CN110453860A - It criticizes and scrapes brick construction technology - Google Patents

It criticizes and scrapes brick construction technology Download PDF

Info

Publication number
CN110453860A
CN110453860A CN201910384844.3A CN201910384844A CN110453860A CN 110453860 A CN110453860 A CN 110453860A CN 201910384844 A CN201910384844 A CN 201910384844A CN 110453860 A CN110453860 A CN 110453860A
Authority
CN
China
Prior art keywords
batch
brick
foundation wall
coating
scraped
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910384844.3A
Other languages
Chinese (zh)
Inventor
李红建
王松刚
任成�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Yongwei Real Estate Co Ltd
Original Assignee
Zhengzhou Yongwei Real Estate Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Yongwei Real Estate Co Ltd filed Critical Zhengzhou Yongwei Real Estate Co Ltd
Priority to CN201910384844.3A priority Critical patent/CN110453860A/en
Publication of CN110453860A publication Critical patent/CN110453860A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/02Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

The present invention relates to batch to scrape brick construction technology, comprising the following steps: step a. handles the surface of foundation wall: removing the dirt on foundation wall surface;Step b. brushes SKK lattice seam paint;Step c. pastes U.S. line paper: it is anticipated that is obtained criticizes the shape for scraping brick, pasting U.S. line paper in the suitable position in foundation wall surface;Step d. crowd, which is applied, batch scrapes brick coating: batch will scrape brick and apply charge and carry out bottoming construction on foundation wall;Step e. makes scratch: batch scrape brick coating surface it is dry before, to batch being coated in batch scraping brick coating and carry out scratch production on foundation wall;Step f. removes U.S. line paper: the U.S. line paper of stickup being taken off, the position after taking off just forms lattice seam;Step g. repairs lattice seam: construction personnel's plaid matching seam is repaired;Step h. smears finishing coat: after the completion of repairing lattice seam, batch scraping brick coating surface and does and scrape brick face to entire batch after 24 hours and carry out smearing finishing coat;The present invention has and can produce modelling effect better than ceramic tile, avoid ceramic tile fall off brought by hidden danger the advantages of.

Description

It criticizes and scrapes brick construction technology
Technical field
The invention belongs to technical field of building construction, more particularly to criticize and scrape brick construction technology.
Background technique
Frequent Accidents caused by falling off because of ceramic tile in recent years, imitate brick with coating and ceramic tile are replaced to have become a kind of trend, It, always can not generation although the features such as it is light with quality compared with ceramic tile that coating imitates brick, high-weatherability durability, and color is various Special formed for ceramic tile bring the visual aesthetic feeling of people, it is therefore desirable to a kind of to produce the modelling effect better than ceramic tile Construction technology dotes on ceramic tile not only to meet people with this, while possessing the exclusive feature of coating itself, is guaranteeing height While quality and perfect effect show, avoids ceramic tile multiple at present and fall off brought hidden danger.
Summary of the invention
It is an object of the invention to overcome the deficiencies in the prior art, and provide a kind of solid that can be produced better than ceramic tile Feel effect, meet people and ceramic tile is doted on, while possessing the exclusive feature of coating itself, guarantees high-quality and perfect effect While fruit shows, avoid ceramic tile fall off brought by hidden danger batch scrape brick construction technology.
To achieve the goals above, brick construction technology is scraped the invention provides the following technical scheme: criticizing, comprising the following steps:
Step a. handles the surface of foundation wall: removing the dirt on foundation wall surface, and the repairing of the surface of foundation wall is smooth;
Step b. brushes SKK lattice seam paint: brushing SKK lattice seam paint on the surface of foundation wall as priming paint, guarantees priming paint during brush Brush is uniform;
Step c. pastes U.S. line paper: it is anticipated that is obtained criticizes the shape for scraping brick, pasting beauty in the suitable position in foundation wall surface Line paper;
Step d. crowd, which is applied, batch scrapes brick coating: batch will scrape brick and apply charge and carry out bottoming construction on foundation wall;
Step e. makes scratch: batch scrape brick coating surface it is dry before, to batch being coated in batch scraping brick coating and carry out scratch on foundation wall Production makes batch surface irregularity for scraping brick coating, shows three-dimensional effect;
Step f. removes U.S. line paper: the U.S. line paper of stickup being taken off, the position after taking off just forms lattice seam;
Step g. repairs lattice seam: relatively rough by taking the lattice seam that U.S. line paper is formed off, construction personnel's plaid matching seam is repaired, and is done Landscaping treatment;
Step h. smears finishing coat: after the completion of repairing lattice seam, batch scrape brick coating surface do after 24 hours to entire batch scrape brick face into Row smears finishing coat.
In the step a, smooth repairing to the surface of foundation wall controls the flatness deviation on foundation wall surface and exists Within 1.5mm.
In the step b, the base of thicker coating is strengthened in the use of used priming paint SKK lattice seam paint, SKK lattice seam paint Face adhesive force, and there is preferable weatherability and anti-ultraviolet ability, it can be directly exposed to outside, when throwing off U.S. line When paper makes the seam paint exposure of SKK lattice, does not have to brushing finish paint again at lattice seam, reduce working procedure, and brush two layers, first layer transverse direction side To brush, the second layer is vertically brushed.
In the step d, it is that brick coating is scraped in SKK calcining batch that used batch, which is scraped brick coating, and brick painting is scraped in SKK calcining batch Material passes through 900 DEG C of high-temperature calcination, pickling can effectively remove mineral oxide ingredient and ferrous components, it is made to be less prone to rusty stain, It is permanent to keep true stone damp, it is colour-fast.
In the step h, used finishing coat is SKK ultra-low contamination protective topcoat, the SKK ultra-low contamination protective topcoat It with low electric charge, is capable of forming with hydrophilic fine and close film, effectively inhibits dirt to rest on above and more easily clear It washes, can make batch to scrape brick more beautiful.
Described step e, f and the g batch scrape brick coating it is dry before operated, avoid batch scraping brick coating surface it is dry after take off beauty One piece of related surrounding falls off when line paper.
In the step h, finishing coat is applied two layers, and two layers of finishing coat increases the protection that brick is scraped to criticizing after finishing coat.
The invention has the following advantages that the present invention is in use, the even application first on the foundation wall surface of smooth completion SKK lattice seam paint, closes the alkalinity of wall, tentatively makes film, avoid material different in the alkalinity and subsequent technique of wall It with influencing each other for wall, forms a connecting link simultaneously, improves the adhesive force of finishing coat;The U.S. line paper of stickup is painted in SKK lattice seam, according to pre- The lines of phase is pasted, and directly U.S. line paper is torn after batch scraping brick coating material, is formed preliminary lattice seam, more just Just;Batch painting batch is painted in SKK lattice seam and scrapes brick coating, and is made to criticize by special tool(s) and scraped brick coating surface with stereoscopic effect, then Criticizing for required shape, which is directly obtained, by the U.S. line paper of removing scrapes brick;By batch scraping brick coating surface brushing finish paint, brick is scraped to batch Coating is protected, and is extended and is used the time;The present invention has the modelling effect that can be produced better than ceramic tile, meets people Ceramic tile is doted on, while possessing the exclusive feature of coating itself, while guaranteeing that high-quality and perfect effect show, is avoided Ceramic tile fall off brought by hidden danger the advantages of.
Figure of description
Fig. 1 is the product effect figure that the present invention crowd scrapes brick construction technology.
Specific embodiment
Below with reference to embodiment, the present invention is further illustrated.
Embodiment 1
It criticizes and scrapes brick construction technology, comprising the following steps:
Step a. handles the surface of foundation wall: removing the dirt on foundation wall surface, and the repairing of the surface of foundation wall is smooth;
Step b. brushes SKK lattice seam paint: brushing SKK lattice seam paint on the surface of foundation wall as priming paint, guarantees priming paint during brush Brush is uniform;
Step c. pastes U.S. line paper: it is anticipated that is obtained criticizes the shape for scraping brick, pasting beauty in the suitable position in foundation wall surface Line paper;
Step d. crowd, which is applied, batch scrapes brick coating: batch will scrape brick and apply charge and carry out bottoming construction on foundation wall;
Step e. makes scratch: batch scrape brick coating surface it is dry before, to batch being coated in batch scraping brick coating and carry out scratch on foundation wall Production makes batch surface irregularity for scraping brick coating, shows three-dimensional effect;
Step f. removes U.S. line paper: the U.S. line paper of stickup being taken off, the position after taking off just forms lattice seam;
Step g. repairs lattice seam: relatively rough by taking the lattice seam that U.S. line paper is formed off, construction personnel's plaid matching seam is repaired, and is done Landscaping treatment;
Step h. smears finishing coat: after the completion of repairing lattice seam, batch scrape brick coating surface do after 24 hours to entire batch scrape brick face into Row smears finishing coat.
The present invention is in use, uniformly brushes SKK lattice seam paint on the foundation wall surface of smooth completion first as priming paint, to wall The alkalinity of body is closed, and film is tentatively made, and avoids the mutual shadow of material and wall different in the alkalinity and subsequent technique of wall It rings, forms a connecting link simultaneously, improve the adhesive force of finishing coat;Paint the U.S. line paper of stickup in SKK lattice seam, it is anticipated that lines paste, Directly U.S. line paper is torn after batch scraping brick coating material, is formed preliminary lattice seam, enhanced convenience;It stitches and paints in SKK lattice Brick coating is scraped in upper batch of painting batch, and is made to criticize by special tool(s) and scraped brick coating surface with stereoscopic effect, then passes through the U.S. line paper of removing It directly obtains criticizing for required shape and scrapes brick;By batch scraping brick coating surface brushing finish paint, brick coating is scraped to batch and is protected, is prolonged It is long to use the time;The present invention has the modelling effect that can be produced better than ceramic tile, meets people and dotes on ceramic tile, together The exclusive feature of Shi Yongyou coating itself avoids ceramic tile and falls off institute's band while guaranteeing that high-quality and perfect effect show The advantages of hidden danger come.
Embodiment 2
It criticizes and scrapes brick construction technology, comprising the following steps:
Step a. handles the surface of foundation wall: removing the dirt on foundation wall surface, and the repairing of the surface of foundation wall is smooth;
Step b. brushes SKK lattice seam paint: brushing SKK lattice seam paint on the surface of foundation wall as priming paint, guarantees priming paint during brush Brush is uniform;
Step c. pastes U.S. line paper: it is anticipated that is obtained criticizes the shape for scraping brick, pasting beauty in the suitable position in foundation wall surface Line paper;
Step d. crowd, which is applied, batch scrapes brick coating: batch will scrape brick and apply charge and carry out bottoming construction on foundation wall;
Step e. makes scratch: batch scrape brick coating surface it is dry before, to batch being coated in batch scraping brick coating and carry out scratch on foundation wall Production makes batch surface irregularity for scraping brick coating, shows three-dimensional effect;
Step f. removes U.S. line paper: the U.S. line paper of stickup being taken off, the position after taking off just forms lattice seam;
Step g. repairs lattice seam: relatively rough by taking the lattice seam that U.S. line paper is formed off, construction personnel's plaid matching seam is repaired, and is done Landscaping treatment;
Step h. smears finishing coat: after the completion of repairing lattice seam, batch scrape brick coating surface do after 24 hours to entire batch scrape brick face into Row smears finishing coat.
For better effect, in the step a, smooth repairing to the surface of foundation wall makes the smooth of foundation wall surface Deviation control is spent within 1.5mm.
For better effect, in the step b, used priming paint SKK lattice seam paint, the use of SKK lattice seam paint Strengthen the basal plane adhesive force of thicker coating, and there is preferable weatherability and anti-ultraviolet ability, can directly expose Outside, when throwing off U.S. line paper makes the seam paint exposure of SKK lattice, do not have to brushing finish paint again at lattice seam, reduce working procedure, and brush Two layers, first layer transverse direction brush, the second layer is vertically brushed.
For better effect, in the step d, it is that brick coating is scraped in SKK calcining batch that used batch, which is scraped brick coating, should SKK calcining batch scrape brick coating by 900 DEG C high-temperature calcination, pickling can effectively remove mineral oxide ingredient and ferrous components, make It is less prone to rusty stain, permanent to keep true stone damp, colour-fast.
For better effect, in the step h, used finishing coat is SKK ultra-low contamination protective topcoat, the SKK Ultra-low contamination protective topcoat has low electric charge, is capable of forming with hydrophilic fine and close film, effectively dirt is inhibited to rest on It cleans above and more easily, can make batch to scrape brick more beautiful.
For better effect, described step e, f and g batch scrape brick coating it is dry before operated, avoid batch scraping brick One piece of related surrounding falls off when taking off U.S. line paper after coating surface is dry.
For better effect, in the step h, finishing coat is applied two layers, and two layers of finishing coat, which is increased, scrapes brick to criticizing after finishing coat Protection.
The present invention is in use, uniformly brushes SKK lattice seam paint on the foundation wall surface of smooth completion first as priming paint, to wall The alkalinity of body is closed, and film is tentatively made, and avoids the mutual shadow of material and wall different in the alkalinity and subsequent technique of wall It rings, forms a connecting link simultaneously, improve the adhesive force of finishing coat;Paint the U.S. line paper of stickup in SKK lattice seam, it is anticipated that lines paste, Directly U.S. line paper is torn after batch scraping brick coating material, is formed preliminary lattice seam, enhanced convenience;It stitches and paints in SKK lattice Brick coating is scraped in upper batch of painting batch, and is made to criticize by special tool(s) and scraped brick coating surface with stereoscopic effect, then passes through the U.S. line paper of removing It directly obtains criticizing for required shape and scrapes brick;By batch scraping brick coating surface brushing finish paint, brick coating is scraped to batch and is protected, is prolonged It is long to use the time;The present invention has the modelling effect that can be produced better than ceramic tile, meets people and dotes on ceramic tile, together The exclusive feature of Shi Yongyou coating itself avoids ceramic tile and falls off institute's band while guaranteeing that high-quality and perfect effect show The advantages of hidden danger come.

Claims (8)

1. batch scraping brick construction technology, it is characterised in that: the following steps are included:
Step a. handles the surface of foundation wall: removing the dirt on foundation wall surface, and the repairing of the surface of foundation wall is smooth;
Step b. brushes SKK lattice seam paint: brushing SKK lattice seam paint on the surface of foundation wall as priming paint, guarantees priming paint during brush Brush is uniform;
Step c. pastes U.S. line paper: it is anticipated that is obtained criticizes the shape for scraping brick, pasting beauty in the suitable position in foundation wall surface Line paper;
Step d. crowd, which is applied, batch scrapes brick coating: batch will scrape brick and apply charge and carry out bottoming construction on foundation wall;
Step e. makes scratch: batch scrape brick coating surface it is dry before, to batch being coated in batch scraping brick coating and carry out scratch on foundation wall Production makes batch surface irregularity for scraping brick coating, shows three-dimensional effect;
Step f. removes U.S. line paper: the U.S. line paper of stickup being taken off, the position after taking off just forms lattice seam;
Step g. repairs lattice seam: relatively rough by taking the lattice seam that U.S. line paper is formed off, construction personnel's plaid matching seam is repaired, and is done Landscaping treatment;
Step h. smears finishing coat: after the completion of repairing lattice seam, batch scrape brick coating surface do after 24 hours to entire batch scrape brick face into Row smears finishing coat.
2. as described in claim 1 batch is scraped brick construction technology, it is characterised in that: in the step a, to the surface of foundation wall Smooth repairing controls the flatness deviation on foundation wall surface within 1.5mm.
3. as described in claim 1 batch is scraped brick construction technology, it is characterised in that: in the step b, used as priming paint SKK lattice stitch two layers of painting brush, and first layer transverse direction brush, the second layer is vertically brushed.
4. as described in claim 1 batch is scraped brick construction technology, it is characterised in that: in the step d, used batch is scraped brick Coating is that brick coating is scraped in SKK calcining batch.
5. as described in claim 1 batch is scraped brick construction technology, it is characterised in that: in the step d, brick coating is scraped in batch painting batch Primary batch is painted, batch apply with a thickness of 3mm.
6. as described in claim 1 batch is scraped brick construction technology, it is characterised in that: in the step h, used finishing coat is SKK ultra-low contamination protective topcoat.
7. as described in claim 1 batch is scraped brick construction technology, it is characterised in that: described step e, f and the g batch is scraping brick coating It is operated before dry.
8. as described in claim 1 batch is scraped brick construction technology, it is characterised in that: in the step h, finishing coat is applied two layers.
CN201910384844.3A 2019-05-09 2019-05-09 It criticizes and scrapes brick construction technology Pending CN110453860A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910384844.3A CN110453860A (en) 2019-05-09 2019-05-09 It criticizes and scrapes brick construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910384844.3A CN110453860A (en) 2019-05-09 2019-05-09 It criticizes and scrapes brick construction technology

Publications (1)

Publication Number Publication Date
CN110453860A true CN110453860A (en) 2019-11-15

Family

ID=68480941

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910384844.3A Pending CN110453860A (en) 2019-05-09 2019-05-09 It criticizes and scrapes brick construction technology

Country Status (1)

Country Link
CN (1) CN110453860A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114135073A (en) * 2021-12-31 2022-03-04 浙江久石工研建材科技有限公司 Flexible patch stone construction process

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101319552A (en) * 2008-07-23 2008-12-10 勾希杰 Construction method of ture mineral varnish face brick-imitation construction exterior wall
CN102206447A (en) * 2011-05-16 2011-10-05 西南科技大学 Method for preparing glimmerite sheet type granite-imitated lacquer coating
JP2014001616A (en) * 2012-05-21 2014-01-09 Aica Kogyo Co Ltd Wall surface finishing method
CN103819147A (en) * 2014-01-13 2014-05-28 福建皓尔宝新材料科技有限公司 Archaistic and distressed texture coating method for diatom ooze coating
CN104386950A (en) * 2014-10-29 2015-03-04 锦宸集团有限公司 Exterior wall brick-imitating elastic texture coating and application process thereof
CN104775575A (en) * 2015-02-13 2015-07-15 中冶建工集团有限公司 Real stone paint construction process
CN104876469A (en) * 2015-05-08 2015-09-02 上海贝塔建筑科技有限公司 Imitation stone paint for preparing imitation sandstone and construction technology of imitation stone paint

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101319552A (en) * 2008-07-23 2008-12-10 勾希杰 Construction method of ture mineral varnish face brick-imitation construction exterior wall
CN102206447A (en) * 2011-05-16 2011-10-05 西南科技大学 Method for preparing glimmerite sheet type granite-imitated lacquer coating
JP2014001616A (en) * 2012-05-21 2014-01-09 Aica Kogyo Co Ltd Wall surface finishing method
CN103819147A (en) * 2014-01-13 2014-05-28 福建皓尔宝新材料科技有限公司 Archaistic and distressed texture coating method for diatom ooze coating
CN104386950A (en) * 2014-10-29 2015-03-04 锦宸集团有限公司 Exterior wall brick-imitating elastic texture coating and application process thereof
CN104775575A (en) * 2015-02-13 2015-07-15 中冶建工集团有限公司 Real stone paint construction process
CN104876469A (en) * 2015-05-08 2015-09-02 上海贝塔建筑科技有限公司 Imitation stone paint for preparing imitation sandstone and construction technology of imitation stone paint

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114135073A (en) * 2021-12-31 2022-03-04 浙江久石工研建材科技有限公司 Flexible patch stone construction process

Similar Documents

Publication Publication Date Title
CN102518271B (en) Coating construction method of faux stones
CN104775575B (en) Real stone paint construction process
CN109025356A (en) A kind of exterior wall retrofit coating process
CN102294322A (en) Method for painting paint face of piano
CN101168988A (en) Construction method for water-based texture wallpaper paint and special-purpose tool for the same
CN109424135A (en) The technique that the putty of metope in building is coated
CN106592899A (en) Construction method of inner wall
CN106760285A (en) The technique coated to indoor wall using putty in furniture factory building
CN104110112B (en) Building wall decoration mortar construction technology
CN104449169A (en) Preparation method of natural slice paint
CN102358099A (en) Processing method of surface-engraved multicolor aluminum profile
CN107989299A (en) A kind of coating application method of Assembled wall panels
CN110453860A (en) It criticizes and scrapes brick construction technology
CN105298045A (en) Interior wall diatom mud coating and coating method
CN108797921A (en) A kind of wall covering construction method of stereo imitating wall brick
CN107574994A (en) White stone material splicing process
CN111364711A (en) Coating structure with imitated marble texture and manufacturing method
JP2013104230A (en) Film laminate
JP2003172009A (en) Wall facing construction method
CN107620434A (en) The technique coated in furniture factory building using putty to indoor wall
CN209837755U (en) Antique structure of wall surface painted with cobblestones on outer wall of historical building
CN209837754U (en) Antique structure of wall surface painted by water brushing stone on outer wall of historical building
CN108407537A (en) A kind of construction method of ink process wall
CN209837528U (en) Old-making structure for brushing and pressing hair on wall surface of external wall of historical building
CN111921823A (en) UV coating construction process for elastic semi-open matte surface of veneer for cladding strip

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination