CN107642240B - 一种在混凝土支座上安装劲性混凝土钢梁的方法 - Google Patents
一种在混凝土支座上安装劲性混凝土钢梁的方法 Download PDFInfo
- Publication number
- CN107642240B CN107642240B CN201610579774.3A CN201610579774A CN107642240B CN 107642240 B CN107642240 B CN 107642240B CN 201610579774 A CN201610579774 A CN 201610579774A CN 107642240 B CN107642240 B CN 107642240B
- Authority
- CN
- China
- Prior art keywords
- concrete
- girder steel
- column
- crossbeam
- strengthening
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
一种在混凝土支座上安装劲性混凝土钢梁的方法,其特征在于包括以下步骤:a、对每个混凝土支座设置二排立柱,b、制作横梁(2),横梁长1100mm,c、在每排立柱离立柱顶端250mm处采用ф16mm钢筋作为固定架,进行混凝土环梁(4)支模、浇注混凝土环梁使立柱固定,d、在横梁(2)上安装钢梁(5),将钢梁与横梁焊接牢固,然后对钢梁按常规扎筋、支模、浇注混凝土形成劲性混凝土钢梁。本发明具有劲性混凝土钢梁的基础装置结构简单、制作方便,解决劲性混凝土钢梁安装在混凝土支座处的技术难题,使钢梁不与环梁直接接触,且预留出下部钢筋安装空间,工程质量安全可靠和保证钢梁支座处的强度,刚度和稳定性的优点。
Description
技术领域
本发明涉及一种劲性混凝土钢梁安装方法,具体地说,是一种在混凝土支座上安装劲性混凝土钢梁的方法。
背景技术
筒仓仓顶结构通常有三种形式:1、钢结构;2、混凝土结构;3、劲性混凝土结构。钢结构安装速度快、工期短,但后期维护成本高;混凝土结构自重大、支模措施工程量大,工期长,后期维护成本低;劲性混凝土结构刚度大,即可减少支模措施工程量,又可降低后期维护成本,在筒仓仓顶中的应用越来越广泛。
然而,劲性混凝土钢梁下翼缘与仓顶环梁连接处钢筋交错纵横,钢梁安装时不能与环梁直接接触,既要预留出下部钢筋安装空间,又要保证钢梁支座处的强度、刚度、稳定性。
因此劲性混凝土钢梁在混凝土支座处安装成了业界技术难题。
发明内容
本发明的目的,在于提出一种安全可靠的在混凝土支座上安装劲性混凝土钢梁的方法。
为实现上述目的,本发明的技术解决方案是:
一种在混凝土支座上安装劲性混凝土钢梁的方法,其特征在于包括以下步骤:
a、对每个混凝土支座设置二排立柱,二排立柱相对应排列,二排立柱间距400mm,每排立柱设有三根立柱,相邻两个立柱之间的距离≤450mm;立柱长1000mm,立柱顶端设有长圆孔以供调节高度,长圆孔规格为Φ14*40mm;
b、制作横梁,横梁长1100mm,距离横梁两端100mm及横梁中间各设有一孔,孔径14mm;使横梁的孔与每排三根立柱顶端的长圆孔通过M12螺栓将立柱与横梁连接;
c、在每排立柱离立柱顶端250mm处采用ф16mm钢筋作为固定架,以长圆孔和M12螺栓调整立柱与横梁,控制好位置和标高后紧固,进行凝土环梁支模、浇注混凝土环梁使立柱固定;
d、在横梁上安装钢梁,将钢梁与横梁焊接牢固,然后对钢梁按常规扎筋、支模、浇注混凝土形成劲性混凝土钢梁。
本发明的在混凝土支座上安装劲性混凝土钢梁的方法还可以采用以下的技术措施来进一步实现。
前述的方法,其中所述立柱为≥14号槽钢。
前述的方法,其中所述横梁为≥10号槽钢。
前述的方法,其中所述钢梁按常规扎筋中,包括在横梁下方设置若干纵向钢筋。
前述的方法,其中所述钢梁按常规扎筋中,包括在钢梁上翼缘板上方设置若干纵向钢筋。
采用上述技术方案后,本发明的在混凝土支座上安装劲性混凝土钢梁的方法具有以下优点:
1、劲性混凝土钢梁的基础装置结构简单、制作方便;
2、解决劲性混凝土钢梁安装在混凝土支座处的技术难题,使钢梁不与环梁直接接触,且预留出下部钢筋安装空间,工程质量安全可靠;
3、保证钢梁支座处的强度,刚度和稳定性。
附图说明
图1为本发明实施例的三根立柱设置示意图;
图2为本发明实施例的混凝土环梁在立柱上位置示意图;
图3为本发明实施例的立柱,横梁在混凝土环梁上的平面位置示意图;
图4为本发明实施例的劲性混凝土钢梁的安装示意图;
图5为本发明实施例的劲性混凝土钢梁的平面位置示意图。
图中:1立柱,2横梁,3长圆孔,4混凝土环梁,5钢梁,6模板,7钢筋。
具体实施方式
以下结合实施例及其附图对本发明作更进一步说明。
实施例1
本发明的在混凝土支座上安装劲性混凝土钢梁的方法的施工流程:制作立柱、横梁→安装立柱→浇注混凝土将立柱固定→安装横梁→采用安装螺栓调整横梁标高→将横梁与立柱焊接牢固→安装劲性混凝土钢梁→扎筋、支模、浇混凝土。
本发明的在混凝土支座上安装劲性混凝土钢梁的方法,包括以下步骤:
图1为本发明实施例的三根立柱设置示意图。
a、对每个混凝土支座设置二排立柱,二排立柱相对应排列,二排立柱间距400mm,每排立柱设有三根立柱1,相邻两个立柱之间的距离为450mm;立柱长1000mm,立柱顶端设有长圆孔3以供调节高度,长圆孔规格为Φ14*40mm;所述立柱1为14号槽钢。
b、制作横梁(2),横梁长1100mm,距离横梁两端100mm及横梁中间各设有一孔,孔径14mm;使横梁的孔与每排三根立柱顶端的长圆孔通过M12螺栓将立柱与横梁连接;所述横梁2为10号槽钢。
图2为本发明实施例的混凝土环梁在立柱上位置示意图。
c、在每排立柱离立柱顶端250mm处采用ф16mm钢筋作为固定架,以长圆孔和M12螺栓调整立柱与横梁,控制好位置和标高后紧固,进行凝土环梁4支模、浇注混凝土环梁使立柱固定;图3为本发明实施例的立柱,横梁在混凝土环梁上的平面位置示意图。
d、在横梁2上安装钢梁5,将钢梁与横梁焊接牢固,然后对钢梁按常规扎筋、支模、浇注混凝土形成劲性混凝土钢梁,其中包括在横梁2下方设置若干纵向钢筋,在钢梁5上翼缘板上方设置若干纵向钢筋,完成在混凝土支座上安装劲性混凝土钢梁。图4为本发明实施例的劲性混凝土钢梁的安装示意图,图5为本发明实施例的劲性混凝土钢梁的平面位置示意图。
本发明具有实质性特点和显著的技术进步,本发明的在混凝土支座上安装劲性混凝土钢梁的方法解决了劲性混凝土钢梁安装在混凝土支座处的技术难题,使钢梁安装时不与环梁直接接触,既预留出下部钢筋安装空间,又保证钢梁支座处的强度、刚度、稳定性。
本发明的在混凝土支座上安装劲性混凝土钢梁的方法在在宝钢煤场E、F料条改建筒仓工程中首次成功运用,效果显著。
以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变化。因此,所有等同的技术方案也应该属于本发明的范畴,应由各权利要求限定。
Claims (5)
1.一种在混凝土支座上安装劲性混凝土钢梁的方法,其特征在于包括以下步骤:
a、对每个混凝土支座设置二排立柱,二排立柱相对应排列,二排立柱间距400mm,每排立柱设有三根立柱(1),相邻两个立柱之间的距离≤450mm;立柱长1000mm,立柱顶端设有长圆孔(3)以供调节高度,长圆孔规格为Φ14*40mm;
b、制作横梁(2),横梁长1100mm,距离横梁两端100mm及横梁中间各设有一孔,孔径14mm;使横梁的孔与每排三根立柱顶端的长圆孔通过M12螺栓将立柱与横梁连接;
c、在每排立柱离立柱顶端250mm处采用ф16mm钢筋作为固定架,以长圆孔和M12螺栓调整立柱与横梁,控制好位置和标高后紧固,进行混凝土环梁(4)支模、浇注混凝土环梁使立柱固定;
d、在横梁(2)上安装钢梁(5),将钢梁与横梁焊接牢固,然后对钢梁按常规扎筋、支模、浇注混凝土形成劲性混凝土钢梁。
2.如权利要求1所述的在混凝土支座上安装劲性混凝土钢梁的方法,其特征在于,所述立柱(1)为≥14号槽钢。
3.如权利要求1所述的在混凝土支座上安装劲性混凝土钢梁的方法,其特征在于,所述横梁(2)为≥10号槽钢。
4.如权利要求1所述的在混凝土支座上安装劲性混凝土钢梁的方法,其特征在于,所述钢梁按常规扎筋中,包括在横梁(2)下方设置若干纵向钢筋。
5.如权利要求1所述的在混凝土支座上安装劲性混凝土钢梁的方法,其特征在于,所述钢梁按常规扎筋中,包括在钢梁(5)上翼缘板上方设置若干纵向钢筋。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610579774.3A CN107642240B (zh) | 2016-07-22 | 2016-07-22 | 一种在混凝土支座上安装劲性混凝土钢梁的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610579774.3A CN107642240B (zh) | 2016-07-22 | 2016-07-22 | 一种在混凝土支座上安装劲性混凝土钢梁的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107642240A CN107642240A (zh) | 2018-01-30 |
CN107642240B true CN107642240B (zh) | 2019-12-03 |
Family
ID=61108926
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610579774.3A Active CN107642240B (zh) | 2016-07-22 | 2016-07-22 | 一种在混凝土支座上安装劲性混凝土钢梁的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107642240B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109896419A (zh) * | 2019-03-07 | 2019-06-18 | 江苏承天新型建材有限公司 | 一种便于安装的钢结构行车梁构件 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0953277A (ja) * | 1995-08-11 | 1997-02-25 | Kajima Corp | 原子力発電所の構築工法 |
CN202866002U (zh) * | 2012-09-26 | 2013-04-10 | 苏州工业园区设计研究院股份有限公司 | 型钢混凝土非埋入式柱脚 |
CN103174302A (zh) * | 2013-03-27 | 2013-06-26 | 江苏省江建集团有限公司 | 大直径筒仓仓顶的施工方法 |
CN104895324A (zh) * | 2015-05-28 | 2015-09-09 | 杭州江润科技有限公司 | 一种型钢混凝土组合结构巨型插入式柱脚结构的施工方法 |
CN104895336A (zh) * | 2015-05-21 | 2015-09-09 | 中冶天工集团有限公司 | 一种劲性混合结构钢梁的安装就位方法 |
CN205224416U (zh) * | 2015-12-14 | 2016-05-11 | 北京天恒建设工程有限公司 | 一种用于劲性钢结构的工字钢支撑 |
-
2016
- 2016-07-22 CN CN201610579774.3A patent/CN107642240B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0953277A (ja) * | 1995-08-11 | 1997-02-25 | Kajima Corp | 原子力発電所の構築工法 |
CN202866002U (zh) * | 2012-09-26 | 2013-04-10 | 苏州工业园区设计研究院股份有限公司 | 型钢混凝土非埋入式柱脚 |
CN103174302A (zh) * | 2013-03-27 | 2013-06-26 | 江苏省江建集团有限公司 | 大直径筒仓仓顶的施工方法 |
CN104895336A (zh) * | 2015-05-21 | 2015-09-09 | 中冶天工集团有限公司 | 一种劲性混合结构钢梁的安装就位方法 |
CN104895324A (zh) * | 2015-05-28 | 2015-09-09 | 杭州江润科技有限公司 | 一种型钢混凝土组合结构巨型插入式柱脚结构的施工方法 |
CN205224416U (zh) * | 2015-12-14 | 2016-05-11 | 北京天恒建设工程有限公司 | 一种用于劲性钢结构的工字钢支撑 |
Also Published As
Publication number | Publication date |
---|---|
CN107642240A (zh) | 2018-01-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106906955B (zh) | 一种剪力墙整体预制钢筋网结构及其施工方法 | |
CN101824800B (zh) | 一种桥位现浇预应力混凝土连续梁的施工方法 | |
CN103306208A (zh) | 1.6次抛物线形新型四柱板式空心变截面高墩爬模方法 | |
CN107268348B (zh) | 地铁柱式检查坑施工方法 | |
CN103882813B (zh) | 用于桥墩与横系梁同步施工的牛腿托架平台及其搭建方法 | |
KR101198711B1 (ko) | 콘크리트 블록 타설용 거푸집 보강을 위한 간격유지장치 및 이 시공방법 | |
CN105649213B (zh) | 一种密集布筋区大型钢结构预埋件的施工方法 | |
CN108755984A (zh) | 基于砼方柱的后浇带支撑施工方法 | |
CN104074142A (zh) | 箱型梁现浇支撑架整体横移施工方法 | |
CN107642240B (zh) | 一种在混凝土支座上安装劲性混凝土钢梁的方法 | |
CN106894345A (zh) | 连续梁边跨合拢装置及方法 | |
CN206800800U (zh) | 水平钢筋间隔件 | |
CN102677624A (zh) | U型渡槽仿真试验装置及方法 | |
CN107297816A (zh) | 用于预制t梁连接的横隔板现浇段模板系统及施工方法 | |
KR20090100476A (ko) | 교각을 이용하여 교량을 인상하는 장치 및 이를 이용한교량인상 방법 | |
CN208072956U (zh) | 混凝土剪力墙根部加固装置 | |
CN104164882A (zh) | 在边坡上构建支护结构梁基础的施工方法及结构 | |
CN104797762B (zh) | 一种建筑物及其施工方法 | |
CN102767378A (zh) | 排架施工隧道双柱式洞门方法 | |
CN104060546A (zh) | 连续梁桥箱型梁现浇支撑架整体纵移施工方法 | |
CN105442628A (zh) | 悬挑基础侧壁重型埋件施工方法 | |
CN210086817U (zh) | 高层悬挑结构支模体系 | |
CN208168349U (zh) | 一种型钢混凝土柱模板加固装置 | |
CN106468101A (zh) | 一种用于现浇上反梁侧模板的定位支架 | |
CN205476472U (zh) | 一种建筑用模板 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |