CN110424274A - 先简支后连续pc轨道梁的施工方法 - Google Patents
先简支后连续pc轨道梁的施工方法 Download PDFInfo
- Publication number
- CN110424274A CN110424274A CN201910819386.1A CN201910819386A CN110424274A CN 110424274 A CN110424274 A CN 110424274A CN 201910819386 A CN201910819386 A CN 201910819386A CN 110424274 A CN110424274 A CN 110424274A
- Authority
- CN
- China
- Prior art keywords
- track girder
- track
- pier
- construction
- cast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
- E01D2101/28—Concrete reinforced prestressed
- E01D2101/285—Composite prestressed concrete-metal
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明涉及先简支后连续PC轨道梁的施工方法,包括以下步骤:第一步,预制PC轨道梁和下部结构施工;第二步,测量放样;第三步,轨道梁架设;第四步,轨道梁精调;第五步,对应中墩现浇段施工;第六步,对应边墩现浇段施工。本发明构成的连续PC轨道梁整体性好,伸缩缝少,受力性能好,刚度大,超载能力强,安全度高,结构简单,节省材料。
Description
技术领域
本发明涉及轨道交通,具体涉及先简支后连续PC轨道梁的施工方法,特别涉及在跨座式单轨交通中先简支后连续的结构形式的PC轨道的施工方法。
背景技术
跨座式单轨交通具有爬坡能力强、转弯半径小;节约城市用地,充分利用城市有限空间;噪音低、乘坐舒适;城市景观性好等优点,在二、三线城市具有非常大的发展空间。
目前,跨座式单轨交通线路,主要为简支PC轨道梁结构形式。由于跨座式单轨交通的特点,轨道梁不仅是承重结构,同时也是轨道结构,因此PC轨道梁在制造和架设过程中按线路的平、纵、竖曲线及横向设计要求形成轨道线形,另外梁端还要预设如指形板座、接触轨等预埋件及组配件。然而,早期建设运营的跨座式单轨交通线路,由于简支梁一经固结后形成连续结构后,无法进行二次线形调整。因此,对从轨道梁预制→架设→精密调整定位→固结体系转换等阶段是一个不断研究总结的过程。
CN 1514066 公开的“一种轻轨交通PC轨道梁运架的设备及施工方法”,主要应用于城市交通轻轨系统建设中PC轨道梁的运输及架设。设备由架桥机、运梁车组成。架桥机由车体、拖拉机构、转向架、2号柱、吊梁小车、0号柱等组成。运梁车由托梁小车、车体、拖梁机构等组成。施工方法是先将PC轨道梁运至运梁基地,将PC轨道梁固定在运梁车的拖梁小车上,运梁车将PC轨道梁运到架桥施工点,运梁车与架桥机对接,PC轨道梁从运梁车拖至架桥机上的吊梁位置,架桥部分实施架桥。其能满足各种地形的PC轨道梁运架施工,包括隧道及车站内、山地、高架桥上的施工;不影响既有交通,无需拆迁;环保性能好,施工方便且费用低,施工效率高。毫无疑问,这是所属技术领域的一种有益的探索。
发明目的
本发明的目的是提供一种先简支后连续PC轨道梁的施工方法,其构成的连续PC轨道梁整体性好,伸缩缝少,受力性能好,刚度大,超载能力强,安全度高,结构简单,节省材料。
单片连续刚构PC轨道梁的标准梁长有20m、25m、30m等,一般采用3×30m形式为一联,梁体为实心矩形截面,跨中梁高1.6m,支点梁高2.2m,梁宽0.69m,30m单片PC轨道梁重量约84t。轻轨车辆直接在PC轨道梁上运行,轻轨交通轨道梁为单线梁,线路的平、纵、竖曲线以及横向超高都直接在轨道梁线形上实现。
本发明所述的先简支后连续PC轨道梁的施工方法,其特征包括以下步骤:
第一步,预制PC轨道梁和下部结构施工;
PC轨道梁统一在梁场制作,下部结构为边墩和中墩,在轨道线路沿途浇筑;PC轨道梁验收合格后,用运梁车运至已完成的下部结构施工现场;
第二步,测量放样;
测量人员在边墩和中墩的盖梁顶临时支撑上放样出轨道梁的中心线、端部位置及高程;
第三步,轨道梁架设;
采用汽车吊双机抬吊,将PC轨道梁按照测量放样点初步放置在盖梁顶临时支撑上,然后用连接丝杠固定;
第四步,轨道梁精调;
完成一联轨道梁架设任务后,将连接丝杠适当调松,利用PC轨道梁两端调整支撑上放置的液压三维千斤顶对PC轨道梁进行支撑,并使用钢垫块及丝杠,配合测量人员对PC轨道梁的纵横向偏位和倾角进行调整;精调完成后,再以一联轨道梁为整体进行联调;
第五步,对应中墩现浇段施工;
精调完成后,将临时支撑及钢垫块焊接固定;绑扎中墩钢筋及预应力施工操作,浇筑对应中墩现浇段混凝土;强度达到设计要求后,张拉并锚固纵向一联轨道梁钢束,再张拉并锚固中墩盖梁钢束,浇筑封端混凝土;
第六步,对应边墩现浇段施工;
绑扎边墩钢筋、指形板预埋施作,浇筑对应边墩现浇段混凝土;强度达到设计要求后,张拉并锚固边墩盖梁钢束,浇筑封端混凝土。
本发明的有益效果:
本发明集合了连续梁和简支梁两种结构的优点:先简支后连续梁受力性能好,整体性好,超载能力强,安全度高,结构简单,节省材料。本方法操作简单,在保证施工质量安全的基础上,保证稳定的施工效率,取得了良好的社会效益。
附图说明
图1是架梁准备示意图;
图2是轨道梁架设示意图;
图3是轨道梁精调示意图;
图4是轨道梁线形调整示意图之一;
图5是轨道梁线形调整示意图之二;
图6是对应中墩现浇段浇筑示意图;
图7对应边墩现浇段浇筑示意图。
图中:1—PC轨道梁;
2—边墩,12—对应边墩现浇段;
3—中墩,13—对应中墩现浇段;
4—盖梁顶临时支撑,5—运梁车,6—汽车吊,7—连接丝杠,8—调整支撑,9—液压三维千斤顶。
具体实施方式
下面结合附图对本发明作进一步的说明。
所述的先简支后连续PC轨道梁的施工方法,其特征是:包括以下步骤:
第一步,预制PC轨道梁和下部结构施工;
PC轨道梁1统一在梁场制作,下部结构为边墩2和中墩3,在轨道线路沿途浇筑;PC轨道梁1验收合格后,用运梁车5运至已完成的下部结构施工现场;参见图1。
第二步,测量放样;
测量人员在边墩2和中墩3的盖梁顶临时支撑4上放样出轨道梁的中心线、端部位置及高程;
第三步,轨道梁架设;
采用汽车吊6双机抬吊,将PC轨道梁1按照测量放样点初步放置在盖梁顶临时支撑4上,然后用连接丝杠7固定;参见图2。
第四步,轨道梁精调;
完成一联轨道梁(3×30m)架设任务后,将连接丝杠7适当调松,利用PC轨道梁1两端调整支撑8上放置的液压三维千斤顶9对PC轨道梁1进行支撑,并使用钢垫块及丝杠,配合测量人员对PC轨道梁1的纵横向偏位和倾角进行调整;精调完成后,再以一联轨道梁为整体进行联调; 参见图3、图4和图5。
第五步,对应中墩现浇段施工;
精调完成后,将临时支撑及垫块焊接固定;绑扎中墩钢筋及预应力施工操作,浇筑对应中墩现浇段13混凝土,浇筑后对应中墩现浇段13与PC轨道梁1为一整体;强度达到设计要求后,张拉并锚固纵向一联轨道梁钢束,再张拉并锚固中墩盖梁钢束,浇筑封端混凝土;参见图6。
第六步,对应边墩现浇段施工;
绑扎边墩钢筋、指形板预埋施作,浇筑对应边墩现浇段12混凝土,浇筑后对应边墩现浇段12与PC轨道梁1为一整体;强度达到设计要求后,张拉并锚固边墩盖梁钢束,浇筑封端混凝土。参见图7。
在繁忙的城市道路路段,利用有限的道路空闲时间先将单榀简支PC轨道梁依次临时架设至盖梁顶部,避免长时间占用城市道路,阻碍交通。后只需在盖梁顶部利用丝杠及三维千斤顶对梁体进行精调,再进行对应中墩现浇段浇筑,张拉梁体纵向预应力筋,最后浇筑对应边墩现浇段。
Claims (1)
1.先简支后连续PC轨道梁的施工方法,其特征是:包括以下步骤:
第一步,预制PC轨道梁和下部结构施工;
PC轨道梁(1)统一在梁场制作,下部结构为边墩(2)和中墩(3),在轨道线路沿途浇筑;PC轨道梁(1)验收合格后,用运梁车(5)运至已完成的下部结构施工现场;
第二步,测量放样;
测量人员在边墩(2)和中墩(3)的盖梁顶临时支撑(4)上放样出轨道梁的中心线、端部位置及高程;
第三步,轨道梁架设;
采用汽车吊(6)双机抬吊,将PC轨道梁(1)按照测量放样点初步放置在盖梁顶临时支撑(4)上,然后用连接丝杠(7)固定;
第四步,轨道梁精调;
完成一联轨道梁架设任务后,先将连接丝杠(7)适当调松,利用PC轨道梁(1)两端调整支撑(8)上放置的液压三维千斤顶(9)对PC轨道梁(1)进行支撑,并使用钢垫块及丝杠,配合测量人员对PC轨道梁(1)的纵横向偏位和倾角进行调整;精调完成后,再以一联轨道梁为整体进行联调;
第五步,对应中墩现浇段施工;
精调完成后,将临时支撑及钢垫块焊接固定;绑扎中墩钢筋及预应力施工操作,浇筑对应中墩现浇段(13)混凝土;强度达到设计要求后,张拉并锚固纵向一联轨道梁钢束,再张拉并锚固中墩盖梁钢束,浇筑封端混凝土;
第六步,对应边墩现浇段施工;
绑扎边墩钢筋、指形板预埋施作,浇筑对应边墩现浇段(12)混凝土;强度达到设计要求后,张拉并锚固边墩盖梁钢束,浇筑封端混凝土。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910819386.1A CN110424274A (zh) | 2019-08-31 | 2019-08-31 | 先简支后连续pc轨道梁的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910819386.1A CN110424274A (zh) | 2019-08-31 | 2019-08-31 | 先简支后连续pc轨道梁的施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110424274A true CN110424274A (zh) | 2019-11-08 |
Family
ID=68418372
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910819386.1A Pending CN110424274A (zh) | 2019-08-31 | 2019-08-31 | 先简支后连续pc轨道梁的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110424274A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110820596A (zh) * | 2019-12-09 | 2020-02-21 | 南京林业大学 | 一种pc轨道梁线形调整临时限位装置及使用方法 |
CN111206507A (zh) * | 2020-02-05 | 2020-05-29 | 石家庄铁道大学 | 骑挂式支承结构及先简支后连续桥梁施工方法 |
CN114214955A (zh) * | 2021-12-28 | 2022-03-22 | 武船重型工程股份有限公司 | 一种跨桥钢板梁的架设方法 |
CN114580797A (zh) * | 2022-05-09 | 2022-06-03 | 湖南省交通科学研究院有限公司 | 一种基于bim模拟的小半径预制梁架设路径规划方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100857925B1 (ko) * | 2007-12-21 | 2008-09-10 | 코레일트랙 주식회사 | 거더 신축부 완화용 콘크리트 궤도 |
CN103485279A (zh) * | 2013-10-08 | 2014-01-01 | 北京交通大学 | 用于跨座式单轨交通的湿接缝 |
CN109162157A (zh) * | 2018-09-17 | 2019-01-08 | 中国建筑第八工程局有限公司 | 轨道梁的施工方法 |
CN109989330A (zh) * | 2017-12-29 | 2019-07-09 | 比亚迪股份有限公司 | 连续式轨道及其架设方法 |
-
2019
- 2019-08-31 CN CN201910819386.1A patent/CN110424274A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100857925B1 (ko) * | 2007-12-21 | 2008-09-10 | 코레일트랙 주식회사 | 거더 신축부 완화용 콘크리트 궤도 |
CN103485279A (zh) * | 2013-10-08 | 2014-01-01 | 北京交通大学 | 用于跨座式单轨交通的湿接缝 |
CN109989330A (zh) * | 2017-12-29 | 2019-07-09 | 比亚迪股份有限公司 | 连续式轨道及其架设方法 |
CN109162157A (zh) * | 2018-09-17 | 2019-01-08 | 中国建筑第八工程局有限公司 | 轨道梁的施工方法 |
Non-Patent Citations (2)
Title |
---|
窦仲赟: "跨坐式单轨简支变连续轨道梁设计", 《城市轨道交通研究》 * |
阳荣辉: "连续PC轨道梁方案(定稿)", 《百度文库》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110820596A (zh) * | 2019-12-09 | 2020-02-21 | 南京林业大学 | 一种pc轨道梁线形调整临时限位装置及使用方法 |
CN111206507A (zh) * | 2020-02-05 | 2020-05-29 | 石家庄铁道大学 | 骑挂式支承结构及先简支后连续桥梁施工方法 |
CN111206507B (zh) * | 2020-02-05 | 2021-06-29 | 石家庄铁道大学 | 骑挂式支承结构及先简支后连续桥梁施工方法 |
CN114214955A (zh) * | 2021-12-28 | 2022-03-22 | 武船重型工程股份有限公司 | 一种跨桥钢板梁的架设方法 |
CN114214955B (zh) * | 2021-12-28 | 2024-03-22 | 武船重型工程股份有限公司 | 一种跨桥钢板梁的架设方法 |
CN114580797A (zh) * | 2022-05-09 | 2022-06-03 | 湖南省交通科学研究院有限公司 | 一种基于bim模拟的小半径预制梁架设路径规划方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110424274A (zh) | 先简支后连续pc轨道梁的施工方法 | |
CN108374296B (zh) | 跨座式单轨轨道梁安装的施工方法 | |
CN109778721A (zh) | 同步顶升桥梁上下部结构进行桥梁加高改造的方法 | |
CN111139749A (zh) | 一种大跨度上承式连续钢桁梁悬臂架设施工方法 | |
CN102691266A (zh) | 桥梁边跨现浇段超高组合支架施工方法 | |
CN101324054B (zh) | 桥梁节段梁临时墩的顶推就位施工方法 | |
CN105714681A (zh) | 一种悬挂式单轨交通刚构体系的实现方法和施工工艺 | |
CN102659027B (zh) | 架梁龙门吊变跨过站的方法 | |
CN106498976A (zh) | 一种城际铁路下穿高速公路明挖施工群顶托换方法 | |
CN101649603A (zh) | 50米t型梁预制安装工艺 | |
CN212375686U (zh) | 一种新型大跨斜腿撑式钢桁反拱桥 | |
CN208328660U (zh) | 公铁两用桥的双拼u型梁结构 | |
CN116427281A (zh) | 一种墩柱、盖梁、t梁一体式架桥机安装施工方法 | |
CN115748413A (zh) | 一种连续钢桁腹-板桁双层组合转体桥梁结构 | |
CN211772868U (zh) | 一种大跨度连续梁中墩临时固结装置 | |
CN111926710A (zh) | 多股道铁路架空固定装置 | |
CN113481871A (zh) | 一种小曲线半径、大跨度连续工型钢混组合桥梁架桥机逐跨过孔方法 | |
CN107604823B (zh) | 一种通过铁路过渡运梁的施工方法 | |
CN207079474U (zh) | 高墩柱现浇道岔梁的拼装式钢管柱临时支墩贝雷梁支架 | |
CN221193021U (zh) | 一种设置上导梁的转体桥梁 | |
CN204780566U (zh) | 一种消除桥头跳车的桥梁接地段结构 | |
CN219690284U (zh) | 一种高速铁路钢管混凝土刚构桥 | |
CN220888347U (zh) | 一种新建盾构隧道下穿既有河道铁路桥梁改造结构 | |
CN218643411U (zh) | 一种设置在桥梁中分带的塔吊基础结构 | |
CN219671101U (zh) | 一种窄断面小曲线半径匝道桥辅助架桥机转向的结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191108 |