CN110528956A - 一种智能电杆基座、安装装置和施工方法 - Google Patents
一种智能电杆基座、安装装置和施工方法 Download PDFInfo
- Publication number
- CN110528956A CN110528956A CN201910937254.9A CN201910937254A CN110528956A CN 110528956 A CN110528956 A CN 110528956A CN 201910937254 A CN201910937254 A CN 201910937254A CN 110528956 A CN110528956 A CN 110528956A
- Authority
- CN
- China
- Prior art keywords
- base station
- drilling rod
- mounting
- mast base
- mast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 14
- 238000005553 drilling Methods 0.000 claims abstract description 37
- 238000009434 installation Methods 0.000 claims abstract description 18
- 238000005266 casting Methods 0.000 claims abstract description 10
- 239000011083 cement mortar Substances 0.000 claims description 10
- 238000005507 spraying Methods 0.000 claims description 10
- 239000002689 soil Substances 0.000 claims description 7
- 239000011150 reinforced concrete Substances 0.000 claims description 5
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims 1
- 239000004567 concrete Substances 0.000 abstract description 5
- 239000000428 dust Substances 0.000 abstract description 4
- 238000000034 method Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 230000005611 electricity Effects 0.000 description 2
- 230000004888 barrier function Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/22—Sockets or holders for poles or posts
- E04H12/2207—Sockets or holders for poles or posts not used
- E04H12/2215—Sockets or holders for poles or posts not used driven into the ground
- E04H12/2223—Sockets or holders for poles or posts not used driven into the ground by screwing
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/34—Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
- E04H12/347—Arrangements for setting poles in the ground
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Foundations (AREA)
- Drilling And Exploitation, And Mining Machines And Methods (AREA)
- Earth Drilling (AREA)
Abstract
本发明提供了一种智能电杆基座、安装装置和施工方法,包括基台,基台中部设有安装凹槽,在基台周侧设有若干个均匀排列的安装孔,所述基台下方设有钻杆,钻杆内部中空,钻杆从上往下设有若干个均匀排列的浇筑孔,所述钻杆的外侧设有螺旋叶片,本发明能够通过螺旋叶片将基台固定,通过基台上的安装凹槽和安装孔固定电杆,不需要进行混凝土浇灌,避免在挖坑时带起尘土污染环境,确保电杆的稳定性,降低安装劳动强度。
Description
技术领域
本发明涉及电杆技术领域,具体涉及一种智能电杆基座、安装装置和施工方法。
背景技术
网电传输线路的架设施工过程中,智能电杆的树立是十分关键的环节,树立智能电杆首先是要挖坑,目前使用的挖坑设备和方法存在的主要缺陷:一是作业效率低,二是挖坑质量差,特别是遇有斜坡地面上挖坑,钻头尖部极易滑移,造成电杆树立位置偏离超差,严重影响施工效率和质量,三是智能电杆挖坑装置在移动过程中,由于钻杆没有合理归置,钻头摆动,容易碰到地面或者碰到障碍物,损坏钻头。
随着农村电网的改造和城镇化的建设,村村通电需要大量的环型混凝土电杆,电杆在土质松散的黄土上,在挖坑时,容易荡起泥土灰尘,通过在电杆地表堆土或设置线杆根部混凝土墩台固定线杆的方法,由于环境天气变化对土堆影响较大,一般不会使用,而混凝土墩需现场灌注,工作量大的同时,需时刻保持电杆的稳定性,难度较大。
发明内容
本发明要解决的技术问题是不需现在混凝土浇灌,避免挖坑产生灰尘,,为解决上述问题,本发明提供一种智能电杆基座、安装装置和施工方法。
本发明的目的是以下述方式实现的:
一种智能电杆基座,包括基台,基台中部设有安装凹槽,在基台周侧设有若干个均匀排列的安装孔,所述基台下方设有钻杆,钻杆内部中空,钻杆从上往下设有若干个均匀排列的浇筑孔,所述钻杆的外侧设有螺旋叶片。
安装孔为螺纹孔。
所述基台、钻杆和螺旋叶片均为钢筋混泥土一体浇筑制成。
钻杆下端设有带螺纹的钻头。
螺旋叶片远离钻杆的一侧的厚度小于螺旋叶片靠近钻杆的一侧的厚度。
一种安装装置,包括机架,机架上端两侧设有伸缩装置,伸缩装置的伸缩端与机架下方的安装板固定连接,在安装板中部设有动力装置,所述安装板的下方设有旋转板,所述动力装置的工作端连接旋转板,在旋转板的周侧设有若干个均匀排列的旋转销轴,所述旋转销轴连接电杆基座的安装孔。
伸缩装置为液压缸。
动力装置为液压马达。
所述伸缩装置的伸缩端垂直于安装板。
一种智能电杆基座的施工方法,包括如下步骤:
第一步,智能电杆基座在预制场场内进行钢筋混凝土一体浇筑制成;
第二步,将智能电杆基座运至施工现场;
第三步,将安装装置的旋转板安置在智能电杆基座的基台上,旋转板上的旋转销轴穿插在安装孔中;
第四步,将动力装置的输出端连接旋转板;
第五步,启动伸缩装置和动力装置,将智能电杆基座旋入工作面之下,使基台与工作面平齐;
第六步,将水泥砂浆喷涂灌浆机的输出端放入钻杆中,启动水泥砂浆喷涂灌浆机往钻杆内部喷浆,通过钻杆的浇筑孔对螺旋叶片周围的泥土进行浇筑;
第七步,完成浇筑后,停止水泥砂浆喷涂灌浆机工作,将电杆安装至基台的安装凹槽中,电杆的底座通过螺栓连接基台上的安装孔,完成电杆的安装。
相对于现有技术,本发明能够通过螺旋叶片将基台固定,通过基台上的安装凹槽和安装孔固定电杆,不需要进行混凝土浇灌,避免在挖坑时带起尘土污染环境,确保电杆的稳定性,降低安装劳动强度。
附图说明
图1是本发明的结构示意图。
图2是基台的结构示意图。
图3是旋转板的结构示意图。
图4是图3的俯视图。
其中,1.伸缩装置,2.机架,3.动力装置,4.安装板,5.旋转板,6.旋转销轴,7.基台,8.安装凹槽,9.钻杆,10.螺旋叶片,11.钻头,12.安装孔,13.卡接槽,14.浇筑孔。
具体实施方式
如附图1到4所示,一种智能电杆基座,包括基台7,基台7中部设有安装凹槽8,在基台7周侧设有若干个均匀排列的安装孔12,所述基台7下方设有钻杆9,钻杆9内部中空,钻杆9从上往下设有若干个均匀排列的浇筑孔14,浇筑孔14至少有三个,所述钻杆9的外侧设有螺旋叶片10。
安装孔12为螺纹孔,通过螺纹孔连接电杆底座,使电杆固定在基台7上。
所述基台7、钻杆9和螺旋叶片10均为钢筋混泥土一体浇筑制成,降低成本,不需要现场进行混凝土浇灌,降低劳动强度,加大电杆的稳定性。
钻杆9下端设有带螺纹的钻头11,螺旋叶片10远离钻杆9的一侧的厚度小于螺旋叶片10靠近钻杆9的一侧的厚度,便于钻入土地,
一种安装装置,包括机架2,机架2上端两侧设有伸缩装置1,伸缩装置1的伸缩端与机架2下方的安装板4固定连接,伸缩装置1的伸缩端竖直往下做往复移动,在安装板4中部设有动力装置3,所述安装板4的下方设有旋转板5,所述动力装置3的工作端连接旋转板5,优选的,动力装置3的工作端与旋转板5卡接,旋转板5中部设有卡接槽13,优选的,卡接槽13为六棱槽,在旋转板5的周侧设有若干个均匀排列的旋转销轴6,旋转销轴6与安装孔12的数量和位置相对应,所述旋转销轴6连接智能电杆基座的安装孔12,旋转销轴6穿插在安装孔12中,智能电杆基座的钻杆9垂直与工作面。
伸缩装置1为液压缸,推动安装板4往下移动。
动力装置3为液压马达,带动旋转板5工作,动力足,工作效率高。
伸缩装置1的伸缩端垂直于安装板4,防止智能电杆基座倾斜,提高工作效率。
一种智能电杆基座的施工方法,包括如下步骤:
第一步,智能电杆基座在预制场场内进行钢筋混凝土一体浇筑制成;
第二步,将智能电杆基座运至施工现场;
第三步,将安装装置的旋转板5安置在智能电杆基座的基台上,旋转板5上的旋转销轴6穿插在安装孔12中;
第四步,将动力装置3的输出端连接旋转板5;
第五步,启动伸缩装置1和动力装置3,将智能电杆基座旋入工作面之下,使基台7与工作面平齐;
第六步,将水泥砂浆喷涂灌浆机的输出端放入钻9杆中,启动水泥砂浆喷涂灌浆机往钻杆9内部喷浆,通过钻杆的浇筑孔14对螺旋叶片周围的泥土进行浇筑;
第七步,完成浇筑后,停止水泥砂浆喷涂灌浆机工作,将电杆安装至基台7的安装凹槽8中,电杆的底座通过螺栓连接基台7上的安装孔,完成电杆的安装。
本发明的工作过程如下:将智能电杆基座竖直放置,旋转板5上的旋转销轴6安装在基台7上的安装孔12中,液压马达的工作端卡接在旋转板5上,启动液压马达和液压缸,液压马达带动旋转板5转动,旋转板5通过旋转销轴6带动基台7转动,基台7带动钻杆9转动,钻杆9带动钻头11和螺旋叶片10转动,同时,液压缸的伸缩端推动安装板4往下移动,进而推动智能电杆基座往下移动,即通过液压缸和液压马达将智能电杆基座钻入土内,直到基台7与工作面平齐,停止工作,移走安装装置,然后将智能电杆插入基台7上的安装凹槽8中,通过螺栓将智能电杆底座固定在安装孔12中,固定智能电杆,完成智能电杆的安装。
尤其值得注意的是液压缸和液压马达均为液压泵带动,水泥砂浆喷涂灌浆机均为现有技术,本说明书中部在进行详细描述。
以上所述的仅是本发明的优选实施方式,应当指出,对于本领域的技术人员来说,在不脱离本发明整体构思前提下,还可以作出若干改变和改进,这些也应该视为本发明的保护范围。
Claims (10)
1.一种智能电杆基座,包括基台,其特征在于:基台中部设有安装凹槽,在基台周侧设有若干个均匀排列的安装孔,所述基台下方设有钻杆,钻杆内部中空,钻杆从上往下设有若干个均匀排列的浇筑孔,所述钻杆的外侧设有螺旋叶片。
2.根据权利要求1所述的电杆基座,其特征在于:安装孔为螺纹孔。
3.根据权利要求1所述的电杆基座,其特征在于:所述基台、钻杆和螺旋叶片均为钢筋混泥土一体浇筑制成。
4.根据权利要求1所述的电杆基座,其特征在于:钻杆下端设有带螺纹的钻头。
5.根据权利要求1所述的电杆基座,其特征在于:螺旋叶片远离钻杆的一侧的厚度小于螺旋叶片靠近钻杆的一侧的厚度。
6.一种安装装置,包括机架,其特征在于:机架上端两侧设有伸缩装置,伸缩装置的伸缩端与机架下方的安装板固定连接,在安装板中部设有动力装置,所述安装板的下方设有旋转板,所述动力装置的工作端连接旋转板,在旋转板的周侧设有若干个均匀排列的旋转销轴,所述旋转销轴连接电杆基座的安装孔。
7.根据权利要求6所述的安装装置,其特征在于:伸缩装置为液压缸。
8.根据权利要求6所述的安装装置,其特征在于:动力装置为液压马达。
9.根据权利要求6所述的安装装置,其特征在于:所述伸缩装置的伸缩端垂直于安装板。
10.一种智能电杆基座的施工方法,其特征在于,包括如下步骤:
第一步,智能电杆基座在预制场场内进行钢筋混凝土一体浇筑制成;
第二步,将智能电杆基座运至施工现场;
第三步,将安装装置的旋转板安置在智能电杆基座的基台上,旋转板上的旋转销轴穿插在安装孔中;
第四步,将动力装置的输出端连接旋转板;
第五步,启动伸缩装置和动力装置,将智能电杆基座旋入工作面之下,使基台与工作面平齐;
第六步,将水泥砂浆喷涂灌浆机的输出端放入钻杆中,启动水泥砂浆喷涂灌浆机往钻杆内部喷浆,通过钻杆的浇筑孔对螺旋叶片周围的泥土进行浇筑;
第七步,完成浇筑后,停止水泥砂浆喷涂灌浆机工作,将电杆安装至基台的安装凹槽中,电杆的底座通过螺栓连接基台上的安装孔,完成电杆的安装。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910937254.9A CN110528956B (zh) | 2019-09-29 | 2019-09-29 | 一种智能电杆基座、安装装置和施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910937254.9A CN110528956B (zh) | 2019-09-29 | 2019-09-29 | 一种智能电杆基座、安装装置和施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110528956A true CN110528956A (zh) | 2019-12-03 |
CN110528956B CN110528956B (zh) | 2024-07-19 |
Family
ID=68671307
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910937254.9A Active CN110528956B (zh) | 2019-09-29 | 2019-09-29 | 一种智能电杆基座、安装装置和施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110528956B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111561215A (zh) * | 2020-05-29 | 2020-08-21 | 国网河南省电力公司桐柏县供电公司 | 一种电线杆支架 |
Citations (30)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0378348A1 (en) * | 1989-01-09 | 1990-07-18 | Katsumi Kitanaka | A cast-in-place piling method and apparatus |
JPH1025737A (ja) * | 1996-05-08 | 1998-01-27 | Kajima Corp | 既設基礎直下の場所打ち杭構築工法 |
KR20000000160A (ko) * | 1999-09-22 | 2000-01-15 | 양승용 | 지상고정용 철주 받침대의 지하 매설 방법 |
JP2000080645A (ja) * | 1998-09-08 | 2000-03-21 | Kajima Corp | 場所打ち杭の施工法 |
WO2000046452A1 (en) * | 1999-02-05 | 2000-08-10 | Northern Technologies, Inc. | Support structure for elevating and supporting monopoles and associated equipment |
JP2001279667A (ja) * | 1996-05-08 | 2001-10-10 | Kajima Corp | 既設基礎直下の場所打ち杭構築工法 |
KR20020009000A (ko) * | 2000-07-22 | 2002-02-01 | 송진호 | 1회용 거푸집을 사용하는 전철주용 기초 콘크리트 시공방법 및 그 방법에 따른 기초 콘크리트 |
JP2004092376A (ja) * | 2002-02-15 | 2004-03-25 | Ntt Infranet Co Ltd | コンクリート製電柱の補強方法、補強コンクリート製電柱、およびコンクリート製電柱の補強材懸吊用治具 |
JP2005026839A (ja) * | 2003-06-30 | 2005-01-27 | Nippon Concrete Ind Co Ltd | 空中線支持装置 |
JP2006118336A (ja) * | 2004-09-21 | 2006-05-11 | Atsushi Nakaya | 錐状螺旋杭 |
RU2286424C1 (ru) * | 2005-05-05 | 2006-10-27 | Государственное образовательное учреждение высшего профессионального образования "Северо-Кавказский государственный технический университет" | Буронабивной ступенчатый фундамент и способ его возведения |
US20100263929A1 (en) * | 2009-04-21 | 2010-10-21 | Soilmec S.P.A. | Excavation and compaction equipment for the construction of screw piles |
US20120070233A1 (en) * | 2010-09-17 | 2012-03-22 | Ensoft, Inc. | Foundation for wind turbine generator |
JP2012219567A (ja) * | 2011-04-12 | 2012-11-12 | Lend Lease Japan Co Ltd | 柱状構造物および柱状構造物の設置方法 |
JP2013047416A (ja) * | 2011-08-29 | 2013-03-07 | Toshihiko Fujii | 柱材の立設施工方法 |
GB2508594A (en) * | 2012-12-03 | 2014-06-11 | Alan Dick Comm Ltd | Communication mast support and installation method |
US20140161539A1 (en) * | 2012-12-07 | 2014-06-12 | Anoop Kumar Arya | Soil anchor footing |
DE202014102748U1 (de) * | 2014-06-13 | 2014-08-04 | Gebr. Sträb GmbH & Co. | Bodendübel zum Befestigen von stabförmigen Gegenständen, insbesondere von Pfosten im urbanen Bereich (Umfeld) |
JP2015047008A (ja) * | 2013-08-28 | 2015-03-12 | 中国電力株式会社 | 電柱の設置工法 |
CN104846820A (zh) * | 2015-06-04 | 2015-08-19 | 中铁第四勘察设计院集团有限公司 | 一种端承型螺纹式挤土桩成桩设备及成桩施工方法 |
CN205502709U (zh) * | 2016-04-14 | 2016-08-24 | 马鞍山宏泰建材股份有限公司 | 一种带基座的电杆 |
KR101663174B1 (ko) * | 2016-02-26 | 2016-10-06 | (주)신화 | 기초선단장치를 구비하는 기초 및 이의 시공방법 |
KR101882628B1 (ko) * | 2017-12-07 | 2018-07-26 | 문형록 | 굴착용 확산안테나를 이용한 동시 확장 및 지반 보강 시공방법 |
KR20180003014U (ko) * | 2017-08-14 | 2018-10-19 | 전재운 | 보강재와 인젝션, 그라우팅, 주입공사 이용 현장타설기초 |
CN108914961A (zh) * | 2018-08-03 | 2018-11-30 | 福州铭林钢塔钢构制造有限公司 | 采用螺旋锚的通讯铁塔基础及施工方法 |
JP2019019647A (ja) * | 2017-07-21 | 2019-02-07 | 鹿島建設株式会社 | 杭の施工方法 |
CN109469392A (zh) * | 2018-09-17 | 2019-03-15 | 深圳市建艺装饰集团股份有限公司 | 智能化弱电立杆及施工方法 |
CN109630040A (zh) * | 2018-12-10 | 2019-04-16 | 李健 | 一种新型长螺旋钻杆及混凝土螺纹桩施工方法 |
