一种龙门架拆除旧梁的施工方法 Download PDFInfo
- Publication number
- CN109537477A CN109537477A CN201811508072.1A CN201811508072A CN109537477A CN 109537477 A CN109537477 A CN 109537477A CN 201811508072 A CN201811508072 A CN 201811508072A CN 109537477 A CN109537477 A CN 109537477A
- Authority
- CN
- China
- Prior art keywords
- suspension centre
- portal frame
- portal
- distance
- left suspension
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
Abstract
一种龙门架拆除旧梁的施工方法涉及公路与市政基础设施改造领域。本发明在有限空间内采用龙门架对既有旧梁进行拆除,从而精准验证龙门架拆除旧梁的可行性,避免发生安全事故。包含以下步骤:1、两龙门架同步提升;2、两龙门架同步向右侧平移;3、围绕右吊点逆时针转动;4、两龙门架同步向左侧平移;5、围绕左吊点顺时针转动;6、两龙门架同步下放,完成拆除过程。本方法利用两台龙门架进行配合,为场地受限情况下提供了一种旧桥拆除的方法,并建立了每一步拆除过程的几何关系算法,确保拆除过程安全可靠。
Description
技术领域
本发明涉及公路与市政基础设施改造领域,特别是在城市市区进行旧桥改造,当场地受限时提供的一种新方法。
背景技术
截至2017年末,全国公路桥梁达到83.25万座,我国已是一个桥梁大国,特别是城市路网系统已基本完善,新建公路交通基础设施工程逐渐减少,然而随着既有道路桥梁在运营过程中逐年病害的增多,存在承载能力逐渐下降的趋势,后续维修改造项目将日益增多。在市区进行桥梁维修改造时,对社会交通影响极大。往往面临着施工场地狭小、交通导行压力大以及工期紧张等情况,传统的施工方法往往不能满足要求。
发明内容
一种龙门架拆除旧梁的施工方法,在有限空间内采用龙门架对既有旧梁进行拆除,从而精准验证龙门架拆除旧梁的可行性,避免发生安全事故。如图1、图2所示,当桥梁两侧无施工场地,无法采用吊车进行拆除作业时。以其中右半幅为例,在既有桥面两侧边梁上铺设龙门架行走轨道,安装两台龙门架,利用龙门架对既有桥梁的中梁进行拆除,待中梁拆除后,也为边梁拆除提供了操作空间。龙门架拆除过程需要在本跨内完成,拆除前首先要做好如下准备工作:
1、旧梁两端横缝、旧梁之间的纵缝已切开;
2、进行龙门架吊梁测试,并测量其摇摆值,从而确定拆梁过程中旧梁与桥梁下部结构保持的最小间距D值;
3、根据实施步骤中的每一步,建立了其运动几何关系,计算出每一步移动的参数值,确保移动过程能够与既有桥梁下部结构保持最小间距D值;
4、龙门架安装完成,并验收合格;
5、将其中一片中梁移至其它中梁上部,为第一片中梁拆除创造空间。
说明:最小间距D值是指拆除对象旧梁与桥梁下部结构(特别是盖梁)保持的最小距离,D值应在试吊阶段确定,在试吊阶段测试旧梁的摇摆值,D值为1.5倍的摇摆值。
具体拆梁实施步骤如下(各参数注释如图3所示,参数定义如下):
A:梁底面距离盖梁顶面的高度;
B:梁端搭设在盖梁上的长度;
C:盖梁高度;
D:1.5倍的测试摇摆值;
H为梁高度;
L1为两个龙门架吊点间距;
S1:步骤1吊起高度;
S2:步骤2右移距离;
S3a:步骤3左吊点下降高度;
S3b:步骤3左吊点向右移动距离;
θ3:步骤3转动角度;
S4:步骤4左移距离;
S5a:步骤5右吊点下降高度;
S5a:步骤5右吊点向右移动距离;
θ5:步骤5转动角度;
步骤1:两龙门架同步提升。两龙门架同步提升,中梁吊起高度S1=A+D,
步骤2:两龙门架同步向右侧平移。第一步提升到位后,两龙门架同步向右移动距离S2=B+D。
步骤3:围绕右吊点逆时针转动。围绕右吊点转动时,右吊点位置固定,左吊点不断下降,直至左吊点下降至盖梁底面以下距离盖梁底面最小间距D值时为止,此时转动到位。但需要注意的是,左吊点在下降过程中,为保持左吊点与龙门架吊绳始终处于竖直状态,需要龙门架随轨道逐渐向右移动,移动距离根据左吊点下降高度和转动角度的几何关系计算确定。转动角度转动过程使左吊点下降的高度S3a=C+H+2D,转动过程使左吊点向右移动距离
步骤4:两龙门架同步向左移动,移动距离S4=2S2+S3b+sin(θ3)*H。
步骤5:围绕左吊点顺时针转动,围绕左吊点转动时,左吊点位置固定,右吊点不断下降,直至右吊点下降至与左吊点水平高度相同为止,此时转动到位。转动角度转动过程使右吊点下降的高度S5a=C+H+2D,转动过程使右吊点向左移动距离
步骤6:两龙门架同步下放,完成拆除过程。此时旧梁已处于水平状态,运梁车移至梁正下方,两龙门架同步下放,将梁至于车上,完成拆除过程。
(1)本发明提出了利用两台龙门架在桥上配合进行拆梁的方法,不必占用桥梁两侧空间。
(2)本发明针对每一步拆梁过程,建立了其运动几何关系,避免与既有桥梁下部结构发生碰撞,确保拆除过程安全可靠。
附图说明
图1龙门架拆梁三维图
图2龙门架拆梁剖面图
图3龙门架拆梁立面图
图4步骤一示意图
图5步骤二示意图
图6步骤三示意图
图7步骤四示意图
图8步骤五示意图
具体实施方式
具体拆梁实施步骤如下(各参数注释如图3所示,参数定义如下):
A:梁底面距离盖梁顶面的高度;
B:梁端搭设在盖梁上的长度;
C:盖梁高度;
D:1.5倍的测试摇摆值;
H为梁高度;
L1为两个龙门架吊点间距;
S1:步骤1吊起高度;
S2:步骤2右移距离;
S3a:步骤3左吊点下降高度;
S3b:步骤3左吊点向右移动距离;
θ3:步骤3转动角度;
S4:步骤4左移距离;
S5a:步骤5右吊点下降高度;
S5a:步骤5右吊点向右移动距离;
θ5:步骤5转动角度;
步骤1:两龙门架同步提升。两龙门架同步提升,中梁吊起高度S1=A+D,
步骤2:两龙门架同步向右侧平移。第一步提升到位后,两龙门架同步向右移动距离S2=B+D。
步骤3:围绕右吊点逆时针转动。围绕右吊点转动时,右吊点位置固定,左吊点不断下降,直至左吊点下降至盖梁底面以下距离盖梁底面最小间距D值时为止,此时转动到位。但需要注意的是,左吊点在下降过程中,为保持左吊点与龙门架吊绳始终处于竖直状态,需要龙门架随轨道逐渐向右移动,移动距离根据左吊点下降高度和转动角度的几何关系计算确定。转动角度转动过程使左吊点下降的高度S3a=C+H+2D,转动过程使左吊点向右移动距离
步骤4:两龙门架同步向左移动,移动距离S4=2S2+S3b+sin(θ3)*H。
步骤5:围绕左吊点顺时针转动,围绕左吊点转动时,左吊点位置固定,右吊点不断下降,直至右吊点下降至与左吊点水平高度相同为止,此时转动到位。转动角度转动过程使右吊点下降的高度S5a=C+H+2D,转动过程使右吊点向左移动距离
步骤6:两龙门架同步下放,完成拆除过程。此时旧梁已处于水平状态,运梁车移至梁正下方,两龙门架同步下放,将梁至于车上,完成拆除过程。
Claims (1)
1.一种龙门架拆除旧梁的施工方法,其特征在于:
先定义以下参数:
A:梁底面距离盖梁顶面的高度;
B:梁端搭设在盖梁上的长度;
C:盖梁高度;
D:1.5倍的测试摇摆值;
H为梁高度;
L1为两个龙门架吊点间距;
S1:步骤1吊起高度;
S2:步骤2右移距离;
S3a:步骤3左吊点下降高度;
S3b:步骤3左吊点向右移动距离;
θ3:步骤3转动角度;
S4:步骤4左移距离;
S5a:步骤5右吊点下降高度;
S5a:步骤5右吊点向右移动距离;
θ5:步骤5转动角度;
步骤1:两龙门架同步提升;两龙门架同步提升,中梁吊起高度S1=A+D,
步骤2:两龙门架同步向右侧平移;第一步提升到位后,两龙门架同步向右移动距离S2=B+D;
步骤3:围绕右吊点逆时针转动;围绕右吊点转动时,右吊点位置固定,左吊点不断下降,直至左吊点下降至盖梁底面以下距离盖梁底面最小间距D值时为止,此时转动到位;左吊点在下降过程中,为保持左吊点与龙门架吊绳始终处于竖直状态,需要龙门架随轨道逐渐向右移动,移动距离根据左吊点下降高度和转动角度的几何关系计算确定;转动角度转动过程使左吊点下降的高度S3a=C+H+2D,转动过程使左吊点向右移动距离
步骤4:两龙门架同步向左移动,移动距离S4=2S2+S3b+sin(θ3)*H;
步骤5:围绕左吊点顺时针转动,围绕左吊点转动时,左吊点位置固定,右吊点不断下降,直至右吊点下降至与左吊点水平高度相同为止,此时转动到位;转动角度转动过程使右吊点下降的高度S5a=C+H+2D,转动过程使右吊点向左移动距离
步骤6:两龙门架同步下放,完成拆除过程;此时旧梁已处于水平状态,运梁车移至梁正下方,两龙门架同步下放,将梁置于车上,完成拆除过程。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811508072.1A CN109537477B (zh) | 2018-12-11 | 2018-12-11 | 一种龙门架拆除旧梁的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811508072.1A CN109537477B (zh) | 2018-12-11 | 2018-12-11 | 一种龙门架拆除旧梁的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109537477A true CN109537477A (zh) | 2019-03-29 |
CN109537477B CN109537477B (zh) | 2021-03-02 |
Family
ID=65854347
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811508072.1A Active CN109537477B (zh) | 2018-12-11 | 2018-12-11 | 一种龙门架拆除旧梁的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109537477B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110904841A (zh) * | 2019-11-07 | 2020-03-24 | 中铁大桥局集团有限公司 | 桥梁主梁抬升方法及抬升系统 |
Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20050051896A (ko) * | 2003-11-28 | 2005-06-02 | 휘선건설(주) | 런칭거더시스템 및 이를 이용한 교량철거방법 |
CN101058968A (zh) * | 2006-04-21 | 2007-10-24 | 中铁一局集团新运工程有限公司 | 地铁窄盾构井吊点置换式钢轨下吊施工方法 |
JP2009052306A (ja) * | 2007-08-28 | 2009-03-12 | Kajima Corp | 橋桁の架替工法 |
CN101413234A (zh) * | 2008-09-27 | 2009-04-22 | 中铁一局集团有限公司 | 地铁窄盾构井倾斜下吊轨排施工方法 |
CN102587299A (zh) * | 2012-03-08 | 2012-07-18 | 中铁二十一局集团有限公司 | 变换吊点拆除横跨既有桥梁或铁路支架横梁的施工方法 |
CN203383148U (zh) * | 2013-06-25 | 2014-01-08 | 宁波市政工程建设集团股份有限公司 | 一种预制小箱梁跨内起梁装置 |
CN104328745A (zh) * | 2014-11-04 | 2015-02-04 | 中铁第四勘察设计院集团有限公司 | 一种小角度上跨高铁小跨桥梁的转体装置及其施工方法 |
CN104790295A (zh) * | 2014-12-17 | 2015-07-22 | 中铁六局集团海外工程有限公司 | 轮胎式龙门吊架梁设施工工法 |
CN104878693A (zh) * | 2015-04-24 | 2015-09-02 | 中铁六局集团有限公司 | 桁架双梁式架桥机侧面喂梁、架设施工方法 |
CN104963301A (zh) * | 2015-06-30 | 2015-10-07 | 武汉二航路桥特种工程有限责任公司 | 用于墩顶梁段与桥墩拆除的拖拉平移下放装置及方法 |
CN105887694A (zh) * | 2016-05-20 | 2016-08-24 | 中交第航务工程局有限公司 | 桥梁盖梁底模拆除装置 |
CN106638312A (zh) * | 2015-12-14 | 2017-05-10 | 中铁上海工程局集团有限公司 | 大悬臂盖梁施工中的移动门架的施工方法 |
CN106758887A (zh) * | 2016-11-25 | 2017-05-31 | 武汉二航路桥特种工程有限责任公司 | 连续梁桥整桥下放拆除方法 |
CN107974944A (zh) * | 2017-12-06 | 2018-05-01 | 浙江中建路桥设备有限公司 | 一种y型公铁两用桥梁桥面板吊装装置及吊装方法 |
CN108004929A (zh) * | 2017-12-06 | 2018-05-08 | 浙江中建路桥设备有限公司 | 一种h型公铁两用桥梁桥面板吊装装置及吊装方法 |
-
2018
- 2018-12-11 CN CN201811508072.1A patent/CN109537477B/zh active Active
Patent Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20050051896A (ko) * | 2003-11-28 | 2005-06-02 | 휘선건설(주) | 런칭거더시스템 및 이를 이용한 교량철거방법 |
CN101058968A (zh) * | 2006-04-21 | 2007-10-24 | 中铁一局集团新运工程有限公司 | 地铁窄盾构井吊点置换式钢轨下吊施工方法 |
JP2009052306A (ja) * | 2007-08-28 | 2009-03-12 | Kajima Corp | 橋桁の架替工法 |
CN101413234A (zh) * | 2008-09-27 | 2009-04-22 | 中铁一局集团有限公司 | 地铁窄盾构井倾斜下吊轨排施工方法 |
CN102587299A (zh) * | 2012-03-08 | 2012-07-18 | 中铁二十一局集团有限公司 | 变换吊点拆除横跨既有桥梁或铁路支架横梁的施工方法 |
CN203383148U (zh) * | 2013-06-25 | 2014-01-08 | 宁波市政工程建设集团股份有限公司 | 一种预制小箱梁跨内起梁装置 |
CN104328745A (zh) * | 2014-11-04 | 2015-02-04 | 中铁第四勘察设计院集团有限公司 | 一种小角度上跨高铁小跨桥梁的转体装置及其施工方法 |
CN104790295A (zh) * | 2014-12-17 | 2015-07-22 | 中铁六局集团海外工程有限公司 | 轮胎式龙门吊架梁设施工工法 |
CN104878693A (zh) * | 2015-04-24 | 2015-09-02 | 中铁六局集团有限公司 | 桁架双梁式架桥机侧面喂梁、架设施工方法 |
CN104963301A (zh) * | 2015-06-30 | 2015-10-07 | 武汉二航路桥特种工程有限责任公司 | 用于墩顶梁段与桥墩拆除的拖拉平移下放装置及方法 |
CN106638312A (zh) * | 2015-12-14 | 2017-05-10 | 中铁上海工程局集团有限公司 | 大悬臂盖梁施工中的移动门架的施工方法 |
CN105887694A (zh) * | 2016-05-20 | 2016-08-24 | 中交第航务工程局有限公司 | 桥梁盖梁底模拆除装置 |
CN106758887A (zh) * | 2016-11-25 | 2017-05-31 | 武汉二航路桥特种工程有限责任公司 | 连续梁桥整桥下放拆除方法 |
CN107974944A (zh) * | 2017-12-06 | 2018-05-01 | 浙江中建路桥设备有限公司 | 一种y型公铁两用桥梁桥面板吊装装置及吊装方法 |
CN108004929A (zh) * | 2017-12-06 | 2018-05-08 | 浙江中建路桥设备有限公司 | 一种h型公铁两用桥梁桥面板吊装装置及吊装方法 |
Non-Patent Citations (1)
Title |
---|
刘永福: "架桥机高低法架梁施工技术", 《施工技术》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110904841A (zh) * | 2019-11-07 | 2020-03-24 | 中铁大桥局集团有限公司 | 桥梁主梁抬升方法及抬升系统 |
CN110904841B (zh) * | 2019-11-07 | 2021-08-10 | 中铁大桥局集团有限公司 | 桥梁主梁抬升方法及抬升系统 |
Also Published As
Publication number | Publication date |
---|---|
CN109537477B (zh) | 2021-03-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107558494A (zh) | 一种轨道交通地下车站结构及其建造方法 | |
CN204662279U (zh) | 带防护体系的滚动式砼箱梁桥转体施工合拢吊架装置 | |
CN106758887A (zh) | 连续梁桥整桥下放拆除方法 | |
CN107747282B (zh) | 上跨既有线旧桥梁体整体拆除方法 | |
CN101265690A (zh) | 保护性拆除拱桥的方法 | |
CN102493346A (zh) | 高空防撞护栏移模吊架及施工方法 | |
CN101210419A (zh) | 小半径曲线混凝土箱梁施工用内外梁系统造桥机及其施工方法 | |
CN104480868A (zh) | 上跨运营铁路的公路桥拆梁方法 | |
CN109537477A (zh) | 一种龙门架拆除旧梁的施工方法 | |
CN106194216A (zh) | 一种矩形箱涵及隧道施工用台车 | |
CN103669902A (zh) | 现浇梁支撑桁架整体降落拆除工装及其施工方法 | |
CN105926672A (zh) | 一种地铁暗挖车站钢管柱施工方法 | |
CN107761568B (zh) | 一种利用气囊载运的钢结构桥梁安装方法 | |
CN105970822B (zh) | 一种50m双幅上行式移动模架及其相应的制梁施工方法 | |
CN107972680A (zh) | 一种用于地铁疏散平台至轨行区的快速疏散装置和方法 | |
CN106285019A (zh) | 一种局限空间下的天车安装方法 | |
CN108086169B (zh) | 桥梁施工用移动模架的安装提升方法 | |
CN104110002A (zh) | 一种更换钢桁梁桥桥面板的方法 | |
CN102242569B (zh) | 工业厂房高空位换梁后抽柱扩距方法 | |
CN206035507U (zh) | 一种矩形箱涵及隧道施工用台车 | |
KR101234090B1 (ko) | 철도 판형교의 거더 교체 방법 | |
CN103032072A (zh) | 一种封闭式车站盾构解体提升转移到换乘线吊出的方法 | |
CN105568785A (zh) | 底板外伸组合箱型轨道梁刚构体系的实现方法和施工工艺 | |
CN205801132U (zh) | 一种抱轨及自锁组合式阻车器 | |
KR101572563B1 (ko) | 교량의 상부구조물 교체 시공방법 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |