CN109736518A - Interior decoration construction method - Google Patents

Interior decoration construction method Download PDF

Info

Publication number
CN109736518A
CN109736518A CN201811645671.8A CN201811645671A CN109736518A CN 109736518 A CN109736518 A CN 109736518A CN 201811645671 A CN201811645671 A CN 201811645671A CN 109736518 A CN109736518 A CN 109736518A
Authority
CN
China
Prior art keywords
base
default base
default
interior decoration
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811645671.8A
Other languages
Chinese (zh)
Inventor
王焕
李占先
苏国举
刘秀芝
高艳花
袁洋
郭勇
曹晶
李腾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Construction Engineering Co Ltd of China Railway 14th Bureau Group Co Ltd
Original Assignee
China Railway 14th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 14th Bureau Group Co Ltd filed Critical China Railway 14th Bureau Group Co Ltd
Priority to CN201811645671.8A priority Critical patent/CN109736518A/en
Publication of CN109736518A publication Critical patent/CN109736518A/en
Pending legal-status Critical Current

Links

Abstract

The present invention provides a kind of interior decoration construction methods, it include: the indoor substrate surface of cleaning, substrate surface is divided into the first default base, the second default base and third and presets base, wherein substrate surface cleaning includes at least cleaning surface dust, cleaning mortar and cleaning residual liquid;Coating is sprayed into the first default base;Bulk is laid in the second default base, wherein bulk includes at least one of floor tile, clinker tile, ceramic wool brick, vitrified tile;Indoor pipeline and ventilating duct are installed, after determining lamp position, ventilation opening and the bright orifice position of dew, lightgage steel joist is lifted to third and is preset in base.Interior decoration construction method of the invention solves the problems, such as that interior decoration construction method in the prior art will appear finishing surface irregularity.

Description

Interior decoration construction method
Technical field
The present invention relates to engineering fields, in particular to a kind of interior decoration construction method.
Background technique
In the prior art, for the building of overlarge area, indoor metope mostly uses coating spraying or bulk to be laid with, and Coating is mostly used to spray or carry out furred ceiling processing top surface.
In specific fitment process, due to construction time and construction method, the method that is commonly used There are some disadvantages, such as easily cause coating hollowing, integral smoothness poor, bulk hollowing, fall off, dividing joint is irregular and metope not It is smooth and other issues.
Summary of the invention
The main purpose of the present invention is to provide a kind of interior decoration construction methods, to solve indoor dress in the prior art Repair the problem of construction method will appear finishing surface irregularity.
To achieve the goals above, the present invention provides a kind of interior decoration construction methods, comprising: clears up indoor base Substrate surface is divided into the first default base, the second default base and third and presets base, wherein substrate surface by surface Cleaning includes at least cleaning surface dust, cleaning mortar and cleaning residual liquid;Coating is sprayed into the first default base;By block Material is laid in the second default base, wherein bulk includes at least one of floor tile, clinker tile, ceramic wool brick, vitrified tile;It will Indoor pipeline and ventilating duct install, and after determining lamp position, ventilation opening and the bright orifice position of dew, lightgage steel joist is hung Third is filled to preset in base.
It further, include: the first default base after the cleaning by the method that coating is sprayed into the first default base It is upper to be watered using water sprinkler, to soak the first default base;Putty is filled up to pitted skin, honeycomb, hole in the first default base Eye and residual indentation, there, and polished using sand paper;By putty-painting in the first default base, to cover the first default base, And it is polished after putty air-dries using sand paper;Coating is sprayed on the putty after polishing.
Further, putty three times is at least smeared in the first default base, and is both needed to pass through sand paper after each smear It polishes.
Further, coating three times is at least sprayed on the putty after polishing, in addition to last time sprays, every time after spraying It is both needed to polish by sand paper.
It further, include: the second default base after the cleaning by the method that bulk is laid in the second default base It is upper to be watered using water sprinkler, to soak the second default base;Plain-water slurry is arranged in the second default base after moistening, is used Wooden rectangular slab strike off and pass through broom sweep it is even;Dry mortar is started with by default spacing from the side of the second default base The floating screed in the second default base, wherein default spacing is between 0.9m to 1.1m;By the height of floating screed in the second default base Interior plastering, and smoothed out by wooden float, so that the plastering height in the second default base is consistent;Bulk is laid on by smearing In the second default base after ash.
Further, before base is preset in wetting second, the method that bulk is laid in the second default base is also wrapped It includes: the second default base after cleaning is completely brushed one times using wire brush, to be carried out to the smooth base in the second default base Frosting treatment.
Further, the method plastered in the second default base includes: that mortar is arranged between two neighboring floating screed, benefit Flat mortar is rubbed with the hands with wooden float, so that the outer surface of floating screed is provided with mortar;Using spilling in the first default base after plastering Hydrophone watering, wherein rub flat mortar with the hands after 24 hours using wooden float, watered using water sprinkler.
Further, in the second default base before floating screed, bulk is laid on the method in the second default base also It include: in the second default base upper berth ash for being provided with plain-water slurry, wherein the speed of the sharp even plain-water slurry of broom and paving The speed of ash is consistent.
Further, lightgage steel joist is lifted to third the method preset in base includes: to preset to draw in base in third The keel stepping position line out;The sunpender of surface brush antirust paint is sequentially arranged at third according to the stepping position line to preset in base; The main joist for being assembled with suspender member is installed on sunpender;Secondary joist is mounted on suspender member.
Further, lightgage steel joist is lifted to third before presetting in base, interior decoration construction method further include: press The structural style for presetting base according to third makes model room, and pipeline, ventilating duct, lamp and lightgage steel joist are completed in model room Installation, and determine fixed form and installation site;According to the fixed form and installation site after determination, lightgage steel joist is lifted It is preset in base to third.
Interior decoration construction method of the invention by carrying out subsequent substrate surface after clearing up indoor substrate surface again Finishing, the problem of out-of-flatness can occurs to avoid the substrate surface after finishing.In specific fitment process, substrate surface is cleared up Substrate surface is divided into the first default base, the second default base and third and presets base by surface dust, mortar and residual liquid Layer, coating is sprayed into the first default base and forms coating base, bulk is laid in the second default base, by light steel Keel are lifted to third and are preset in base.Interior decoration construction method of the invention by clear up after indoor substrate surface again into The subsequent substrate surface finishing of row, the problem of out-of-flatness can occurs to avoid the substrate surface after finishing, to solve existing Interior decoration construction method in technology will appear the problem of finishing surface irregularity.
Detailed description of the invention
The accompanying drawings constituting a part of this application is used to provide further understanding of the present invention, and of the invention shows Examples and descriptions thereof are used to explain the present invention for meaning property, does not constitute improper limitations of the present invention.In the accompanying drawings:
Fig. 1 shows the flow diagram of interior decoration construction method according to the present invention.
Specific embodiment
It should be noted that in the absence of conflict, the features in the embodiments and the embodiments of the present application can phase Mutually combination.The present invention will be described in detail below with reference to the accompanying drawings and embodiments.
It is noted that following detailed description is all illustrative, it is intended to provide further instruction to the application.Unless another It indicates, all technical and scientific terms used herein has usual with the application person of an ordinary skill in the technical field The identical meanings of understanding.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singular Also it is intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " packet Include " when, indicate existing characteristics, step, operation, device, component and/or their combination.
The present invention provides a kind of interior decoration construction methods, referring to FIG. 1, interior decoration construction method includes: cleaning Substrate surface is divided into the first default base, the second default base and third and presets base by indoor substrate surface, In, substrate surface cleaning includes at least cleaning surface dust, cleaning mortar and cleaning residual liquid;Coating is sprayed into first to preset In base;Bulk is laid in the second default base, wherein bulk include floor tile, clinker tile, ceramic wool brick, in vitrified tile It is at least one;Indoor pipeline and ventilating duct are installed, after determining lamp position, ventilation opening and the bright orifice position of dew, Lightgage steel joist is lifted to third and is preset in base.
Interior decoration construction method of the invention by carrying out subsequent substrate surface after clearing up indoor substrate surface again Finishing, the problem of out-of-flatness can occurs to avoid the substrate surface after finishing.In specific fitment process, substrate surface is cleared up Substrate surface is divided into the first default base, the second default base and third and presets base by surface dust, mortar and residual liquid Layer, coating is sprayed into the first default base and forms coating base, bulk is laid in the second default base, by light steel Keel are lifted to third and are preset in base.Interior decoration construction method of the invention by clear up after indoor substrate surface again into The subsequent substrate surface finishing of row, the problem of out-of-flatness can occurs to avoid the substrate surface after finishing, to solve existing Interior decoration construction method in technology will appear the problem of finishing surface irregularity.
In the present embodiment, bulk includes at least one of floor tile, clinker tile, ceramic wool brick, vitrified tile, by by bulk It is laid in the second default base, so that the second default base forms brick wall.
In the present embodiment, indoor pipeline and ventilating duct are installed, it is bright determines lamp position, ventilation opening and dew After orifice position, lightgage steel joist is lifted to third and is preset in base, i.e., it is indoor top that third, which presets base,.
It preferably, include: in the first default base after the cleaning by the method that coating is sprayed into the first default base It is watered using water sprinkler, to soak the first default base;Putty is filled up to pitted skin, honeycomb, hole eye in the first default base And residual indentation, there, and polished using sand paper;By putty-painting in the first default base, to cover the first default base, and It is polished after putty air-dries using sand paper;Coating is sprayed on the putty after polishing.
In the present embodiment, for the specific steps being sprayed into coating in the first default base are as follows: after the cleaning It is watered in one default base using water sprinkler, to soak the first default base, is then filled up putty in the first default base Pitted skin, honeycomb, hole eye and residual indentation, there, and polished using sand paper, so as to form an opposed flattened substrate surface, Certain thickness putty is smeared in smooth substrate surface, guarantees that putty covers the first default base, benefit after putty air-dries It is polished with sand paper, finally coating is sprayed on the putty after polishing, to complete coating metope.
Preferably, putty three times is at least smeared in the first default base, and is both needed to grind by sand paper after each smear It is flat.
In the present embodiment, putty three times is at least smeared in the first default base, is both needed to grind by sand paper after smearing every time It is flat, and the granularity of the sand paper for floating is gradually reduced.
Preferably, coating three times is at least sprayed on the putty after polishing, in addition to last time sprays, every time after spraying It need to be polished by sand paper.
In the present embodiment, coating three times is at least sprayed on the putty after polishing, not in addition to last time sprayed coating It is polished outside with sand paper, requires sand paper after other sprayings and polish, and the granularity of the sand paper for floating is gradually reduced.
It preferably, include: in the second default base after the cleaning by the method that bulk is laid in the second default base It is watered using water sprinkler, to soak the second default base;Plain-water slurry is arranged in the second default base after moistening, with wood Rectangular slab processed strike off and pass through broom sweep it is even;Dry mortar is started with from the side of the second default base to exist by default spacing Floating screed in second default base, wherein default spacing is between 0.9m to 1.1m;By the height of floating screed in the second default base Plastering, and smoothed out by wooden float, so that the plastering height in the second default base is consistent;Bulk is laid on by plastering In the default base of second afterwards.
In the present embodiment, plain-water slurry is the mixture for only including water and cement.
In the present embodiment, the specific steps being laid on for bulk in the second default base are as follows: after the cleaning second It is watered in default base using water sprinkler, so that the second default base be soaked, second after moistening is arranged in plain-water slurry In default base, struck off with wooden rectangular slab and pass through broom sweep it is even, i.e., with a laminin cement in the second default base of guarantee Slurry.From the side of the second default base start with dry mortar by default spacing the floating screed in the second default base, wherein Second default link base layer is crossed floating screed and is divided into multiple regions by default spacing between 0.9m to 1.1m, then by floating screed Height is plastered in the second default base, and is smoothed out by wooden float, so that the plastering height in the second default base is consistent, Finally bulk is laid in the second default base after plastering.
In the present embodiment, the material of floating screed is consistent with subsequent plastering material.
In order to be securely provided in plain-water slurry in the second default base, wetting second preset base it Before, bulk is laid on the method in the second default base further include: expire the second default base after cleaning using wire brush It brushes one times, to carry out frosting treatment to the smooth base in the second default base.
In the present embodiment, the second default base after cleaning is completely brushed one times using wire brush, i.e., by the second default base The each region of layer requires to brush one times by wire brush, as far as possible the texturing degree phase one of each region of the second default base of guarantee Extremely.
Preferably, the method plastered in the second default base includes: that mortar is arranged between two neighboring floating screed, is utilized Wooden float rubs flat mortar with the hands, so that the outer surface of floating screed is provided with mortar;Watering is utilized in the first default base after plastering Device watering, wherein rub flat mortar with the hands after 24 hours using wooden float, watered using water sprinkler.
Preferably, in the second default base before floating screed, the method that bulk is laid in the second default base is also wrapped It includes: in the second default base upper berth ash for being provided with plain-water slurry, wherein the speed and paving ash of the sharp even plain-water slurry of broom Speed it is consistent.
In the present embodiment, it after being arranged plain-water slurry in the second default base, needs to set on plain-water slurry layer It sets and is laid with one layer of lime mortar.When specific operation, since plain-water slurry needs to sweep by broom even, even plain water is then swept again It plasters on mud.In order to guarantee that the speed that plain-water slurry is arranged is consistent with the speed of paving ash, i.e., the sharp even plain water of broom The speed of mud and the speed of paving ash are consistent it is to be understood that broom sweeps 1 square meter of even plain-water slurry per minute, then in plain water A grey square meter is spread on mud, per minute so as to which after the completion of sweeping even plain-water slurry, paving ash can also be completed therewith.
Preferably, lightgage steel joist is lifted to third the method preset in base includes: to preset to mark in base in third The keel stepping position line;The sunpender of surface brush antirust paint is sequentially arranged at third according to the stepping position line to preset in base;It will The main joist for being assembled with suspender member is installed on sunpender;Secondary joist is mounted on suspender member.
In the present embodiment, when need to lift lightgage steel joist to third preset in base when, first in third preset base On mark the keel stepping position line, that is, plan the Hoisting Position of good each lightgage steel joist, provide a basic division region.So The sunpender of surface brush antirust paint is sequentially arranged at third according to the stepping position line afterwards to preset in base, hanging will be assembled with therewith The main joist of part is installed on sunpender, and finally secondary joist is mounted on suspender member.
In view of the area of indoor hoisting lightgage steel joist is larger, lightgage steel joist is lifted to third before presetting in base, Interior decoration construction method further include: make model room according to the structural style that third presets base, pipe is completed in model room The installation of line, ventilating duct, lamp and lightgage steel joist, and determine fixed form and installation site;According to the fixation side after determination Formula and installation site, lightgage steel joist is lifted to third and is preset in base.
In the present embodiment, the setting that the setting of model room presets base with practical indoor third is restored in ratio, from And the reliability of lifting can be tried.
It can be seen from the above description that the above embodiments of the present invention realized the following chievements:
Interior decoration construction method of the invention by carrying out subsequent substrate surface after clearing up indoor substrate surface again Finishing, the problem of out-of-flatness can occurs to avoid the substrate surface after finishing.In specific fitment process, substrate surface is cleared up Substrate surface is divided into the first default base, the second default base and third and presets base by surface dust, mortar and residual liquid Layer, coating is sprayed into the first default base and forms coating base, bulk is laid in the second default base, by light steel Keel are lifted to third and are preset in base.Interior decoration construction method of the invention by clear up after indoor substrate surface again into The subsequent substrate surface finishing of row, the problem of out-of-flatness can occurs to avoid the substrate surface after finishing, to solve existing Interior decoration construction method in technology will appear the problem of finishing surface irregularity.
It should be noted that the description and claims of this application and term " first " in above-mentioned attached drawing, " Two " etc. be to be used to distinguish similar objects, without being used to describe a particular order or precedence order.It should be understood that using in this way Data be interchangeable under appropriate circumstances, so that presently filed embodiment described herein for example can be in addition to herein Sequence other than those of diagram or description is implemented.In addition, term " includes " and " having " and their any deformation, it is intended that Be to cover it is non-exclusive include, for example, containing the process, method, system, product or equipment of a series of steps or units not Those of be necessarily limited to be clearly listed step or unit, but may include be not clearly listed or for these processes, side The intrinsic other step or units of method, product or equipment.
For ease of description, spatially relative term can be used herein, as " ... on ", " ... top ", " ... upper surface ", " above " etc., for describing such as a device shown in the figure or feature and other devices or spy The spatial relation of sign.It should be understood that spatially relative term is intended to comprising the orientation in addition to device described in figure Except different direction in use or operation.For example, being described as if the device in attached drawing is squeezed " in other devices It will be positioned as " under other devices or construction after part or construction top " or the device of " on other devices or construction " Side " or " under other devices or construction ".Thus, exemplary term " ... top " may include " ... top " and " in ... lower section " two kinds of orientation.The device can also be positioned with other different modes and (is rotated by 90 ° or in other orientation), and And respective explanations are made to the opposite description in space used herein above.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any to repair Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of interior decoration construction method characterized by comprising
Indoor substrate surface is cleared up, the substrate surface is divided into the first default base, the second default base and third Default base, wherein the substrate surface cleaning includes at least cleaning surface dust, cleaning mortar and cleaning residual liquid;
Coating is sprayed into the described first default base;
Bulk is laid in the described second default base, wherein the bulk includes floor tile, clinker tile, ceramic wool brick, vitrified tile At least one of;
The indoor pipeline and ventilating duct are installed, it, will after determining lamp position, ventilation opening and the bright orifice position of dew Lightgage steel joist is lifted to the third and is preset in base.
2. interior decoration construction method according to claim 1, which is characterized in that the coating is sprayed into described first Method in default base includes:
It is watered in the described first default base after the cleaning using water sprinkler, to soak the described first default base;
Putty is filled up into pitted skin, honeycomb, hole eye and residual indentation, there in the described first default base, and is ground using sand paper It is flat;
By the putty-painting in the described first default base, to cover the described first default base, and in the putty wind It is polished after dry using sand paper;
The coating is sprayed on the putty after polishing.
3. interior decoration construction method according to claim 2, which is characterized in that in the described first default base at least The putty three times is smeared, and is both needed to polish by sand paper after each smear.
4. interior decoration construction method according to claim 2, which is characterized in that on the putty after polishing at least The coating is both needed to polish by sand paper after spraying every time in addition to last time sprays three times for spraying.
5. interior decoration construction method according to claim 1, which is characterized in that the bulk is laid on described second Method in default base includes:
It is watered in the described second default base after the cleaning using water sprinkler, to soak the described second default base;
Plain-water slurry is arranged in the described second default base after moistening, is struck off with wooden rectangular slab and is swept by broom It is even;
Dry mortar is started with by default spacing in the described second default base from the side of the described second default base Floating screed, wherein the default spacing is between 0.9m to 1.1m;
It plasters in the described second default base by the height of the floating screed, and is smoothed out by wooden float, so that described second is pre- If the plastering height in base is consistent;
The bulk is laid in the described second default base after plastering.
6. interior decoration construction method according to claim 5, which is characterized in that soak the second default base it Before, the bulk is laid on the method in the described second default base further include:
The described second default base after cleaning is completely brushed one times using wire brush, to smooth in the described second default base Base carries out frosting treatment.
7. interior decoration construction method according to claim 5, which is characterized in that plaster in the described second default base Method include:
Mortar is set between the two neighboring floating screed, puts down the mortar using wooden float stranding, so that the floating screed Outer surface is provided with the mortar;
It is watered in the described first default base after plastering using the water sprinkler, wherein rub flat institute with the hands using the wooden float After stating mortar 24 hours, watered using the water sprinkler.
8. interior decoration construction method according to claim 5, which is characterized in that the floating screed in the described second default base Before, the method bulk being laid in the described second default base further include:
In the described second default base upper berth ash for being provided with the plain-water slurry, wherein sweep the even element using the broom The speed of cement slurry is consistent with the speed of the paving ash.
9. interior decoration construction method according to claim 1, which is characterized in that lifting the lightgage steel joist to described Third preset base on method include:
It is preset in the third and marks the keel stepping position line in base;
The sunpender of surface brush antirust paint is sequentially arranged at the third according to the stepping position line to preset in base;
The main joist for being assembled with suspender member is installed on the sunpender;
Secondary joist is mounted on the suspender member.
10. interior decoration construction method according to claim 1, which is characterized in that lifting the lightgage steel joist to institute Before stating in the default base of third, the interior decoration construction method further include:
Model room is made according to the structural style that the third presets base, pipeline, ventilating duct, lamp are completed in the model room And the installation of the lightgage steel joist, and determine fixed form and installation site;
According to the fixed form and the installation site after determination, the lightgage steel joist is lifted to the third and presets base On layer.
CN201811645671.8A 2018-12-30 2018-12-30 Interior decoration construction method Pending CN109736518A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811645671.8A CN109736518A (en) 2018-12-30 2018-12-30 Interior decoration construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811645671.8A CN109736518A (en) 2018-12-30 2018-12-30 Interior decoration construction method

Publications (1)

Publication Number Publication Date
CN109736518A true CN109736518A (en) 2019-05-10

Family

ID=66362742

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811645671.8A Pending CN109736518A (en) 2018-12-30 2018-12-30 Interior decoration construction method

Country Status (1)

Country Link
CN (1) CN109736518A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110409725A (en) * 2019-07-25 2019-11-05 中泰建工(北京)建筑工程有限公司 A kind of interior decoration method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2346870Y (en) * 1998-11-27 1999-11-03 清华大学建筑设计研究院 Stones/floor tile decorative concrete compound floor
KR20070094716A (en) * 2007-09-03 2007-09-21 이영규 Combination part of cover panel for wall drainage plate
CN101565997A (en) * 2009-05-25 2009-10-28 青岛恒生源集团建设有限公司 Construction method for large-area irregular floor tile
CN102094496A (en) * 2010-12-30 2011-06-15 富思特制漆(北京)有限公司 Method for manufacturing imitation brick wall
CN105421773A (en) * 2015-10-30 2016-03-23 深圳市亚泰国际建设股份有限公司 Construction method for light steel skeleton special-shaped model suspended ceiling
CN105464309A (en) * 2014-09-01 2016-04-06 福建省郦屋生态建筑装饰有限公司 Integral indoor decorating method and integral indoor decorating component
CN106760285A (en) * 2016-11-11 2017-05-31 曾成富 The technique coated to indoor wall using putty in furniture factory building
CN207812947U (en) * 2017-10-18 2018-09-04 江苏欧西建材科技发展有限公司 Waterproof floor structure in a kind of sunk type room
CN108952179A (en) * 2018-07-16 2018-12-07 深圳市中建南方建设集团有限公司 A kind of bumps mirror surface wall of the moulding and construction method of smallpox

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2346870Y (en) * 1998-11-27 1999-11-03 清华大学建筑设计研究院 Stones/floor tile decorative concrete compound floor
KR20070094716A (en) * 2007-09-03 2007-09-21 이영규 Combination part of cover panel for wall drainage plate
CN101565997A (en) * 2009-05-25 2009-10-28 青岛恒生源集团建设有限公司 Construction method for large-area irregular floor tile
CN102094496A (en) * 2010-12-30 2011-06-15 富思特制漆(北京)有限公司 Method for manufacturing imitation brick wall
CN105464309A (en) * 2014-09-01 2016-04-06 福建省郦屋生态建筑装饰有限公司 Integral indoor decorating method and integral indoor decorating component
CN105421773A (en) * 2015-10-30 2016-03-23 深圳市亚泰国际建设股份有限公司 Construction method for light steel skeleton special-shaped model suspended ceiling
CN106760285A (en) * 2016-11-11 2017-05-31 曾成富 The technique coated to indoor wall using putty in furniture factory building
CN207812947U (en) * 2017-10-18 2018-09-04 江苏欧西建材科技发展有限公司 Waterproof floor structure in a kind of sunk type room
CN108952179A (en) * 2018-07-16 2018-12-07 深圳市中建南方建设集团有限公司 A kind of bumps mirror surface wall of the moulding and construction method of smallpox

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110409725A (en) * 2019-07-25 2019-11-05 中泰建工(北京)建筑工程有限公司 A kind of interior decoration method

Similar Documents

Publication Publication Date Title
CN107254954A (en) Ground paving ceramic tile construction technology
CN109736534A (en) Flooring construction method
CN108952041A (en) A kind of external wall Stucco finish structure and its method for repairing and constructing
CN103572845B (en) A kind of insulation clay reflective heat-insulation paint exterior wall heat-preserving system and construction technology thereof
CN107152145A (en) A kind of stone material flooring construction method
CN103952052A (en) Travertine-like elastic texture coating and preparation method thereof
CN102477797A (en) Construction method for preventing crack of infilled wall
CN108343203A (en) A kind of metope anticracking batch embedding technology
CN106592899A (en) Construction method of inner wall
CN113006397A (en) Construction method for square leveling of kitchen and bathroom space
CN109736518A (en) Interior decoration construction method
CN110145083A (en) A kind of technique of thin-coat plaster rock wool heat-preservation system
CN112267628A (en) Construction method of plastering-free system for interior wall decoration of constructional engineering
Ochilova Technology of painting works in construction
CN106049780A (en) Plastering-free construction technique for high-precision brickwork
CN107761968A (en) Exterior wall internal insulation mortar joins position construction method
CN106869428A (en) A kind of heat insulating reflecting colored mortar construction technology
CN109025109A (en) A kind of construction technology coating inner wall of building face
CN208996342U (en) A kind of external wall Stucco finish structure
CN109826325A (en) A kind of anti-seepage construction method of architectural engineering
CN109555316A (en) Environment protection architecture construction method
CN109853888A (en) A kind of historical building plucking wall surface construction technology
CN110409725A (en) A kind of interior decoration method
JP4104432B2 (en) Pattern surface formation method
CN211949245U (en) Roof stone flashing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20200415

Address after: Lixia District, Shandong city of Ji'nan province 250000 Olympic road No. 2666, building A, railway construction

Applicant after: CHINA RAILWAY 14TH CONSTRUCTION BUREAU GROUP BUILDING ENGINEERING Co.,Ltd.

Address before: Lixia District, Shandong city of Ji'nan province 250000 Olympic road No. 2666, building A, railway construction

Applicant before: CHINA RAILWAY SHISIJU GROUP Corp.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20190510

RJ01 Rejection of invention patent application after publication