 | 一种隧道施工用运输机构 |
CN102322278A (zh) * | 2011-07-23 | 2012-01-18 | 上海市第二市政工程有限公司 | 隧道中隔墙施工专用机械 |
CN102535444A (zh) * | 2011-12-06 | 2012-07-04 | 中铁十八局集团第五工程有限公司 | 富水砂层浅埋暗挖地铁车站洞桩机械施工方法 |
CN103437783A (zh) * | 2013-08-22 | 2013-12-11 | 天津市市政工程设计研究院 | 浅埋暗挖大跨度隧道导洞拱盖组合施工工法 |
-
2008
- 2008-12-22 CN CNU200820233638XU patent/CN201330609Y/zh not_active Expired - Fee Related
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102061927A (zh) * | 2010-12-10 | 2011-05-18 | 中铁隧道集团有限公司 | 隧道防水材料铺设装置及其铺设方法 |
CN102061927B (zh) * | 2010-12-10 | 2012-07-18 | 中铁隧道集团有限公司 | 隧道防水材料铺设装置及其铺设方法 |
CN102061928A (zh) * | 2010-12-26 | 2011-05-18 | 广州广船国际股份有限公司 | 一种盾构机管片吊运装置 |
CN102061928B (zh) * | 2010-12-26 | 2012-07-25 | 广州广船国际股份有限公司 | 一种盾构机管片吊运装置 |
CN102322278A (zh) * | 2011-07-23 | 2012-01-18 | 上海市第二市政工程有限公司 | 隧道中隔墙施工专用机械 |
CN102322278B (zh) * | 2011-07-23 | 2013-08-28 | 上海城建市政工程(集团)有限公司 | 隧道中隔墙施工专用机械 |
CN102296986A (zh) * | 2011-07-29 | 2011-12-28 | 中铁一局集团有限公司 | 一种隧道施工用运输机构 |
CN102535444A (zh) * | 2011-12-06 | 2012-07-04 | 中铁十八局集团第五工程有限公司 | 富水砂层浅埋暗挖地铁车站洞桩机械施工方法 |
CN102535444B (zh) * | 2011-12-06 | 2016-01-13 | 中铁十八局集团第五工程有限公司 | 富水砂层浅埋暗挖地铁车站洞桩机械施工方法 |
CN103437783A (zh) * | 2013-08-22 | 2013-12-11 | 天津市市政工程设计研究院 | 浅埋暗挖大跨度隧道导洞拱盖组合施工工法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201330609Y (zh) | 浅埋暗挖大洞室洞内钢支撑机械化吊运装置 | |
CN202936736U (zh) | 一种斜拉桥组合梁施工桥面吊机 | |
CN206942764U (zh) | 一种洞内组装和拆卸盾构机或tbm掘进机的辅助结构 | |
CN203855866U (zh) | 工便梁大跨度框架桥架空顶 | |
CN103669216A (zh) | 一种钢箱梁散拼滑移装置及安装方法 | |
CN106150511A (zh) | 盾构掘进式空推过地裂缝暗挖隧道施工方法 | |
CN207363606U (zh) | 一种钻机滑移系统 | |
CN105484162B (zh) | 悬索桥施工岸上加劲梁二次荡移装置及方法 | |
CN102433844B (zh) | 一种预制梁桥面架设施工方法 | |
CN104060830A (zh) | 一种地下核电站大件吊装运输方法 | |
CN103194977B (zh) | 运架一体式架桥机架设首孔箱梁前导梁机就位方法 | |
CN111661761A (zh) | 一种新型地铁铺轨施工设备及工艺 | |
CN201339209Y (zh) | 逆作法施工土方开挖运土装置 | |
CN202560321U (zh) | 盾构分体始发管线同步移动装置 | |
CN212503680U (zh) | 一种大型桥机重大件的起吊系统 | |
CN101949215A (zh) | 钢结构支座安装施工方法 | |
CN104120701A (zh) | 一种垂直升船机重大件吊装的施工方法及装置 | |
CN203684060U (zh) | 钢架便桥 | |
CN211141349U (zh) | 一种轨排井龙门吊基础固定结构 | |
CN208684247U (zh) | 一种预制节段用吊装装置 | |
CN204311457U (zh) | 一种地铁车站基坑开挖施工用组合式支护体系 | |
CN202688882U (zh) | 深水桥墩双壁钢围堰施工用围堰下放定位平台 | |
CN207293981U (zh) | 一种砂砾石隧洞内二衬台车的吊装装置 | |
CN203846503U (zh) | 一种两条已建地铁隧道中部明挖区间基坑支护体系 | |
CN203096774U (zh) | 一种明挖隧道抗浮结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20091021 Termination date: 20141222 |
|
EXPY | Termination of patent right or utility model |