CN1710208A - 钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法 - Google Patents

钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法 Download PDF

Info

Publication number
CN1710208A
CN1710208A CN 200510042909 CN200510042909A CN1710208A CN 1710208 A CN1710208 A CN 1710208A CN 200510042909 CN200510042909 CN 200510042909 CN 200510042909 A CN200510042909 A CN 200510042909A CN 1710208 A CN1710208 A CN 1710208A
Authority
CN
China
Prior art keywords
loop wheel
wheel machine
land
beam section
steel case
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200510042909
Other languages
English (en)
Other versions
CN100354477C (zh
Inventor
薛光雄
金仓
沈良成
先正权
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Highway Engineering Co Ltd
Original Assignee
No2 Road Engineering Bureau Luqiao Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No2 Road Engineering Bureau Luqiao Group filed Critical No2 Road Engineering Bureau Luqiao Group
Priority to CNB2005100429094A priority Critical patent/CN100354477C/zh
Publication of CN1710208A publication Critical patent/CN1710208A/zh
Application granted granted Critical
Publication of CN100354477C publication Critical patent/CN100354477C/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明提供一种钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移的施工方法,它能充分发挥常规起吊设备跨缆吊机的工作能力,最大限度减少陆上、浅滩区钢箱梁支架长度或不需再搭设临时支架,即可进行陆上梁段的安装,达到陆上、浅滩区钢箱梁安装施工经济、安全的目的。它采用两台跨缆吊机组合吊装陆上、浅滩区的钢箱梁,梁段荷载在一前一后两台吊机间交替转移,吊机在荷载转移完成后,空载吊机沿主缆行走,持载吊机在主缆上临时定位,梁段荷载在一前一后两台吊机间进行固定持载-空载行走-荷载转移-固定持载-空载行走-荷载转移的交替过程中,梁段逐步荡移到设计位置,最后单台吊机垂直提升安装就位梁段。

Description

钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法
                     技术领域
本发明涉及一种悬索桥陆上、浅滩区钢箱梁吊装方法,特别是钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法。
                     背景技术
随着我国公路交通等基础建设的突飞猛进,作为跨越能力最强的悬索桥,逐步成为跨江、跨海通道的首选桥型之一。在悬索桥钢箱梁施工中,钢箱梁重量一般达2000kN以上,梁段由水运运抵桥位,采用专用跨缆吊机进行安装。跨缆吊机因作业条件限制,只能进行垂直或小范围荡移施工。当因桥位地理条件限制,陆上及浅滩区有较多梁段时,由于运梁驳船不能到达梁段安装位置下方,跨缆吊机的垂直或小范围荡移已不能满足施工需要。在这种情况下,按照常规施工方法需要搭设支架,先由跨缆吊机将梁段提升、荡移放置在支架上,再利用支架上的移位支撑系统将梁段牵引滑移到设计位置。悬索桥由于通航净空要求,梁段距地面高度一般在40m以上,陆上梁段数量较多时,钢箱梁临时支撑支架庞大,经济性比较差。而且受桥位地质条件限制,支架基础难以施工时,造成施工困难。
                     发明内容
本发明的目的是提供一种钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法,它能充分发挥常规起吊设备跨缆吊机的工作能力,最大限度减少陆上、浅滩区钢箱梁支架长度或不需再搭设临时支架,即可进行陆上梁段的安装,达到陆上、浅滩区钢箱梁安装施工经济、安全的目的。
本发明解决问题所采用的技术方案是:设计一种钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法:它采用两台跨缆吊机组合吊装陆上、浅滩区的钢箱梁,梁段荷载在一前一后两台吊机间交替转移,吊机在荷载转移完成后,空载吊机沿主缆行走,持载吊机在主缆上临时定位,梁段荷载在一前一后两台吊机间进行固定持载空载行走荷载转移固定持载---空载行走---荷载转移的交替过程中,梁段逐步荡移到设计位置,最后单台吊机垂直提升安装就位梁段。
所述的提升索在持载额定荷载范围内允许荡移转角为20°。
所述的两台吊机在主缆上的水平最小间距为9.0m。(该吊机行走轨道长度为9.0m,因此两台吊机前后并拢间距为9.0m)。
本发明的特点是:钢箱梁悬索桥梁段施工的跨缆吊机,其本身具有空载时可在主缆上行走,提升钢箱梁后的持载状态下吊机提升系统(起吊钢丝绳、或液压提升钢绞线)可允许荡移一定转角的基本性能,由此,采用两台跨缆吊机组合吊装陆上、浅滩区的钢箱梁,梁段荷载在一前一后两台吊机间交替转移,吊机在荷载转移完成后,空载吊机沿主缆行走,持载吊机在主缆上临时定位,梁段荷载在一前一后两台吊机间进行固定持载---空载行走---荷载转移---固定持载---空载行走---荷载转移的交替过程中,梁段逐步荡移到设计位置,最后单台吊机垂直提升安装就位梁段。双吊机荡移施工原理为:跨缆吊机设计性能具有在持载时提升索允许荡移转角为20°,因吊机在主缆上的行走系统尺寸影响,两台吊机在主缆上的水平最小间距为9.0m。当以20°荡移转角控制两台吊机在缆上的距离时,梁段提升越过地面障碍后,距吊机的距离大于9.0m/tan20°=24.73m时,两台吊机缆上定位距离大于9.0m,即可进行双吊机荡移施工,梁段每一个荡移循环水平移动距离为吊机初始定位间距减去最小间距9.0m。所以本发明能充分发挥常规起吊设备跨缆吊机的工作能力,最大限度减少陆上、浅滩区钢箱梁支架长度或不需再搭设临时支架,即可进行陆上梁段的安装,达到陆上、浅滩区钢箱梁安装施工经济、安全的目的。
                    附图说明
下面结合实施例附图对本发明作进一步说明。
图1是实施例方法说明图。
图中:1、主桥锚碇;2、悬索桥主缆;3、钢箱梁吊索;4、跨缆吊机;5、运梁驳船;6、钢箱梁;7、钢箱梁吊具吊点;8、山体障碍物。
实施例如图1所示,悬索桥主缆2固定在主桥锚碇1上,悬索桥主缆2上连接有一定间距相互平行的多根钢箱梁吊索3,钢箱梁吊索3为钢箱梁提升后与主缆永久连接吊索,属桥梁结构的一部分如图1所示a、b、c、d、e、f、g、h、j;钢箱梁6提升后与钢箱梁吊索3固定,提升索为吊机的功能件,跨缆吊机4的提升索允许最大转角为20°,因所述的两台吊机在悬索桥主缆2上的水平最小间距为9.0m(该吊机行走轨道长度为9.0m,因此两台吊机前后并拢间距为9.0m)。吊机行走系统影响两台吊机水平最小间距为9.0m;5是运梁驳船;6是钢箱梁,最大吊装重量290t;7是钢箱梁吊具吊点;8是山体障碍物。实施原理为:钢箱梁6由吊机A提离运梁驳船5,超越山体8高度,即停止提升,吊机B加载,梁段荷载逐步转移到吊机B,钢箱梁也随之荡移到吊机B下方;在悬索桥主缆2上的吊机A与吊机B定位时存在一定间距,此时吊机A空载行走到与吊机B相邻位置定位;吊机A加载、吊机B卸载,钢箱梁6再次转移到吊机A正下方,吊机B空载行走到下一荡移位置,准备下一循环荡移施工。一个循环后钢箱梁向边跨移动了一定距离,反复进行荡移循环作业,即可使钢箱梁荡移到预定位置进行安装。
在图1中悬索桥主缆2呈倒悬链线状;a、b、c、d、e、f、g、h、j是钢箱梁吊索3的编号;A、B是跨缆吊机4的两台吊机的编号。钢箱梁6最大吊重290t,陆上及浅滩区的梁段数量较多,由于山体8影响运梁驳船5不能达到梁段设计位置下方。施工梁段距运梁驳船5可抛锚水域最大水平距离为106.75m,梁段由吊机提升后吊点7距吊机最大距离61.03m,最小距离为37.54m满足双吊机荡移施工条件。
施工时,边跨钢箱梁6由运梁驳船5运抵可垂直起吊的跨缆吊机4的吊机A正下方的水域抛锚定位,以跨缆吊机允许最大荡移转角20°在主缆上定位吊机B,此时吊机A与吊机B水平间距为20.25m。跨缆吊机4的A、B两台吊机起吊系统与钢箱梁6吊具7连接,吊机A垂直提升钢箱梁6超过山体8高度后停止提升,吊机B加载梁段逐步荡移到吊机B正下方。此时吊机B持载、吊机A空载,吊机A空载行走到吊机B相邻位置;然后,吊机A加载梁段荷载转移回吊机A,吊机B空载行走到下一定位位置,一个荡移循环钢箱梁水平荡移距离约11.2m。如此反复,梁段交替荡移到a吊索对应梁段设计位置,吊机B垂直提升梁段与吊索连接,即完成该段梁段吊装。a吊索对应梁段吊装完成后,吊机A、B返回初始定位位置,进行下一梁段的吊装,其余b~g吊索相应梁段采用同样方法进行吊装。
实施例用单台跨缆吊机设计技术参数如下:
提升能力:               370T
提升用索股千斤顶         2台185T
提升速度                 36m/h
放索速度                 30m/h
提升索股长度                      250m
总自重                            110T
作用与主缆上的最大压强             4.0N/mm2
最大主缆水平倾角                   30°
持载后提升索最大转角(限制操作)      28°
持载后提升索最大转角(全操作)        20°
空载吊机在缆上平均行走速度          10m/h
吊机移动索股千斤顶                  2台60T
跨越索夹能力                       1900mm×高300mm
动力供应                           柴油发电机
最低工作温度                       -10℃
工作状态最大风速(吊机处3s阵风)      25m/s
非工作状态暴风速(吊机处3s阵风)      55m/s

