CN201306007Y CNU2008203030070U CN200820303007U CN201306007Y CN 201306007 Y CN201306007 Y CN 201306007Y CN U2008203030070 U CNU2008203030070 U CN U2008203030070U CN 200820303007 U CN200820303007 U CN 200820303007U CN 201306007 Y CN201306007 Y CN 201306007Y
Authority
CN
China
Prior art keywords
stretch
draw
truss
frame
box girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2008203030070U
Other languages
English (en)
Inventor
刘继锋
张树春
仲昭怀
肖剑光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Civil Engineering Co Ltd filed Critical China Construction Civil Engineering Co Ltd
Priority to CNU2008203030070U priority Critical patent/CN201306007Y/zh
Application granted granted Critical
Publication of CN201306007Y publication Critical patent/CN201306007Y/zh
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

一种高铁900吨箱梁预应力张拉架,其张拉架主体结构由横杆、立杆和水平纵杆固定连接成三维框架结构,张拉架主体结构顶部的两根横杆为槽钢,这两根槽钢上支撑有爬行系统,该爬行系统由横移桁架和纵移小车两部分组成;横移桁架由纵轨和横梁连接成横移架体,横移架体的底部连接桁架滚轮,桁架滚轮置于张拉架主体结构顶部的两根横杆的槽内,与横杆滚动连接;纵移小车由横向钢筋和纵向钢筋焊接成车底架,车底架四角连接有小车滚轮,小车滚轮与横移桁架的两根纵轨滚动连接。本实用新型改变了以往张拉架使用中千斤顶不易移动对位的问题,可以很方便的进行张拉千斤顶的纵横向移动,使张拉工作速度大大的提高,极大的方便了张拉千斤顶的移动和安装到位。

Description

高铁900吨箱梁预应力张拉架
技术领域
本实用新型涉及一种预应力钢筋的张拉辅助工具。
背景技术
在后张法预应力钢筋混凝土构筑物的施工中,特别是在高速铁路900吨箱梁预应力张拉作业中,由于张拉用千斤顶的重量达225KG左右,过于笨重的机体移动困难,而现有张拉架不具备快速准确移动对位张拉千斤顶的功能,所以,转顶工序进行缓慢,常常拖延整个工程的施工进度。
实用新型内容
本实用新型提供一种高铁900吨箱梁预应力张拉架,要解决现有张拉架不能快速移动、不具备与张拉千斤顶准确对位的技术问题。
本实用新型解决其技术问题所采用的技术方案是:
一种高铁900吨箱梁预应力张拉架,其张拉架主体结构由横杆、立杆和水平纵杆固定连接成三维框架结构,其特征在于:
张拉架主体结构顶部的两根横杆为槽钢,这两根槽钢上支撑有爬行系统,该爬行系统由横移桁架和纵移小车两部分组成。
横移桁架由纵轨和横梁连接成横移架体,横移架体的底部连接桁架滚轮,桁架滚轮置于张拉架主体结构顶部的两根横杆的槽内,与横杆滚动连接。
纵移小车由横向钢筋和纵向钢筋焊接成车底架,车底架四角连接有小车滚轮,小车滚轮与横移桁架的两根纵轨滚动连接。
所述张拉架主体结构上可固定连接有加强筋或斜撑,或者,加强筋和斜撑。
所述纵移小车的车底架上可以焊接棱锥形车身或框架形车身。
所述张拉架主体结构上可以连接有爬梯。
所述张拉架主体结构上可以铺有走行道板。
本实用新型的有益效果如下:
本实用新型的高铁900吨箱梁预应力张拉架,全部采用型钢焊接制作而成,结构简单,轻巧坚固,对位准确,张拉速度快,能够多次周转反复使用。张拉架顶部的爬行系统有横移桁架和纵移小车,横移桁架和纵移小车采用螺纹钢和滚轮焊接而成,可在顶部槽钢制成的滑道中纵横移动,改变了以往张拉架使用中千斤顶不易移动对位的问题,可以很方便的进行张拉千斤顶的纵横向移动,同时,纵移小车可以和手拉葫芦进行配合,能够很方便的将千斤顶安装就位进行张拉。使千斤顶的转顶工作方便快捷,使张拉工作速度大大的提高,极大的方便了张拉千斤顶的移动和安装到位。
附图说明
下面结合附图和实施例对本实用新型进一步说明。
图1是本实用新型的正立面示意图。
图2是本实用新型的背立面示意图。
图3是本实用新型的侧面示意图。
图4是本实用新型的顶面示意图。
图5是本实用新型的底面示意图。
图6是纵移小车的示意图。
图7是爬行系统的示意图。
附图标记:1—张拉架主体结构、2—横移桁架、2.1—纵轨、2.2—横梁、2.3—桁架滚轮、3—纵移小车、3.1—横向钢筋、3.2—纵向钢筋、3.3—小车滚轮、3.4—棱锥形车身、4—加强筋、5—爬梯、6—走行道板、7—横杆、8—立杆、9—水平纵杆、10—斜撑。
具体实施方式
实施例参见图1—7所示,这种高铁900吨箱梁预应力张拉架,其张拉架主体结构1由横杆7、立杆8和水平纵杆9固定连接成三维框架结构,张拉架主体结构1顶部的两根横杆7为槽钢,这两根槽钢上支撑有爬行系统,该爬行系统由横移桁架2和纵移小车3两部分组成;横移桁架2由纵轨2.1和横梁2.2连接成横移架体,横移架体的底部连接桁架滚轮2.3,桁架滚轮2.2置于张拉架主体结构顶部的两根横杆7的槽内,与横杆7滚动连接;纵移小车3由横向钢筋3.1和纵向钢筋3.2焊接成车底架,车底架四角连接有小车滚轮3.3,小车滚轮3.3与横移桁架2的两根纵轨滚动连接。本实用新型中钢件连接可统一采用焊接连接,焊缝长度和宽度应符合相关规范要求。
所述张拉架主体结构1上固定连接有加强筋4和斜撑10,但也可以只固定连接加强筋4或只固定连接斜撑10。本实用新型中的各加强筋或斜撑可采用型钢或螺纹钢与钢架焊接进行连接。
所述纵移小车3的车底架上焊接棱锥形车身3.4或框架形车身。
参见图1,图3,所述张拉架主体结构1上连接有爬梯5,爬梯5可采用直径16mm的HRB335焊接制成。
参见图5,张拉架主体结构1上还铺有走行道板6,走行道板6可为竹胶板。
参见图6,图7,本实用新型的爬行系统分为两部分,分别为横移桁架2和纵移小车3。其中横移桁架2采用角钢焊接而成,配以滚轮,主要负责千斤顶的横向移动,可以方便的转移张拉用千斤顶到对应位置。纵移小车采用直径25的HRB335钢筋制成,轴承和滚轮根据实际情况合理采用。在实际使用时,纵移小车可以和手拉葫芦进行配合,能够很方便的将千斤顶安装就位进行张拉。
本实用新型的工作过程:本实用新型是在经过反复的试验后,在张拉架主体结构1的顶部加了一个移动系统,该移动系统分为纵移小车3和横移桁架2。其中横移桁架2主要负责张拉千斤顶的转顶工作,纵移小车3主要负责张拉千斤顶的对孔穿束,且在配以手拉葫芦后,还可以上下移动。
本实用新型是在高铁900吨箱梁预应力张拉架上设计了一个能够纵横向移动的装置,在配以手拉葫芦后,可以快速准确的将千斤顶对准就位。

Claims (5)

  1. 【权利要求1】一种高铁900吨箱梁预应力张拉架,其张拉架主体结构(1)由横杆(7)、立杆(8)和水平纵杆(9)固定连接成三维框架结构,其特征在于:
    张拉架主体结构(1)顶部的两根横杆(7)为槽钢,这两根槽钢上支撑有爬行系统,该爬行系统由横移桁架(2)和纵移小车(3)两部分组成;
    横移桁架(2)由纵轨(2.1)和横梁(2.2)连接成横移架体,横移架体的底部连接桁架滚轮(2.3),桁架滚轮(2.2)置于张拉架主体结构顶部的两根横杆(7)的槽内,与横杆(7)滚动连接;
    纵移小车(3)由横向钢筋(3.1)和纵向钢筋(3.2)焊接成车底架,车底架四角连接有小车滚轮(3.3),小车滚轮(3.3)与横移桁架(2)的两根纵轨滚动连接。
  2. 【权利要求2】根据权利要求1所述的高铁900吨箱梁预应力张拉架,其特征在于:所述张拉架主体结构(1)上固定连接有加强筋(4)或斜撑(10),或者,加强筋(4)和斜撑(10)。
  3. 【权利要求3】根据权利要求1所述的高铁900吨箱梁预应力张拉架,其特征在于:所述纵移小车(3)的车底架上焊接棱锥形车身(3.4)或框架形车身。
  4. 【权利要求4】根据权利要求1所述的高铁900吨箱梁预应力张拉架,其特征在于:所述张拉架主体结构(1)上连接有爬梯(5)。
  5. 【权利要求5】根据权利要求1所述的高铁900吨箱梁预应力张拉架,其特征在于:所述张拉架主体结构(1)上铺有走行道板(6)。
CNU2008203030070U 2008-11-28 2008-11-28 高铁900吨箱梁预应力张拉架 Expired - Lifetime CN201306007Y (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008203030070U CN201306007Y (zh) 2008-11-28 2008-11-28 高铁900吨箱梁预应力张拉架

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008203030070U CN201306007Y (zh) 2008-11-28 2008-11-28 高铁900吨箱梁预应力张拉架

Publications (1)

Publication Number Publication Date
CN201306007Y true CN201306007Y (zh) 2009-09-09

Family

ID=41098474

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008203030070U Expired - Lifetime CN201306007Y (zh) 2008-11-28 2008-11-28 高铁900吨箱梁预应力张拉架

Country Status (1)

Country Link
CN (1) CN201306007Y (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103787203A (zh) * 2013-12-16 2014-05-14 重庆岩安科技有限公司 用于安装预制梁千斤顶的支撑架
CN104032832A (zh) * 2014-06-09 2014-09-10 南京林业大学 一种后张法预应力竹木结构框架
CN113482379A (zh) * 2021-07-01 2021-10-08 中国建筑土木建设有限公司 一种插入式防护栏杆底座

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103787203A (zh) * 2013-12-16 2014-05-14 重庆岩安科技有限公司 用于安装预制梁千斤顶的支撑架
CN103787203B (zh) * 2013-12-16 2016-06-08 重庆岩安科技有限公司 用于安装预制梁千斤顶的支撑架
CN104032832A (zh) * 2014-06-09 2014-09-10 南京林业大学 一种后张法预应力竹木结构框架
CN113482379A (zh) * 2021-07-01 2021-10-08 中国建筑土木建设有限公司 一种插入式防护栏杆底座
CN113482379B (zh) * 2021-07-01 2022-09-27 中国建筑土木建设有限公司 一种插入式防护栏杆底座

Similar Documents

Publication Publication Date Title
CN201003145Y (zh) 上行自行式移动模架
CN204690605U (zh) 大跨度梁桥的自行式三角桁架挂篮
CN202578714U (zh) 直线及曲线段隧洞通用式钢模衬砌台车
CN201306007Y (zh) 高铁900吨箱梁预应力张拉架
CN211395397U (zh) 一种t梁梁板剪力筋定位装置
CN201560587U (zh) 后张法箱梁张拉架
CN203684101U (zh) 简支梁横移就位的装置
CN204626932U (zh) 一种用于弧形幕墙施工的移动措施支架
CN105464000B (zh) 一种现浇箱梁移动模板
CN202202874U (zh) 用于隧道加固的门式弧型钢架
CN201695345U (zh) 一种步履过孔式架桥机
CN216914329U (zh) 一种梁端钢筋对齐小车
CN217078420U (zh) 一种可调节桥梁线性的钢梁自行式滑移安装装置
CN206477616U (zh) 一种防止悬挑钢梁下挠的装置
CN201619955U (zh) 新型工字钢电缆滑车
CN201330365Y (zh) 用于隧道内双层路面结构施工的台模车
CN214644551U (zh) 一种用于预制梁的侧模装置
CN210684497U (zh) 一种用于悬臂浇注小曲率半径连续梁的挂篮
CN210193245U (zh) 一种吊钩门式铸造起重机
CN207696751U (zh) 一种预制梁体钢筋骨架安装限位装置
CN207672429U (zh) 一种公路桥梁现浇护栏活动检修车
CN205276136U (zh) 一种现浇箱梁移动模板
CN209024062U (zh) 一种吊运装置
CN211395377U (zh) 一种曲线钢箱梁拖拉滑移的装置及系统
CN216469703U (zh) 一种预制梁端模存放架

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA CONSTRUCTION EIGHTH ENGINEERING DIVISION CO.

Free format text: FORMER OWNER: CHINA CONSTRUCTION CIVIL CONSTRUCTION CORP.

Effective date: 20140613

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 100068 FENGTAI, BEIJING TO: 200135 PUDONG NEW AREA, SHANGHAI

TR01 Transfer of patent right

Effective date of registration: 20140613

Address after: 200135 Pudong New Area Century Avenue, Shanghai, No. 27, layer 1568

Patentee after: CHINA CONSTRUCTION EIGHTH ENGINEERING DIVISION Co.,Ltd.

Address before: 100068 Beijing city Fengtai District Road No. 8 No. 1 hospital zoneach building room 811

Patentee before: CHINA CONSTRUCTION CIVIL ENGINEERING Co.,Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20090909