CN111021387A - 一种基础胎模快速施工的方法 - Google Patents
一种基础胎模快速施工的方法 Download PDFInfo
- Publication number
- CN111021387A CN111021387A CN201911242588.0A CN201911242588A CN111021387A CN 111021387 A CN111021387 A CN 111021387A CN 201911242588 A CN201911242588 A CN 201911242588A CN 111021387 A CN111021387 A CN 111021387A
- Authority
- CN
- China
- Prior art keywords
- precast block
- concrete precast
- construction
- concrete
- block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Foundations (AREA)
Abstract
本发明公布了一种基础胎模快速施工的方法,它包括以下步骤:A、制作定制好规格的混凝土预制块;B、将钢筋预留插孔内注满水灰比为0.5:1的水泥砂浆;C、在预制块内部孔道填塞水灰比为1:2.5的水泥砂浆;D、将连接钢筋插入钢筋预留插孔内将混凝土预制块进行连接拼装;E、在两块混凝土预制块连接时两边用小锤敲击确保锚入预制块深度。F、最后在混凝土预制块连接固定处用水泥砂浆填补加强。本发明采用一种快速施工的混凝土预制块,能够实现在基础胎模施工过程中,以更少的人工,更少的材料,更少的工序,进行更加快速、同时质量不低于传统砖胎模施工,从而达到节省成本、加快施工进度的目的。
Description
技术领域
本发明涉及建筑施工技术领域,尤其是涉及一种基础胎模快速施工的方法。
背景技术
目前国内基础胎模的施工方法主要采用烧结页岩砖砌筑胎模,需在现场拌制砂浆,且烧结页岩砖多采用黏土烧制而成,不利于环保。尤其是绿色建造已经是建筑施工发展的一种趋势,为保护环境,现在越来越多的地方禁止施工现场拌制砂浆,均要求采用预拌砂浆施工。在基础施工阶段,现场设置预拌砂浆罐较为困难,不利于砂浆转运。根据施工经验,现场平均每人每天砌筑量为2~3m³烧结页岩砖,折合承台约2个,施工周期长,施工效率低、施工成本大,且现场砂浆及烧结页岩砖损耗率大,不利于绿色施工。
因此,急需一种更加快速、方便、能够加快工程进度、增强施工质量的基础胎模施工方法。
发明内容
本发明的目的是针对以上问题,提供一种基础胎模快速施工的方法,它能够实现在基础胎模施工过程中,以更少的人工,更少的材料,更少的工序,进行更加快速、同时质量不低于传统砖胎模施工,从而达到节省成本、加快施工进度的目的。
为实现以上目的,本发明采用的技术方案是:一种基础胎模快速施工的方法,其特征在于,该方法采用一种快速施工的预制块,所述预制块包括外部结构和内部构造,所述外部结构包括上下两层混凝土预制块,所述内部构造包括预制块内部孔道、冷拔钢丝、钢筋预留插孔和连接钢筋,所述上层的混凝土预制块上设置有连接钢筋,下层的混凝土预制块下开设有钢筋预留插孔,上下两层混凝土预制块中间开设有预制块内部孔道,上下两层混凝土预制块中间设置有冷拔钢丝。
进一步的,所述冷拔钢丝为单排单向,纵向铺设在混凝土预制块内部。
进一步的,所述预制块内部孔道可根据需要开设多个,其使得预制块重量减小,材料消耗降低。
一种基础胎模快速施工的方法,其包括以下步骤:
A、制作定制好规格的混凝土预制块;
B、将钢筋预留插孔内注满水灰比为0.5:1的水泥砂浆;
C、在预制块内部孔道填塞水灰比为1:2.5的水泥砂浆;
D、将连接钢筋插入钢筋预留插孔内将混凝土预制块进行连接拼装;
E、在两块混凝土预制块连接时两边用小锤敲击确保锚入预制块深度。
F、最后在混凝土预制块连接固定处用水泥砂浆填补加强。
进一步的,所述步骤A中的混凝土预制块制作好后,在垫层施工期间,直接平放在基础垫层面上或锚入基础垫层中均可。
进一步的,所述步骤D中混凝土预制块进行连接拼装时,可在胎模内部添加支撑钢管防止回填土进行回填时胎模内倒,待胎模外侧土方回填并夯实后,可拆除支撑钢管仅靠连接钢筋及水泥砂浆连接固定。
本发明解决了传统施工方式因工序繁琐、所需材料多、所需人工多导致施工周期长、施工成本高的问题,达到了方便操作、节约成本、缩短施工周期的目的,本发明具有如下的有益效果:
1、本施工方式是在基础胎模施工时,利用混凝土预制块整体拼装,摒弃了传统的以烧结页岩砖砌筑,预制混凝土块拼装相较于传统烧结页岩砖砌筑,操作简单,效率大大提高。
2、本施工方式的预制块可在现场用施工余料预制,避免了浪费,节省了成本,符合绿色发展的理念。
3、本施工方式较传统胎模砌筑方式,施工时仅需2人拼装,且施工简便,平均每人每天能够拼装7~8个承台,同时减少了抹灰工艺,减少了工序,同时减少了砂及水泥的用量,省时省力,节约成本、工期。
4、本施工方式在底部加设短钢筋锚入土层和垫层中,可以使胎模更加稳固。
综上所述,采用本发明的胎模砌筑方法,减少了作业难度、简化了施工流程、加快了施工进度、节省了材料,且材料轻便小巧,方便调运,占用场地少,同时保证了胎模的整体性与稳固性。
附图说明
图1为本发明的基础胎模预制块平面图。
图2为本发明基础胎模预制块的侧面图。
图3为本发明基础胎模拼装完成后的示意图。
图4是本发明的基础胎模预制块拼装的示意图及节点详图。
图5是本发明基础胎模快速施工特例的示意图及节点详图。
图中所述文字标注表示为: 1、混凝土预制块;2、预制块内部孔道;3、钢筋预留插孔;4、连接钢筋;5、冷拔钢丝;6、水泥砂浆;7、支撑钢管;8、基础垫层;9、回填土。
具体实施方式
以下通过实施例进一步对本发明做出阐释。
一种基础胎模快速施工的方法,其特征在于,该方法采用一种快速施工的预制块,所述预制块包括外部结构和内部构造,所述外部结构包括上下两层混凝土预制块1,所述内部构造包括预制块内部孔道2、冷拔钢丝5、钢筋预留插孔3和连接钢筋4,所述上层的混凝土预制块1上设置有连接钢筋4,下层的混凝土预制块1下开设有钢筋预留插孔3,上下两层混凝土预制块1中间开设有预制块内部孔道2,上下两层混凝土预制块1中间设置有冷拔钢丝5。
优选的,请参照图1所示,所述冷拔钢丝5为单排单向,纵向铺设在混凝土预制块1内部。
优选的,请参照图1和图2所示,所述预制块内部孔道2可根据需要开设多个,其使得预制块重量减小,材料消耗降低。
一种基础胎模快速施工的方法,其包括以下步骤:
A、制作定制好规格的混凝土预制块1;
B、将钢筋预留插孔3内注满水灰比为0.5:1的水泥砂浆6;
C、在预制块内部孔道2填塞水灰比为1:2.5的水泥砂浆6;
D、将连接钢筋4插入钢筋预留插孔3内将混凝土预制块1进行连接拼装;
E、在两块混凝土预制块1连接时两边用小锤敲击确保锚入预制块深度。
F、最后在混凝土预制块1连接固定处用水泥砂浆6填补加强。
优选的,所述步骤A中的混凝土预制块1制作好后,在垫层施工期间,直接平放在基础垫层8上或锚入基础垫层8中均可。
优选的,所述步骤D中混凝土预制块1进行连接拼装时,可在胎模内部添加支撑钢管7防止回填土9进行回填时胎模内倒,待胎模外侧土方回填并夯实后,可拆除支撑钢管7仅靠连接钢筋4及水泥砂浆6连接固定。
本施工方法参照装配式建筑的原理,在施工前将混凝土块预制完成,在施工时直接拼装连接。
本施工方法将装配式建筑建筑的原理结合胎模施工方法,优化了施工,适用于矩形胎模、形状简单的异型胎模及高度不超过3米的胎模砌筑。
需要说明的是,在本文中,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。
本文中对本发明的原理及实施方式进行了阐述,以上实施例的说明只是用于帮助理解本发明的方法及其核心思想;同时,对于本领域的一般技术人员,依据本发明的思想,在具体实施方式及应用范围上均会有改变之处,综上所述,本说明书内容不应理解为对本发明的限制。
Claims (6)
1.一种基础胎模快速施工的方法,其特征在于,该方法采用一种快速施工的预制块,所述预制块包括外部结构和内部构造,所述外部结构包括上下两层混凝土预制块(1),所述内部构造包括预制块内部孔道(2)、冷拔钢丝(5)、钢筋预留插孔(3)和连接钢筋(4),所述上层的混凝土预制块(1)上设置有连接钢筋(4),下层的混凝土预制块(1)下开设有钢筋预留插孔(3),上下两层混凝土预制块(1)中间开设有预制块内部孔道(2),上下两层混凝土预制块(1)中间设置有冷拔钢丝(5)。
2.根据权利要求1所述的一种基础胎模快速施工的方法,其特征在于,所述冷拔钢丝(5)为单排单向,纵向铺设在混凝土预制块(1)内部。
3.根据权利要求1所述的一种基础胎模快速施工的方法,其特征在于,所述预制块内部孔道(2)可根据需要开设多个,其使得预制块重量减小,材料消耗降低。
4.根据权利要求1述的一种基础胎模快速施工的方法,其包括以下步骤:
A、制作定制好规格的混凝土预制块(1);
B、将钢筋预留插孔(3)内注满水灰比为0.5:1的水泥砂浆(6);
C、在预制块内部孔道(2)填塞水灰比为1:2.5的水泥砂浆(6);
D、将连接钢筋(4)插入钢筋预留插孔(3)内将混凝土预制块(1)进行连接拼装;
E、在两块混凝土预制块(1)连接时两边用小锤敲击确保锚入预制块深度;
F、最后在混凝土预制块(1)连接固定处用水泥砂浆(6)填补加强。
5.根据权利要求4所述的一种基础胎模快速施工的方法,其特征在于,所述步骤A中的混凝土预制块(1)制作好后,在垫层施工期间,直接平放在基础垫层(8)上或锚入基础垫层(8)中均可。
6.根据权利要求4所述的一种基础胎模快速施工的方法,其特征在于,所述步骤D中混凝土预制块(1)进行连接拼装时,可在胎模内部添加支撑钢管(7)防止回填土(9)进行回填时胎模内倒,待胎模外侧土方回填并夯实后,可拆除支撑钢管(7)仅靠连接钢筋(4)及水泥砂浆(6)连接固定。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911242588.0A CN111021387A (zh) | 2019-12-06 | 2019-12-06 | 一种基础胎模快速施工的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911242588.0A CN111021387A (zh) | 2019-12-06 | 2019-12-06 | 一种基础胎模快速施工的方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111021387A true CN111021387A (zh) | 2020-04-17 |
Family
ID=70204550
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911242588.0A Pending CN111021387A (zh) | 2019-12-06 | 2019-12-06 | 一种基础胎模快速施工的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111021387A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114687371A (zh) * | 2022-03-31 | 2022-07-01 | 成都建工第二建筑工程有限公司 | 一种装配式预制砖胎模斜筑施工工法 |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3922124A (en) * | 1971-08-12 | 1975-11-25 | Georg Bjorhaag | Sliding mould for concrete piles including slipform and rollers |
JPH10231529A (ja) * | 1997-02-18 | 1998-09-02 | Musashino Senento Kogyo Kk | コンクリート積みブロック用基盤及びコンクリート積みブロックの積み重ね工法 |
CN1904258A (zh) * | 2003-09-15 | 2007-01-31 | 邱则有 | 一种现浇砼用轻质胎模构件 |
CN2885965Y (zh) * | 2006-03-02 | 2007-04-04 | 陶献发 | 预制构件建筑胎模 |
CN201962828U (zh) * | 2011-01-31 | 2011-09-07 | 赵生亮 | 一种装配式非承重成品墙体 |
CN203782730U (zh) * | 2014-03-27 | 2014-08-20 | 中建海峡建设发展有限公司 | 组装式砖胎膜 |
CN204080841U (zh) * | 2014-09-19 | 2015-01-07 | 三箭建设工程集团有限公司 | 基础grc胎膜的固定结构 |
CN105970995A (zh) * | 2016-05-25 | 2016-09-28 | 宁波市建设集团股份有限公司 | 承台胎模 |
CN207998854U (zh) * | 2018-03-16 | 2018-10-23 | 龙元建设集团股份有限公司 | 预制空心板组成的承台基础梁模 |
CN110466037A (zh) * | 2019-07-08 | 2019-11-19 | 河海大学 | 一种钢筋水泥基复合材料预制三层叠合梁的模板体系 |
-
2019
- 2019-12-06 CN CN201911242588.0A patent/CN111021387A/zh active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3922124A (en) * | 1971-08-12 | 1975-11-25 | Georg Bjorhaag | Sliding mould for concrete piles including slipform and rollers |
JPH10231529A (ja) * | 1997-02-18 | 1998-09-02 | Musashino Senento Kogyo Kk | コンクリート積みブロック用基盤及びコンクリート積みブロックの積み重ね工法 |
CN1904258A (zh) * | 2003-09-15 | 2007-01-31 | 邱则有 | 一种现浇砼用轻质胎模构件 |
CN2885965Y (zh) * | 2006-03-02 | 2007-04-04 | 陶献发 | 预制构件建筑胎模 |
CN201962828U (zh) * | 2011-01-31 | 2011-09-07 | 赵生亮 | 一种装配式非承重成品墙体 |
CN203782730U (zh) * | 2014-03-27 | 2014-08-20 | 中建海峡建设发展有限公司 | 组装式砖胎膜 |
CN204080841U (zh) * | 2014-09-19 | 2015-01-07 | 三箭建设工程集团有限公司 | 基础grc胎膜的固定结构 |
CN105970995A (zh) * | 2016-05-25 | 2016-09-28 | 宁波市建设集团股份有限公司 | 承台胎模 |
CN207998854U (zh) * | 2018-03-16 | 2018-10-23 | 龙元建设集团股份有限公司 | 预制空心板组成的承台基础梁模 |
CN110466037A (zh) * | 2019-07-08 | 2019-11-19 | 河海大学 | 一种钢筋水泥基复合材料预制三层叠合梁的模板体系 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114687371A (zh) * | 2022-03-31 | 2022-07-01 | 成都建工第二建筑工程有限公司 | 一种装配式预制砖胎模斜筑施工工法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101831970A (zh) | 一种装配整体式墙板墙体及其施工方法 | |
CN105201012B (zh) | L型混凝土预制件装配后浇筑电缆沟及其施工方法 | |
CN104405123B (zh) | 现浇钢筋砼薄壁矩形小截面空心柱用模板组件及其施工方法 | |
CN104264862A (zh) | 一种3d打印配筋砌体剪力墙结构及其施工方法 | |
CN109648696A (zh) | 钢筋连接的边坡预制格构梁及其制作方法和施工方法 | |
CN111021387A (zh) | 一种基础胎模快速施工的方法 | |
KR100304861B1 (ko) | 건축용단열프리캐스트콘크리트판넬 | |
CN106592818A (zh) | 预制剪力墙及其制作方法 | |
WO2018186612A1 (ko) | 현장 타설 보강 팽이말뚝 기초 및 이의 시공방법 | |
CN208023601U (zh) | 一种互扣式的预制桩基承台侧模 | |
CN210395436U (zh) | 预制胎模装置 | |
CN216380553U (zh) | 一种旋流池逆作法池壁外模板的支模装置 | |
CN215630069U (zh) | 一种地下室独立基础防水一体化预制构件 | |
CN210507502U (zh) | 一种预制装配式混凝土板胎膜结构 | |
JPH05230845A (ja) | L型ブロック擁壁の構造およびその施工方法 | |
CN212835365U (zh) | 一种phc管桩的施工结构 | |
CN113235645B (zh) | 一种塔吊基础预留插筋装配式胎模施工方法 | |
CN211498929U (zh) | 一种路灯基础预制结构 | |
CN212925885U (zh) | 一种组合式隔离栅混凝土立柱及基础 | |
CN210508372U (zh) | 地下室悬挑免拆模板梁板 | |
CN102561360A (zh) | 一种深基坑支护方法 | |
CN219952020U (zh) | 一种互扣式的预制承台侧模 | |
CN111254965A (zh) | 一种注浆型再生混凝土预制墩基础及其制作方法 | |
CN219862914U (zh) | 一种全预制型快速拼装式塔吊基础结构 | |
CN212194890U (zh) | 一种大型景观假山内部支撑结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200417 |
|