CN109424135A - The technique that the putty of metope in building is coated - Google Patents

The technique that the putty of metope in building is coated Download PDF

Info

Publication number
CN109424135A
CN109424135A CN201710788981.4A CN201710788981A CN109424135A CN 109424135 A CN109424135 A CN 109424135A CN 201710788981 A CN201710788981 A CN 201710788981A CN 109424135 A CN109424135 A CN 109424135A
Authority
CN
China
Prior art keywords
putty
coating
metope
smooth
brush
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710788981.4A
Other languages
Chinese (zh)
Inventor
吴洋忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Meiji Real Estate Marketing Planning Co Ltd
Original Assignee
Chengdu Meiji Real Estate Marketing Planning Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Meiji Real Estate Marketing Planning Co Ltd filed Critical Chengdu Meiji Real Estate Marketing Planning Co Ltd
Priority to CN201710788981.4A priority Critical patent/CN109424135A/en
Publication of CN109424135A publication Critical patent/CN109424135A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/02Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/02Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster
    • E04F13/04Bases for plaster

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Coating Apparatus (AREA)

Abstract

The invention discloses the techniques that the putty of metope in a kind of pair of building is coated, comprising the following steps: base treatment repairs, scrapes first pass putty and polish, scrape second time putty and polish, under-coating varnish, mend putty again, polish, second coating, polish, third road coating.The step of technique, is simple, shortens construction period, has standardized operation, it can be improved the flatness of metope, resource has been saved, has solved existing putty coating processes low efficiency, has been constructed according to the experience of worker oneself, the experience of each worker is different, it causes quality different, so that the flatness of metope is affected, causes to do over again, waste of resource, the problem of extending the duration.

Description

The technique that the putty of metope in building is coated
Technical field
The present invention relates to a kind of technique, the technique coated more particularly, to the putty of metope in a kind of pair of building.
Background technique
Powder of lacquer putty for use on is one kind of building decoration materials, and main component is talcum powder and glue.The rough house table just purchased One layer of white --- the putty in face, the whiteness of usual putty is in 90 or more fineness 330 or more.Putty is looked for for wall-surface patching A kind of flat substrate is laid a good foundation for decoration in next step (brush paint wallpaper).Putty is divided into interior wall and two kinds of exterior wall, Exterior wall putty to resist exposing to the weather so colloidality is big, intensity is high, and environmentally friendly index is slightly lower.Inner wall putty composite index is preferable, is good for Kang Huanbao, so interior wall not external application, exterior wall is not interior to be used.Usual putty is gypsum or cement base, and such rough surface compares It is secured to be easy bonding.But a bed boundary Ji Lai sealing base is still brushed in base when construction while improving wall Putty can be preferably bonded on basal plane for the adhesive force in face.Putty (fillering) is a kind of decoration type of smooth surface of wall Material is a kind of thick slurry coating material, is essential a kind of product before coating paints.Painting is imposed on priming paint or is directly applied and imposes on On object, to remove rugged defect on coated article surface.Using a small amount of Qi Ji, auxiliary agent, mass filler and suitable Coloring pigment is formulated, and pigment used is mainly iron oxide red, carbon black, chrome yellow etc..Filler is mainly calcium bicarbonate, talcum powder etc.. The working surface that there is recess in part can be filled up, can also be struck off in all surfaces, usually after prime coat parches, be applied over priming paint Layer surface.It is required that adhesion is good, does not crack in baking process.Existing putty coating processes low efficiency is all according to work The experience of people oneself is constructed, and the experience of each worker is different, causes quality different, so that the flatness of metope is by shadow It rings, causes to do over again, waste of resource extends the duration.
Summary of the invention
It is all the experience according to worker oneself it is an object of the invention to overcome above-mentioned existing putty coating processes low efficiency It constructs, the experience of each worker is different, and it causes quality different, so that the flatness of metope is affected, causes to do over again, wave The problem of taking resource, extending the duration technique that the putty of metope in a kind of pair of building is coated is devised, the technique Step is simple, shortens construction period, has standardized operation, can be improved the flatness of metope, has saved resource, solves existing Putty coating processes low efficiency is constructed according to the experience of worker oneself, and the experience of each worker is different, causes quality The problem of difference causes to do over again so that the flatness of metope is affected, waste of resource, extends the duration.
The purpose of the invention is achieved by the following technical solution: the technique coated to the putty of metope in building, The following steps are included:
(1) base treatment: chipping is removed at peeling, loosening and bulge position in wall basic level, by the dust in base, dirt The sundries such as dirt, splash and mortar current mark clean up, and the iron wire steel bar end of surface of wall is polished, the processing of outside brush antirust paint;
(2) repair: with water gypsum, by the hole collided in the bases such as metope, recessed, gap etc. is levelling respectively, with No. 1 after drying Sand paper polishes protrusion, and will drift along etc. and to clean out;
(3) it scrapes first pass putty and polishes: after the biggish gap of coating surface fills up smooth, completely scraping cream using batch embedding tool Glue putty one time, all small sand holes and contraction fissure are both needed to completely scrape, with the neat degree of being of closely knit, smooth, line angle seamed edge, meanwhile, It answers one to scrape down one to scrape along metope is horizontal with scraping, scrapes thin thickness 1-2mm as far as possible, must not leak and scrape, connector must not stay raft, be careful not to flaw Dirty door and window and other object planes after putty parches, wrap up in smooth small plank with No. 1 sand paper, and putty slag and the place of being uneven are polished It is smooth, pay attention to firmly uniform, protection corner angle, is criticized clearly with palm broom completely after mill, first pass is laterally completely scraped with scraper plate, and a scraper plate connects One scraper plate, connector must not stay raft, and each scraper plate wants agile when finally receiving head;
(4) scrape second time putty and polish: second time full putty method requires this all over putty with before to head time putty To smear direction orthogonal all over scraping, i.e., should scrape along metope is perpendicular, metope is further scraped it is full and polish flat it is smooth, smooth until, It is vertically completely scraped with scraper plate for second time, a scraper plate connects a scraper plate, and connector must not stay raft, and each scraper plate wants agile when finally receiving head;
(5) under-coating varnish: must clean up substrate surface before first pass coating application, clean floating ash, brush appropriate to the occasion use Spread pen, brushing sequence are usually from top to bottom, from left to right, to erect after first horizontal, first sideline, corner angle, facet, rear big face, at inner corner trim Must not have residual coating, rib must not be wrapped up at external corner, as wall once brush cannot from it is upper on earth when, should at many levels up and down simultaneously operation, Work in coordination cooperation, avoid connecing raft, brush overlapping phenomenon, independent face it is every all over application with a collection of coating, and once complete;
(6) mend putty again: after first pass coating parches, answering general inspection one time, such as it is defective should locally answer coating material it is greasy Son one time, and scraped and smeared with ox horn, in order to avoid damage coating paint film;
(7) polish: mended after putty parches again, coated surface polished using fine sandpaper smooth, pays attention to exerting oneself to answer it is light and even, and Must not worn out paint film, surface is cleaned up after mill;
(8) second coating: must clean up substrate surface before first pass coating application, clean floating ash, when brushing Spread pen is preferably used, brushing sequence is usually from top to bottom, from left to right, to erect after first horizontal, first sideline, corner angle, facet, rear big face, yin Must not have residual coating at angle, rib must not be wrapped up at external corner, as wall once brush cannot from it is upper on earth when, should make simultaneously up and down at many levels Industry, cooperation of working in coordination avoid connecing raft, brush overlapping phenomenon, and independent face is every all over the same a collection of coating of application, and once completes;
(9) polish: mended after putty parches again, coated surface polished using fine sandpaper smooth, pays attention to exerting oneself to answer it is light and even, and Must not worn out paint film, surface is cleaned up after mill;
(10) third road coating: for third all over coating using spraying, spray gun uses No. 1 spray gun, and spray gun pressure adjusts 0.3- 0.5N/mm2At an angle of 90 degrees, distance is advisable for 40-50cm for nozzle and facing, and when spraying answers specking uniform, and moving distance is all suitable In, when spraying generally since inconspicuous one, gradually moved in proper order to other end, it, must not until unobtrusively brush is received at place Appearance connects raft, after, whole surface is bright and clean consistent, round and smooth exquisiteness, no stream pendant film color phenomenon, when spraying, by metope it is all its Its facing all covered with newspaper it is tight, in order to avoid pollute, before swabbing should by substrate surface dust, dirt, splash and smear Clean, the coating of extemporaneous preparation is removed with mortar current mark, it is necessary to bonding agent is mixed, coating thickness is uniform, and it is flat and smooth, it does not flow It hangs, bottom drain, third time do not scrape spot putting after metope strikes off light drying with scraper plate and polish polishing with fine sandpaper, be careful not to Leakage mill or putty is worn out, brush emulsion paint three times.
In conclusion shortening construction period, having standardized behaviour the beneficial effects of the present invention are: the step of technique is simple Make, can be improved the flatness of metope, saved resource, solve existing putty coating processes low efficiency, be all according to worker The experience of oneself is constructed, and the experience of each worker is different, and it is different to cause quality, so that the flatness of metope is affected, It causes to do over again, waste of resource, the problem of extending the duration.
Specific embodiment
Below with reference to embodiment, the present invention is described in further detail, but embodiments of the present invention are not limited only to This.
Embodiment:
The technique that the putty of metope in building is coated, comprising the following steps:
(1) base treatment: chipping is removed at peeling, loosening and bulge position in wall basic level, by the dust in base, dirt The sundries such as dirt, splash and mortar current mark clean up, and the iron wire steel bar end of surface of wall is polished, the processing of outside brush antirust paint;
(2) repair: with water gypsum, by the hole collided in the bases such as metope, recessed, gap etc. is levelling respectively, with No. 1 after drying Sand paper polishes protrusion, and will drift along etc. and to clean out;
(3) it scrapes first pass putty and polishes: after the biggish gap of coating surface fills up smooth, completely scraping cream using batch embedding tool Glue putty one time, all small sand holes and contraction fissure are both needed to completely scrape, with the neat degree of being of closely knit, smooth, line angle seamed edge, meanwhile, It answers one to scrape down one to scrape along metope is horizontal with scraping, scrapes thin thickness 1-2mm as far as possible, must not leak and scrape, connector must not stay raft, be careful not to flaw Dirty door and window and other object planes after putty parches, wrap up in smooth small plank with No. 1 sand paper, and putty slag and the place of being uneven are polished It is smooth, pay attention to firmly uniform, protection corner angle, is criticized clearly with palm broom completely after mill, first pass is laterally completely scraped with scraper plate, and a scraper plate connects One scraper plate, connector must not stay raft, and each scraper plate wants agile when finally receiving head;
(4) scrape second time putty and polish: second time full putty method requires this all over putty with before to head time putty To smear direction orthogonal all over scraping, i.e., should scrape along metope is perpendicular, metope is further scraped it is full and polish flat it is smooth, smooth until, It is vertically completely scraped with scraper plate for second time, a scraper plate connects a scraper plate, and connector must not stay raft, and each scraper plate wants agile when finally receiving head;
(5) under-coating varnish: must clean up substrate surface before first pass coating application, clean floating ash, brush appropriate to the occasion use Spread pen, brushing sequence are usually from top to bottom, from left to right, to erect after first horizontal, first sideline, corner angle, facet, rear big face, at inner corner trim Must not have residual coating, rib must not be wrapped up at external corner, as wall once brush cannot from it is upper on earth when, should at many levels up and down simultaneously operation, Work in coordination cooperation, avoid connecing raft, brush overlapping phenomenon, independent face it is every all over application with a collection of coating, and once complete;
(6) mend putty again: after first pass coating parches, answering general inspection one time, such as it is defective should locally answer coating material it is greasy Son one time, and scraped and smeared with ox horn, in order to avoid damage coating paint film;
(7) polish: mended after putty parches again, coated surface polished using fine sandpaper smooth, pays attention to exerting oneself to answer it is light and even, and Must not worn out paint film, surface is cleaned up after mill;
(8) second coating: must clean up substrate surface before first pass coating application, clean floating ash, when brushing Spread pen is preferably used, brushing sequence is usually from top to bottom, from left to right, to erect after first horizontal, first sideline, corner angle, facet, rear big face, yin Must not have residual coating at angle, rib must not be wrapped up at external corner, as wall once brush cannot from it is upper on earth when, should make simultaneously up and down at many levels Industry, cooperation of working in coordination avoid connecing raft, brush overlapping phenomenon, and independent face is every all over the same a collection of coating of application, and once completes;
(9) polish: mended after putty parches again, coated surface polished using fine sandpaper smooth, pays attention to exerting oneself to answer it is light and even, and Must not worn out paint film, surface is cleaned up after mill;
(10) third road coating: for third all over coating using spraying, spray gun uses No. 1 spray gun, and spray gun pressure adjusts 0.3- 0.5N/mm2At an angle of 90 degrees, distance is advisable for 40-50cm for nozzle and facing, and when spraying answers specking uniform, and moving distance is all suitable In, when spraying generally since inconspicuous one, gradually moved in proper order to other end, it, must not until unobtrusively brush is received at place Appearance connects raft, after, whole surface is bright and clean consistent, round and smooth exquisiteness, no stream pendant film color phenomenon, when spraying, by metope it is all its Its facing all covered with newspaper it is tight, in order to avoid pollute, before swabbing should by substrate surface dust, dirt, splash and smear Clean, the coating of extemporaneous preparation is removed with mortar current mark, it is necessary to bonding agent is mixed, coating thickness is uniform, and it is flat and smooth, it does not flow It hangs, bottom drain, third time do not scrape spot putting after metope strikes off light drying with scraper plate and polish polishing with fine sandpaper, be careful not to Leakage mill or putty is worn out, brush emulsion paint three times.
The step of technique, is simple, shortens construction period, has standardized operation, can be improved the flatness of metope, saves Resource, solves existing putty coating processes low efficiency, is constructed according to the experience of worker oneself, each worker's Experience is different, causes quality different, so that the flatness of metope is affected, causes to do over again, waste of resource extends the duration Problem.
The above is only presently preferred embodiments of the present invention, not does limitation in any form to the present invention, it is all according to According to technology of the invention, method any simple modification substantially to the above embodiments, equivalent variations, the present invention is each fallen within Protection scope within.

Claims (1)

1. the technique that the putty of metope is coated in pair building, which comprises the following steps:
(1) base treatment: removing chipping for peeling in wall basic level, loosening and bulge position, by base dust, dirt, The sundries such as splash and mortar current mark clean up, and the iron wire steel bar end of surface of wall is polished, the processing of outside brush antirust paint;
(2) repair: with water gypsum, by the hole collided in the bases such as metope, recessed, gap etc. is levelling respectively, with No. 1 sand paper after drying Protrusion is polished, and will be drifted along etc. and cleaned out;
(3) it scrapes first pass putty and polishes: after the biggish gap of coating surface fills up smooth, it is greasy completely to scrape latex using batch embedding tool Son one time, all small sand holes and contraction fissure are both needed to completely scrape, with the neat degree of being of closely knit, smooth, line angle seamed edge, meanwhile, Ying Yi It scrapes down one to scrape along metope is horizontal with scraping, scrapes thin thickness 1-2mm as far as possible, must not leak and scrape, connector must not stay raft, be careful not to stain door Window and other object planes after putty parches, wrap up in smooth small plank with No. 1 sand paper, putty slag and the place of being uneven are polished flat, Pay attention to firmly uniform, protection corner angle, is criticized clearly with palm broom completely after mill, first pass is laterally completely scraped with scraper plate, and a scraper plate connects one and scrapes Plate, connector must not stay raft, and each scraper plate wants agile when finally receiving head;
(4) scrape second time putty and polish: second time full putty method requires this to scrape all over putty with preceding time to head time putty It is orthogonal to smear direction, i.e., should be scraped along metope is perpendicular, metope is further scraped it is full and polish flat it is smooth, smooth until, second All over vertically completely being scraped with scraper plate, a scraper plate connects a scraper plate, and connector must not stay raft, and each scraper plate wants agile when finally receiving head;
(5) under-coating varnish: must clean up substrate surface before first pass coating application, clean floating ash, brush appropriate to the occasion spread pen, Brushing sequence is usually from top to bottom, from left to right, to erect after first horizontal, first sideline, corner angle, facet, rear big face, must not have at inner corner trim Residual coating must not wrap up in rib at external corner, as wall once brush cannot from it is upper on earth when, should operation simultaneously up and down at many levels, mutually match Cooperation is closed, avoids connecing raft, brush overlapping phenomenon, every time application of independent face is once completed with a collection of coating;
(6) putty is mended again: after first pass coating parches, being answered general inspection one time, should locally mend paint render one again Ru defective Time, and scraped and smeared with ox horn, in order to avoid damage coating paint film;
(7) polish: mended after putty parches again, coated surface polished using fine sandpaper smooth, pays attention to exerting oneself to answer it is light and even, and must not Worn out paint film cleans up surface after mill;
(8) second coating: must clean up substrate surface before first pass coating application, clean floating ash, brush appropriate to the occasion use Spread pen, brushing sequence are usually from top to bottom, from left to right, to erect after first horizontal, first sideline, corner angle, facet, rear big face, at inner corner trim Must not have residual coating, rib must not be wrapped up at external corner, as wall once brush cannot from it is upper on earth when, should at many levels up and down simultaneously operation, Work in coordination cooperation, avoid connecing raft, brush overlapping phenomenon, independent face it is every all over application with a collection of coating, and once complete;
(9) polish: mended after putty parches again, coated surface polished using fine sandpaper smooth, pays attention to exerting oneself to answer it is light and even, and must not Worn out paint film cleans up surface after mill;
(10) third road coating: for third all over coating using spraying, spray gun uses No. 1 spray gun, and spray gun pressure adjusts 0.3-0.5N/mm2 At an angle of 90 degrees, distance is advisable for 40-50cm for nozzle and facing, and when spraying answers specking uniform, and moving distance is all moderate, when spraying Generally since inconspicuous one, gradually moved in proper order to other end, until unobtrusively brush is received at place, there is not allowed that raft is connect, After, whole surface is bright and clean consistent, round and smooth exquisiteness, no stream pendant film color phenomenon, when spraying, all other facing of metope is complete Portion's newspaper cover it is tight, in order to avoid pollute, before swabbing should by substrate surface dust, dirt, splash and smear and mortar current mark Remove clean, the coating of extemporaneous preparation, it is necessary to bonding agent is mixed, coating thickness is uniform, flat and smooth, not sagging, non-bottom drain, the Scrape spot putting with scraper plate three times, metope strike off light it is dry after, polish polishing with fine sandpaper, be careful not to leakage and grind or by putty It is worn out, brush emulsion paint three times.
CN201710788981.4A 2017-09-05 2017-09-05 The technique that the putty of metope in building is coated Withdrawn CN109424135A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710788981.4A CN109424135A (en) 2017-09-05 2017-09-05 The technique that the putty of metope in building is coated

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710788981.4A CN109424135A (en) 2017-09-05 2017-09-05 The technique that the putty of metope in building is coated

Publications (1)

Publication Number Publication Date
CN109424135A true CN109424135A (en) 2019-03-05

Family

ID=65513949

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710788981.4A Withdrawn CN109424135A (en) 2017-09-05 2017-09-05 The technique that the putty of metope in building is coated

Country Status (1)

Country Link
CN (1) CN109424135A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111691620A (en) * 2020-05-27 2020-09-22 浙江新中源建设有限公司 Green and environment-friendly indoor wall surface decoration method
CN112065087A (en) * 2020-08-01 2020-12-11 秋尊(上海)设计装饰工程有限公司 Indoor wall surface renovation decoration process
CN112247710A (en) * 2020-10-26 2021-01-22 张杰华 Wall surface polishing and painting method
CN113323439A (en) * 2021-06-09 2021-08-31 湖北恒沁环保科技有限责任公司 Matched repair process for wall surface alkali removal
CN114352055A (en) * 2021-12-23 2022-04-15 上海建工集团股份有限公司 Construction process for renovating paint on old wall
CN115110720A (en) * 2021-03-23 2022-09-27 广东博智林机器人有限公司 Putty construction method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111691620A (en) * 2020-05-27 2020-09-22 浙江新中源建设有限公司 Green and environment-friendly indoor wall surface decoration method
CN112065087A (en) * 2020-08-01 2020-12-11 秋尊(上海)设计装饰工程有限公司 Indoor wall surface renovation decoration process
CN112247710A (en) * 2020-10-26 2021-01-22 张杰华 Wall surface polishing and painting method
CN115110720A (en) * 2021-03-23 2022-09-27 广东博智林机器人有限公司 Putty construction method
CN113323439A (en) * 2021-06-09 2021-08-31 湖北恒沁环保科技有限责任公司 Matched repair process for wall surface alkali removal
CN114352055A (en) * 2021-12-23 2022-04-15 上海建工集团股份有限公司 Construction process for renovating paint on old wall

Similar Documents

Publication Publication Date Title
CN109424135A (en) The technique that the putty of metope in building is coated
CN106760285A (en) The technique coated to indoor wall using putty in furniture factory building
CN109267709B (en) Deformation joint anti-leakage structure and repairing method thereof
CN107044196A (en) A kind of concrete is plastered face emulsion paint brushing technique
CN101832015B (en) Construction process for outer wall metal fluorocarbon coating
CN102518271A (en) Coating construction method of faux stones
CN109098370A (en) A kind of construction techniques
CN101864843B (en) Method for repairing floriation and linellae of granitic plaster on historical building
CN101956463B (en) GRC (Glass-fiber Reinforced Composite) plate surface plain finish concrete coating technology
CN106592898A (en) Construction method of inner wall putty
CN107989299A (en) A kind of coating application method of Assembled wall panels
CN106592899A (en) Construction method of inner wall
CN109797920A (en) A kind of interior covering with paint construction method
CN103691653A (en) Coach surface smearing and scraping method
CN102744190A (en) Coating method for imitating marble effect
CN107620434A (en) The technique coated in furniture factory building using putty to indoor wall
CN107386681A (en) Puttying and the construction technology of brush emulsion paint
CN110359651A (en) A kind of metope brushing latex lacquer craftwork
CN104453131A (en) Building external wall heat insulation coating construction process
CN104453133A (en) Real stone paint construction technology
CN109555316A (en) Environment protection architecture construction method
CN106401145A (en) Construction technology of ground glue
CN114352055A (en) Construction process for renovating paint on old wall
CN109610833B (en) Construction technology of building coating
CN105598011A (en) Method for rapidly repairing defect on outer surface of automobile through weathered stone

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20190305

WW01 Invention patent application withdrawn after publication