Claims (3)

1、钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法:它采用两台跨缆吊机组合吊装陆上、浅滩区的钢箱梁,梁段荷载在一前一后两台吊机间交替转移,吊机在荷载转移完成后,空载吊机沿主缆行走,持载吊机在主缆上临时定位,梁段荷载在一前一后两台吊机间进行固定持载---空载行走---荷载转移---固定持载---空载行走---荷载转移的交替过程中,梁段逐步荡移到设计位置,最后单台吊机垂直提升安装就位梁段。
2、根据权利要求1所述的钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法,其特征是:所述提升索允许荡移转角为20°。
3、根据权利要求1所述的钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法,其特征是:所述的两台吊机在主缆上的水平最小间距为9.0m。
CNB2005100429094A 2005-07-03 2005-07-03 钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法 Active CN100354477C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2005100429094A CN100354477C (zh) 2005-07-03 2005-07-03 钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2005100429094A CN100354477C (zh) 2005-07-03 2005-07-03 钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法

Publications (2)

Publication Number Publication Date
CN1710208A true CN1710208A (zh) 2005-12-21
CN100354477C CN100354477C (zh) 2007-12-12

Family

ID=35706495

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005100429094A Active CN100354477C (zh) 2005-07-03 2005-07-03 钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法

Country Status (1)

Country Link
CN (1) CN100354477C (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101481903B (zh) * 2009-01-19 2010-09-22 华东交通大学 跨缆吊机倒退拼装架设山区悬索桥主桁方法
CN104674668A (zh) * 2015-01-19 2015-06-03 中铁大桥局集团有限公司 一种通过缆索吊装施工主梁节段的方法
CN105484162A (zh) * 2015-12-15 2016-04-13 中交一公局第三工程有限公司 悬索桥施工岸上加劲梁二次荡移装置及方法
CN105839537A (zh) * 2016-04-11 2016-08-10 中交第四公路工程局有限公司 跨缆吊机带梁行走吊装悬索桥加劲梁的施工方法
CN107119567A (zh) * 2017-04-28 2017-09-01 武汉智汇高桥科技股份有限公司 悬索桥钢箱梁用跨缆吊机和接长吊索的荡移施工方法
CN107245957A (zh) * 2017-08-16 2017-10-13 湖南路桥建设集团有限责任公司 一种空中无轨架设悬索桥加劲梁的方法和设备
CN109761137A (zh) * 2019-01-24 2019-05-17 中交二公局第五工程有限公司 一种浅水区钢箱梁荡移施工方法及系统和一种吊具
CN112520578A (zh) * 2020-12-01 2021-03-19 中建八局第四建设有限公司 一种大跨度超重钢桁架梁浮船驳运的吊装施工方法

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002061114A (ja) * 2000-08-21 2002-02-28 Shinko Wire Co Ltd 吊構造物の半自碇築造方法及び半自碇吊構造物

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101481903B (zh) * 2009-01-19 2010-09-22 华东交通大学 跨缆吊机倒退拼装架设山区悬索桥主桁方法
CN104674668A (zh) * 2015-01-19 2015-06-03 中铁大桥局集团有限公司 一种通过缆索吊装施工主梁节段的方法
CN104674668B (zh) * 2015-01-19 2016-06-29 中铁大桥局集团有限公司 一种通过缆索吊装施工主梁节段的方法
CN105484162B (zh) * 2015-12-15 2017-01-04 中交一公局第三工程有限公司 悬索桥施工岸上加劲梁二次荡移装置及方法
CN105484162A (zh) * 2015-12-15 2016-04-13 中交一公局第三工程有限公司 悬索桥施工岸上加劲梁二次荡移装置及方法
CN105839537B (zh) * 2016-04-11 2017-04-12 中交第四公路工程局有限公司 跨缆吊机带梁行走吊装悬索桥加劲梁的施工方法
CN105839537A (zh) * 2016-04-11 2016-08-10 中交第四公路工程局有限公司 跨缆吊机带梁行走吊装悬索桥加劲梁的施工方法
CN107119567A (zh) * 2017-04-28 2017-09-01 武汉智汇高桥科技股份有限公司 悬索桥钢箱梁用跨缆吊机和接长吊索的荡移施工方法
CN107245957A (zh) * 2017-08-16 2017-10-13 湖南路桥建设集团有限责任公司 一种空中无轨架设悬索桥加劲梁的方法和设备
CN107245957B (zh) * 2017-08-16 2022-11-15 湖南路桥建设集团有限责任公司 一种空中无轨架设悬索桥加劲梁的方法和设备
CN109761137A (zh) * 2019-01-24 2019-05-17 中交二公局第五工程有限公司 一种浅水区钢箱梁荡移施工方法及系统和一种吊具
CN109761137B (zh) * 2019-01-24 2023-10-24 中交二公局第五工程有限公司 一种浅水区钢箱梁荡移施工方法及系统和一种吊具
CN112520578A (zh) * 2020-12-01 2021-03-19 中建八局第四建设有限公司 一种大跨度超重钢桁架梁浮船驳运的吊装施工方法

Also Published As

Publication number Publication date
CN100354477C (zh) 2007-12-12

Similar Documents

Publication Publication Date Title
CN100354477C (zh) 钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法
CN101418543B (zh) 一种自锚式悬索桥斜拉施工法
CN102561191A (zh) 一种拱桥拱肋的整体提升系统及施工方法
CN105839537B (zh) 跨缆吊机带梁行走吊装悬索桥加劲梁的施工方法
CN106049293B (zh) 通航河流上悬索桥加劲梁安装方法及所用荡移系统
CN103882812A (zh) 斜拉索桥中跨主梁的施工方法
CN107119567A (zh) 悬索桥钢箱梁用跨缆吊机和接长吊索的荡移施工方法
CN104652298A (zh) 一种基于桥面支撑的整跨箱梁下放拆除系统及其施工方法
CN109098089A (zh) 一种悬索桥塔塔顶主索鞍吊装装置及施工方法
CN110258293A (zh) 斜拉桥钢桁梁主塔墩顶架设施工方法
CN106976797A (zh) 三吊点回转吊具
CN101487234B (zh) 先拱后梁系杆拱桥的横梁吊装就位的施工方法
CN102587284B (zh) 独立扒杆梁板安装施工工法
CN101725114B (zh) 一种大跨度斜拉桥缆索吊装方法及其设备
CN102433844A (zh) 栈桥悬臂提梁系统、桥面预制梁架设施工系统及方法
JP2009127317A (ja) 橋梁架設装置
CN105484168A (zh) 一种悬索桥加劲梁旋转吊装设备及加劲梁架设方法
CN107933834A (zh) 一种多功能轨道式起重船
CN113026563B (zh) 一种悬索桥高低位移梁栈桥吊装钢梁设施及其施工方法
CN105484166A (zh) 一种梯型桅杆式悬拼吊机
CN104404888A (zh) 一种大型空中坡度调整吊装系统及应用
CN211141313U (zh) 一种适用于低高度地下连续墙钢筋笼吊装的龙门吊
CN107858936A (zh) 大型履带起重机吊装上跨铁路桥箱梁施工方法
CN102071646A (zh) 大吨位箱梁下海系统及施工方法
CN103061268A (zh) 一种高速公路(双跨)跨线桥梁架设方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: ZHONGJIAO SECOND HIGHWAY ENGINEERING BUREAU CO., L

Free format text: FORMER NAME: NO.2 ROAD ENGINEERING BUREAU, LUQIAO GROUP

CP03 Change of name, title or address

Address after: 710065 Shaanxi Province, Xi'an City Road eight No. 262

Patentee after: Zhongjiao Second Highway Engineering Bureau Co., Ltd.

Address before: 710065 Shaanxi Province, Xi'an City Road eight No. 262 Luqiao Group Second Highway Engineering Bureau of Technology Development Department

Patentee before: No.2 Road Engineering Bureau, Luqiao Group

EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20051221

Assignee: Long Highway Bridge Construction CCCC National Engineering Research Center Co., Ltd.

Assignor: Zhongjiao Second Highway Engineering Bureau Co., Ltd.

Contract record no.: 2013610000056

Denomination of invention: Swing-construction method for mounting dual-hoist at land-shoul beam section for steel box girder suspension bridge

Granted publication date: 20071212

License type: Exclusive License

Record date: 20130524

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model