CN110284749A (zh) * | 2019-07-02 | 2019-09-27 | 合肥海银杆塔有限公司 | 一种混凝土电杆用的快速拼接件 |
CN211286905U (zh) * | 2019-09-29 | 2020-08-18 | 国网河南省电力公司新密市供电公司 | 一种智能电杆基座以及安装装置 |
-
2019
- 2019-09-29 CN CN201910937254.9A patent/CN110528956B/zh active Active
Patent Citations (30)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0378348A1 (en) * | 1989-01-09 | 1990-07-18 | Katsumi Kitanaka | A cast-in-place piling method and apparatus |
JPH1025737A (ja) * | 1996-05-08 | 1998-01-27 | Kajima Corp | 既設基礎直下の場所打ち杭構築工法 |
JP2001279667A (ja) * | 1996-05-08 | 2001-10-10 | Kajima Corp | 既設基礎直下の場所打ち杭構築工法 |
JP2000080645A (ja) * | 1998-09-08 | 2000-03-21 | Kajima Corp | 場所打ち杭の施工法 |
WO2000046452A1 (en) * | 1999-02-05 | 2000-08-10 | Northern Technologies, Inc. | Support structure for elevating and supporting monopoles and associated equipment |
KR20000000160A (ko) * | 1999-09-22 | 2000-01-15 | 양승용 | 지상고정용 철주 받침대의 지하 매설 방법 |
KR20020009000A (ko) * | 2000-07-22 | 2002-02-01 | 송진호 | 1회용 거푸집을 사용하는 전철주용 기초 콘크리트 시공방법 및 그 방법에 따른 기초 콘크리트 |
JP2004092376A (ja) * | 2002-02-15 | 2004-03-25 | Ntt Infranet Co Ltd | コンクリート製電柱の補強方法、補強コンクリート製電柱、およびコンクリート製電柱の補強材懸吊用治具 |
JP2005026839A (ja) * | 2003-06-30 | 2005-01-27 | Nippon Concrete Ind Co Ltd | 空中線支持装置 |
JP2006118336A (ja) * | 2004-09-21 | 2006-05-11 | Atsushi Nakaya | 錐状螺旋杭 |
RU2286424C1 (ru) * | 2005-05-05 | 2006-10-27 | Государственное образовательное учреждение высшего профессионального образования "Северо-Кавказский государственный технический университет" | Буронабивной ступенчатый фундамент и способ его возведения |
US20100263929A1 (en) * | 2009-04-21 | 2010-10-21 | Soilmec S.P.A. | Excavation and compaction equipment for the construction of screw piles |
US20120070233A1 (en) * | 2010-09-17 | 2012-03-22 | Ensoft, Inc. | Foundation for wind turbine generator |
JP2012219567A (ja) * | 2011-04-12 | 2012-11-12 | Lend Lease Japan Co Ltd | 柱状構造物および柱状構造物の設置方法 |
JP2013047416A (ja) * | 2011-08-29 | 2013-03-07 | Toshihiko Fujii | 柱材の立設施工方法 |
GB2508594A (en) * | 2012-12-03 | 2014-06-11 | Alan Dick Comm Ltd | Communication mast support and installation method |
US20140161539A1 (en) * | 2012-12-07 | 2014-06-12 | Anoop Kumar Arya | Soil anchor footing |
JP2015047008A (ja) * | 2013-08-28 | 2015-03-12 | 中国電力株式会社 | 電柱の設置工法 |
DE202014102748U1 (de) * | 2014-06-13 | 2014-08-04 | Gebr. Sträb GmbH & Co. | Bodendübel zum Befestigen von stabförmigen Gegenständen, insbesondere von Pfosten im urbanen Bereich (Umfeld) |
CN104846820A (zh) * | 2015-06-04 | 2015-08-19 | 中铁第四勘察设计院集团有限公司 | 一种端承型螺纹式挤土桩成桩设备及成桩施工方法 |
KR101663174B1 (ko) * | 2016-02-26 | 2016-10-06 | (주)신화 | 기초선단장치를 구비하는 기초 및 이의 시공방법 |
CN205502709U (zh) * | 2016-04-14 | 2016-08-24 | 马鞍山宏泰建材股份有限公司 | 一种带基座的电杆 |
JP2019019647A (ja) * | 2017-07-21 | 2019-02-07 | 鹿島建設株式会社 | 杭の施工方法 |
KR20180003014U (ko) * | 2017-08-14 | 2018-10-19 | 전재운 | 보강재와 인젝션, 그라우팅, 주입공사 이용 현장타설기초 |
KR101882628B1 (ko) * | 2017-12-07 | 2018-07-26 | 문형록 | 굴착용 확산안테나를 이용한 동시 확장 및 지반 보강 시공방법 |
CN108914961A (zh) * | 2018-08-03 | 2018-11-30 | 福州铭林钢塔钢构制造有限公司 | 采用螺旋锚的通讯铁塔基础及施工方法 |
CN109469392A (zh) * | 2018-09-17 | 2019-03-15 | 深圳市建艺装饰集团股份有限公司 | 智能化弱电立杆及施工方法 |
CN109630040A (zh) * | 2018-12-10 | 2019-04-16 | 李健 | 一种新型长螺旋钻杆及混凝土螺纹桩施工方法 |
CN110284749A (zh) * | 2019-07-02 | 2019-09-27 | 合肥海银杆塔有限公司 | 一种混凝土电杆用的快速拼接件 |
CN211286905U (zh) * | 2019-09-29 | 2020-08-18 | 国网河南省电力公司新密市供电公司 | 一种智能电杆基座以及安装装置 |
Non-Patent Citations (1)
Title |
---|
祁琪: "桩锚结构在超大型深基坑工程中的应用", 城市建设理论研究(电子版), no. 001, 31 December 2013 (2013-12-31) * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111561215A (zh) * | 2020-05-29 | 2020-08-21 | 国网河南省电力公司桐柏县供电公司 | 一种电线杆支架 |
Also Published As
Publication number | Publication date |
---|---|
CN110528956B (zh) | 2024-07-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN211816278U (zh) | 一种建筑工程施工用可拆式支护 | |
CN103147689A (zh) | 多功能旋挖钻机 | |
CN110528956A (zh) | 一种智能电杆基座、安装装置和施工方法 | |
CN110331936B (zh) | 一种组合式钻孔扩底植桩施工方法 | |
CN215859995U (zh) | 一种旋挖钻筒式清孔钻头 | |
CN209741844U (zh) | 一种水利工程用拔桩装置 | |
CN211286905U (zh) | 一种智能电杆基座以及安装装置 | |
CN208917830U (zh) | 用于植入桩施工的静压管桩抱箍 | |
CN216572565U (zh) | 一种土木桥梁施工用搅拌装置 | |
CN108360502B (zh) | 土壤及地下水原位单轴大直径注药搅拌修复系统及方法 | |
CN106759339B (zh) | 免桩间土挖除的桩帽混凝土施工方法及其装置 | |
CN209836762U (zh) | 一种土木工程挤压平整装置 | |
CN109797635A (zh) | 一种用于公路施工的混凝土浇筑模板自动施工方法及配套装置 | |
CN215057352U (zh) | 一种大口井用旋挖及滑膜装置 | |
CN217001722U (zh) | 一种钻杆拆解装置 | |
CN221072634U (zh) | 一种钢筋笼吊杆 | |
CN219218974U (zh) | 一种岩土工程用搅拌桩 | |
CN212837583U (zh) | 一种建筑工程混凝土管桩掏桩装置 | |
CN217841509U (zh) | 一种自行走钻机 | |
CN212254669U (zh) | 一种钻孔灌注桩用取土装置 | |
CN215212249U (zh) | 一种基于港口工程灌注桩的施工平台 | |
CN216405426U (zh) | 一种用于土木工程的基坑加固结构 | |
CN211922628U (zh) | 一种制造管桩用清土装置 | |
CN207878715U (zh) | 一种免模叠合剪力墙 | |
CN216515640U (zh) | 一种水利工程施工用渠道侧壁支撑设备 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |