CN101481903B - 跨缆吊机倒退拼装架设山区悬索桥主桁方法 - Google Patents
跨缆吊机倒退拼装架设山区悬索桥主桁方法 Download PDFInfo
- Publication number
- CN101481903B CN101481903B CN2009101148594A CN200910114859A CN101481903B CN 101481903 B CN101481903 B CN 101481903B CN 2009101148594 A CN2009101148594 A CN 2009101148594A CN 200910114859 A CN200910114859 A CN 200910114859A CN 101481903 B CN101481903 B CN 101481903B
- Authority
- CN
- China
- Prior art keywords
- cable
- truss
- crane
- sides
- span
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000000725 suspension Substances 0.000 title claims abstract description 26
- 238000000034 method Methods 0.000 title claims abstract description 13
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 14
- 239000010959 steel Substances 0.000 claims abstract description 14
- 238000009434 installation Methods 0.000 claims description 3
- 238000005096 rolling process Methods 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 8
- 238000010586 diagram Methods 0.000 description 5
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009101148594A CN101481903B (zh) | 2009-01-19 | 2009-01-19 | 跨缆吊机倒退拼装架设山区悬索桥主桁方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009101148594A CN101481903B (zh) | 2009-01-19 | 2009-01-19 | 跨缆吊机倒退拼装架设山区悬索桥主桁方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101481903A CN101481903A (zh) | 2009-07-15 |
CN101481903B true CN101481903B (zh) | 2010-09-22 |
Family
ID=40879180
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009101148594A Expired - Fee Related CN101481903B (zh) | 2009-01-19 | 2009-01-19 | 跨缆吊机倒退拼装架设山区悬索桥主桁方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101481903B (zh) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102153022A (zh) * | 2011-04-11 | 2011-08-17 | 西南交通大学 | 自行式液压缆载吊机 |
CN103061262B (zh) * | 2011-10-19 | 2016-02-24 | 中交第一公路工程局有限公司 | 一种跨缆吊机及其应用方法 |
CN102720138B (zh) * | 2012-06-29 | 2014-09-24 | 中铁大桥局集团有限公司 | 钢桁梁架设系统、方法及提升站 |
CN105839537B (zh) * | 2016-04-11 | 2017-04-12 | 中交第四公路工程局有限公司 | 跨缆吊机带梁行走吊装悬索桥加劲梁的施工方法 |
CN110644372B (zh) * | 2019-10-08 | 2021-02-12 | 焦作大学 | 一种山区高空附塔悬臂式提梁桁吊系统 |
CN111691305A (zh) * | 2020-06-11 | 2020-09-22 | 中交二公局第二工程有限公司 | 一种悬索桥主梁安装方法 |
CN112695645B (zh) * | 2021-01-06 | 2022-04-29 | 中铁大桥局集团有限公司 | 一种大跨度悬索桥加劲梁架设方法 |
CN115303957A (zh) * | 2022-07-14 | 2022-11-08 | 中交第二航务工程局有限公司 | 一种缆载吊机整体提升安装施工方法 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1710208A (zh) * | 2005-07-03 | 2005-12-21 | 路桥集团第二公路工程局 | 钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法 |
CN200992687Y (zh) * | 2006-12-30 | 2007-12-19 | 中交第二公路工程局有限公司 | 一种悬索桥钢箱粱安装的吊具装置 |
-
2009
- 2009-01-19 CN CN2009101148594A patent/CN101481903B/zh not_active Expired - Fee Related
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1710208A (zh) * | 2005-07-03 | 2005-12-21 | 路桥集团第二公路工程局 | 钢箱梁悬索桥陆上、浅滩区梁段安装双吊机荡移施工方法 |
CN200992687Y (zh) * | 2006-12-30 | 2007-12-19 | 中交第二公路工程局有限公司 | 一种悬索桥钢箱粱安装的吊具装置 |
Non-Patent Citations (3)
Title |
---|
JP特开2006-16795A 2006.01.19 |
廖建宏.矮寨悬索桥初步方案研究.《中南公路工程》.2006,31(3),全文. * |
陈明宪.矮寨特大桥方案研究.《第十七届全国桥梁学术会议论文集》(上册).2006,全文. * |
Also Published As
Publication number | Publication date |
---|---|
CN101481903A (zh) | 2009-07-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101514586B (zh) | 吊轨式电动吊船及其施工方法 | |
CN202936736U (zh) | 一种斜拉桥组合梁施工桥面吊机 | |
CN101481903B (zh) | 跨缆吊机倒退拼装架设山区悬索桥主桁方法 | |
CN100543235C (zh) | 斜拉索辅助全悬臂架设钢桁梁的方法及系统 | |
CN105421249A (zh) | 一种拖吊结合式新型挂篮结构及施工方法 | |
CN102182147B (zh) | 一种钢箱梁架设方法 | |
CN103882812B (zh) | 斜拉索桥中跨主梁的施工方法 | |
CN205223872U (zh) | 一种拖吊结合式新型挂篮结构 | |
CN201106155Y (zh) | 斜拉索辅助全悬臂架设钢桁梁装置 | |
CN101559905A (zh) | 一种缆载吊机 | |
CN110344334B (zh) | 采用背索式架桥机的两跨连做钢混组合桥梁施工方法 | |
CN101666068A (zh) | 山区悬索桥加劲梁的吊装架设方法 | |
CN104695337A (zh) | 自提升滑翻施工系统及施工方法 | |
CN103911957A (zh) | 一种预应力连续箱梁悬臂施工挂篮 | |
CN110396931A (zh) | 一种中央双索面斜拉桥过索式桥面吊机及其施工方法 | |
CN205369055U (zh) | 悬索桥加劲梁旋转吊装设备 | |
CN110468743B (zh) | 一种用于旧桥墩帽改造的移动式吊架及施工方法 | |
CN107022958A (zh) | 使用缆索吊机安装斜拉桥的中跨主梁的方法 | |
CN111691305A (zh) | 一种悬索桥主梁安装方法 | |
CN105484168B (zh) | 一种悬索桥加劲梁旋转吊装设备及加劲梁架设方法 | |
CN209652741U (zh) | 一种跨铁路站场大跨度高架桥 | |
CN110656570A (zh) | 一种伸缩式人行桥梁、施工装置与施工方法 | |
CN113931068A (zh) | 钢与混凝土叠合梁安装的桥面吊机及其架梁方法 | |
CN104179123A (zh) | 一种两孔连做节段拼装造桥机 | |
CN103061268A (zh) | 一种高速公路(双跨)跨线桥梁架设方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20090715 Assignee: Wuhan Iron and steel bridge heavy industry (Zhuhai) Co., Ltd. Assignor: East-China Communication Univ Contract record no.: 2012440000439 Denomination of invention: Method for constructing hilly region rope-suspension bridge main beam by span cable supported crane assembling Granted publication date: 20100922 License type: Exclusive License Record date: 20120806 |
|
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100922 Termination date: 20130119 |
|
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20090715 Assignee: Wuhan Iron and steel bridge heavy industry (Zhuhai) Co., Ltd. Assignor: East-China Communication Univ Contract record no.: 2012440000439 Denomination of invention: Method for constructing hilly region rope-suspension bridge main beam by span cable supported crane assembling Granted publication date: 20100922 License type: Exclusive License Record date: 20120806 |
|
LICC | Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model |