CN108154308A - Power construction process management optimization method and system - Google Patents

Power construction process management optimization method and system Download PDF

Info

Publication number
CN108154308A
CN108154308A CN201711481140.5A CN201711481140A CN108154308A CN 108154308 A CN108154308 A CN 108154308A CN 201711481140 A CN201711481140 A CN 201711481140A CN 108154308 A CN108154308 A CN 108154308A
Authority
CN
China
Prior art keywords
data
construction
scheduling
power construction
item
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711481140.5A
Other languages
Chinese (zh)
Other versions
CN108154308B (en
Inventor
林克全
孙思光
杨荣霞
赵亮
王嘉延
马志刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Guangzhou Power Supply Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Power Supply Bureau Co Ltd filed Critical Guangzhou Power Supply Bureau Co Ltd
Priority to CN201711481140.5A priority Critical patent/CN108154308B/en
Publication of CN108154308A publication Critical patent/CN108154308A/en
Application granted granted Critical
Publication of CN108154308B publication Critical patent/CN108154308B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Quality & Reliability (AREA)
  • Development Economics (AREA)
  • Operations Research (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

This application involves a kind of power construction process management optimization method, system, readable storage medium storing program for executing and computer equipments.The method includes:When monitoring that electric power construction starts, the construction site data of upload are received;Scheduling message is issued according to live video data, scheduling message is used for the operation of management and control construction site;Index analysis is carried out to construction site according to inspection item data, check item correction scheme is issued according to the result of index analysis;Receive the live video data after the scheduling uploaded and the inspection item data after correction, and the Construction State information of the check item data update power construction according to the live video data after scheduling and after correction.The scheme of the application is by receiving construction site data, the situation of construction site is grasped in real time, and is scheduled management and control and the rectification of check item problem by issuing scheduling information and check item correction scheme, and management process facilitates implementation, remote scheduling management can be achieved, the management and control of power construction process is efficient.

Description

Power construction process management optimization method and system
Technical field
This application involves electric system construction technique field, more particularly to a kind of power construction process management optimization side Method, system, computer readable storage medium and computer equipment.
Background technology
With continuous increase of the country to urban electric power construction investment, within following long period of time, carry out simultaneously How the engineering quantity of construction can strengthen Construction of Intercity Network quality management far more than previous, persistently carry out construction quality and promoted Activity pushes project construction to make safe, high-quality, environmentally friendly excellent project etc. to the transformation of standardization direction, become power construction The new opportunities and challenges of industry.At present, urban electric power construction has substantially carried out the informationization of service management, workflow management, It ensure that certain working efficiency, power construction management level is also being promoted steadily.
But in current power construction engineering, the management for construction site is still paused, and needs a large amount of manpower Working feature carries out process management into each construction site, and power construction process management is difficult, and management and control efficiency is low.
Invention content
Based on this, it is necessary in view of the above-mentioned problems, providing a kind of administrative convenience and the efficient power construction process of management and control Management optimization method, system, computer readable storage medium and computer equipment.
A kind of power construction process management optimization method, including step:
When monitoring that electric power construction starts, the construction site data of upload are received, construction site data include existing Field video data and inspection item data;
Scheduling message is issued according to live video data, scheduling message is used for the operation of management and control construction site;
Index analysis is carried out, and issue check item according to the result of index analysis and entangle to construction site according to inspection item data Direction-determining board;
The live video data after the scheduling uploaded and the inspection item data after correction are received, and according to the scene after scheduling Inspection item data after video data and correction updates the Construction State information of power construction.
In one embodiment, the step of issuing scheduling message according to live video data includes:
Preset personnel's distribution map is inquired, obtains the distributed intelligence of everyone;
According to live video data and distributed intelligence generation scheduling message, and issue scheduling message.
In one embodiment, according to item data is checked to construction site progress index analysis, according to the knot of index analysis Fruit issues the step of check item correction scheme and includes:
Item data is checked from check item extracting data quality safety;
Preset quality safety check item index is inquired, according to quality safety check item index to quality safety inspection item number According to being analyzed, quality safety check item analysis result is obtained;
It is generated according to quality safety check item analysis result and issues check item correction scheme, check item correction scheme includes Quality examination item correction scheme and/or safety inspection item correction scheme.
In one embodiment, after monitoring that electric power construction starts, the step of the construction site data of upload is received It is further included before rapid:
The data of registering uploaded are received, data of registering include register identity information, project of registering, register location information and label To the time;
It is further included after the step of updating the Construction State information of power construction:
Receive upload checks out data, checks out data and includes checking out identity information, checking out project, check out location information and label Go out the time.
In one embodiment, it further includes:
Inquire the construction geographical map of power construction;
According to data of registering, check out data and the geographical map structuring personnel's distribution map of construction.
In one embodiment, it further includes:
According to data of registering, data and Construction State information are checked out, build charge book table, charge book table is used to record The history operational data of everyone.
In one embodiment, include after the step of updating the Construction State information of power construction:
When meeting Construction State querying triggering condition, Construction State information is sent to terminal, and receives terminal return Evaluation suggest message;
Message adjustment scheduling message and index analysis are suggested according to evaluation.
A kind of power construction process management optimization system, including:
Construction data receiving module, for when monitoring that electric power construction starts, receiving the construction site number of upload According to construction site data include live video data and check item data;
Scheduler module, for issuing scheduling message according to live video data, scheduling message is made for management and control construction site Industry;
Indicator analysis module, for carrying out index analysis to construction site according to inspection item data, and according to index analysis Result issue check item correction scheme;
Construction State update module, for receiving the live video data after the scheduling uploaded and the inspection item number after correction According to, and according to the live video data after scheduling and the inspection item data after correction, update the Construction State information of power construction.
A kind of computer readable storage medium is stored with computer program, when the computer program is executed by processor, So that the processor performs the step of method as described above.
A kind of computer equipment, including memory and processor, the memory is stored with computer program, the calculating When machine program is performed by the processor so that the processor performs the step of method as described above.
Above-mentioned power construction process management optimization method, system, computer readable storage medium and computer equipment, work as prison When measuring electric power construction and starting, the construction site data of upload are received, specifically include live video data and check item number According on the one hand scheduling message for the operation of management and control construction site being issued according to live video data, on the other hand according to inspection Item data carries out index analysis to construction site, and issues check item correction scheme, last basis according to the result of index analysis The Construction State information of check item data update power construction after live video data and correction after the scheduling of upload.This Shen Scheme please grasps the situation of construction site, and by issuing scheduling information and inspection in real time by receiving construction site data Item correction scheme is scheduled management and control and the rectification of check item problem, and management process facilitates implementation, it can be achieved that remote scheduling management, electricity The management and control of power process of construction is efficient.
Description of the drawings
Fig. 1 is the flow diagram of power construction process management optimization method in one embodiment of the application;
Fig. 2 is the structural schematic block diagram of power construction process management optimization system in one embodiment of the application.
Specific embodiment
Object, technical solution and advantage to make the application are more clearly understood, with reference to the accompanying drawings and embodiments, to this Application is described in further detail.It should be appreciated that the specific embodiments described herein are only used to explain the application, The protection domain of the application is not limited.
In current power construction engineering, the management for construction site needs a large amount of manual labor to put into, into each Construction site carries out process management, and power construction process management is difficult, and management and control efficiency is low.Current construction site management mode is deposited In following several respects problem:First, information of project management degree is not high, the narrow range of project information, item related information It is shared low with transmission efficiency;Power construction process management is difficult, and management and control efficiency is low;Second, work progress management and control is difficult, i.e. " people Controlling " management causes each link linking hardly possible of constructing, and construction speed is difficult to effectively control, and construction site relies on limited on-site examination Comprehensive management and control is difficult to, meanwhile, construction speed is difficult to effectively control, and the construction period is caused not control, so as to which management cost is difficult Management and control;Third, construction quality promoted it is difficult, complexity, dynamic feature and the construction site of power construction and management " away from From " limit the promotion of construction quality management;Fourth, Safety Management implements difficulty, traditional construction management mode completely Management link is caused easily to become a mere formality, practical implementation effect is poor, and supervision is difficult to implement comprehensively, so as to implement bursting tube Reason.Based on this, this application provides a kind of administrative convenience and the efficient power construction process management optimization method of management and control, it is System, computer readable storage medium and computer equipment.
Fig. 1 is the flow diagram of power construction process management optimization method in one embodiment of the application.As shown in Figure 1, In the present embodiment, power construction process management optimization method includes step:
Step S101:When monitoring that electric power construction starts, the construction site data of upload, construction site number are received According to including live video data and inspection item data.
The Construction State of power construction engineering is monitored, specifically, can monitor whether to receive applying for power construction engineering Work triggers message.When receiving construction triggering message, then it is believed that current power construction project has started to construct, at this point, connecing The construction site data uploaded are received, construction site data include live video data and check item data.Wherein, live video number According to the video data for the captured in real-time that can include being uploaded by on-site terminal, check that item data can include the quality of construction site Check item data and/or safety inspection item data, quality examination item data checks management and control, safety inspection item number for construction quality Management and control is checked according to for construction safety.Specifically, mode the construction site data of upload can be received by radio communication, such as Construction site data transmission is carried out by Wireless LAN.By when monitoring that electric power construction starts, real-time reception The construction site data uploaded by on-site terminal, can grasp electric power construction field condition in real time, existing to constructing to realize The real-time management and control of field, so as to improve the management and control efficiency to power construction engineering.
Step S103:Scheduling message is issued according to live video data, scheduling message is used for the operation of management and control construction site.
After obtaining the construction site data uploaded, according to the live video data in the data of construction site, issue scheduling and disappear Breath, the scheduling message are used for the operation of management and control construction site.Specifically, the live video data that on-site terminal uploads is obtained, it can be with The construction operation situation of construction site is grasped in real time, and is commanded according to current construction operation situation by issuing scheduling message Scheduling, realizes remote scheduling management and control.
Step S105:Index analysis is carried out, and under the result according to index analysis to construction site according to inspection item data Send out check item correction scheme.
On the other hand, the inspection item data in the data of construction site carries out index analysis, and index analysis can include Index of construction quality and construction safety index issue check item correction scheme according to the result of index analysis.Wherein, item number is checked According to can be preset according to the item types of current power construction.During electric power construction, need based on matter Buret is managed and safety management requirement, carries out index analysis to construction site, can specifically be carried out by the inspection item data of upload Index analysis, and check item correction scheme is issued according to the result of index analysis, to ensure that occurring quality in the construction process asks It can be solved in time when topic or safety problem, improve quality and the safety of electric power construction.
Step S107:The live video data after the scheduling uploaded and the inspection item data after correction are received, and according to tune The inspection item data after live video data and correction after degree updates the Construction State information of power construction.
Scheduling message is being issued according to live video data, and inspection is issued according to the index analysis result for checking item data After item correction scheme, the inspection item data after live video data and correction after the scheduling for the upload for receiving upload, and according to The Construction State information of check item data update power construction after live video data and correction after scheduling.Specifically, it connects The live video data after scheduling and the inspection item data after correction are received, to realize the management and control to construction site, in addition, also according to The Construction State information of check item data update power construction after live video data and correction after scheduling, to record in time The Construction State of electric power construction can realize the progress control to electric power construction, improve the pipe of power construction process Control efficiency.
Above-mentioned power construction process management optimization method when monitoring that electric power construction starts, receives applying for upload Work field data specifically includes live video data and checks item data, on the one hand issues to manage according to live video data The scheduling message of construction site operation is controlled, on the other hand according to inspection item data to construction site progress index analysis, and according to The result of index analysis issues check item correction scheme, finally according to the live video data after the scheduling of upload and correction after The Construction State information of check item data update power construction.The scheme of the present embodiment is by receiving construction site data, in real time The situation of construction site is grasped, and management and control and check item problem are scheduled by issuing scheduling information and check item correction scheme Rectification, management process facilitate implementation, it can be achieved that remote scheduling management, the management and control of power construction process are efficient.
Further, the step of issuing scheduling message according to live video data can include:
Preset personnel's distribution map is inquired, obtains the distributed intelligence of everyone;
According to live video data and distributed intelligence generation scheduling message, and issue scheduling message.
Specifically, inquiring preset personnel's distribution map, the distributed intelligence of everyone is obtained.Wherein, personnel's distribution map records There is the distributed intelligence of everyone, personnel's distribution map can be obtained according to electric power construction map and worker tasks' allocation rule are advance It arrives.In specific implementation, preset personnel's distribution map can be set as dynamic map, can be based on electric power construction map, It is marked and obtains according to the current present position of everyone on map, in this way, can be to power construction process pipe During reason, the distributed intelligence of everyone can be grasped in time.After the distributed intelligence for obtaining everyone, according to live video data and Distributed intelligence generates scheduling message, and issues scheduling message, and scheduling message is used for personnel's operation of dispatch control construction site. In concrete application, scheduling message can be the message of the forms such as speech message, text message or image information.It is uploaded by combining Live video data and personnel's distribution map generation scheduling message carry out remote scheduling management and control, can be in time according to construction site situation It is scheduled, improves the management and control efficiency to power construction.
Further, index analysis is carried out to construction site according to inspection item data, is issued according to the result of index analysis The step of check item correction scheme, can include:
Item data is checked from check item extracting data quality safety;
Preset quality safety check item index is inquired, according to quality safety check item index to quality safety inspection item number According to being analyzed, quality safety check item analysis result is obtained;
It is generated according to quality safety check item analysis result and issues check item correction scheme, check item correction scheme includes Quality examination item correction scheme and/or safety inspection item correction scheme.
Wherein, quality safety check item data include quality examination item data and/or safety inspection item data, data lattice Formula can be but be not limited to text, picture or list;Quality safety check item index includes index of construction quality and construction safety Index, quality safety check item index check that item data corresponds to setting according to quality safety.Specifically, it is carried from checking in item data Quality safety is taken to check item data, then inquires preset quality safety check item index, quality safety is checked into item data and matter It measures safety inspection item index and carries out the matching analysis, obtain quality safety check item analysis result, finally given birth to according to the analysis result Into and issue check item correction scheme, to realize the real-time management and control to the quality problems and/or safety problem of construction site.Its In, check item correction scheme includes quality examination item correction scheme and/or safety inspection item correction scheme, and quality examination item is corrected Scheme corresponds to quality examination item data, and safety inspection item correction scheme corresponds to safety inspection item data.By to reception It checks that item data carries out index analysis, and issues check item correction scheme according to the result of index analysis, realizes existing to constructing The real-time management and control of the quality problems and/or safety problem of field, improves quality and the safety of electric power construction operation.
Further, after monitoring that electric power construction starts, before the step of receiving the construction site data of upload It further includes:
The data of registering uploaded are received, data of registering include register identity information, project of registering, register location information and label To the time;
It is further included after the step of updating the Construction State information of power construction:
Receive upload checks out data, checks out data and includes checking out identity information, checking out project, check out location information and label Go out the time.
Wherein, data of registering are in the step for the construction site data for after monitoring that electric power construction starts, receiving upload It is received before rapid, and checks out data and received after the step of Construction State information for updating power construction.It registers Data can include registering identity information, project of registering, register and location information and register the time, checking out data can include checking out Identity information checks out project, checks out location information and checks out the time.By receive register/check out data, can obtain in time each The operational data of personnel to perform dispatch control, can be used for examination reference.In specific implementation, everyone can be enabled It registers after reaching construction site, is checked out when leaving construction site.Specifically registering/check out can also be according to each one The task of execution of the member during electric power construction is set, such as site operation unit construction responsible person, It registers after reaching construction site, the corresponding project of registering of selection uploads corresponding location information, time of registering, work people Number and scene photograph etc.;And when leaving construction site, it is checked out, uploads corresponding location information, checks out time etc..For Project manager is accordingly registered after showing up, and is selected project, is inputted same administrative staff, upload etc. of taking pictures;When leaving workshop, into Row checks out, and uploads corresponding photo etc..It is accordingly registered when reaching scene for safety supervision personnel, selects project, input is same Pedestrian's number, with administrative staff etc.;It is checked out when leaving workshop.
Further, the power construction process management optimization method of the application can also include:
Inquire the construction geographical map of power construction;
According to data of registering, check out data and the geographical map structuring personnel's distribution map of construction.
Wherein, the construction geographical map of power construction builds each project under construction location distribution to be marked with current power Geographical map.According to inquiry obtained construction geographical map, data of registering and data are checked out, build personnel's distribution map, the people Member's distribution map includes the distributed intelligence of everyone.Data and data and power construction are checked out by combining registering for everyone Construction geography map structuring personnel's distribution map, the distributed intelligence of everyone can be obtained in real time, be conducive to improve constructing In journey personnel are scheduled with the efficiency of commander, so as to improve the management and control efficiency to power construction process.
Further, the power construction process management optimization method of the application can also include:
According to data of registering, data and Construction State information are checked out, build charge book table, charge book table is used to record The history operational data of everyone.
Specifically, it obtains data of registering, check out data and Construction State information, and build charge book table, for recording The history operational data of everyone.In specific implementation, the individual work record of everyone as unit of personnel, can be built Table, the data that will register check out data and Construction State information is recorded into the individual work record sheet, each so as to record The history operational data of personnel so as to obtain the history operational data of everyone in time, realizes the achievement that works everyone The management of effect.
Further, can include after the step of updating the Construction State information of power construction:
When meeting Construction State querying triggering condition, Construction State information is sent to terminal, and receives terminal return Evaluation suggest message;
Message adjustment scheduling message and index analysis are suggested according to evaluation.
Wherein, Construction State querying triggering condition can be whether to receive Construction State information request message, work as reception During to the request message, Construction State information is sent to terminal, and message, last basis are suggested in the evaluation for receiving terminal return Message adjustment scheduling message and index analysis are suggested in evaluation.Specifically, when receiving Construction State information request message, extraction Current is Construction State information, sends it to terminal, and message is suggested in the evaluation for receiving terminal return, is built according to the evaluation Discuss message adjustment scheduling message and index analysis.For example, when it is " project progress needs to accelerate " that message is suggested in the evaluation received, Scheduling message is adjusted, to accelerate the operating speed at electric power construction scene.
Based on this, the application also provides a kind of power construction process management optimization system.
Fig. 2 is the structural schematic block diagram of power construction process management optimization system in one embodiment of the application.Such as Fig. 2 institutes Show, in the present embodiment, power construction process management optimization system includes:
Construction data receiving module 201, for when monitoring that electric power construction starts, receiving the construction site of upload Data, construction site data include live video data and check item data;
Scheduler module 203, for issuing scheduling message according to live video data, scheduling message is used for management and control construction site Operation;
Indicator analysis module 205, for carrying out index analysis to construction site according to inspection item data, and according to index point The result of analysis issues check item correction scheme;
Construction State update module 207, for receiving the live video data after the scheduling uploaded and the inspection after correction Item data, and according to the live video data after scheduling and the inspection item data after correction, update the Construction State of power construction Information.
Above-mentioned power construction process management optimization system is monitoring electric power construction by construction data receiving module During beginning, the construction site data of upload are received, specifically include live video data and check item data, on the one hand pass through scheduling Module issues the scheduling message for the operation of management and control construction site according to live video data, on the other hand passes through index analysis mould Root tuber carries out index analysis, and issue check item correction side according to the result of index analysis according to inspection item data to construction site Case, finally by Construction State update module according to the live video data after the scheduling of upload and the inspection item data after correction Update the Construction State information of power construction.It is existing to grasp construction by receiving construction site data in real time for the scheme of the present embodiment The situation of field, and it is scheduled management and control and the rectification of check item problem, management by issuing scheduling information and check item correction scheme Process facilitates implementation, it can be achieved that remote scheduling management, the management and control of power construction process are efficient.
Based on above-mentioned power construction process management optimization method, the application also provide a kind of computer readable storage medium and A kind of computer equipment.
In one embodiment, the computer readable storage medium of the application is stored with computer program, the computer When program is executed by processor so that the processor performs the step of power construction process management optimization method as described above.
In one embodiment, the computer equipment of the application, including memory and processor, the memory is stored with Computer program, when the computer program is performed by the processor so that the processor performs electric power as described above and builds If the step of process management optimization method.
One of ordinary skill in the art will appreciate that realizing all or part of flow in above-described embodiment method, being can be with Relevant hardware is instructed to complete by computer program, the program can be stored in a non-volatile computer and can be read In storage medium, the program is when being executed, it may include such as the flow of the embodiment of above-mentioned each method.Wherein, it is provided herein Each embodiment used in any reference to memory, storage, database or other media, may each comprise non-volatile And/or volatile memory.Nonvolatile memory may include that read-only memory (ROM), programming ROM (PROM), electricity can be compiled Journey ROM (EPROM), electrically erasable ROM (EEPROM) or flash memory.Volatile memory may include random access memory (RAM) or external cache.By way of illustration and not limitation, RAM is available in many forms, such as static state RAM (SRAM), dynamic ram (DRAM), synchronous dram (SDRAM), double data rate sdram (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronization link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) directly RAM (RDRAM), straight Connect memory bus dynamic ram (DRDRAM) and memory bus dynamic ram (RDRAM) etc..
Each technical characteristic of embodiment described above can be combined arbitrarily, to make description succinct, not to above-mentioned reality It applies all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, it is all considered to be the range of this specification record.
Embodiment described above only expresses the several embodiments of the application, and description is more specific and detailed, but simultaneously It cannot therefore be construed as limiting the scope of the patent.It should be pointed out that those of ordinary skill in the art are come It says, under the premise of the application design is not departed from, various modifications and improvements can be made, these belong to the protection of the application Range.Therefore, the protection domain of the application patent should be determined by the appended claims.

Claims (10)

1. a kind of power construction process management optimization method, which is characterized in that including step:
When monitoring that electric power construction starts, the construction site data of upload are received, the construction site data include existing Field video data and inspection item data;
Scheduling message is issued according to the live video data, the scheduling message is used for the operation of management and control construction site;
Index analysis is carried out, and issue according to the result of the index analysis to the construction site according to the inspection item data Check item correction scheme;
The live video data after the scheduling uploaded and the inspection item data after correction are received, and according to the scene after the scheduling Inspection item data after video data and the correction updates the Construction State information of the power construction.
2. power construction process management optimization method according to claim 1, which is characterized in that described according to the scene Video data issues the step of scheduling message and includes:
Preset personnel's distribution map is inquired, obtains the distributed intelligence of everyone;
According to the live video data and distributed intelligence generation scheduling message, and issue the scheduling message.
3. power construction process management optimization method according to claim 1, which is characterized in that described according to the inspection Item data carries out index analysis to the construction site, and the step of check item correction scheme is issued according to the result of the index analysis Suddenly include:
Item data is checked from the check item extracting data quality safety;
Preset quality safety check item index is inquired, according to the quality safety check item index to the quality safety inspection Item data is analyzed, and obtains quality safety check item analysis result;
It is generated according to the quality safety check item analysis result and issues check item correction scheme, the check item correction scheme Including quality examination item correction scheme and/or safety inspection item correction scheme.
4. power construction process management optimization method according to claim 1, which is characterized in that
It is described after monitoring that electric power construction starts, further included before the step of receiving the construction site data of upload:
The data of registering uploaded are received, the data of registering include register identity information, project of registering, register location information and label To the time;
It is further included after the step of Construction State information of the update power construction:
The data that check out uploaded are received, the data that check out include checking out identity information, checking out project, check out location information and label Go out the time.
5. power construction process management optimization method according to claim 4, which is characterized in that further include:
Inquire the construction geographical map of the power construction;
According to the data of registering, described check out data and the geographical map structuring personnel's distribution map of the construction.
6. power construction process management optimization method according to claim 4, which is characterized in that further include:
According to the data of registering, it is described check out data and the Construction State information, build charge book table, the operation note Record table is used to record the history operational data of everyone.
7. power construction process management optimization method according to claim 1, which is characterized in that the update electric power Include after the step of Construction State information of construction:
When meeting Construction State querying triggering condition, the Construction State information is sent to terminal, and receives terminal return Evaluation suggest message;
Suggest that message adjusts the scheduling message and the index analysis according to the evaluation.
8. a kind of power construction process management optimization system, which is characterized in that including:
Construction data receiving module, for when monitoring that electric power construction starts, receiving the construction site data of upload, institute Construction site data are stated to include live video data and check item data;
Scheduler module, for issuing scheduling message according to the live video data, the scheduling message is existing for management and control construction Field operation;
Indicator analysis module, for carrying out index analysis to the construction site, and according to described according to the inspection item data The result of index analysis issues check item correction scheme;
Construction State update module, for receiving the live video data after the scheduling uploaded and the inspection item data after correction, And according to the live video data after the scheduling and the inspection item data after the correction, update the construction of the power construction Status information.
9. a kind of computer readable storage medium is stored with computer program, when the computer program is executed by processor, makes The processor is obtained to perform such as the step of any one of claim 1 to 7 the method.
10. a kind of computer equipment, including memory and processor, the memory is stored with computer program, the calculating When machine program is performed by the processor so that the processor is performed such as the step of any one of claim 1 to 7 the method Suddenly.
CN201711481140.5A 2017-12-29 2017-12-29 Power construction process management optimization method and system Active CN108154308B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711481140.5A CN108154308B (en) 2017-12-29 2017-12-29 Power construction process management optimization method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711481140.5A CN108154308B (en) 2017-12-29 2017-12-29 Power construction process management optimization method and system

Publications (2)

Publication Number Publication Date
CN108154308A true CN108154308A (en) 2018-06-12
CN108154308B CN108154308B (en) 2020-11-03

Family

ID=62460200

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711481140.5A Active CN108154308B (en) 2017-12-29 2017-12-29 Power construction process management optimization method and system

Country Status (1)

Country Link
CN (1) CN108154308B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109034550A (en) * 2018-07-03 2018-12-18 广州供电局有限公司 Project survey and construction field monitoring method, system and computer equipment
CN109299915A (en) * 2018-09-07 2019-02-01 江苏核电有限公司 A kind of scaffold operational method
CN109754181A (en) * 2018-12-30 2019-05-14 国网北京市电力公司 The treating method and apparatus of engineering project information
CN110163512A (en) * 2019-05-24 2019-08-23 中铝视拓智能科技有限公司 A kind of monitored by personnel's method and monitored by personnel's system
CN110458421A (en) * 2019-07-19 2019-11-15 浙江龙腾畅想软件有限公司 A kind of quality safety management method, apparatus and storage device
CN112200490A (en) * 2020-10-30 2021-01-08 深圳云联万企科技有限公司 Information method and system for engineering quality safety manual
CN113421170A (en) * 2021-06-16 2021-09-21 广东诚誉工程咨询监理有限公司 Comprehensive optimization management system and method for power engineering quality
CN115168647A (en) * 2022-07-19 2022-10-11 四川省世鉴信用管理有限公司 Video checking system and method based on environmental credit evaluation

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040210470A1 (en) * 2003-04-16 2004-10-21 John Rusk System and method for project management
CN104329120A (en) * 2014-10-17 2015-02-04 成都四为电子信息股份有限公司 Tunnel construction safety monitoring and management system and tunnel construction safety monitoring and management method
CN104951883A (en) * 2015-06-15 2015-09-30 中国葛洲坝集团国际工程有限公司 Earth-rock dam engineering construction dispatching auxiliary system adopting machine vision technology
CN106203728A (en) * 2016-07-22 2016-12-07 深圳市赛普爱德科技股份有限公司 A kind of interactive engineering supervision method
CN106485433A (en) * 2016-12-08 2017-03-08 中国矿业大学(北京) A kind of enterprise's hidden danger Information Collecting & Processing technology based on big data and system
CN106980919A (en) * 2017-02-17 2017-07-25 河南城建学院 A kind of engineering information management method and system
CN107392562A (en) * 2017-06-07 2017-11-24 黄建钊 The interactive supervision method of object-oriented based on network multimedia intelligent terminal system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040210470A1 (en) * 2003-04-16 2004-10-21 John Rusk System and method for project management
CN104329120A (en) * 2014-10-17 2015-02-04 成都四为电子信息股份有限公司 Tunnel construction safety monitoring and management system and tunnel construction safety monitoring and management method
CN104951883A (en) * 2015-06-15 2015-09-30 中国葛洲坝集团国际工程有限公司 Earth-rock dam engineering construction dispatching auxiliary system adopting machine vision technology
CN106203728A (en) * 2016-07-22 2016-12-07 深圳市赛普爱德科技股份有限公司 A kind of interactive engineering supervision method
CN106485433A (en) * 2016-12-08 2017-03-08 中国矿业大学(北京) A kind of enterprise's hidden danger Information Collecting & Processing technology based on big data and system
CN106980919A (en) * 2017-02-17 2017-07-25 河南城建学院 A kind of engineering information management method and system
CN107392562A (en) * 2017-06-07 2017-11-24 黄建钊 The interactive supervision method of object-oriented based on network multimedia intelligent terminal system

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109034550A (en) * 2018-07-03 2018-12-18 广州供电局有限公司 Project survey and construction field monitoring method, system and computer equipment
CN109299915A (en) * 2018-09-07 2019-02-01 江苏核电有限公司 A kind of scaffold operational method
CN109754181A (en) * 2018-12-30 2019-05-14 国网北京市电力公司 The treating method and apparatus of engineering project information
CN110163512A (en) * 2019-05-24 2019-08-23 中铝视拓智能科技有限公司 A kind of monitored by personnel's method and monitored by personnel's system
CN110458421A (en) * 2019-07-19 2019-11-15 浙江龙腾畅想软件有限公司 A kind of quality safety management method, apparatus and storage device
CN112200490A (en) * 2020-10-30 2021-01-08 深圳云联万企科技有限公司 Information method and system for engineering quality safety manual
CN113421170A (en) * 2021-06-16 2021-09-21 广东诚誉工程咨询监理有限公司 Comprehensive optimization management system and method for power engineering quality
CN115168647A (en) * 2022-07-19 2022-10-11 四川省世鉴信用管理有限公司 Video checking system and method based on environmental credit evaluation

Also Published As

Publication number Publication date
CN108154308B (en) 2020-11-03

Similar Documents

Publication Publication Date Title
CN108154308A (en) Power construction process management optimization method and system
Liu et al. Automatically updating maintenance information from a BIM database
CN103325153A (en) Inspection method and inspection system
CN105809575A (en) Mobile operation system and method for water and electricity production management
CN107240165A (en) Security cruising inspection system
CN109086895A (en) A kind of operation management system and method for heating ventilation air-conditioning system
CN109858724B (en) Intelligent dispatching method and device based on data analysis and computer equipment
WO2012058472A3 (en) Method and apparatus for managing and capturing communications in a recruiting environment
CN105868936B (en) Intelligent operation and maintenance system applied to integrated operation and maintenance of transformer equipment
CN106815681A (en) Substation secondary device closed loop management platform and its management system based on Quick Response Code
CN109710696A (en) The System and method for the mobile operation of unusual fluctuation is verified for power equipment
CN105243440A (en) Marketing mobile working platform based paperless office on-site working method
CN104700192A (en) Aided intelligent management and control system for power transmission and transformation project and management and control method thereof
US20220324497A1 (en) System and method for strategic track and maintenance planning inspection
CN109299851A (en) A kind of intelligence progress kinetic-control system
CN109472326A (en) Distribution net equipment and asset management mobile application system based on RFID
CN111008906A (en) Manufacturing enterprise production execution management system
CN105335558A (en) Engineering circle establishment method and system on basis of BIM (building information modeling)
CN108171383A (en) Electric Power Capital Construction engineering management optimization method and system
CN109190361A (en) A kind of method, apparatus, system and readable storage medium that sequence number generates
CN109003432A (en) Information copy reading method based on power-line carrier communication system
CN111291982A (en) Rental work order recommendation sequence evaluation method, system, electronic equipment and storage medium
CN116307428A (en) Project progress management method and device and terminal equipment
CN109919517B (en) Power station equipment maintenance welding operation flow control method
CN108985604B (en) Construction period compression method for construction planning

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20200927

Address after: 510620 Tianhe District, Guangzhou, Tianhe South Road, No. two, No. 2, No.

Applicant after: Guangzhou Power Supply Bureau of Guangdong Power Grid Co.,Ltd.

Address before: 510620 Tianhe District, Guangzhou, Tianhe South Road, No. two, No. 2, No.

Applicant before: GUANGZHOU POWER SUPPLY Co.,Ltd.

GR01 Patent grant
GR01 Patent grant