CN111576236A - 一种整体式预制桥面附属结构的安装方法 - Google Patents
一种整体式预制桥面附属结构的安装方法 Download PDFInfo
- Publication number
- CN111576236A CN111576236A CN202010483525.0A CN202010483525A CN111576236A CN 111576236 A CN111576236 A CN 111576236A CN 202010483525 A CN202010483525 A CN 202010483525A CN 111576236 A CN111576236 A CN 111576236A
- Authority
- CN
- China
- Prior art keywords
- prefabricated member
- beam body
- bridge deck
- installing
- walls
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及一种整体式预制桥面附属结构的安装方法,包括以下步骤:将桥面附属结构整体成型作为预制件;于梁体内预埋连接件;于梁体表面铺设砂浆垫层至预制件高度;将预制件置于梁体表面的砂浆垫层上,通过连接件固定;本发明适用于高速铁路整体装配式桥面附属防护墙、竖墙和边墙整体一次施工完成,与传统桥面系施工方法相比,现场不需要设置模板和浇筑混凝土,在梁面有限空间内为施工作业人员提供了方便,是一种场地适用性强,安装简单、快捷,减少施工工序、可一次成型的安装方法。
Description
技术领域
本发明涉及桥梁工程领域,尤其涉及一种整体式预制桥面附属结构的安装方法。
背景技术
目前,中国的铁路桥梁占线路总长的比例比较大,桥面附属结构主要包括防护墙、竖墙、边墙等,现有的箱梁桥面附属结构需要分块实施安装,而不能一次完成,存在施工周期较长的问题,该实施过程的浇混凝土工作量大,通常要先安装遮板,再做防护墙,最后做竖墙和边墙,每个工序需要提前绑扎钢筋、安装模板和浇筑混凝土,每个工序要依次进行需要不同的模板,加上施工现场模板倒运困难,极大的影响了施工效率。
发明内容
本发明的目的在于提供一种整体式预制桥面附属结构的安装方法,解决桥面附属结构施工工期长,工作量大的问题。
为实现上述目的,本发明采用了以下技术方案:
一种整体式预制桥面附属结构的安装方法,包括以下步骤:
1)将桥面附属结构整体成型作为预制件;
2)于梁体内预埋连接件;
3)于梁体表面铺设砂浆垫层至预制件底高度;
4)将预制件置于梁体表面的砂浆垫层上,通过连接件固定。
进一步,所述预制包括电缆槽底板,以及垂直固定于电缆槽底板上的边墙、防护墙和竖墙;所述边墙、防护墙和竖墙相互平行,所述边墙和防护墙分别位于电缆槽底板的两端,所述竖墙固定于边墙和防护墙之间;所述电缆槽底板上竖直设有用于与梁体连接的安装孔。
进一步,所述的连接件为连接套筒,所述的安装孔与连接套筒对应通过连接螺栓固定连接。
进一步,所述预制件通过钢板模具浇筑混凝土一体成型,预制件内置有钢筋笼。
进一步,所述砂浆垫层采用M35水泥砂浆。
进一步,所述连接螺栓采用高强螺栓。
本发明的有益效果在于:
本发明有效的解决了传统桥面系防护墙、竖墙、边墙等桥面附属结构安装工序多,使用的模板量大,混凝土浇筑分多次进行,现场施工空间狭小,施工难度大,模板拆装过程繁琐,拆除摸板需要等待混凝土强度,各工序依次进行,施工周期长,使用人员多,倒运拆装材料费时费力的缺点。
本发明适用于所有高速铁路桥面附属结构的整体安装施工,且场地适用性强,安装、简单快捷,安装模块化可自由组合,可多个工作面同时施工相互间不干扰,在箱梁架设完成后可以及时施工,不影响箱梁架设,节约了施工周期。
附图说明
图1是本发明的安装结构示意图;
其中:1-预制件,11-电缆槽底板,12-边墙,13-防护墙,14-竖墙,15-安装孔,2-连接套筒,3-砂浆垫层,4-梁体,5-连接螺栓。
具体实施方式
下面结合具体实施方式对本发明做进一步说明:
本发明的具体实施方法如下:
首先,将桥面附属结构整体成型作为预制件1,作为优选实施方式,预制件的结构参照图1所示,包括电缆槽底板11,以及垂直固定于电缆槽底板11上的边墙12、防护墙13和竖墙14。
所述边墙12、防护墙13和竖墙14相互平行,边墙12和防护墙13分别位于电缆槽底板11的两端,竖墙14固定于边墙12和防护墙13之间.分隔形成槽,电缆槽底板11上竖直设有用于与梁体2连接的安装孔15。
预制件1的制作可以采用钢模板组成模具(钢模板可拆卸重复使用,之间用螺栓连接),将钢筋笼放置于模具内,浇筑混凝土整体成型,脱模后钢筋笼置于预制件内增加结构强度。
将预制件1运输至桥面待用。
在桥面梁体4内预埋连接件用于对预制件1的连接固定,作为优选实施方式,本实施例在梁体4内预埋的连接件为连接套筒2,可以通过固定架将预埋套筒2固定在工装架上,工装架固定在模板上,再浇筑梁体的混凝土形成梁体预埋。
之后再梁体4表面铺设一层砂浆垫层3,优选采用M35水泥砂浆,根据预制件的高度,在梁体4表面测量出需要铺设砂浆的厚度,设置垫块,铺设砂浆至垫块高度,留出梁体预埋的连接套筒2的位置不铺设砂浆。
砂浆垫层3是梁体4与预制件1之间的找平层,通过调整砂浆层3的厚度即可调整预制件1的高度。
砂浆垫层3铺设完成后,将预制件1吊运至桥面,预制件1预留的安装孔15与梁体4预埋的连接套筒2位置完全重合后落在砂浆垫层3上,通过连接螺栓5穿过安装孔15将预制件1与连接套筒2连接并拧紧;
连接螺栓5,优选采用高强螺栓,连接螺栓5与安装孔15的间隙注浆封闭后,即可完成整个桥面附属结构的安装。
以上所述的实施例仅仅是对本发明的优选实施方式进行描述,并非对本发明的范围进行限定,在不脱离本发明设计精神的前提下,本领域普通技术人员对本发明的技术方案作出的各种变形和改进,均应落入本发明权利要求书确定的保护范围内。
Claims (6)
1.一种整体式预制桥面附属结构的安装方法,其特征在于:包括以下步骤:
1)将桥面附属结构整体成型作为预制件;
2)于梁体内预埋连接件;
3)于梁体表面铺设砂浆垫层至预制件底高度;
4)将预制件置于梁体表面的砂浆垫层上,通过连接件固定。
2.根据权利要求1所述的一种整体式预制桥面附属结构的安装方法,其特征在于:所述预制包括电缆槽底板,以及垂直固定于电缆槽底板上的边墙、防护墙和竖墙;所述边墙、防护墙和竖墙相互平行,所述边墙和防护墙分别位于电缆槽底板的两端,所述竖墙固定于边墙和防护墙之间;所述电缆槽底板上竖直设有用于与梁体连接的安装孔。
3.根据权利要求2所述的一种整体式预制桥面附属结构的安装方法,其特征在于:所述的连接件为连接套筒,所述的安装孔与连接套筒对应通过连接螺栓固定连接。
4.根据权利要求1或2所述的一种整体式预制桥面附属结构的安装方法,其特征在于:所述预制件通过钢板模具浇筑混凝土一体成型,预制件内置有钢筋笼。
5.根据权利要求1所述的一种整体式预制桥面附属结构的安装方法,其特征在于:所述砂浆垫层采用M35水泥砂浆。
6.根据权利要求3所述的一种整体式预制桥面附属结构的安装方法,其特征在于:所述连接螺栓采用高强螺栓。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010483525.0A CN111576236A (zh) | 2020-06-01 | 2020-06-01 | 一种整体式预制桥面附属结构的安装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010483525.0A CN111576236A (zh) | 2020-06-01 | 2020-06-01 | 一种整体式预制桥面附属结构的安装方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111576236A true CN111576236A (zh) | 2020-08-25 |
Family
ID=72118243
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010483525.0A Pending CN111576236A (zh) | 2020-06-01 | 2020-06-01 | 一种整体式预制桥面附属结构的安装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111576236A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114193611A (zh) * | 2021-12-02 | 2022-03-18 | 中铁四局集团第二工程有限公司 | 装配式桥面预制件的施工成型方法 |
CN114214944A (zh) * | 2021-12-03 | 2022-03-22 | 中铁四局集团第二工程有限公司 | 一种铁路施工预制构件的精调施工方法 |
CN114411808A (zh) * | 2022-02-07 | 2022-04-29 | 中庆建设有限责任公司 | 一种装配式地铁车站首环拼装装置及施工方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20140139217A (ko) * | 2013-05-27 | 2014-12-05 | (주)브릿지하이텍 | 선배수 기능을 내포한 현장타설 콘크리트 방호벽 구조물 및 그 시공방법 |
CN106245526A (zh) * | 2016-09-30 | 2016-12-21 | 中铁上海工程局集团有限公司 | 铁路箱梁防护墙、竖墙及遮板的拼装结构及施工方法 |
CN206279441U (zh) * | 2016-12-01 | 2017-06-27 | 中铁第四勘察设计院集团有限公司 | 一种高速铁路箱梁桥面预制电缆槽 |
CN109868721A (zh) * | 2019-03-12 | 2019-06-11 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | 一种整体式预制桥面附属设施 |
CN110055878A (zh) * | 2019-05-30 | 2019-07-26 | 中国铁路设计集团有限公司 | 一种装配式桥面结构 |
CN210420845U (zh) * | 2019-03-12 | 2020-04-28 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | 一种预制桥面附属设施的连接件 |
CN210636300U (zh) * | 2019-08-16 | 2020-05-29 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | 一种铁路整体式装配桥面下锚拉线处附属设施 |
-
2020
- 2020-06-01 CN CN202010483525.0A patent/CN111576236A/zh active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20140139217A (ko) * | 2013-05-27 | 2014-12-05 | (주)브릿지하이텍 | 선배수 기능을 내포한 현장타설 콘크리트 방호벽 구조물 및 그 시공방법 |
CN106245526A (zh) * | 2016-09-30 | 2016-12-21 | 中铁上海工程局集团有限公司 | 铁路箱梁防护墙、竖墙及遮板的拼装结构及施工方法 |
CN206279441U (zh) * | 2016-12-01 | 2017-06-27 | 中铁第四勘察设计院集团有限公司 | 一种高速铁路箱梁桥面预制电缆槽 |
CN109868721A (zh) * | 2019-03-12 | 2019-06-11 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | 一种整体式预制桥面附属设施 |
CN210420845U (zh) * | 2019-03-12 | 2020-04-28 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | 一种预制桥面附属设施的连接件 |
CN110055878A (zh) * | 2019-05-30 | 2019-07-26 | 中国铁路设计集团有限公司 | 一种装配式桥面结构 |
CN210636300U (zh) * | 2019-08-16 | 2020-05-29 | 中国铁道科学研究院集团有限公司铁道建筑研究所 | 一种铁路整体式装配桥面下锚拉线处附属设施 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114193611A (zh) * | 2021-12-02 | 2022-03-18 | 中铁四局集团第二工程有限公司 | 装配式桥面预制件的施工成型方法 |
CN114214944A (zh) * | 2021-12-03 | 2022-03-22 | 中铁四局集团第二工程有限公司 | 一种铁路施工预制构件的精调施工方法 |
CN114214944B (zh) * | 2021-12-03 | 2024-02-23 | 中铁四局集团第二工程有限公司 | 一种铁路施工预制构件的精调施工方法 |
CN114411808A (zh) * | 2022-02-07 | 2022-04-29 | 中庆建设有限责任公司 | 一种装配式地铁车站首环拼装装置及施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105317137B (zh) | 预制墙体、墙板及其施工方法以及预制墙板生产方法 | |
CN109235499B (zh) | 一种明挖地下建筑结构装配式施工方法 | |
CN111576236A (zh) | 一种整体式预制桥面附属结构的安装方法 | |
CN105201012A (zh) | L型混凝土预制件装配后浇筑电缆沟及其施工方法 | |
CN102286932B (zh) | 移动模架桥台后方拼装自行上桥施工方法 | |
CN110005200B (zh) | 水平暗梁混凝土浇筑密实的施工工艺 | |
CN109895239B (zh) | 一种装配式混凝土楼梯缓台梁板及其建造方法 | |
CN105649248B (zh) | 装配式预应力混凝土空心板与现浇梁一体化施工方法 | |
CN110552706A (zh) | 永临结合盾构吊装孔封闭结构及方法 | |
CN205224332U (zh) | 预制墙体和预制墙板 | |
CN101476290B (zh) | 一种桥梁遮板现浇施工工法 | |
CN207110214U (zh) | 一种预制内填充混凝土墙板 | |
WO2024074079A1 (zh) | 一种预制拼装式钢筋混凝土挡土墙及其施工方法 | |
CN105244835A (zh) | L型混凝土电缆沟预制件及其生产工艺 | |
CN110468723B (zh) | 转体桥主墩外包钢板安装施工工法 | |
CN209779683U (zh) | 一种拼板装配式综合管廊 | |
KR101826094B1 (ko) | 트랜스퍼 매트의 시공방법 및 이를 이용하여 시공된 트랜스퍼 매트 | |
CN109267578B (zh) | 一种斜面素混凝土结构及其施工方法 | |
CN214737289U (zh) | 一种装配式高架道路、桥梁安装结构 | |
CN106142339A (zh) | 一种机械挤压成型预应力混凝土底板的自动化生产线 | |
CN211285212U (zh) | 适用于中小跨径简支梁桥的小箱梁结构 | |
CN211900603U (zh) | 永临结合盾构吊装孔封闭结构 | |
CN112240111A (zh) | 一种地铁预制装配立柱式检查坑结构及施工方法 | |
CN111535361A (zh) | 地下车站装配式轨顶风道结构及其构建方法 | |
CN110607738A (zh) | 适用于中小跨径简支梁桥的小箱梁结构及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200825 |