CN110295576A - Improve the concrete face rockfill dam of stress and deformations of concrete face slab state - Google Patents

Improve the concrete face rockfill dam of stress and deformations of concrete face slab state Download PDF

Info

Publication number
CN110295576A
CN110295576A CN201910663386.7A CN201910663386A CN110295576A CN 110295576 A CN110295576 A CN 110295576A CN 201910663386 A CN201910663386 A CN 201910663386A CN 110295576 A CN110295576 A CN 110295576A
Authority
CN
China
Prior art keywords
dam
upstream
downstream
concrete face
area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910663386.7A
Other languages
Chinese (zh)
Other versions
CN110295576B (en
Inventor
徐琨
杨启贵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changjiang Institute of Survey Planning Design and Research Co Ltd
Original Assignee
Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changjiang Institute of Survey Planning Design and Research Co Ltd filed Critical Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority to CN201910663386.7A priority Critical patent/CN110295576B/en
Publication of CN110295576A publication Critical patent/CN110295576A/en
Application granted granted Critical
Publication of CN110295576B publication Critical patent/CN110295576B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • E02B7/06Earth-fill dams; Rock-fill dams

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention relates to a kind of concrete face rockfill dam for improving stress and deformations of concrete face slab state, including concrete slab, bed course, transition zone, the main rockfill area of increasing mould, main rockfill area, secondary rockfill area, downstream protection slope and the drainage prism set gradually by upstream to downstream, increase the upstream lateral boundaries of the main rockfill area of mould and the downstream side overlapping margins of transition zone;The downstream lateral boundaries for increasing the main rockfill area of mould include axis of dam upstream part and axis of dam downstream side part, and axis of dam upstream part is parallel to upstream dam slope, and axis of dam downstream side part is horizontally disposed with and extends to the inside of downstream protection slope.The present invention avoid or reduce the dam deformation by caused by water storage caused by concrete slab unfavorable stress deformation state, concrete slab is reduced to come to nothing, collapse, squeezing a possibility that the problems such as destruction, the degree of safety of concrete face rockfill dam is improved, the construction for promoting high or ultra high concrete panel rock-fill dams is conducive to.

Description

Improve the concrete face rockfill dam of stress and deformations of concrete face slab state
Technical field
The present invention relates to hydraulic engineering technical fields, and in particular to a kind of concrete surface for improving stress and deformations of concrete face slab state Sheetpile masonry dam.
Background technique
Concrete face rockfill dam is one of main force's dam type of China's high dam construction.As what HYDROELECTRIC ENERGY was developed gos deep into, Rock-fill dams construction in China's gradually develops from 200m grades to 300m grades of height of dam, and more and more high rock-fill dams are being planned or built In.As the water retaining structure of hydropower complex, the concrete slab of concrete face rockfill dam upstream side is its main antiseepage Structure, rockfill are the support construction of concrete slab.
Since the mechanical deformation different from those of concrete slab and dam embankment material is very big, to guarantee panel leakage preventing structure not It is destroyed, the deformation between panel and dam body answers mutually coordinated namely panel that should be able to adapt to the deformation of dam body, dam deformation Ying Jinke Can it is small.By decades continuous practical studies development, concrete face rockfill dam is in design, construction stage at present, mainly It chosen from dam zoning, material source, fill timing, water sealing structure etc. and conduct a research, proposed a variety of reduction dam deformations, change The engineering measure of kind panel force and deformation state and the panel water sealing structure for adapting to large deformation.
Existing research shows that the dam deformation of 200m grades of high concrete panel rock-fill dams occur mainly in dam embankment and During reservoir filling, later, sedimentation gradually tends to restrain.Due to the mechanical characteristic of dam material itself, completion is poured in panel Afterwards, during reservoir initial filling, under the action of water ballast(ing) dam body inevitably again can occur significantly to deform, especially with Dam body upstream region is very;In addition, dam body middle and upper part width narrows, and overall deformation is also vulnerable to water storage as elevation increases It influences.The deformation as caused by water storage is unfavorable for the stress of panel above, will cause panel damage, then will lead to leakage hair when serious It is raw;For 300m grades of ultra-high concrete panel rock-fill dams, only head just promotes 100m, this problem will become more prominent.So And existing engineering measure can not after the completion of effective solution CFRD Embankment the dam deformation due to caused by water storage and its To the adverse effect of concrete slab stress deformation.
Summary of the invention
In order to solve the above problem, the present invention, which provides one kind, can reduce water storage to dam deformation influence, and then improve panel The concrete face rockfill dam of stress deformation state.
The technical solution adopted by the present invention is that: a kind of concrete face rockfill dam improving stress and deformations of concrete face slab state, It is characterized in that: including the concrete slab, bed course, transition zone, the main rockfill area of increasing mould, main enrockment set gradually by upstream to downstream Area, secondary rockfill area, downstream protection slope and drainage prism, the downstream side of the upstream lateral boundaries for increasing the main rockfill area of mould and transition zone Boundary is overlapped;
The downstream lateral boundaries for increasing the main rockfill area of mould include axis of dam upstream part and axis of dam downstream side part, institute It states axis of dam upstream part and is parallel to upstream dam slope, axis of dam downstream side part is horizontally disposed with and extends to downstream protection slope Inside.
Preferably, horizontal width between the axis of dam upstream part and transition zone downstream lateral boundaries be 0.15~ 0.40 times of height of dam.
Further, the downstream side overlapping margins of the main rockfill area upstream lateral boundaries and the increasing main rockfill area of mould, the master Rockfill area downstream lateral boundaries include horizontal boundary and tendency downstream boundary.
Further, the height of dam that the elevation of the horizontal boundary is 0.4~0.6 times.
Further, the horizontal boundary extends to downstream protection slope.
Further, the slope ratio of the tendency downstream boundary is 1:0.1~1:0.3, and the tendency downstream boundary rises Horizontal distance of the point apart from the axis of dam is less than horizontal distance of the terminal of tendency downstream boundary apart from the axis of dam.
Further, horizontal distance of the starting point of the tendency downstream boundary apart from the axis of dam is 0~0.2 times of height of dam.
Further, the terminal of the tendency downstream boundary be that tendency downstream boundary extends to intersection point at basement rock.
Preferably, further including upstream apron area, the special bed course area Gai Chongqu and bottom, the upstream apron area is located at heap Masonry dam upstream side bottom, and it is close to concrete slab arrangement;The upstream apron area includes sloping portion and horizontal component, inclination Partial upstream side slope ratio is identical as dam slope, and horizontal component upstream extends 1~2 times of concrete toe board width;The Gai Chongqu It is close to be arranged in the upstream side in upstream apron area, the Gai Chongqu cope level is consistent with upstream apron area, the Gai Chongqu's Upstream side slope compares upstream dam slope slope than slow;The special bed course area is located at concrete slab downstream side bottom.
Preferably, the downstream protection slope is close to dam body downstream side profile.
Preferably, further including positioned at the special bed course area in bottom in concrete slab downstream side.
The beneficial effect that the present invention obtains is:
(1), increase the main rockfill area of mould by being arranged between transition zone and main rockfill area, increase the main rockfill area resistance to deformation energy of mould Power is stronger, effectively reduces the influence that water storage deforms dam body upstream side;
(2) it by the way that main rockfill area is arranged with upper bit in 0.5 times of height of dam elevation and increases the main rockfill area of mould, effectively reduces Dam body middle and upper part deforms the influence degree by water storage, and the later period deflection of dam body middle and upper part can be effectively reduced;
(3) the unfavorable stress of the concrete slab caused by the present invention avoids or reduce the dam deformation by caused by water storage Deformation state reduces concrete slab and comes to nothing, collapses, squeezing a possibility that the problems such as destruction, improves concrete surface The degree of safety of sheetpile masonry dam is conducive to the construction for promoting high or ultra high concrete panel rock-fill dams, can be Southwestern China area water Electricity deeply develops offer and benefits.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is the enlarged drawing at the A of Fig. 1;
Appended drawing reference: 1, concrete slab;2, bed course;3, transition zone;4, increase the main rockfill area of mould;41, axis of dam upstream side Part;42, axis of dam downstream side part;5, main rockfill area;51, horizontal boundary;52, it is inclined to downstream boundary;521, starting point;522, Terminal;6, secondary rockfill area;7, downstream protection slope;8, drainage prism;9, upstream apron area;91, sloping portion;92, horizontal component 10, Gai Chongqu;11, concrete toe board;12, special bed course area;13, the axis of dam.
Specific embodiment
The present invention will be further explained in the following with reference to the drawings and specific embodiments.
As shown in Figs. 1-2, the concrete face rockfill dam of a kind of improvement stress and deformations of concrete face slab state of the invention, including by Concrete slab 1 that upstream to downstream is set gradually, transition zone 3, increases the main rockfill area 4 of mould, main rockfill area 5, secondary enrockment at bed course 2 Area 6, downstream protection slope 7 and drainage prism 8.
Concrete slab 1, bed course 2 and transition zone 3 are arranged at 13 upstream side of the axis of dam, are parallel to upstream dam slope, top Dam crest is extended to, concrete toe board 11 and special bed course area 12 are equipped between lower part and basement rock.
Increase the main rockfill area 4 of mould to be arranged between transition zone 3 and main rockfill area 5, the stockpile for increasing the main rockfill area 4 of mould, which is resisted, to be become The ability of shape is better than the ability of the stockpile resistance to deformation of main rockfill area 5, can be by increasing main 4 stockpile of rockfill area of increasing mould Number of rolling promotes rolling compaction machine tonnage or the modes such as quantitative perfusion stickiness slurries is taken to realize.Increase the main rockfill area 4 of mould to resist Deformability is stronger, effectively reduces the influence that water storage deforms dam body upstream side.
The upstream lateral boundaries and 3 downstream side overlapping margins of transition zone for increasing the main rockfill area 4 of mould, can be completely on the axis of dam 13 Swim side;The downstream lateral boundaries for increasing the main rockfill area 4 of mould include axis of dam upstream part 41 and axis of dam downstream side part 42, dam axis Line upstream part 41 is parallel to upstream dam slope, and axis of dam downstream side part 42 is horizontally disposed and extends to downstream protection slope 7, dam axis The height of dam that horizontal width between 3 downstream lateral boundaries of line upstream part 41 and transition zone is 0.15~0.40 times, horizontal width Too small, the effect for increasing main 4 resistance to deformation of rockfill area of mould is unobvious, and horizontal width is excessive, and economic cost of building a dam is excessively high.It is horizontal wide Degree be 0.15~0.4 times of height of dam when, on the one hand can promote dam resistance capacity to deformation, on the other hand can rationally control build a dam through It helps cost, in the present embodiment, selects 0.25 times of height of dam.
Main 5 upstream lateral boundaries of rockfill area and the downstream side overlapping margins for increasing the main rockfill area 4 of mould, are completely under the axis of dam 13 Swim side;Main 5 downstream lateral boundaries of rockfill area include horizontal boundary 51 and tendency downstream boundary 52, and the elevation of horizontal boundary 51 is 0.4 The range of~0.6 times of height of dam, the too small then main rockfill area 5 of the elevation of horizontal boundary 51 increases, and economic cost of building a dam increases;It is horizontal The range of the excessively high main rockfill area 5 of the elevation on boundary 51 becomes smaller, and dam body middle and upper part deforms the effect weakened by the influence degree of water storage It is bad.In the present embodiment, 0.5 times of height of dam is selected.
Horizontal boundary 51 extends to 7 side of downstream protection slope.The slope ratio for being inclined to downstream boundary 52 is 1:0.1~1:0.3, and slope was compared The interface of big then secondary main rockfill area 6 and main rockfill area 5 is excessively steep, and easily deform problem of disharmony, and slope is than too small then main enrockment The range in area 5 increases, and economic cost of building a dam increases, and in the present embodiment, tendency 52 slope of downstream boundary is than selecting 1:0.2;Under tendency It swims horizontal distance of the starting point 521 on boundary 52 apart from the axis of dam 13 and is less than the terminal 522 of tendency downstream boundary 52 apart from the axis of dam 13 horizontal distance (i.e. tendency downstream side).
Horizontal distance of the starting point 521 apart from the axis of dam 13 for being inclined to downstream boundary 52 is 0~0.2 times of height of dam, starting point 521 away from The range of the excessive then main rockfill area 5 of horizontal distance from the axis of dam 13 increases, and economic cost of building a dam increases;If starting point 521 is arranged Increase in the 13 upstream side rockfill area Ze Ci of the axis of dam, 6 range, will lead to dam body settlement increase;In the present embodiment, 0.1 times of dam is selected It is high;The terminal 522 of tendency downstream boundary 52 be that tendency downstream boundary 52 extends to intersection point at basement rock.
Downstream protection slope 7 is close to dam body downstream side profile.
A kind of concrete face rockfill dam of improvement stress and deformations of concrete face slab state of the invention, further include upstream apron area 9, Gai Chongqu 10 and special bed course area 12, upstream apron area 9 are located at rock-fill dams upstream side bottom, and are close to the arrangement of concrete slab 1; Upstream apron area 9 includes sloping portion 91 and horizontal component 92, and the upstream side slope ratio of sloping portion 91 is identical as dam slope, horizontal part 92 are divided upstream to extend 1~2 times of 11 width of concrete toe board;Gai Chongqu 10 is close to be arranged in the upstream side in upstream apron area 9, lid The cope level in weight area 10 is consistent with upstream apron area 9;The upstream side slope of Gai Chongqu 10 compares upstream dam slope slope than slow;It is special Bed course area 12 is located at 1 downstream side bottom of concrete slab.
In practical engineering applications, the strength grade of concrete of concrete slab 1 is not less than C25, and seepage-resistant grade is not less than W8, and meet the freeze proof grade of response;1 thickness of concrete slab is linearly increasing from top to bottom, and top thickness is not less than 0.3m, bottom thickness 0.3+0.0035H, H are the vertical range calculated apart from 1 top of concrete slab.
Bed course 2, transition zone 3 increase the main rockfill area 4 of mould, main rockfill area 5, secondary rockfill area 6, downstream protection slope 7 and drainage prism 8 Filling material should make full use of local excavated material, and meet correlation test index and design requirement.
The horizontal width of bed course 2 is not less than 3m, and for the bedding material used for continuous grading, maximum particle diameter is 80~100mm, pressure Internal leak should be stablized after reality.
The horizontal width of transition zone 3 is not less than 3m, and is not less than the horizontal width of bed course 2, and the Transition Materials used are continuous Gradation, maximum particle diameter are no more than 300mm, have free drainage performance after compacting.
The stockpile for increasing the main rockfill area 4 of mould is hard rock, and maximum particle diameter is no more than compacted lift thickness, specifically, being no more than 800 ~1000mm;Increasing is improved by increasing number of rolling, promoting the modes such as rolling compaction machine tonnage, quantitative perfusion stickiness slurries when rolling The deformation resistivity of main 4 stockpile of rockfill area of mould.
The stockpile of main rockfill area 5 be hard rock, maximum particle diameter be no more than compacted lift thickness, specifically, be no more than 800~ 1000mm is less than 5mm granule content and is no more than 20%.
Hard rock can be used in the stockpile of secondary rockfill area 6, and the slightly lower soft rock of intensity can also be used, and maximum particle diameter is no more than 800 ~1000mm is less than 5mm granule content and is no more than 20%.
The rock for being 270m for certain height of dam, the stockpile E-B Parameters of constitutive model obtained using laboratory test Carry out two dimensional finite element to calculate, obtains identical original partition scheme and this patent preferred embodiment achievement when completely storing operating condition and what is reached have Beneficial effect is as shown in table 1.Dam body maximum settlement reduces 7.3%, and dam body is downstream displaced maximum value and reduces 9.6%, panel deflection 10.6% is reduced, panel inclined slope aspect compression reduces by 12.5%, and panel inclined slope aspect tensile stress reduces by 17.1%.Dam deformation value drop Low, stress and deformations of concrete face slab is effectively improved.
1 FEM calculation achievement of table
Basic principle and key structural feature of the invention has been shown and described above.The present invention is not by the limit of examples detailed above System, without departing from the spirit and scope of the present invention, various changes and improvements may be made to the invention, these changes and improvements It both falls in the range of claimed invention.The claimed scope of the invention is by appended claims and its equivalent It defines.

Claims (10)

1. a kind of concrete face rockfill dam for improving stress and deformations of concrete face slab state, it is characterised in that: including by upstream to downstream Concrete slab, bed course, transition zone, the main rockfill area of increasing mould, main rockfill area, secondary rockfill area, downstream protection slope and the row set gradually Water rib body, the downstream side overlapping margins of the upstream lateral boundaries for increasing the main rockfill area of mould and transition zone;
The downstream lateral boundaries for increasing the main rockfill area of mould include axis of dam upstream part and axis of dam downstream side part, the dam Axis upstream part is parallel to upstream dam slope, and axis of dam downstream side part is horizontally disposed with and extends to the interior of downstream protection slope Side.
2. the concrete face rockfill dam according to claim 1 for improving stress and deformations of concrete face slab state, it is characterised in that: The height of dam that horizontal width between the axis of dam upstream part and transition zone downstream lateral boundaries is 0.15~0.40 times.
3. the concrete face rockfill dam according to claim 1 for improving stress and deformations of concrete face slab state, it is characterised in that: The main rockfill area upstream lateral boundaries and the downstream side overlapping margins for increasing the main rockfill area of mould, the main rockfill area downstream lateral boundaries packet Include horizontal boundary and tendency downstream boundary.
4. the concrete face rockfill dam according to claim 3 for improving stress and deformations of concrete face slab state, it is characterised in that: The height of dam that the elevation of the horizontal boundary is 0.4~0.6 times.
5. the concrete face rockfill dam according to claim 3 for improving stress and deformations of concrete face slab state, it is characterised in that: The horizontal boundary extends to downstream protection slope.
6. the concrete face rockfill dam according to claim 3 for improving stress and deformations of concrete face slab state, it is characterised in that: The slope ratio of the tendency downstream boundary is 1:0.1~1:0.3, the starting point of the tendency downstream boundary apart from the axis of dam it is horizontal away from The horizontal distance of the axis of dam with a distance from the terminal for being less than tendency downstream boundary.
7. the concrete face rockfill dam according to claim 6 for improving stress and deformations of concrete face slab state, it is characterised in that: Horizontal distance of the starting point of the tendency downstream boundary apart from the axis of dam is 0~0.2 times of height of dam.
8. the concrete face rockfill dam according to claim 6 for improving stress and deformations of concrete face slab state, it is characterised in that: The terminal of the tendency downstream boundary be that tendency downstream boundary extends to intersection point at basement rock.
9. the concrete face rockfill dam according to claim 1 for improving stress and deformations of concrete face slab state, it is characterised in that: It further include upstream apron area, the special bed course area Gai Chongqu and bottom, the upstream apron area is located at rock-fill dams upstream side bottom, and It is close to concrete slab arrangement;The upstream apron area includes sloping portion and horizontal component, the upstream side slope ratio of sloping portion Identical as dam slope, horizontal component upstream extends 1~2 times of concrete toe board width;It is close to be arranged in upstream paving in the area Gai Chong The upstream side of cover region, the Gai Chongqu cope level is consistent with upstream apron area, and the upstream side slope of the Gai Chongqu compares upstream Dam slope slope is than slow;The special bed course area is located at concrete slab downstream side bottom.
10. the concrete face rockfill dam according to claim 1 for improving stress and deformations of concrete face slab state, feature exist In: the downstream protection slope is close to dam body downstream side profile.
CN201910663386.7A 2019-07-22 2019-07-22 Concrete face rockfill dam for improving face stress deformation state Active CN110295576B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910663386.7A CN110295576B (en) 2019-07-22 2019-07-22 Concrete face rockfill dam for improving face stress deformation state

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910663386.7A CN110295576B (en) 2019-07-22 2019-07-22 Concrete face rockfill dam for improving face stress deformation state

Publications (2)

Publication Number Publication Date
CN110295576A true CN110295576A (en) 2019-10-01
CN110295576B CN110295576B (en) 2024-04-12

Family

ID=68031604

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910663386.7A Active CN110295576B (en) 2019-07-22 2019-07-22 Concrete face rockfill dam for improving face stress deformation state

Country Status (1)

Country Link
CN (1) CN110295576B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203795389U (en) * 2014-04-26 2014-08-27 黄河勘测规划设计有限公司 Dam body sectioning structure of concrete face rockfill dam with large overburden depth
CN104110012A (en) * 2014-07-28 2014-10-22 中国电建集团西北勘测设计研究院有限公司 Low-permeability rock-fill material concrete panel rock-fill dam
CN106120662A (en) * 2016-08-17 2016-11-16 中国电建集团西北勘测设计研究院有限公司 High-modulus rock-faced dam dam, a kind of local
CN106192909A (en) * 2016-08-25 2016-12-07 中国电建集团西北勘测设计研究院有限公司 A kind of rock reducing panel stress strain level and method
CN106284215A (en) * 2016-08-17 2017-01-04 中国电建集团西北勘测设计研究院有限公司 A kind of mixed dam
KR101755157B1 (en) * 2016-05-13 2017-07-06 한국수자원공사 Hybrid Dam Combined Concrete Zone and Fill Zone
CN206359990U (en) * 2016-12-29 2017-07-28 中国电建集团华东勘测设计研究院有限公司 Structure for reducing dam body water level during rock panel is poured to retaining
CN208441056U (en) * 2018-03-21 2019-01-29 中国电建集团中南勘测设计研究院有限公司 A kind of rock
CN210917243U (en) * 2019-07-22 2020-07-03 长江勘测规划设计研究有限责任公司 Concrete face rockfill dam for improving face plate stress deformation state

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203795389U (en) * 2014-04-26 2014-08-27 黄河勘测规划设计有限公司 Dam body sectioning structure of concrete face rockfill dam with large overburden depth
CN104110012A (en) * 2014-07-28 2014-10-22 中国电建集团西北勘测设计研究院有限公司 Low-permeability rock-fill material concrete panel rock-fill dam
KR101755157B1 (en) * 2016-05-13 2017-07-06 한국수자원공사 Hybrid Dam Combined Concrete Zone and Fill Zone
CN106120662A (en) * 2016-08-17 2016-11-16 中国电建集团西北勘测设计研究院有限公司 High-modulus rock-faced dam dam, a kind of local
CN106284215A (en) * 2016-08-17 2017-01-04 中国电建集团西北勘测设计研究院有限公司 A kind of mixed dam
CN106192909A (en) * 2016-08-25 2016-12-07 中国电建集团西北勘测设计研究院有限公司 A kind of rock reducing panel stress strain level and method
CN206359990U (en) * 2016-12-29 2017-07-28 中国电建集团华东勘测设计研究院有限公司 Structure for reducing dam body water level during rock panel is poured to retaining
CN208441056U (en) * 2018-03-21 2019-01-29 中国电建集团中南勘测设计研究院有限公司 A kind of rock
CN210917243U (en) * 2019-07-22 2020-07-03 长江勘测规划设计研究有限责任公司 Concrete face rockfill dam for improving face plate stress deformation state

Also Published As

Publication number Publication date
CN110295576B (en) 2024-04-12

Similar Documents

Publication Publication Date Title
CN203256699U (en) Construction structure for water passing earth-rock dam
CN106638486B (en) High-tech zones cut-pff wall and gallery stage construction method
CN210917243U (en) Concrete face rockfill dam for improving face plate stress deformation state
CN212866006U (en) Soft soil foundation anti-settlement structure
CN206438356U (en) A kind of levee crown asphalt concrete pavement
CN207685789U (en) A kind of dam structure of dam
CN110295576A (en) Improve the concrete face rockfill dam of stress and deformations of concrete face slab state
CN108301384B (en) Joint structure of asphalt concrete core wall and dam foundation concrete impervious wall
CN106087976A (en) A kind of prefabricated friction pile of new concrete and pile sinking process
CN206495188U (en) A kind of buttress type duplex rock
CN202055261U (en) Landslide-proofing retaining wall
CN215252687U (en) Partition structure of gravel soil core wall dam
CN212000904U (en) Mixed seepage-proofing dam
CN210262945U (en) Cemented sand gravel buttress dam structure
CN210395268U (en) Flood discharge and energy dissipation structure for high-flow-rate non-pressure tunnel
CN210636388U (en) Composite drainage structure of homogeneous earth dam
CN208650011U (en) A kind of anti-skid structure of rock-fill dams spillway on dam body
CN211036890U (en) Narrow toe board structure of ultrahigh panel dam for narrow river valley deep and thick silt covering layer
CN113123301A (en) Partition structure of gravel soil core wall dam
CN206495190U (en) A kind of arch duplex rock
CN206768890U (en) A kind of reinforcement operation platform of the building foundation of river bank
CN205857160U (en) A kind of prefabricated friction pile of new concrete
CN219930896U (en) Gravity dam rectangular funnel weir surface hole spillway structure
CN215165306U (en) Asphalt concrete core rock-fill dam arrangement structure
CN103911970B (en) A kind of process of submerged breakwater pipe bag Separation of Solid and Liquid and equipment for separating liquid from solid thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant