CN102561360A - 一种深基坑支护方法 - Google Patents

一种深基坑支护方法 Download PDF

Info

Publication number
CN102561360A
CN102561360A CN2012100247804A CN201210024780A CN102561360A CN 102561360 A CN102561360 A CN 102561360A CN 2012100247804 A CN2012100247804 A CN 2012100247804A CN 201210024780 A CN201210024780 A CN 201210024780A CN 102561360 A CN102561360 A CN 102561360A
Authority
CN
China
Prior art keywords
concrete
hollow shell
hollow pipe
cement paste
maintaining method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012100247804A
Other languages
English (en)
Other versions
CN102561360B (zh
Inventor
程华根
王涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Chemical Civil Engineering Co ltd
Original Assignee
Chemical Industry Geotechnical Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chemical Industry Geotechnical Engineering Co ltd filed Critical Chemical Industry Geotechnical Engineering Co ltd
Priority to CN201210024780.4A priority Critical patent/CN102561360B/zh
Publication of CN102561360A publication Critical patent/CN102561360A/zh
Application granted granted Critical
Publication of CN102561360B publication Critical patent/CN102561360B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明涉及一种深基坑支护方法,具体包括如下步骤:(1)、在待支护坑基周围打入若干根下端设有闭合桩尖的空心管桩;(2)、在上述空心管桩内放入设有注浆管的钢筋笼并将其固定于空心管桩内的中心部位;(3)、在所述空心管桩内浇注一定强度的混凝土,振捣密实;(4)、上述混凝土初凝后,从注浆管上端向空心管桩内部注入一定浓度的水泥浆,在所述空心管桩内的混凝土和水泥浆终凝后,支护桩完成。它同圈梁或内支撑共同组成支护体系。本发明采用了生产速度快的预应力空心管桩,便于迅速进行作业施工;本发明在空心管桩空腔内采取了加筋填芯和后压浆技术,大大增加了原有空心管桩的了抗弯能力,满足基坑支护技术需要。

Description

一种深基坑支护方法
技术领域
本发明涉及一种深基坑支护方法。
背景技术
国家城市建设投入加大,为了节约有限的土地空间,许多高层建筑和地下通道也随之形成。在这些以及其它类似大型工程中深基坑得到非常广泛应用。深基坑支护技术尤为重要。特别在地下水位较高,周围环境复杂的软土地区,采用水泥土、土钉墙等支护结构无法满足基坑安全要求情况下,一般采用排桩或地下连续墙支护结构。由于排桩常规采用灌注桩或预制实心桩,灌注桩施工进度慢,预制实心桩现不能实行生产线生产,质量差异大等特点。如果采用一般的先张法预应力空心管桩,因其抗弯能力差,不易满足要求。
发明内容
本发明目的在于克服上述现有技术之不足,提供了一种施工效率高且支护管桩强度高的一种深基坑支护方法,该方法由以下技术方案实现:
    一种深基坑支护方法,用于支护10米以下深的坑基,其特征在于包括如下步骤:
(1)、在待支护坑基周围打入若干根下端设有闭合桩尖的空心管桩;
(2)、在上述空心管桩内放入设有注浆管的钢筋笼并将其固定于空心管桩内的中心部位;
(3)、在所述空心管桩内浇注一定强度的混凝土,振捣密实;
(4)、上述混凝土初凝后,从注浆管上端向空心管桩内部注入一定浓度的水泥浆,在所述空心管桩内的混凝土和水泥浆终凝后,支护桩完成。它同圈梁或内支撑共同组成支护体系。
    所述的深基坑支护方法,其特征在于:所述注浆管设置于钢筋笼部分的管壁上设有若干个出浆孔,浇注混凝土前用塑料膜从出浆孔的外侧对该孔进行封挡,在向注浆管注入所述水泥浆时,具有一定压强的水泥浆推开该塑料膜的封挡,注入到所述初凝的混凝土中。
    所述的深基坑支护方法,其特征在于:所述水泥浆的压强为0.5-1MPa。
所述的深基坑支护方法,其特征在于:所述水泥浆浓度为水灰比,为0.5-0.7。
所述的深基坑支护方法,其特征在于:   所述混凝土掺入按重量比为1%~2%的氯化物或0.5%~2%的硫酸盐的早强剂。
    所述的深基坑支护方法,其特征在于:所述混凝土掺入按重量比为1.5-2%的硫铝酸钙型混凝土膨胀剂。
    所述的深基坑支护方法,其特征在于:所述钢筋笼包括若干个圆形或者方形的箍筋和多根主筋,所述主筋垂直设置,所述若干个箍筋按一定间距连接在主筋上。
    所述的深基坑支护方法,其特征在于:所述空心管桩为先张法预应力空心管桩。
本发明在深基坑支护时利用了预制的预应力空心管桩,便于迅速进行作业施工,提高工作效率,同时在空心管桩空腔内采取加筋填芯和后压浆技术,又大大增加了原有空心管桩的了抗弯能力,满足基坑支护技术需要。 
附图说明
图1为空心管桩加筋填芯作业后结构示意图。
图2为图1的俯视图。
具体实施方式
以下结合说明书附图1、附图2对本发明进行进一步说明。
该方法如下:
(1)打设空心管桩:按设计图纸采用锤击或静压法在基坑周围打入多根带闭合桩尖先张法预应力空心管桩1。
(2)加筋:将钢筋笼2放入空心管桩1内部并固定,钢筋笼2由10个方形(或者圆形)的箍筋21以及均匀垂直设置在箍筋上的8根主筋22组成, 4根注浆管23均匀捆扎在主筋22上,并且注浆管23上端超出管桩上端,注浆管23对应于钢筋笼2部分的管壁上沿长度方向开设有多个出浆孔(图中未画出),出浆孔外部用塑料胶带(图中未画出)封挡住。
(3)填混凝土:为提高所填混凝土早期强度和控制收缩变形,在所填装的混凝土中掺入早强剂和膨胀剂。采用硫酸盐系列或氯化物系列早强剂,按混凝土与早强剂重量比为1%~2%的掺入比掺入氯化物系列早强剂或按0.5%~2%掺入比掺入硫酸盐系列早强剂。例如按1%~2%的掺入比掺入氯化钙或氯化钠;又如按0.5%~2%掺入比掺入硫酸钠或硫酸钾。采用硫铝酸钙型混凝土膨胀剂,按混凝土与膨胀剂重量比为1.5-2%掺入比掺入。对掺入有上述早强剂和膨胀剂的混凝土进行充分拌合,拌合好后将该混凝土注入空心管桩1的空腔部分,并振捣密实。由于注浆管23上的出浆孔用塑料胶带封挡,因此混凝土3不能从浆孔灌入注浆管23内。
4)注入水泥浆:待桩芯混凝土初凝后,自注浆管23上端注入水灰比0.5-0.70的水泥浆,注浆压力控制在0.5-1Mpa,该压力下的水泥浆突破出浆孔外侧的塑料胶带,与初凝状态的混凝土接触,等空心管桩内的混凝土和水泥浆终凝后,钢筋笼被稳固地设置在管桩内部,支护作业完成。它同圈梁或内支撑共同组成支护体系。
本发明采用了生产速度快的预应力空心管桩,便于迅速进行作业施工且费用较低,适用于深度小于10米深基坑支护作业;本发明在空心管桩空腔内采取了加筋填芯和后压浆技术,大大增加了原有空心管桩的了抗弯能力,满足基坑支护技术需要。

Claims (8)

1. 一种深基坑支护方法,用于支护10米以内深坑基,其特征在于包括如下步骤:
(1)、在待支护坑基周围打入若干根下端设有闭合桩尖的空心管桩;
(2)、在上述空心管桩内放入设有注浆管的钢筋笼并将其固定于空心管桩内的中心部位;
(3)、在所述空心管桩内浇注一定强度的混凝土,振捣密实;
(4)、上述混凝土初凝后,从注浆管上端向空心管桩内部注入一定浓度的水泥浆,在所述空心管桩内的混凝土和水泥浆终凝后,支护桩完成。
2. 根据权利要求1所述的深基坑支护方法,其特征在于:所述注浆管设置于钢筋笼部分的管壁上设有若干个出浆孔,浇注混凝土前用塑料膜从出浆孔的外侧对该孔进行封挡,在向注浆管注入所述水泥浆时,具有一定压强的水泥浆推开该塑料膜的封挡,注入到所述初凝的混凝土中。
3.根据权利要求2所述的深基坑支护方法,其特征在于:所述水泥浆的压强为0.5-1MPa。
4. 根据权利要求1所述的深基坑支护方法,其特征在于:所述水泥浆浓度为水灰比,为0.5-0.7。
5. 根据权利要求1所述的深基坑支护方法,其特征在于:所述混凝土掺入按重量比为1%~2%的氯化物或0.5%~2%的硫酸盐早强剂。
6. 根据权利要求1所述的深基坑支护方法,其特征在于:所述混凝土掺入按重量比为1.5-2%的硫铝酸钙型混凝土膨胀剂。
7. 根据权利要求1所述的深基坑支护方法,其特征在于:所述钢筋笼包括若干个圆形或者方形的箍筋和多根主筋,所述主筋垂直设置,所述若干个箍筋按一定间距连接在主筋上。
8. 根据权利要求1所述的深基坑支护方法,其特征在于:所述空心管桩为先张法预应力空心管桩。
CN201210024780.4A 2012-02-06 2012-02-06 一种深基坑支护方法 Active CN102561360B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210024780.4A CN102561360B (zh) 2012-02-06 2012-02-06 一种深基坑支护方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210024780.4A CN102561360B (zh) 2012-02-06 2012-02-06 一种深基坑支护方法

Publications (2)

Publication Number Publication Date
CN102561360A true CN102561360A (zh) 2012-07-11
CN102561360B CN102561360B (zh) 2015-04-29

Family

ID=46407840

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210024780.4A Active CN102561360B (zh) 2012-02-06 2012-02-06 一种深基坑支护方法

Country Status (1)

Country Link
CN (1) CN102561360B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102864775A (zh) * 2012-08-28 2013-01-09 福建省大地管桩有限公司 利用二次注浆法生产预应力抗拔管桩的方法
CN106767681A (zh) * 2016-11-21 2017-05-31 山东大学 适用于黄土地区的地表沉降监测装置及其监测方法
CN107386301A (zh) * 2017-08-31 2017-11-24 高波 一种地下工程明挖施工结构临时支护体系及施工方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0959973A (ja) * 1995-08-24 1997-03-04 Kajima Corp 場所打ちコンクリート杭およびその施工法
CN1609347A (zh) * 2004-11-25 2005-04-27 河北建设勘察研究院有限公司 后压浆旋挖钻孔灌注桩技术
CN2900627Y (zh) * 2004-07-19 2007-05-16 福建省大地管桩有限公司 混凝土打头管桩
CN101054799A (zh) * 2007-01-12 2007-10-17 建研地基基础工程有限责任公司 长螺旋钻孔压灌桩后注浆处理施工方法及其后置注浆装置
CN101105033A (zh) * 2007-07-31 2008-01-16 华丰建设股份有限公司 采用横隔式预应力混凝土管桩对建筑基坑进行支护的方法
CN101148874A (zh) * 2007-10-11 2008-03-26 李树源 一种提高干螺旋钻孔灌注桩承载力的施工方法
CN102220764A (zh) * 2011-04-19 2011-10-19 威海建设集团股份有限公司 深基坑支护体系及其施工方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0959973A (ja) * 1995-08-24 1997-03-04 Kajima Corp 場所打ちコンクリート杭およびその施工法
CN2900627Y (zh) * 2004-07-19 2007-05-16 福建省大地管桩有限公司 混凝土打头管桩
CN1609347A (zh) * 2004-11-25 2005-04-27 河北建设勘察研究院有限公司 后压浆旋挖钻孔灌注桩技术
CN101054799A (zh) * 2007-01-12 2007-10-17 建研地基基础工程有限责任公司 长螺旋钻孔压灌桩后注浆处理施工方法及其后置注浆装置
CN101105033A (zh) * 2007-07-31 2008-01-16 华丰建设股份有限公司 采用横隔式预应力混凝土管桩对建筑基坑进行支护的方法
CN101148874A (zh) * 2007-10-11 2008-03-26 李树源 一种提高干螺旋钻孔灌注桩承载力的施工方法
CN102220764A (zh) * 2011-04-19 2011-10-19 威海建设集团股份有限公司 深基坑支护体系及其施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
卓维松: "用后注浆技术加固桩基的工程实例", 《山西建筑》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102864775A (zh) * 2012-08-28 2013-01-09 福建省大地管桩有限公司 利用二次注浆法生产预应力抗拔管桩的方法
CN106767681A (zh) * 2016-11-21 2017-05-31 山东大学 适用于黄土地区的地表沉降监测装置及其监测方法
CN107386301A (zh) * 2017-08-31 2017-11-24 高波 一种地下工程明挖施工结构临时支护体系及施工方法
CN107386301B (zh) * 2017-08-31 2019-12-03 中建三局第一建设工程有限责任公司 一种地下工程明挖施工结构临时支护体系及施工方法

Also Published As

Publication number Publication date
CN102561360B (zh) 2015-04-29

Similar Documents

Publication Publication Date Title
CN112593549B (zh) 载体桩施工工艺
CN110318393B (zh) 一种复合桩的施工方法
CN103485349B (zh) 加固软弱土坡石灰钉复合框架预应力锚管结构及施工方法
CN103821138A (zh) 复合桩的施工方法
CN107587506A (zh) 一种预制预应力锚杆杆件及施工工法
CN106930277A (zh) 一种人工挖孔灌注桩施工方法
CN106192999A (zh) 抗拔桩的施工方法
CN102644269A (zh) 非取土复合桩及其施工方法
CN110777836A (zh) 一种钢筋混凝土板式-锚杆复合基础及其使用方法
CN203891087U (zh) 一种重力式挡土墙加固结构
CN202323938U (zh) 预应力混凝土空心管桩填芯构造
CN102561360B (zh) 一种深基坑支护方法
CN111980050A (zh) 一种小型基础承台模板及其施工方法
CN107938696A (zh) 一种用于岩石地区的预应力扩底锚索风机基础
CN105369799A (zh) 预制桩地下连续墙混凝土预制桩及施工方法
CN202482889U (zh) 一种连锁预制桩地下连续墙
RU2679172C1 (ru) Способ изготовления набивной сваи и устройство для его осуществления
CN106917402B (zh) 一种cfg桩预制桩头及cfg桩施工方法
CN105484230A (zh) 桩土混凝一体化复合桩及其施工方法
CN1214158C (zh) 现浇混凝土锚桩的施工方法
CN207846456U (zh) 一种用于岩石地区的预应力扩底锚索风机基础
CN207469230U (zh) 一种水泥土墙内插刚度可调节工型预制桩支护结构
CN102561315A (zh) 一种连锁预制桩地下连续墙
CN201187055Y (zh) 复合支护墙板
CN205205829U (zh) 一种软土基坑支护结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 210031 building 4, Yangzi science and technology innovation headquarters base, No.5, Pudong North Road, Jiangbei new district, Nanjing City, Jiangsu Province

Patentee after: China Chemical Civil Engineering Co.,Ltd.

Address before: No. 357, Dachang Yangxin Road, Liuhe District, Nanjing, Jiangsu 210044

Patentee before: CHEMICAL INDUSTRY GEOTECHNICAL ENGINEERING Co.,Ltd.

CP03 Change of name, title or address