CN110820596A - 一种pc轨道梁线形调整临时限位装置及使用方法 - Google Patents

一种pc轨道梁线形调整临时限位装置及使用方法 Download PDF

Info

Publication number
CN110820596A
CN110820596A CN201911254382.XA CN201911254382A CN110820596A CN 110820596 A CN110820596 A CN 110820596A CN 201911254382 A CN201911254382 A CN 201911254382A CN 110820596 A CN110820596 A CN 110820596A
Authority
CN
China
Prior art keywords
steel
track beam
limiting device
embedded
track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911254382.XA
Other languages
English (en)
Inventor
李建慧
寇恒武
端茂军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Forestry University
Original Assignee
Nanjing Forestry University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Forestry University filed Critical Nanjing Forestry University
Priority to CN201911254382.XA priority Critical patent/CN110820596A/zh
Publication of CN110820596A publication Critical patent/CN110820596A/zh
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

一种PC轨道梁线形调整临时限位装置及使用方法,所述装置主要由预埋钢销帽(3),钢垫板(4),高强螺栓(5),工字钢(6),预埋钢板(7)共同组成。其特征在于,工字钢(6)焊接在墩身盖梁(1)上的预埋钢板(7)上。工字钢(6)插入预埋在轨道梁(2)上的预埋钢销帽(3)中,钢垫板(4)与预埋钢销帽(3)及工字钢(6)用高强螺栓(5)紧固在一起组成临时限位装置,本发明的特点在于限位装置束缚了梁的运动幅度,保证了后续施工的安全性。

Description

一种PC轨道梁线形调整临时限位装置及使用方法
技术领域
本发明涉及一种PC轨道梁线形调整临时限位装置及使用方法,属于轨道梁安装临时固定装置。
背景技术
随着经济的高速发展,我国轨道梁的结构形式也越来越与国际接轨。但是对新型的连续刚构PC轨道梁安装架设技术及线形调整时的临时支撑技术还处于摸索阶段。
连续刚构PC轨道梁安装精度要求非常高,安装工艺复杂,尤其是在线形调整时更需要保证施工的安全,对于PC轨道梁的架设施工,属于高空危险作业,轨道梁架设完成以后不能直接浇筑,因为线形还需要调整,而且轨道梁自重较大,为了保证安全稳定的对轨道梁进行线形调整,所以一种PC轨道梁线形调整临时限位装置是需要的。
发明内容
本发明涉及一种PC轨道梁线形调整临时限位装置及使用方法,将装置直接安装在轨道梁上,实现PC轨道梁线形调整的临时限位,同时还可以避免遇强风被吹落的危险,对于多跨的轨道梁安装更是能先临时限位,然后统一线形调整,极大的提高效率。其主要结构为钢板和高强螺栓,材料常见,结构也简单,装置形式简单明了,便于推广应用。临时限位装置在线形调整结束之前一直存在,可以有效保证施工作业的安全。
为实现上述目的,本发明采用以下技术方案:一种PC轨道梁线形调整临时限位装置,所述装置主要由预埋钢销帽、钢垫板、高强螺栓、工字钢、预埋钢板组成,临时限位装置在整个轨道梁线形调整阶段一直存在。
所述的一种PC轨道梁线形调整临时限位装置,预埋钢销帽、钢垫板、工字钢由厚0.5-4cm,材质为高强度合金的钢板加工而成。
所述的一种PC轨道梁线形调整临时限位装置,预埋钢板下方焊接在墩身盖梁内的钢筋上并浇筑。
所述的一种PC轨道梁线形调整临时限位装置,预埋钢板上方与工字钢焊接在一起。
所述的一种PC轨道梁线形调整临时限位装置,吊装PC轨道梁时,将预埋钢销帽与工字钢对准后落梁。
所述的一种PC轨道梁线形调整临时限位装置,将垫板放在预埋钢销帽两侧,然后用高强螺栓将工字钢与预埋钢销帽及钢垫板紧固在一起。
所述的一种PC轨道梁线形调整临时限位装置,预制轨道梁时将预埋钢销帽与轨道梁内钢筋焊接并放入模板内浇筑成型,埋入轨道梁内0.5m-3m,露在外面5cm-50cm。
一种轨道梁临时限位装置使用方法,包括以下步骤:
A.预制轨道梁时将预埋钢销帽与轨道梁内钢筋焊接并放入模板内浇筑成型;预埋钢板与墩身盖梁内钢筋焊接,然后浇筑。
B.使用吊机将预制好的轨道梁进行安装,使工字钢准确插入预埋钢销帽内。
C.将钢垫板贴放在预埋钢销帽两侧,将钢垫板与预埋钢销帽及工字钢的孔对齐,然后将高强螺栓放入孔中并紧固。
本发明具有以下有益效果:
本发明涉及一种PC轨道梁线形调整临时限位装置,将装置直接安装在轨道梁上,实现PC轨道梁线形调整的临时限位,同时还可以避免遇强风被吹落的危险,对于多跨的轨道梁安装更是能先临时限位,然后统一线形调整,极大的提高效率。其主要结构为钢板和高强螺栓,材料常见,结构也简单,装置形式简单明了,便于推广应用。临时限位装置在线形调整结束之前一直存在,可以有效保证施工作业的安全。
附图说明
图1是临时限位装置的正视图;
图2是临时限位装置的俯视图;
图3是临时限位装置的侧视图;
图4是A局部放大示意图;
图5是3的正视图;
图6是3的侧视图;
图7是3的俯视图;
图8是6的俯视图。
在附图中,1为墩身盖梁;2为轨道梁;3为预埋钢销帽;4为钢垫板;5为高强螺栓;6为工字钢;7为预埋钢板。
具体实施方式
为了对本发明的技术特征、目的和效果有更深刻的理解,现对照附图说明本发明的具体实施方式。
请参阅附图,本发明的实例中,一种PC轨道梁线形调整临时限位装置及使用方法,所述装置包括预埋钢销帽3;钢垫板4;高强螺栓5;工字钢6;预埋钢板7共同组成,临时限位装置在整个轨道梁线形调整阶段一直存在。
一种轨道梁临时限位装置使用方法,利用临时限位装置操作实施,包括以下步骤:
A.预制轨道梁2时将预埋钢销帽3与轨道梁2内钢筋焊接并放入模板内浇筑成型;预埋钢板7与墩身盖梁1内钢筋焊接,然后浇筑。
B.使用吊机将预制好的轨道梁2进行安装,使工字钢6准确插入预埋钢销帽3内。
C.将钢垫板4贴放在预埋钢销帽3两侧,将钢垫板4与预埋钢销帽3及工字钢6的孔对齐,然后将高强螺栓5放入孔中并紧固。
本发明具体流程如下,即:
步骤一:在预制梁厂预制轨道梁2时将预埋钢销帽3与轨道梁2内钢筋焊接并放入模板内浇筑成型;
步骤二:浇筑墩身盖梁1时,预埋钢板7与墩身盖梁1内钢筋焊接,然后浇筑。
步骤三:用运输车将轨道梁2运送至吊装现场,使用吊机将预制好的轨道梁2进行安装,使工字钢6准确插入预埋钢销帽3内。
步骤四:将钢垫板4贴放在预埋钢销帽3两侧,将钢垫板4与预埋钢销帽3及工字钢6的孔对齐,然后将高强螺栓5放入孔中并紧固。
凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。

Claims (7)

1.一种PC轨道梁线形调整临时限位装置,所述装置主要由预埋钢销帽(3),钢垫板(4),高强螺栓(5),工字钢(6),预埋钢板(7)共同组成,其特征在于,预埋钢板(7)下方焊接在墩身盖梁(1)内的钢筋上,上方与工字钢(6)焊接在一起,工字钢(6)与预埋钢销帽(3)及钢垫板(4)用高强螺栓(5)紧固在一起,预埋钢销帽(3)与轨道梁(2)内钢筋焊接在一起并与钢垫板(4),高强螺栓(5),工字钢(6),预埋钢板(7)一起组成限位装置。
2.根据权利要求1所述的一种PC轨道梁线形调整临时限位装置,其特征在于,预埋钢销帽(3)、钢垫板(4)、工字钢(6)由厚0.5-4cm,材质为高强度合金的钢板加工而成。
3.根据权利要求1所述的一种PC轨道梁线形调整临时限位装置,其特征在于,预埋钢板(7)下方焊接在墩身盖梁(1)内的钢筋上。
4.根据权利要求1所述的一种PC轨道梁线形调整临时限位装置,其特征在于,预埋钢板(7)上方与工字钢(6)焊接在一起。
5.根据权利要求1所述的一种PC轨道梁线形调整临时限位装置,其特征在于,工字钢(6)与预埋钢销帽(3)及钢垫板(4)用高强螺栓(5)紧固在一起。
6.根据权利要求1所述的一种PC轨道梁线形调整临时限位装置,其特征在于,预埋钢销帽(3)与轨道梁(2)内钢筋焊接在一起。
7.一种轨道梁临时限位装置使用方法,其特征在于:包括以下步骤:
A.预制轨道梁时将预埋钢销帽(3)与轨道梁(2)内钢筋焊接并放入模板内浇筑成型;预埋钢板(7)与墩身盖梁(1)内钢筋焊接,然后浇筑。
B.使用吊机将预制好的轨道梁(2)进行安装,使工字钢(6)准确插入预埋钢销帽(3)内。
C.将钢垫板(4)贴放在预埋钢销帽(3)两侧,将钢垫板(4)与预埋钢销(3)及工字钢(6)的孔对齐,然后将高强螺栓(5)放入孔中并紧固。
CN201911254382.XA 2019-12-09 2019-12-09 一种pc轨道梁线形调整临时限位装置及使用方法 Pending CN110820596A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911254382.XA CN110820596A (zh) 2019-12-09 2019-12-09 一种pc轨道梁线形调整临时限位装置及使用方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911254382.XA CN110820596A (zh) 2019-12-09 2019-12-09 一种pc轨道梁线形调整临时限位装置及使用方法

Publications (1)

Publication Number Publication Date
CN110820596A true CN110820596A (zh) 2020-02-21

Family

ID=69544171

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911254382.XA Pending CN110820596A (zh) 2019-12-09 2019-12-09 一种pc轨道梁线形调整临时限位装置及使用方法

Country Status (1)

Country Link
CN (1) CN110820596A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111719414A (zh) * 2020-07-07 2020-09-29 郑琼华 内焊外浇筑式桥墩横梁连接结构及横梁桥墩对接方法

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11158818A (ja) * 1997-11-25 1999-06-15 Katayama Stratec Kk 橋梁における単純桁の連結工法およびその連結工法に用いる撓み力付与装置
JP2002212903A (ja) * 2001-01-17 2002-07-31 Hitachi Ltd 跨座式モノレール軌道桁及びその設置方法
KR200345792Y1 (ko) * 2003-12-24 2004-03-24 동양종합건업 주식회사 스틸브라켓에 의한 피.에스.씨-i빔
CN103485279A (zh) * 2013-10-08 2014-01-01 北京交通大学 用于跨座式单轨交通的湿接缝
CN105178194A (zh) * 2015-09-10 2015-12-23 重庆市轨道交通设计研究院有限责任公司 连续梁式轨道建设施工方法
CN204959578U (zh) * 2015-09-10 2016-01-13 重庆市轨道交通设计研究院有限责任公司 Pc轨道梁
CN105274939A (zh) * 2015-09-10 2016-01-27 重庆市轨道交通设计研究院有限责任公司 Pc轨道梁连接装置
CN107841954A (zh) * 2017-12-06 2018-03-27 中铁十局集团第三建设有限公司 一种轨道梁球铰线形精调装置和方法
CN108221508A (zh) * 2018-03-21 2018-06-29 成都市新筑路桥机械股份有限公司 一种集成式单轨梁端部预埋装置
CN108374296A (zh) * 2018-02-27 2018-08-07 中建五局土木工程有限公司 跨座式单轨轨道梁安装的施工方法
CN108729335A (zh) * 2018-06-01 2018-11-02 苏交科集团股份有限公司 钢混结合段及其安装方法
CN109440644A (zh) * 2018-08-28 2019-03-08 浙江中南建设集团钢结构有限公司 一种连续钢梁桥安装用临时结构及其对梁段施工方法
CN109868723A (zh) * 2019-03-29 2019-06-11 四川迈铁龙科技有限公司 空中轨道交通钢桥铰轴连接构造
CN109989330A (zh) * 2017-12-29 2019-07-09 比亚迪股份有限公司 连续式轨道及其架设方法
CN110424274A (zh) * 2019-08-31 2019-11-08 中铁八局集团有限公司 先简支后连续pc轨道梁的施工方法
CN211420889U (zh) * 2019-12-09 2020-09-04 南京林业大学 一种pc轨道梁线形调整临时限位装置

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11158818A (ja) * 1997-11-25 1999-06-15 Katayama Stratec Kk 橋梁における単純桁の連結工法およびその連結工法に用いる撓み力付与装置
JP2002212903A (ja) * 2001-01-17 2002-07-31 Hitachi Ltd 跨座式モノレール軌道桁及びその設置方法
KR200345792Y1 (ko) * 2003-12-24 2004-03-24 동양종합건업 주식회사 스틸브라켓에 의한 피.에스.씨-i빔
CN103485279A (zh) * 2013-10-08 2014-01-01 北京交通大学 用于跨座式单轨交通的湿接缝
CN105178194A (zh) * 2015-09-10 2015-12-23 重庆市轨道交通设计研究院有限责任公司 连续梁式轨道建设施工方法
CN204959578U (zh) * 2015-09-10 2016-01-13 重庆市轨道交通设计研究院有限责任公司 Pc轨道梁
CN105274939A (zh) * 2015-09-10 2016-01-27 重庆市轨道交通设计研究院有限责任公司 Pc轨道梁连接装置
CN107841954A (zh) * 2017-12-06 2018-03-27 中铁十局集团第三建设有限公司 一种轨道梁球铰线形精调装置和方法
CN109989330A (zh) * 2017-12-29 2019-07-09 比亚迪股份有限公司 连续式轨道及其架设方法
CN108374296A (zh) * 2018-02-27 2018-08-07 中建五局土木工程有限公司 跨座式单轨轨道梁安装的施工方法
CN108221508A (zh) * 2018-03-21 2018-06-29 成都市新筑路桥机械股份有限公司 一种集成式单轨梁端部预埋装置
CN108729335A (zh) * 2018-06-01 2018-11-02 苏交科集团股份有限公司 钢混结合段及其安装方法
CN109440644A (zh) * 2018-08-28 2019-03-08 浙江中南建设集团钢结构有限公司 一种连续钢梁桥安装用临时结构及其对梁段施工方法
CN109868723A (zh) * 2019-03-29 2019-06-11 四川迈铁龙科技有限公司 空中轨道交通钢桥铰轴连接构造
CN110424274A (zh) * 2019-08-31 2019-11-08 中铁八局集团有限公司 先简支后连续pc轨道梁的施工方法
CN211420889U (zh) * 2019-12-09 2020-09-04 南京林业大学 一种pc轨道梁线形调整临时限位装置

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111719414A (zh) * 2020-07-07 2020-09-29 郑琼华 内焊外浇筑式桥墩横梁连接结构及横梁桥墩对接方法

Similar Documents

Publication Publication Date Title
US7765766B2 (en) Assembly structure and procedure for concrete towers used in wind turbines
CN102900024B (zh) 大型混凝土结构翻升模板的使用方法
CN101858163B (zh) 火炬塔架散装方法
CN211420889U (zh) 一种pc轨道梁线形调整临时限位装置
CN110820596A (zh) 一种pc轨道梁线形调整临时限位装置及使用方法
CN108222526B (zh) 高层连体建筑塔楼侧向位移控制装置及施工方法
CN212249282U (zh) 钢构柱垂直度微调工具
CN212224589U (zh) 一种应用于桥梁圆柱墩的一体化安全作业平台
CN205617664U (zh) 预制墩柱钢筋笼用定位架
CN205224073U (zh) 一种接触网固定胎具
CN212335664U (zh) 一种pc轨道梁的支撑以及线形调整临时固定装置
CN211621558U (zh) 一种钻孔灌注桩钢筋笼标高控制安装结构
CN212613819U (zh) 一种大截面钢梁高强螺栓连接板安装滑道装置
CN209797236U (zh) 一种箱梁外模吊装装置
CN216583828U (zh) 一种组合周转式竖向钢构件安装平台
CN205077876U (zh) 一种预应力钢绞线穿束机及张拉千斤顶悬挂装置
CN215618974U (zh) 装配式方形墩柱承台预埋筋定位系统
CN204343317U (zh) 一种塔吊基础的直锚式钢平台
CN110725551A (zh) 高空无斜拉杆大悬挑钢梁的安装方法
CN109505304A (zh) 一种永冻土地区输电线路铁塔装配式基础预制模板
CN213202080U (zh) 预制箱梁外模吊具施工装置
CN203905431U (zh) 一种可提升的工具堆载平台
CN109838087A (zh) 可重复使用的装配式建筑支撑装置
CN212832343U (zh) 一种pc柱安装辅助工装组件
CN114351656B (zh) 一种水电站液压启闭机油缸支铰固定结构及固定方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination