CN105484162B - 悬索桥施工岸上加劲梁二次荡移装置及方法 - Google Patents
悬索桥施工岸上加劲梁二次荡移装置及方法 Download PDFInfo
- Publication number
- CN105484162B CN105484162B CN201510932177.XA CN201510932177A CN105484162B CN 105484162 B CN105484162 B CN 105484162B CN 201510932177 A CN201510932177 A CN 201510932177A CN 105484162 B CN105484162 B CN 105484162B
- Authority
- CN
- China
- Prior art keywords
- stiff girder
- bank
- girder
- swings
- suspension bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D11/00—Suspension or cable-stayed bridges
- E01D11/02—Suspension bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510932177.XA CN105484162B (zh) | 2015-12-15 | 2015-12-15 | 悬索桥施工岸上加劲梁二次荡移装置及方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510932177.XA CN105484162B (zh) | 2015-12-15 | 2015-12-15 | 悬索桥施工岸上加劲梁二次荡移装置及方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105484162A CN105484162A (zh) | 2016-04-13 |
CN105484162B true CN105484162B (zh) | 2017-01-04 |
Family
ID=55671408
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510932177.XA Active CN105484162B (zh) | 2015-12-15 | 2015-12-15 | 悬索桥施工岸上加劲梁二次荡移装置及方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105484162B (zh) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106049293B (zh) * | 2016-07-29 | 2017-10-13 | 德阳天元重工股份有限公司 | 通航河流上悬索桥加劲梁安装方法及所用荡移系统 |
CN106320182B (zh) * | 2016-09-19 | 2019-06-25 | 中交第一公路工程局有限公司 | 悬索桥岸坡梁段长吊索荡移安装装置和方法 |
CN107119567A (zh) * | 2017-04-28 | 2017-09-01 | 武汉智汇高桥科技股份有限公司 | 悬索桥钢箱梁用跨缆吊机和接长吊索的荡移施工方法 |
CN107476195B (zh) * | 2017-08-16 | 2023-04-07 | 湖南路桥建设集团有限责任公司 | 一种悬索桥运送加劲梁的运梁滑车系统 |
CN108625275B (zh) * | 2018-05-09 | 2019-12-20 | 中交一公局集团有限公司 | 一种悬索桥加劲梁段安装方法 |
CN113026563B (zh) * | 2021-03-19 | 2022-11-18 | 中铁建大桥工程局集团第一工程有限公司 | 一种悬索桥高低位移梁栈桥吊装钢梁设施及其施工方法 |
CN113152299B (zh) * | 2021-04-23 | 2023-07-04 | 中交第二航务工程局有限公司 | 一种斜拉桥钢梁节段荡移装置及吊装方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1710208A (zh) * | 2005-07-03 | 2005-12-21 | 路桥集团第二公路工程局 | 钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法 |
CN2793147Y (zh) * | 2005-06-10 | 2006-07-05 | 路桥集团第二公路工程局 | 多跨悬索桥无索区钢箱吊梁 |
CN101225638A (zh) * | 2007-12-20 | 2008-07-23 | 中铁大桥局股份有限公司 | 地锚式悬索桥预应力混凝土加劲箱梁安装方法 |
RU2514331C1 (ru) * | 2012-12-14 | 2014-04-27 | Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" | Способ монтажа балки жесткости вантового моста |
CN205369040U (zh) * | 2015-12-15 | 2016-07-06 | 中交一公局第三工程有限公司 | 悬索桥施工岸上加劲梁二次荡移装置 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6701564B2 (en) * | 2002-05-24 | 2004-03-09 | Snead Edwin Desteiguer | System and method for positioning a pile cap underneath an existing elevated bridge assembly |
-
2015
- 2015-12-15 CN CN201510932177.XA patent/CN105484162B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2793147Y (zh) * | 2005-06-10 | 2006-07-05 | 路桥集团第二公路工程局 | 多跨悬索桥无索区钢箱吊梁 |
CN1710208A (zh) * | 2005-07-03 | 2005-12-21 | 路桥集团第二公路工程局 | 钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法 |
CN101225638A (zh) * | 2007-12-20 | 2008-07-23 | 中铁大桥局股份有限公司 | 地锚式悬索桥预应力混凝土加劲箱梁安装方法 |
RU2514331C1 (ru) * | 2012-12-14 | 2014-04-27 | Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" | Способ монтажа балки жесткости вантового моста |
CN205369040U (zh) * | 2015-12-15 | 2016-07-06 | 中交一公局第三工程有限公司 | 悬索桥施工岸上加劲梁二次荡移装置 |
Also Published As
Publication number | Publication date |
---|---|
CN105484162A (zh) | 2016-04-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105484162B (zh) | 悬索桥施工岸上加劲梁二次荡移装置及方法 | |
CN101831888B (zh) | 1200吨级水利渡槽运、架设备 | |
CN102367650A (zh) | 一种钢管拱桥的施工方法 | |
CN102653938A (zh) | 下行式移动模架海上拆除施工工法 | |
CN105484164A (zh) | 一种跨式贝雷梁支架及其施工方法 | |
CN106400693B (zh) | 一种斜坡道钢箱梁运梁车及运梁方法 | |
CN106223303B (zh) | 一种升船机承船厢安装方法 | |
CN203452009U (zh) | 一种钢梁安装用自行走装置 | |
CN202658590U (zh) | 整体装配式钻孔平台 | |
CN104060543A (zh) | 一种预制桥面板的安装装置 | |
CN206873495U (zh) | 一种便携移动式管廊侧墙模板台车 | |
CN203199913U (zh) | 一种装拆式起吊桁架 | |
CN202689016U (zh) | 深水桥墩双壁钢围堰施工用围堰拼装及提升平台 | |
CN205369040U (zh) | 悬索桥施工岸上加劲梁二次荡移装置 | |
CN204662929U (zh) | 一种跨线行走式防护操作装置 | |
CN204385629U (zh) | 一种用于悬索桥主塔上横梁施工的支架 | |
CN103806374B (zh) | 装配式公路钢桥整体轨道架设推送系统及架设推送工艺 | |
CN202220400U (zh) | 搭接式模架支撑梁 | |
CN104929000A (zh) | 一种节段式铁路铺轨机组及其组装方法 | |
CN101695984B (zh) | 中承式钢管混凝土拱桥拱下纵横梁的安装方法及吊具 | |
CN204282843U (zh) | 一种劲性混合结构中钢梁安装的滑移式吊装就位装置 | |
JP2020153208A (ja) | 吊り足場及びその架設方法 | |
CN205804178U (zh) | 用于桥梁盖梁施工的可升降可伸缩无支架装置 | |
CN203960753U (zh) | 一种预制桥面板的安装装置 | |
CN204919348U (zh) | 一种自锚式悬索桥安装辅助用钢塔 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Li Hongsheng Inventor after: Yang Yang Inventor after: Zeng Xiongxing Inventor after: Guo Dengke Inventor after: Zhang Yubai Inventor after: Zhang Zhixin Inventor after: Bin Xiong Inventor after: Ren Wei Inventor after: Gu Yueqiang Inventor after: Mao Chaojun Inventor after: Qu Jialin Inventor after: Jing Zhenshuai Inventor after: Rong Wei Inventor before: Li Hongsheng Inventor before: Zhang Zhixin Inventor before: Bin Xiong Inventor before: Ren Wei Inventor before: Gu Yueqiang Inventor before: Mao Chaojun |