CN110120643B - A method for uninterrupted operation of ground potential distribution network power lines - Google Patents

A method for uninterrupted operation of ground potential distribution network power lines Download PDF

Info

Publication number
CN110120643B
CN110120643B CN201910318800.0A CN201910318800A CN110120643B CN 110120643 B CN110120643 B CN 110120643B CN 201910318800 A CN201910318800 A CN 201910318800A CN 110120643 B CN110120643 B CN 110120643B
Authority
CN
China
Prior art keywords
rod
pole
insulating
operator
load
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910318800.0A
Other languages
Chinese (zh)
Other versions
CN110120643A (en
Inventor
洪盟忠
徐科
汪宁
方利剑
孙红晓
余镇海
潘磊
张堡
胡维洲
黄夏丽
方新泽
陈雪鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chunan County Electric Power Industry Co ltd
ChunAn Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Chunan County Electric Power Industry Co ltd
ChunAn Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chunan County Electric Power Industry Co ltd, ChunAn Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical Chunan County Electric Power Industry Co ltd
Priority to CN201910318800.0A priority Critical patent/CN110120643B/en
Publication of CN110120643A publication Critical patent/CN110120643A/en
Application granted granted Critical
Publication of CN110120643B publication Critical patent/CN110120643B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

本发明提供一种地电位配网电力线路不停电作业方法,对登杆的工作人员进行编号,通过杆上1号工作人员、杆上2号工作人员和杆上3号工作人员的协作工作实现最大效率的不停电作业操作,接着进行安装杆上开关,并测量线路电流、测量和制作引线及安装六相引线,然后电源侧和负荷侧设置绝缘遮蔽罩,紧接着搭接柱上开关负荷侧和电源侧六相引线试塔,接着搭接负荷开关负荷侧中相引线和拆除绝缘遮蔽措施,然后搭接负荷开关负荷侧边相引线和搭接负荷开关电源侧边相引线,最后断线路耐张杆原负荷侧和电源侧引流线。本发明实现了地电位配网电力线路不停电作业操作,有效提高不停电作业的安全性和效率,保证地电位配网电力线路不停电高效运转。

Figure 201910318800

The invention provides a method for uninterrupted operation of power lines of a ground potential distribution network. The numbering of the staff on the pole is realized by the cooperative work of the No. 1 staff on the pole, the No. 2 staff on the pole and the No. 3 staff on the pole. The most efficient operation without power failure, then switch on the installation pole, measure the line current, measure and fabricate the lead and install the six-phase lead, then set the insulation shield on the power supply side and the load side, and then switch the load side on the lap pole Test the tower with the six-phase lead on the power supply side, then overlap the middle phase lead on the load side of the load switch and remove the insulation shielding measures, then overlap the phase lead on the load side of the load switch and the phase lead on the power supply side of the load switch, and finally disconnect the line resistance. Drainage lines on the original load side and power supply side of the tension rod. The invention realizes the uninterrupted operation of the power lines of the ground potential distribution network, effectively improves the safety and efficiency of the uninterrupted operation, and ensures the uninterrupted and efficient operation of the power lines of the ground potential distribution network.

Figure 201910318800

Description

一种地电位配网电力线路不停电作业方法A method for uninterrupted operation of ground potential distribution network power lines

技术领域technical field

本发明涉及电力的技术领域,尤其涉及一种地电位配网电力线路不停电作业方法。The invention relates to the technical field of electric power, in particular to a method for uninterrupted operation of power lines in a ground potential distribution network.

背景技术Background technique

带电作业是电网设备检测、检修维护和改造的重要手段和方法,是保证电力系统可靠稳定运行的重要技术措施。随着配电网供电可靠性要求的不断提高,配电线路带电作业和不停电作业法也得到广泛应用和推广。带电作业关键技术参数主要包括最小安全距离、最小组合间隙和绝缘工具最小有效绝缘长度等。随着我国经济的快速发展和人民生活水平的不断提高,用户对供电可靠性要求日益提高。此外,随着城市化水平的快速推进,需要改造道路,迁移线路、箱式变压器、环网柜、电缆等情况日益增多。故亟需开发一种地电位配网电力线路不停电作业方法来解决现有技术中的问题。Live work is an important means and method for power grid equipment inspection, maintenance and renovation, and an important technical measure to ensure the reliable and stable operation of the power system. With the continuous improvement of the reliability requirements of the power supply of the distribution network, the live operation and uninterrupted operation methods of the distribution line have also been widely used and promoted. The key technical parameters of live work mainly include minimum safety distance, minimum combination gap and minimum effective insulation length of insulating tools. With the rapid development of my country's economy and the continuous improvement of people's living standards, users' requirements for power supply reliability are increasing. In addition, with the rapid advancement of urbanization, roads need to be renovated, and the number of relocation lines, box-type transformers, ring network cabinets, and cables is increasing. Therefore, there is an urgent need to develop a method for uninterrupted operation of power lines in a ground potential distribution network to solve the problems in the prior art.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于提供一种地电位配网电力线路不停电作业方法,能够实现地电位配网电力线路的停电作业,保证用户不间断供电,实现不停电检修。The purpose of the present invention is to provide an uninterrupted operation method for the power lines of the ground potential distribution network, which can realize the uninterrupted operation of the power lines of the ground potential distribution network, ensure the uninterrupted power supply of users, and realize the uninterrupted maintenance.

为了达到上述目的,本发明采用如下技术方案:一种地电位配网电力线路不停电作业方法,包括如下步骤:In order to achieve the above purpose, the present invention adopts the following technical scheme: a method for uninterrupted operation of power lines of a ground potential distribution network, comprising the following steps:

S1、登杆:对登杆人员进行编号,分为1号作业人员、2号作业人员和3号作业人员;S1. Climbing the pole: Number the pole-climbing personnel and divide them into No. 1 operator, No. 2 operator and No. 3 operator;

S2、安装杆上开关:地面电工使用绝缘绳将绝缘测距杆传递给杆上2号作业人员,杆上1号作业人员使用绝缘测距杆测量,在距主线下横担0.8m处安装支线负荷开关的位置,做好标志,然后安装绝缘横担遮蔽挡板,接着安装支线负荷开关和杆上电缆,安装结束后拆除绝缘横担遮蔽挡板;S2. Install the switch on the pole: the ground electrician uses an insulating rope to pass the insulating distance measuring pole to the No. 2 operator on the pole, and the No. 1 operator on the pole uses the insulating distance measuring pole to measure, and install the branch line 0.8m away from the cross arm under the main line Mark the position of the load switch, then install the insulating cross-arm shielding baffle, then install the branch line load switch and the cable on the pole, and remove the insulating cross-arm shielding baffle after installation;

S3、测量线路电流:杆上1号作业人员使用绝缘杆电流表测三相主导线电流并做好记录;S3. Measure line current: The No. 1 operator on the pole uses an insulating pole ammeter to measure the current of the three-phase main line and make a record;

S4、测量和制作引线及安装六相引线:杆上1号作业人员用绝缘测距杆测量出每相柱上开关电源侧桩头和负荷侧桩头至各相导线间的引线长度,并根据测量引线长度制作六根支线引线;S4. Measure and make lead wires and install six-phase lead wires: The No. 1 operator on the pole measures the lead length from the switch power supply side pile head and the load side pile head on each phase column to the wires of each phase with an insulated distance measuring rod, and according to Measure the lead length to make six branch leads;

S5、电源侧和负荷侧设置绝缘遮蔽罩:地面作业人员将绝缘叉杆操作杆、绝缘遮蔽罩依次传递给杆上2号作业人员,杆上1号作业人员使用绝缘叉杆操作杆将绝缘遮蔽罩设置在电源侧和负荷侧两边相导线上,进行绝缘遮蔽;S5. Install insulating shields on the power supply side and the load side: the ground operators pass the insulating fork rod operating rod and the insulating shielding cover to the No. 2 operator on the pole in turn, and the No. 1 operator on the pole uses the insulating fork rod operating rod to shield the insulation The cover is arranged on the phase conductors on both sides of the power supply side and the load side for insulation shielding;

S6、搭接柱上开关负荷侧和电源侧六相引线试塔:杆上1号作业人员在杆上2号作业人员的配合下把六相引线分别安装在相对应的柱上开关的电源侧和负荷侧桩头上,拉开柱上开关的刀闸,使刀闸处于断开状态;地面作业人员将绝缘线夹操作杆、绝缘锁杆操作杆、绝缘套筒操作杆依次传递给杆上2号作业人员,杆上1号作业人员调整好位置,用绝缘锁杆操作杆锁住边相引线的自由端,在边相主导线搭接处进行试搭,察看引线是否够长,两边相引线试搭后,调整好两边相引线的长度,然后对柱上开关负荷侧的另三相引线也进行试搭,察看引线的长度是否够长;杆上1号作业人员使用绝缘叉杆操作杆取下负荷侧导线上的绝缘遮蔽罩;S6. Test tower of six-phase leads on the load side and power supply side of the switch on the lap column: The No. 1 operator on the pole, with the cooperation of the No. 2 operator on the pole, installs the six-phase lead on the power supply side of the corresponding column switch respectively. On the pile head on the load side, pull open the knife switch of the switch on the column, so that the knife switch is in a disconnected state; the ground operator transmits the operating rod of the insulating wire clamp, the operating rod of the insulating lock rod, and the operating rod of the insulating sleeve to the rod in turn. Operator No. 2, the operator No. 1 on the rod adjusts the position, locks the free end of the side-phase lead with the insulating lock rod operating rod, and tries to lap the edge-phase main lead to check whether the lead is long enough, and the two sides are connected to each other. After the lead wire is tested, adjust the length of the phase leads on both sides, and then test the other three-phase leads on the load side of the switch on the column to check whether the length of the lead is long enough; the No. 1 operator on the pole uses an insulating fork lever to operate the lever Remove the insulating shield on the load side wire;

S7、搭接负荷开关负荷侧中相引线和拆除绝缘遮蔽措施:杆上1号工作人员与杆上2号工作人员相互配合搭接中相引线,每相引线安装2只异型线夹,杆上1号作业人员用绝缘锁杆锁住柱上开关负荷侧中相引线的自由端,在中相带电主导线搭接处进行试搭,杆上2号作业人员用绝缘线夹操作杆将异形线夹安装在中相主导线搭接处,杆上1号作业人员用绝缘锁杆将中相引线自由端穿入异形线夹内;杆上3号作业人员用绝缘套筒操作杆将异形线夹的各螺栓拧紧,并检查连接是否牢固可靠;杆上1号作业人使用绝缘叉杆操作杆取下电源侧导线上的绝缘遮蔽罩;S7. Measures for connecting the middle phase lead on the load side of the load switch and removing the insulation shielding measures: the No. 1 staff on the pole and the No. 2 staff on the pole cooperate with each other to overlap the middle phase lead, each phase lead is installed with 2 special-shaped clips, and the pole Operator No. 1 locks the free end of the middle-phase lead wire on the load side of the switch on the column with an insulating lock rod, and conducts a trial connection at the lap joint of the live main wire of the middle-phase. The clip is installed at the lap joint of the main wire of the middle phase. The No. 1 operator on the pole uses an insulating lock rod to insert the free end of the middle phase lead into the special-shaped wire clip; the No. 3 operator on the pole uses an insulating sleeve to operate the rod to clamp the special-shaped wire. Tighten the bolts on the power supply side, and check whether the connection is firm and reliable; the No. 1 operator on the pole uses the insulating fork lever to remove the insulating shield on the power supply side wire;

S8、搭接负荷开关负荷侧边相引线:杆上1号作业人员、杆上2号作业人员和杆上3号作业人员相互配合按相同的作业方法搭接负荷开关负荷侧另一边相引线;三相引线搭接完毕后,要检查相间距离是否符合规范,工作负责人用望远镜查看异形线夹或穿刺线夹的螺丝紧固情况,装置是否符合规范;S8. Lap the load side phase lead of the load switch: the No. 1 operator on the pole, the No. 2 operator on the pole, and the No. 3 operator on the pole cooperate with each other to overlap the phase lead on the other side of the load side of the load switch according to the same operation method; After the three-phase lead wires are overlapped, check whether the interphase distance meets the specifications. The person in charge of the work uses a telescope to check the screw tightening of the special-shaped wire clip or puncture wire clip, and whether the device meets the specifications;

S9、搭接负荷开关电源侧边相引线:杆上1号作业人员用绝缘锁杆锁住负荷开关电源侧边相引线的自由端,杆上2号作业人员用绝缘线夹操作杆将异形线夹,安装在边相主导线搭接处,杆上1号作业人员用绝缘锁杆将边相引线自由端穿入异形线夹内,杆上3号作业人员用绝缘套筒操作杆将异形线夹的各螺栓拧紧,并检查连接是否牢固可靠,采用同样的方式搭接负荷开关电源侧另一边相引线;S9. Lap the side phase lead of the load switch power supply: the No. 1 operator on the pole locks the free end of the side phase lead of the load switch power supply with an insulating lock rod, and the No. 2 operator on the pole uses an insulated wire clamp to operate the rod to lock the special-shaped wire The clamp is installed at the overlap of the side-phase main wires. The No. 1 operator on the pole uses an insulating lock rod to insert the free end of the side-phase lead into the special-shaped wire clip. Tighten the bolts of the clamp, and check whether the connection is firm and reliable, and use the same method to overlap the phase lead on the other side of the power supply side of the load switch;

S10、断线路耐张杆原负荷侧和电源侧引流线:杆上1号作业人员与杆上2号作业人员和杆上3号作业人员相互配合剪断线路耐张杆原负荷侧和电源侧边相引流线;作业人员全面检查杆上装置安全可靠,并确定杆上无遗留物后,杆上1号作业人员与杆上2号作业人员和杆上3号作业人员依次下杆。S10. Drainage lines on the original load side and the power supply side of the tension rod of the broken line: the No. 1 operator on the pole, the No. 2 operator on the pole and the No. 3 operator on the pole cooperate with each other to cut the original load side and the power supply side of the line tension pole Phase drainage line; the operator comprehensively checks the safety and reliability of the device on the pole, and after confirming that there is no residue on the pole, the No. 1 operator on the pole, the No. 2 operator on the pole, and the No. 3 operator on the pole sequentially lower the pole.

在本实施例中,S2中,绝缘横担遮蔽挡板的具体安装步骤如下:地面作业人员将两片绝缘横坦遮蔽挡板依次传递给杆上2号作业人员,杆上1号作业人员将扎钩固定在主导线下横担的抱箍螺栓上,然后将两片遮蔽挡板安放进双片夹板中锁住,并与电杆捆绑牢固。In this embodiment, in S2, the specific installation steps of the insulating cross-arm shielding baffle are as follows: the ground operator transfers the two insulating transverse shielding baffles to the No. 2 operator on the pole in turn, and the No. 1 operator on the pole The hook is fixed on the hoop bolt of the cross arm under the main wire, and then the two shielding baffles are placed in the double-piece splint to lock, and are firmly tied to the pole.

在本实施例中,S2中,安装支线负荷开关和杆上电缆的具体步骤如下:I、地面作业人员使用绝缘绳将钢丝套传递给2号作业人员,杆上1号作业人员将钢丝套套牢水泥杆后移至下横担下方处,并将2号作业人员传递上的绝缘三轮滑车组的定滑轮端挂入钢丝套中;II、地面作业人员将绝缘三轮滑车组的动滑轮端挂入负荷开关吊绳中,滑车组绳通过杆根转向滑车收紧,将负荷开关拧浮,地面作业人员在负荷开关上安装氧化锌避雷器及负荷开关杆上固定架后,继续收紧滑车组绳,将负荷开关提升至主线横担下方1.5-2.5m处的水泥杆上固定,并将负荷开关的开关和刀闸都拉开,负荷开关固定后拆除绝缘三轮滑车组和钢丝套;杆上1号作业人员使用钢丝套将小滑车固定在负荷开关安装处附近的水泥杆上,将绝缘工作绳一端通过滑车系牢电缆线头下2米,地面作业人员收紧绝缘工作绳的另一端,使电缆线头提升至负荷开关上侧,杆上1号作业人员和杆上2号作业人员配合将电缆头固定在负荷开关负荷端,然后安装杆上固定电缆抱箍、电缆护套管和氧化锌避雷器的引下线连接,接着拆除钢丝套和滑车。In the present embodiment, in S2, the concrete steps of installing the branch line load switch and the cable on the pole are as follows: 1. The ground operator uses the insulating rope to transfer the wire sleeve to the No. 2 operator, and the No. 1 operator on the pole will fasten the wire sleeve The cement pole is moved to the bottom of the lower cross arm, and the fixed pulley end of the insulated tricycle block passed by the No. 2 operator is hung into the steel wire sleeve; II. The ground operator hangs the movable pulley end of the insulated tricycle block. Put into the load switch sling, the pulley rope is tightened through the pole root steering pulley, and the load switch is unscrewed. After the ground operator installs the zinc oxide arrester on the load switch and the fixing frame on the load switch rod, continue to tighten the pulley rope , lift the load switch to the cement pole 1.5-2.5m below the main line cross arm and fix it, and open the switch and knife switch of the load switch. After the load switch is fixed, remove the insulated tricycle block and wire sleeve; The No. 1 operator uses a steel wire sleeve to fix the small pulley on the cement pole near the installation of the load switch, and fastens one end of the insulating working rope 2 meters below the cable head through the pulley, and the ground operators tighten the other end of the insulating working rope to make the The cable head is lifted to the upper side of the load switch, the No. 1 operator on the pole and the No. 2 operator on the pole cooperate to fix the cable head on the load end of the load switch, and then install the pole to fix the cable hoop, cable sheath and zinc oxide arrester the down-conductor connection, then remove the wire sleeve and pulley.

在本实施例中,S5中,绝缘叉杆操作杆的有效绝缘长度大于0.7m。In this embodiment, in S5, the effective insulation length of the insulating fork lever operating rod is greater than 0.7m.

在本实施例中,S5中,导线和绝缘遮蔽罩重叠部分大于15cm。In this embodiment, in S5, the overlapping portion of the wire and the insulating shield is greater than 15 cm.

在本实施例中,S6中,六相引线安装时,六相引线的另一端朝向负荷侧桩头方向,引线与带电导体之间的空气距离小于0.4m。In this embodiment, in S6, when the six-phase lead is installed, the other end of the six-phase lead faces the direction of the pile head on the load side, and the air distance between the lead and the live conductor is less than 0.4m.

在本实施例中,S7中,引线与电杆之间的距离大于30cm。In this embodiment, in S7, the distance between the lead and the pole is greater than 30 cm.

在本实施例中,S10中,杆上1号作业人员与杆上2号作业人员和杆上3号作业人员相互配合剪断线路耐张杆原负荷侧和电源侧边相引流线具体包括如下步骤:a、地面作业人员使用绝缘工作绳将绝缘锁杆、绝缘剪刀依次传递给杆上2号作业人员;b、杆上2号作业人员戴好绝缘手套和防护手套使用绝缘锁杆锁住负荷侧边相引线导线侧合适位置;c、杆上1号作业人员使用绝缘断线剪刀将引线的导线侧剪断;d、杆上2号作业人员用绝缘锁杆将剪断的引线放下至合适位置,并与横担等导电体保持足够的安全距离;e、杆上1号作业人员转位至电源侧合适位置,杆上3号作业人员戴好绝缘手套和防护手套使用绝缘锁杆锁住电源侧边相引线导线侧合适位置,杆上1号作业人员使用绝缘断线剪刀将引线的导线侧剪断;f、杆上1号作业人员分别将横担侧的引流线剪断;杆上2号作业人员使用绝缘工作绳将剪断的引流线传递至地面。In this embodiment, in S10, the No. 1 operator on the pole, the No. 2 operator on the pole, and the No. 3 operator on the pole cooperate with each other to cut the drain line between the original load side and the power supply side of the line tension rod, specifically including the following steps : a. The ground operator uses the insulating work rope to pass the insulating lock rod and the insulating scissors to the No. 2 worker on the pole in turn; b. The No. 2 worker on the pole wears insulating gloves and protective gloves and uses the insulating lock bar to lock the load side Appropriate position on the lead wire side of the side-phase lead; c. The No. 1 operator on the pole cuts off the wire side of the lead wire with insulated wire cutting scissors; d. The No. 2 operator on the pole uses an insulating lock rod to lower the cut lead to a suitable position, and Keep a sufficient safety distance from conductors such as cross arms; e. The No. 1 operator on the pole is moved to a suitable position on the power supply side, and the No. 3 operator on the pole wears insulating gloves and protective gloves, and uses an insulating lock rod to lock the side of the power supply At the appropriate position on the wire side of the phase lead, the No. 1 operator on the pole cuts off the wire side of the lead wire with insulated wire scissors; f. The No. 1 operator on the pole cuts the drainage wire on the cross arm side respectively; the No. 2 operator on the pole uses Insulated work ropes deliver the cut drain wire to the ground.

采用上述技术方案后,本发明对登杆的工作人员进行编号,分成杆上1号工作人员、杆上2号工作人员和杆上3号工作人员,通过杆上1号工作人员、杆上2号工作人员和杆上3号工作人员的协作工作实现最大效率的不停电作业操作,接着进行安装杆上开关操作,并由1号工作人员用绝缘杆电流表测三相主导线电流并作记录,杆上1号作业人员用绝缘测距杆测量出每相柱上开关电源侧桩头和负荷侧桩头至各相导线间的引线长度,并根据测量引线长度制作六根支线引线,然后电源侧和负荷侧设置绝缘遮蔽罩,紧接着搭接柱上开关负荷侧和电源侧六相引线试塔,接着搭接负荷开关负荷侧中相引线和拆除绝缘遮蔽措施,然后搭接负荷开关负荷侧边相引线和搭接负荷开关电源侧边相引线,最后断线路耐张杆原负荷侧和电源侧引流线。通过杆上1号工作人员、杆上2号工作人员和杆上3号工作人员的高效配合操作,实现了地电位配网电力线路不停电作业操作,有效提高不停电作业的安全性和效率,保证地电位配网电力线路不停电高效运转。After the above technical solution is adopted, the present invention numbers the staff on the pole, and divides them into No. 1 staff on the pole, No. 2 staff on the pole and No. 3 staff on the pole. The cooperative work of No. 1 staff and No. 3 staff on the pole realizes the maximum efficiency of non-stop operation, and then performs the switch operation on the installation pole, and the No. 1 staff uses an insulating rod ammeter to measure the current of the three-phase main line and record it. The No. 1 operator on the pole measures the lead length from the switch power supply side pile head and the load side pile head on each phase column to the wires of each phase with an insulated distance measuring rod, and makes six branch lead wires according to the measured lead length, and then the power supply side and The load side is provided with an insulating shield, followed by the test tower of the six-phase lead of the switch load side and the power supply side on the lap column, and then the middle phase lead of the load side of the load switch is overlapped and the insulation shielding measures are removed, and then the load side phase of the load switch is overlapped. Lead and overlap the phase lead on the side of the load switch power supply, and finally disconnect the original load side of the line tension rod and the drain line on the power supply side. Through the efficient cooperation of the No. 1 staff on the pole, the No. 2 staff on the pole and the No. 3 staff on the pole, the uninterrupted operation of the power lines of the ground potential distribution network is realized, and the safety and efficiency of the uninterrupted operation are effectively improved. Ensure that the power lines of the ground potential distribution network operate efficiently without interruptions.

附图说明Description of drawings

下面结合附图对本发明作进一步说明:The present invention will be further described below in conjunction with the accompanying drawings:

图1为本发明提出的一种地电位配网电力线路不停电作业方法的流程示意图。FIG. 1 is a schematic flowchart of a method for uninterrupted operation of a power line in a ground potential distribution network proposed by the present invention.

具体实施方式Detailed ways

下面结合附图和具体实施例对本发明作进一步说明。需要理解的是,下述的“上”、“下”、“左”、“右”、“纵向”、“横向”、“内”、“外”、“竖直”、“水平”、“顶”、“底”等指示方位或位置关系的词语仅基于附图所示的方位或位置关系,仅为了便于描述本发明和简化描述,而不是指示或暗示所指的装置/元件必须具有特定的方位或以特定的方位构造和操作,因此不能理解为对本发明的限制。The present invention will be further described below with reference to the accompanying drawings and specific embodiments. It should be understood that the following "up", "down", "left", "right", "portrait", "horizontal", "inner", "outer", "vertical", "horizontal", " The words indicating the orientation or positional relationship such as "top" and "bottom" are only based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device/element must have a specific orientation or be constructed and operated in a particular orientation, and therefore should not be construed as limiting the invention.

如图1所示,本发明提供一种地电位配网电力线路不停电作业方法,包括如下步骤:As shown in FIG. 1 , the present invention provides a method for uninterrupted operation of power lines in a ground potential distribution network, including the following steps:

S1、登杆:对登杆人员进行编号,分为1号作业人员、2号作业人员和3号作业人员;S1. Climbing the pole: Number the pole-climbing personnel and divide them into No. 1 operator, No. 2 operator and No. 3 operator;

S2、安装杆上开关:地面电工使用绝缘绳将绝缘测距杆传递给杆上2号作业人员,杆上1号作业人员使用绝缘测距杆测量,在距主线下横担0.8m处安装支线负荷开关的位置,做好标志,然后安装绝缘横担遮蔽挡板,接着安装支线负荷开关和杆上电缆,安装结束后拆除绝缘横担遮蔽挡板;S2. Install the switch on the pole: the ground electrician uses an insulating rope to pass the insulating distance measuring pole to the No. 2 operator on the pole, and the No. 1 operator on the pole uses the insulating distance measuring pole to measure, and install the branch line 0.8m away from the cross arm under the main line Mark the position of the load switch, then install the insulating cross-arm shielding baffle, then install the branch line load switch and the cable on the pole, and remove the insulating cross-arm shielding baffle after installation;

S3、测量线路电流:杆上1号作业人员使用绝缘杆电流表测三相主导线电流并做好记录;S3. Measure line current: The No. 1 operator on the pole uses an insulating pole ammeter to measure the current of the three-phase main line and make a record;

S4、测量和制作引线及安装六相引线:杆上1号作业人员用绝缘测距杆测量出每相柱上开关电源侧桩头和负荷侧桩头至各相导线间的引线长度,并根据测量引线长度制作六根支线引线;S4. Measure and make lead wires and install six-phase lead wires: The No. 1 operator on the pole measures the lead length from the switch power supply side pile head and the load side pile head on each phase column to the wires of each phase with an insulated distance measuring rod, and according to Measure the lead length to make six branch leads;

S5、电源侧和负荷侧设置绝缘遮蔽罩:地面作业人员将绝缘叉杆操作杆、绝缘遮蔽罩依次传递给杆上2号作业人员,杆上1号作业人员使用绝缘叉杆操作杆将绝缘遮蔽罩设置在电源侧和负荷侧两边相导线上,进行绝缘遮蔽;S5. Install insulating shields on the power supply side and the load side: the ground operators pass the insulating fork rod operating rod and the insulating shielding cover to the No. 2 operator on the pole in turn, and the No. 1 operator on the pole uses the insulating fork rod operating rod to shield the insulation The cover is arranged on the phase conductors on both sides of the power supply side and the load side for insulation shielding;

S6、搭接柱上开关负荷侧和电源侧六相引线试塔:杆上1号作业人员在杆上2号作业人员的配合下把六相引线分别安装在相对应的柱上开关的电源侧和负荷侧桩头上,拉开柱上开关的刀闸,使刀闸处于断开状态;地面作业人员将绝缘线夹操作杆、绝缘锁杆操作杆、绝缘套筒操作杆依次传递给杆上2号作业人员,杆上1号作业人员调整好位置,用绝缘锁杆操作杆锁住边相引线的自由端,在边相主导线搭接处进行试搭,察看引线是否够长,两边相引线试搭后,调整好两边相引线的长度,然后对柱上开关负荷侧的另三相引线也进行试搭,察看引线的长度是否够长;杆上1号作业人员使用绝缘叉杆操作杆取下负荷侧导线上的绝缘遮蔽罩;S6. Test tower of six-phase leads on the load side and power supply side of the switch on the lap column: The No. 1 operator on the pole, with the cooperation of the No. 2 operator on the pole, installs the six-phase lead on the power supply side of the corresponding column switch respectively. On the pile head on the load side, pull open the knife switch of the switch on the column, so that the knife switch is in a disconnected state; the ground operator transmits the operating rod of the insulating wire clamp, the operating rod of the insulating lock rod, and the operating rod of the insulating sleeve to the rod in turn. Operator No. 2, the operator No. 1 on the rod adjusts the position, locks the free end of the side-phase lead with the insulating lock rod operating rod, and tries to lap the edge-phase main lead to check whether the lead is long enough, and the two sides are connected to each other. After the lead wire is tested, adjust the length of the phase leads on both sides, and then test the other three-phase leads on the load side of the switch on the column to check whether the length of the lead is long enough; the No. 1 operator on the pole uses an insulating fork lever to operate the lever Remove the insulating shield on the load side wire;

S7、搭接负荷开关负荷侧中相引线和拆除绝缘遮蔽措施:杆上1号工作人员与杆上2号工作人员相互配合搭接中相引线,每相引线安装2只异型线夹,杆上1号作业人员用绝缘锁杆锁住柱上开关负荷侧中相引线的自由端,在中相带电主导线搭接处进行试搭,杆上2号作业人员用绝缘线夹操作杆将异形线夹安装在中相主导线搭接处,杆上1号作业人员用绝缘锁杆将中相引线自由端穿入异形线夹内;杆上3号作业人员用绝缘套筒操作杆将异形线夹的各螺栓拧紧,并检查连接是否牢固可靠;杆上1号作业人使用绝缘叉杆操作杆取下电源侧导线上的绝缘遮蔽罩;S7. Measures for connecting the middle phase lead on the load side of the load switch and removing the insulation shielding measures: the No. 1 staff on the pole and the No. 2 staff on the pole cooperate with each other to overlap the middle phase lead, each phase lead is installed with 2 special-shaped clips, and the pole Operator No. 1 locks the free end of the middle-phase lead wire on the load side of the switch on the column with an insulating lock rod, and conducts a trial connection at the lap joint of the live main wire of the middle-phase. The clip is installed at the lap joint of the main wire of the middle phase. The No. 1 operator on the pole uses an insulating lock rod to insert the free end of the middle phase lead into the special-shaped wire clip; the No. 3 operator on the pole uses an insulating sleeve to operate the rod to clamp the special-shaped wire. Tighten the bolts on the power supply side, and check whether the connection is firm and reliable; the No. 1 operator on the pole uses the insulating fork lever to remove the insulating shield on the power supply side wire;

S8、搭接负荷开关负荷侧边相引线:杆上1号作业人员、杆上2号作业人员和杆上3号作业人员相互配合按相同的作业方法搭接负荷开关负荷侧另一边相引线;三相引线搭接完毕后,要检查相间距离是否符合规范,工作负责人用望远镜查看异形线夹或穿刺线夹的螺丝紧固情况,装置是否符合规范;S8. Lap the load side phase lead of the load switch: the No. 1 operator on the pole, the No. 2 operator on the pole, and the No. 3 operator on the pole cooperate with each other to overlap the phase lead on the other side of the load side of the load switch according to the same operation method; After the three-phase lead wires are overlapped, check whether the interphase distance meets the specifications. The person in charge of the work uses a telescope to check the screw tightening of the special-shaped wire clip or puncture wire clip, and whether the device meets the specifications;

S9、搭接负荷开关电源侧边相引线:杆上1号作业人员用绝缘锁杆锁住负荷开关电源侧边相引线的自由端,杆上2号作业人员用绝缘线夹操作杆将异形线夹,安装在边相主导线搭接处,杆上1号作业人员用绝缘锁杆将边相引线自由端穿入异形线夹内,杆上3号作业人员用绝缘套筒操作杆将异形线夹的各螺栓拧紧,并检查连接是否牢固可靠,采用同样的方式搭接负荷开关电源侧另一边相引线;S9. Lap the side phase lead of the load switch power supply: the No. 1 operator on the pole locks the free end of the side phase lead of the load switch power supply with an insulating lock rod, and the No. 2 operator on the pole uses an insulated wire clamp to operate the rod to lock the special-shaped wire The clamp is installed at the overlap of the side-phase main wires. The No. 1 operator on the pole uses an insulating lock rod to insert the free end of the side-phase lead into the special-shaped wire clip. Tighten the bolts of the clamp, and check whether the connection is firm and reliable, and use the same method to overlap the phase lead on the other side of the power supply side of the load switch;

S10、断线路耐张杆原负荷侧和电源侧引流线:杆上1号作业人员与杆上2号作业人员和杆上3号作业人员相互配合剪断线路耐张杆原负荷侧和电源侧边相引流线;作业人员全面检查杆上装置安全可靠,并确定杆上无遗留物后,杆上1号作业人员与杆上2号作业人员和杆上3号作业人员依次下杆。S10. Drainage lines on the original load side and the power supply side of the tension rod of the broken line: the No. 1 operator on the pole, the No. 2 operator on the pole and the No. 3 operator on the pole cooperate with each other to cut the original load side and the power supply side of the line tension pole Phase drainage line; the operator comprehensively checks the safety and reliability of the device on the pole, and after confirming that there is no residue on the pole, the No. 1 operator on the pole, the No. 2 operator on the pole, and the No. 3 operator on the pole sequentially lower the pole.

在本实施例中,S2中,绝缘横担遮蔽挡板的具体安装步骤如下:地面作业人员将两片绝缘横坦遮蔽挡板依次传递给杆上2号作业人员,杆上1号作业人员将扎钩固定在主导线下横担的抱箍螺栓上,然后将两片遮蔽挡板安放进双片夹板中锁住,并与电杆捆绑牢固。In this embodiment, in S2, the specific installation steps of the insulating cross-arm shielding baffle are as follows: the ground operator transfers the two insulating transverse shielding baffles to the No. 2 operator on the pole in turn, and the No. 1 operator on the pole The hook is fixed on the hoop bolt of the cross arm under the main wire, and then the two shielding baffles are placed in the double-piece splint to lock, and are firmly tied to the pole.

在本实施例中,S2中,安装支线负荷开关和杆上电缆的具体步骤如下:I、地面作业人员使用绝缘绳将钢丝套传递给2号作业人员,杆上1号作业人员将钢丝套套牢水泥杆后移至下横担下方处,并将2号作业人员传递上的绝缘三轮滑车组的定滑轮端挂入钢丝套中;II、地面作业人员将绝缘三轮滑车组的动滑轮端挂入负荷开关吊绳中,滑车组绳通过杆根转向滑车收紧,将负荷开关拧浮,地面作业人员在负荷开关上安装氧化锌避雷器及负荷开关杆上固定架后,继续收紧滑车组绳,将负荷开关提升至主线横担下方1.5-2.5m处的水泥杆上固定,并将负荷开关的开关和刀闸都拉开,负荷开关固定后拆除绝缘三轮滑车组和钢丝套;杆上1号作业人员使用钢丝套将小滑车固定在负荷开关安装处附近的水泥杆上,将绝缘工作绳一端通过滑车系牢电缆线头下2米,地面作业人员收紧绝缘工作绳的另一端,使电缆线头提升至负荷开关上侧,杆上1号作业人员和杆上2号作业人员配合将电缆头固定在负荷开关负荷端,然后安装杆上固定电缆抱箍、电缆护套管和氧化锌避雷器的引下线连接,接着拆除钢丝套和滑车。In the present embodiment, in S2, the concrete steps of installing the branch line load switch and the cable on the pole are as follows: 1. The ground operator uses the insulating rope to transfer the wire sleeve to the No. 2 operator, and the No. 1 operator on the pole will fasten the wire sleeve The cement pole is moved to the bottom of the lower cross arm, and the fixed pulley end of the insulated tricycle block passed by the No. 2 operator is hung into the steel wire sleeve; II. The ground operator hangs the movable pulley end of the insulated tricycle block. Put into the load switch sling, the pulley rope is tightened through the pole root steering pulley, and the load switch is unscrewed. After the ground operator installs the zinc oxide arrester on the load switch and the fixing frame on the load switch rod, continue to tighten the pulley rope , lift the load switch to the cement pole 1.5-2.5m below the main line cross arm and fix it, and open the switch and knife switch of the load switch. After the load switch is fixed, remove the insulated tricycle block and wire sleeve; The No. 1 operator uses a steel wire sleeve to fix the small pulley on the cement pole near the installation of the load switch, and fastens one end of the insulating working rope 2 meters below the cable head through the pulley, and the ground operators tighten the other end of the insulating working rope to make the The cable head is lifted to the upper side of the load switch, the No. 1 operator on the pole and the No. 2 operator on the pole cooperate to fix the cable head on the load end of the load switch, and then install the pole to fix the cable hoop, cable sheath and zinc oxide arrester the down-conductor connection, then remove the wire sleeve and pulley.

在本实施例中,S5中,绝缘叉杆操作杆的有效绝缘长度大于0.7m。可以有效提高绝缘叉杆操作杆的安全性,提高带电作业操作的安全性。In this embodiment, in S5, the effective insulation length of the insulating fork lever operating rod is greater than 0.7m. The safety of the insulating fork rod operating rod can be effectively improved, and the safety of live work operation can be improved.

在本实施例中,S5中,导线和绝缘遮蔽罩重叠部分大于15cm,可以有效提高绝缘遮蔽的效果,提高了绝缘性能。In this embodiment, in S5, the overlapping portion of the wire and the insulating shielding cover is greater than 15 cm, which can effectively improve the insulating shielding effect and improve the insulating performance.

在本实施例中,S6中,六相引线安装时,六相引线的另一端朝向负荷侧桩头方向,引线与带电导体之间的空气距离小于0.4m,可以有效提高带电操作的安全性。In this embodiment, in S6, when the six-phase lead is installed, the other end of the six-phase lead faces the direction of the pile head on the load side, and the air distance between the lead and the live conductor is less than 0.4m, which can effectively improve the safety of live operation.

在本实施例中,S7中,引线与电杆之间的距离大于30cm,可以有效提高带电操作的安全性。In this embodiment, in S7, the distance between the lead and the pole is greater than 30 cm, which can effectively improve the safety of live operation.

在本实施例中,S10中,杆上1号作业人员与杆上2号作业人员和杆上3号作业人员相互配合剪断线路耐张杆原负荷侧和电源侧边相引流线具体包括如下步骤:a、地面作业人员使用绝缘工作绳将绝缘锁杆、绝缘剪刀依次传递给杆上2号作业人员;b、杆上2号作业人员戴好绝缘手套和防护手套使用绝缘锁杆锁住负荷侧边相引线导线侧合适位置;c、杆上1号作业人员使用绝缘断线剪刀将引线的导线侧剪断;d、杆上2号作业人员用绝缘锁杆将剪断的引线放下至合适位置,并与横担等导电体保持足够的安全距离;e、杆上1号作业人员转位至电源侧合适位置,杆上3号作业人员戴好绝缘手套和防护手套使用绝缘锁杆锁住电源侧边相引线导线侧合适位置,杆上1号作业人员使用绝缘断线剪刀将引线的导线侧剪断;f、杆上1号作业人员分别将横担侧的引流线剪断;杆上2号作业人员使用绝缘工作绳将剪断的引流线传递至地面。In this embodiment, in S10, the No. 1 operator on the pole, the No. 2 operator on the pole, and the No. 3 operator on the pole cooperate with each other to cut the drain line between the original load side and the power supply side of the line tension rod, specifically including the following steps : a. The ground operator uses the insulating work rope to pass the insulating lock rod and the insulating scissors to the No. 2 worker on the pole in turn; b. The No. 2 worker on the pole wears insulating gloves and protective gloves and uses the insulating lock bar to lock the load side Appropriate position on the lead wire side of the side-phase lead; c. The No. 1 operator on the pole cuts off the wire side of the lead wire with insulated wire cutting scissors; d. The No. 2 operator on the pole uses an insulating lock rod to lower the cut lead to a suitable position, and Keep a sufficient safety distance from conductors such as cross arms; e. The No. 1 operator on the pole is moved to a suitable position on the power supply side, and the No. 3 operator on the pole wears insulating gloves and protective gloves, and uses an insulating lock rod to lock the side of the power supply At the appropriate position on the wire side of the phase lead, the No. 1 operator on the pole cuts off the wire side of the lead wire with insulated wire scissors; f. The No. 1 operator on the pole cuts the drainage wire on the cross arm side respectively; the No. 2 operator on the pole uses Insulated work ropes deliver the cut drain wire to the ground.

可以理解的是,登杆操作后底面电工使用绝缘绳将绝缘测距杆传递给杆上2号工作人员,杆上1号作业人员戴绝缘手套使用绝缘测距杆测量,在距主线下横担0.8m处安装支线负荷开关的位置,做好标记,地面电工安装好绝缘遮蔽挡板手柄,调整吊杆后将绝缘吊绳扎在吊环上,地面作业人员使用绝缘绳将两片绝缘横坦遮蔽挡板依次传递给杆上2号作业人员,杆上1号作业人员戴绝缘手套,手握遮蔽挡板手柄吊杆将扎钩固定在主导线下横担的抱箍螺栓上,然后将两片遮蔽挡板安放进双片夹板中锁住,并与电杆捆绑牢固。It is understandable that the electrician on the underside uses an insulating rope to pass the insulating distance measuring rod to the No. 2 worker on the pole, and the No. 1 worker on the pole wears insulating gloves and uses the insulating distance measuring pole to measure, and cross-arm the distance from the main line. The position where the branch line load switch is installed at 0.8m is marked. The ground electrician installs the handle of the insulating shielding baffle. After adjusting the boom, the insulating suspending rope is tied to the hoisting ring. The ground operator uses the insulating rope to shield the two insulating horizontal planes. The baffle is passed to the No. 2 operator on the pole in turn. The No. 1 operator on the pole wears insulating gloves, holds the handle boom of the shielding baffle and fixes the hook on the hoop bolt of the cross arm under the main wire, and then attaches the two pieces. The shielding baffle is placed in the double-piece splint and locked, and is firmly tied to the pole.

可以理解的是,在设置绝缘遮蔽措施结束后,紧接着安装支线负荷开关和杆上电缆,地面作业人员使用绝缘绳将钢丝套传递给2号作业人员,杆上1号作业人员将钢丝套套牢水泥杆后移至下横担下方处,并将2号作业人员传递上的绝缘三轮滑车组的定滑轮端挂入钢丝套中。地面作业人员将绝缘三轮滑车组的动滑轮端挂入负荷开关吊绳中,滑车组绳通过杆根转向滑车收紧,将负荷开关拧浮。地面作业人员在负荷开关上安装氧化锌避雷器及负荷开关杆上固定架后。继续收紧滑车组绳,将负荷开关提升至主线横担下方2m左右处的水泥杆上固定,并将负荷开关的开关和刀闸都拉开。负荷开关固定后拆除绝缘三轮滑车组和钢丝套。杆上1号作业人员使用钢丝套将小滑车固定在负荷开关安装处附近的水泥杆上,将绝缘工作绳一端通过滑车系牢电缆线头下2米,地面作业人员收紧绝缘工作绳的另一端,使电缆线头提升至负荷开关上侧,杆上1号、2号作业人员配合将电缆头固定在负荷开关负荷端。然后安装杆上固定电缆抱箍、电缆护套管和氧化锌避雷器的引下线连接及拆除钢丝套和滑车。杆上1号作业人戴绝缘手套取下绝缘横坦遮蔽挡板,2号作业人员使用绝缘绳将绝缘遮蔽挡板传递至地面。It is understandable that after the insulation and shielding measures are completed, the branch line load switch and the cable on the pole are installed immediately. The ground operator uses the insulating rope to pass the wire sleeve to the No. 2 operator, and the No. 1 operator on the pole traps the wire sleeve. The cement pole is moved to the bottom of the lower cross arm, and the fixed pulley end of the insulated three-wheel pulley set passed on by the No. 2 operator is hung into the steel wire sleeve. The ground operator hangs the movable pulley end of the insulated tricycle block into the load switch sling, and the pulley rope is tightened through the pole root steering pulley to unscrew the load switch. After the ground operators install the zinc oxide arrester on the load switch and the fixing frame on the load switch pole. Continue to tighten the rope of the pulley, lift the load switch to the cement pole about 2m below the cross arm of the main line and fix it, and open the switch and the knife switch of the load switch. After the load switch is fixed, remove the insulated tricycle block and wire sleeve. The No. 1 operator on the pole uses a steel wire sleeve to fix the small pulley on the cement pole near the installation of the load switch, and fastens one end of the insulating working rope through the pulley to 2 meters below the cable head, and the ground operator tightens the other end of the insulating working rope , so that the cable head is lifted to the upper side of the load switch, and the No. 1 and No. 2 operators on the pole cooperate to fix the cable head on the load end of the load switch. Then fix the cable hoop, the cable sheath and the down-conductor connection of the zinc oxide arrester on the installation pole, and remove the steel wire sleeve and the pulley. Operator No. 1 on the pole wears insulating gloves to remove the insulating horizontal shielding baffle, and operator No. 2 uses an insulating rope to transfer the insulating shielding baffle to the ground.

可以理解的是,在负荷开关上安装并连接电缆线头时,主线下横担下方要使用横担遮蔽挡板遮蔽,确保杆上操作人员保持安全距离。It is understandable that when installing and connecting the cable head on the load switch, the cross arm shielding baffle should be used to cover the lower cross arm of the main line to ensure that the operator on the pole maintains a safe distance.

在搭接线路负荷开关电源侧和负荷侧的作业结束后,对线路杆上开关的安装和质量进行验收,确定装置符合运行标准,线路杆上开关的接线相位与导线相位相同后,使用绝缘棒合上线路杆上开关,使线路杆上开关投入运行。检查并证实线路杆上开关运行正常后,杆上1号作业人员戴好绝缘手套,使用绝缘杆式电流表测杆上开关负荷侧三相引线电流,证实负荷开关负荷侧有电流通过,并做好记录。After the work of connecting the power supply side and the load side of the line load switch is completed, check the installation and quality of the switch on the line pole, make sure that the device meets the operating standards, and use an insulating rod after the wiring phase of the switch on the line pole is the same as the phase of the conductor. Close the switch on the line pole to put the switch on the line pole into operation. After checking and verifying that the switch on the line pole is operating normally, the No. 1 operator on the pole wears insulating gloves, and uses an insulating pole-type ammeter to measure the three-phase lead current on the load side of the switch on the pole to verify that there is current passing through the load side of the load switch, and do Record.

除上述优选实施例外,本发明还有其他的实施方式,本领域技术人员可以根据本发明作出各种改变和变形,只要不脱离本发明的精神,均应属于本发明所附权利要求所定义的范围。In addition to the above-mentioned preferred embodiments, the present invention also has other embodiments, and those skilled in the art can make various changes and modifications according to the present invention, as long as they do not depart from the spirit of the present invention, they shall all belong to the definitions of the appended claims of the present invention scope.

Claims (8)

1. A method for operating a ground potential distribution network power line without power outage is characterized by comprising the following steps:
s1, climbing a rod: numbering the pole climbing personnel, and dividing the pole climbing personnel into No. 1 operating personnel, No. 2 operating personnel and No. 3 operating personnel;
s2, installing a switch on the rod: the ground electrician uses an insulating rope to transmit an insulating distance measuring rod to No. 2 operators on the rod, No. 1 operators on the rod use the insulating distance measuring rod to measure, marks the position of a branch load switch at a position 0.8m away from a cross arm under a main line, installs an insulating cross arm shielding baffle, then installs the branch load switch and a cable on the rod, and removes the insulating cross arm shielding baffle after the installation is finished;
s3, measuring line current: the operator No. 1 on the rod uses an insulating rod ammeter to measure and record the current of the three-phase wire;
s4, measuring and manufacturing a lead and installing a six-phase lead: the operator No. 1 on the pole measures the length of a lead between a power supply side pile head and a load side pile head of each phase of load switch and each phase of conductor by using an insulating distance measuring pole, and six branch leads are manufactured according to the measured lead length;
s5, arranging insulation shielding covers on the power supply side and the load side: the ground operator sequentially transfers the insulating fork rod operating rod and the insulating shielding cover to No. 2 operators on the rod, and No. 1 operators on the rod use the insulating fork rod operating rod to arrange the insulating shielding cover on the phase conductors on the two sides of the power supply side and the load side for insulating shielding;
s6, lapping the six-phase lead test tower on the load side and the power supply side of the load switch: the operator No. 1 on the pole respectively installs the six-phase lead wires on the power side and the load side pile heads of the corresponding load switches under the coordination of the operator No. 2 on the pole, and pulls open the disconnecting link of the load switches to enable the disconnecting link to be in a disconnected state; the ground operator sequentially transfers an insulating wire clamp operating rod, an insulating lock rod operating rod and an insulating sleeve operating rod to No. 2 operators on the rod, the No. 1 operator on the rod adjusts the position, the free ends of the side phase leads are locked by the insulating lock rod operating rod, trial lapping is carried out at the lap joint of the side phase leads to check whether the leads are long enough, the lengths of the side phase leads are adjusted after the side phase leads are trial lapped, then trial lapping is carried out on the other three-phase leads on the load side of the load switch, and the lengths of the leads are checked whether the leads are long enough; no. 1 operator on the rod uses an insulating fork lever operating rod to take down an insulating shielding cover on a load side conductor;
s7, lapping the middle phase lead wire on the load side of the load switch and removing the insulation shielding measures: the working personnel No. 1 on the pole and the working personnel No. 2 on the pole are matched with each other to lap the middle phase lead, each phase lead is provided with 2 special-shaped wire clamps, the working personnel No. 1 on the pole uses an insulating lock rod operating rod to lock the free end of the middle phase lead on the load side of the load switch, trial lapping is carried out at the lap joint of the middle phase live lead, the working personnel No. 2 on the pole uses the insulating wire clamp operating rod to install the special-shaped wire clamps at the lap joint of the middle phase lead, and the working personnel No. 1 on the pole uses the insulating lock rod operating rod to penetrate the free end of; the No. 3 operator on the rod uses the insulating sleeve operating rod to screw up each bolt of the special-shaped wire clamp and checks whether the connection is firm and reliable; the No. 1 worker on the rod uses the insulating fork lever to operate the rod to take down the insulating shielding cover on the power supply side wire;
s8, lapping a load side phase lead of the load switch: the operator No. 1 on the rod, the operator No. 2 on the rod and the operator No. 3 on the rod are matched with each other to lap joint the phase lead on the other side of the load switch according to the same operation method; after the three-phase lead is lapped, whether the distance between phases meets the standard or not is checked, a working person in charge checks the screw fastening condition of the special-shaped wire clamp through a telescope, and whether the device meets the standard or not is judged;
s9, lapping a side phase lead of the load switch power supply: the method comprises the following steps that 1, an operator on a rod locks the free end of a phase lead at the side of a load switch power supply by using an insulating lock rod operating rod, 2, the operator on the rod uses an insulating wire clamp operating rod to install a special-shaped wire clamp at the lap joint of side phase leads, 1, the operator on the rod uses the insulating lock rod operating rod to penetrate the free end of the side phase lead into the special-shaped wire clamp, 3, the operator on the rod uses an insulating sleeve operating rod to screw bolts of the special-shaped wire clamp tightly and check whether connection is firm and reliable, and the other side of the load switch power supply is lapped in the same mode;
s10, breaking the original load side of the tension rod and the power supply side drainage wire: the No. 1 operator on the pole, the No. 2 operator on the pole and the No. 3 operator on the pole are matched with each other to cut off the original load side and the power side phase drainage wires of the tension-resistant pole of the line; the device on the pole is examined safely and reliably comprehensively to the operating personnel to No. 1 operating personnel on the pole and No. 2 operating personnel on the pole and No. 3 operating personnel on the pole get off the pole in proper order after determining that there is no relic on the pole.
2. The uninterrupted power operation method for the power line of the ground potential distribution network according to claim 1, wherein in the step S2, the specific installation steps of the shielding baffle of the insulating cross arm are as follows: ground operating personnel shield the baffle with two insulating cross arms and transmit for No. 2 operating personnel on the pole in proper order, and No. 1 operating personnel will prick the hook and fix under the wire on the staple bolt of cross arm, then lay into biplate splint with two shield the baffle and pin to it is firm to bind with the pole.
3. The uninterrupted operation method for the power line of the ground potential distribution network according to claim 1, wherein in the step S2, the specific steps for installing the branch load switch and the cable on the rod are as follows: I. the ground operator uses an insulating rope to transmit the steel wire sleeve to No. 2 operator, the No. 1 operator on the rod sleeves the steel wire sleeve on the cement rod and then moves to the lower part of the lower cross arm, and the fixed pulley end of the insulating three-wheel sliding car group transmitted by the No. 2 operator is hung in the steel wire sleeve; II. The ground operator hangs the movable pulley end of the insulated three-wheel pulley block into a load switch lifting rope, the pulley block rope turns to the pulley through a rod root to tighten the pulley, the load switch is twisted to float, the ground operator continues to tighten the pulley block rope after installing a zinc oxide arrester and a load switch rod upper fixing frame on the load switch, the load switch is lifted to a cement rod 1.5-2.5m below a main line cross arm to be fixed, a switch and a disconnecting link of the load switch are pulled open, and the insulated three-wheel pulley block and a steel wire sleeve are removed after the load switch is fixed; no. 1 operation personnel uses the steel wire cover to fix the coaster on the near cement pole of load switch installation department on the pole, 2 meters below the firm cable end of going through the coaster with insulating work rope one end, ground operation personnel tighten up the other end of insulating work rope, make the cable end promote to the load switch upside, No. 1 operation personnel cooperates with No. 2 operation personnel on the pole and fixes the cable end at load switch load end on the pole, then fixed cable staple bolt on the installation pole, the downlead of cable sheathing pipe and zinc oxide arrester is connected, demolish steel wire cover and coaster after that.
4. The uninterrupted operation method for the power line of the ground potential distribution network according to claim 1, wherein in the step S5, the effective insulation length of the insulating fork rod operating rod is greater than 0.7 m.
5. The method of claim 1, wherein in step S5, the overlap between the conductor and the insulating shield is greater than 15 cm.
6. The uninterrupted operation method for the power line of the ground potential distribution network according to claim 1, wherein in the step S6, when the six-phase lead is installed, the other end of the six-phase lead faces the direction of the pile head on the load side, and the air distance between the lead and the live conductor is less than 0.4 m.
7. The uninterrupted operation method for the power line of the ground potential distribution network according to claim 1, wherein in the step S7, the distance between the lead and the electric pole is more than 30 cm.
8. The uninterrupted power operation method of the power line of the ground potential distribution network according to claim 1, wherein in the step S10, the step S of cutting off the phase diversion line at the original load side and the power side of the tension-resistant rod of the line by the cooperation of the operator No. 1 on the rod, the operator No. 2 on the rod and the operator No. 3 on the rod comprises the following steps: a. the ground operator uses the insulated working rope to sequentially transfer the insulated lock rod operating rod and the insulated wire-breaking scissors to No. 2 operators on the rod; b. no. 2 operators on the rod wear insulating gloves and protective gloves to lock the proper position of the phase lead wire side of the load side by using an insulating lock rod operating rod; c. no. 1 operator on the rod uses an insulated wire cutting scissors to cut off the wire side of the lead; d. the operator No. 2 on the rod uses an insulating lock rod to operate the rod to put down the cut lead to a proper position and keep a sufficient safety distance with the cross arm conductor; e. the operator No. 1 on the rod is rotated to a proper position on the power supply side, the operator No. 3 on the rod uses an insulating lock rod operating rod to lock a proper position on the phase lead wire side on the power supply side after wearing insulating gloves and protective gloves, and the operator No. 1 on the rod uses insulating wire-breaking scissors to cut off the lead wire side of the lead wire; f. no. 1 operating personnel on the pole respectively cut off the drainage threads on the cross arm side; no. 2 operating personnel use insulating work rope to transmit the drainage wire of cutting to ground on the pole.
CN201910318800.0A 2019-04-19 2019-04-19 A method for uninterrupted operation of ground potential distribution network power lines Active CN110120643B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910318800.0A CN110120643B (en) 2019-04-19 2019-04-19 A method for uninterrupted operation of ground potential distribution network power lines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910318800.0A CN110120643B (en) 2019-04-19 2019-04-19 A method for uninterrupted operation of ground potential distribution network power lines

Publications (2)

Publication Number Publication Date
CN110120643A CN110120643A (en) 2019-08-13
CN110120643B true CN110120643B (en) 2020-10-27

Family

ID=67521214

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910318800.0A Active CN110120643B (en) 2019-04-19 2019-04-19 A method for uninterrupted operation of ground potential distribution network power lines

Country Status (1)

Country Link
CN (1) CN110120643B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111697482B (en) * 2020-05-07 2021-11-23 国网浙江省电力有限公司金华供电公司 10KV overhead line non-outage moving and modifying method
CN111817202B (en) * 2020-06-30 2021-12-14 国网上海市电力公司 Arc extinction device and method for live lapping of no-load cable terminal lead of distribution line
CN112072555A (en) * 2020-09-11 2020-12-11 云南电网有限责任公司带电作业分公司 Working method for live installation of 35kV overhead line lightning arrester
CN112909822B (en) * 2021-03-10 2022-08-30 国网河南省电力公司社旗县供电公司 Unmanned aerial vehicle-assisted uninterrupted power supply operation system and method for power distribution network

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102842867A (en) * 2012-08-31 2012-12-26 辽宁省电力有限公司鞍山供电公司 Method for electrically disconnecting or connecting disconnector with drainage wire between buses
CN106356758A (en) * 2016-09-07 2017-01-25 国网浙江淳安县供电公司 Operating method for replacing pole-mounted switch live on indirect bypass of 10 KV line insulating pole
CN106451220A (en) * 2016-12-01 2017-02-22 华北电力科学研究院有限责任公司 Bypass equipment and method for live replacement of equipment on same-tower multi-loop pole tower

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102842867A (en) * 2012-08-31 2012-12-26 辽宁省电力有限公司鞍山供电公司 Method for electrically disconnecting or connecting disconnector with drainage wire between buses
CN106356758A (en) * 2016-09-07 2017-01-25 国网浙江淳安县供电公司 Operating method for replacing pole-mounted switch live on indirect bypass of 10 KV line insulating pole
CN106451220A (en) * 2016-12-01 2017-02-22 华北电力科学研究院有限责任公司 Bypass equipment and method for live replacement of equipment on same-tower multi-loop pole tower

Also Published As

Publication number Publication date
CN110120643A (en) 2019-08-13

Similar Documents

Publication Publication Date Title
CN110120643B (en) A method for uninterrupted operation of ground potential distribution network power lines
CN108155601A (en) A kind of method that on-load straight line pole changes tension-resistant rod
CN104868403B (en) A kind of portable 120~400mm2Steel-cored aluminium strand shunt line fixture and application method
CN109217151A (en) Electric substation's installation engineering method
CN101640391B (en) Live-wire operation method for replacing insulator for 35kV distribution circuit
CN206471747U (en) It is a kind of can charged for replacement insulator arrangement
CN103746315A (en) Quick hot-line by-pass jumper overlapping operation method for 10kV insulated power distribution line
CN101640392A (en) Live-wire operation method for cutting off drainage wire for 35kV distribution circuit
CN101277002B (en) Method for construction of charged assembling 10kV bi-gyrus distribution line concrete lever
CN102664358B (en) Live replacement method for static contact of 220 kV flexible busbar
CN103618252A (en) Operation method for replacing tension insulator for 35kV overhead line in electrified mode
CN107104387A (en) One kind can second lift wire insulation cross-arm and lifting wire method
CN106356758B (en) 10KV line insulations bar bypasses charged for replacement on-pole switch operational method indirectly
CN101640390A (en) Live-wire operation method for lapping drainage wire for 35kV distribution circuit
CN103474909B (en) Drainage thread supports the method for expansion live-line replacing multiloop strain insulator string
CN107482535A (en) The Method of Installing Segment Switch on Straight Rod of 10KV Line with Load Breaking
CN104505763B (en) UHVDC Transmission Lines charged for replacement duplex V string composite insulator operational methods
CN201440584U (en) The device for replacing the insulator and accessories of the tension tower of the transmission line by the ground potential
CN108390311A (en) A kind of V-type insulator chain charged for replacement method of electric power line pole tower
CN106410674A (en) Hot-line work method for 10-kV distribution line and equipment
CN104113007A (en) Operation method for replacing strain insulator of 35kV overhead distribution line in live state
CN102064498B (en) New line bridging method and special bridging line
CN211701243U (en) Electrified defect eliminating device for jumper spacer
CN114362041B (en) Method for changing straight line rod into tension rod and hardware fitting for changing straight line rod into tension rod
CN206575086U (en) Insulate turnbuckle plate pulling device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant