CN107522062A - A kind of installation construction method for elevator - Google Patents

A kind of installation construction method for elevator Download PDF

Info

Publication number
CN107522062A
CN107522062A CN201710965671.5A CN201710965671A CN107522062A CN 107522062 A CN107522062 A CN 107522062A CN 201710965671 A CN201710965671 A CN 201710965671A CN 107522062 A CN107522062 A CN 107522062A
Authority
CN
China
Prior art keywords
load
column
installation
section steel
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710965671.5A
Other languages
Chinese (zh)
Inventor
高昇伟
周莳备
徐永华
彭宪辉
李华
许张狄
陈强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
(group) Co Ltd Is Built In Pudong New Area Shanghai
Original Assignee
(group) Co Ltd Is Built In Pudong New Area Shanghai
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (group) Co Ltd Is Built In Pudong New Area Shanghai filed Critical (group) Co Ltd Is Built In Pudong New Area Shanghai
Priority to CN201710965671.5A priority Critical patent/CN107522062A/en
Publication of CN107522062A publication Critical patent/CN107522062A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B7/00Other common features of elevators
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B11/00Main component parts of lifts in, or associated with, buildings or other structures
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B5/00Applications of checking, fault-correcting, or safety devices in elevators

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The invention discloses a kind of installation construction method for elevator, it first blocks layer door door opening, carry out security protection, then top layer platform is built, computer room installation is carried out by top layer platform, then first guide rail is fixed, it can allow two of guide rail to be fixed, and stretcher and buffer are installed in shaft bottom, sedan-chair frame and compartment system are correspondingly installed, then the counterweight for being used to balance between compartment system is installed, finally, control the height of car, other guide rails are installed, simultaneously, also first guide rail is reinforced, and, when reaching designated layer door position, layer door is installed, after integral installation, finally the gate of compartment system is installed, finally debug, in whole process, scaffold need not be increased in elevator, it is more convenient so as to be installed in whole process.

Description

A kind of installation construction method for elevator
Technical field
The present invention relates to architecture storey means of transport construction method, more specifically, it relates to a kind of elevator installation Method.
Background technology
Elevator is the nowadays indispensable instrument of skyscraper, and it can allow people to be rapidly performed by the shuttle of floor part, Therefore, in order to configure elevator to high-rise building, when high-rise building is built, elevator is left, after the completion of building, in electricity Stair shaft position is installed by elevator.
When elevator hoistways install elevator, it is necessary to build scaffold, by scaffold by the track of elevator, layer door and sedan-chair Railway carriage or compartment etc. is installed, and finally again removes scaffold, and then elevator is debugged again, it is necessary to enter in this work progress Hand cradle of traveling far and wide being built and removing, and inside hoistway, it is relatively difficult.
The content of the invention
For existing technical problem, the present invention provides a kind of installation construction method for elevator, and it need not build scaffold Elevator installation can be just carried out, it is more convenient so as to install.
To achieve the above object, the invention provides following technical scheme:
A kind of installation construction method for elevator, comprises the following steps:S1, by layer door door opening block;S2, build top layer platform;S3, simultaneously And computer room mechanism is installed, first guide rail is installed;S4, installation buffer and stretcher;S5, installation compartment system;S6, peace Fill counterweight;S7, operation compartment system install other guide rails;S8, mounting layer door;S9, installation gate;S10, debugging.
Pass through above-mentioned technical proposal, first layer door door opening is blocked, carry out security protection, then build top layer platform, pass through Top layer platform carries out computer room installation, and then first guide rail is fixed, and it can allow two of guide rail to be fixed, and Stretcher and buffer are installed in shaft bottom, sedan-chair frame and compartment system are correspondingly installed, then with compartment system it Between be used for balance counterweight installed, finally, control the height of car, other guide rails installed, meanwhile, also to first Root guide rail is reinforced, also, when reaching designated layer door position, layer door is installed, after integral installation, finally by sedan-chair The gate of railway carriage or compartment system is installed, and is finally debugged, in whole process, it is not necessary to increases scaffold in elevator, so as to whole Installed during individual more convenient.
The present invention is further arranged to:The top layer platform includes overlap joint load-bearing channel-section steel on the wall, consolidated with load-bearing channel-section steel Determine and provide the column of pulling force, with the transverse slat of load-bearing channel-section steel fixation and on load-bearing channel-section steel and transverse slat for load-bearing channel-section steel Pedal, brace is provided between the load-bearing channel-section steel and column, the branch corresponding with column is provided with the load-bearing channel-section steel Strut, fender rod is provided with the support bar and column, guardrail is provided between the column and support bar.
Pass through above-mentioned technical proposal, load-bearing channel-section steel can allow the stress intensity of whole top layer platform high, column and brace Setting, make the horizontal level of whole load-bearing channel-section steel more stable, the setting of pedal can allow people stand it is convenient, so as to right The installation of computer room is more convenient, and the setting of fender rod and guardrail can allow whole top layer platform safer.
The present invention is further arranged to:Turnbuckle is provided between the load-bearing channel-section steel and wall.
Pass through above-mentioned technical proposal, the setting of turnbuckle allow load-bearing channel-section steel further to be protected with wall, improve The security of top layer platform.
The present invention is further arranged to:The pedal surrounding is mounted on toeguard.
Pass through above-mentioned technical proposal, the setting of toeguard can place pin and extend into elevator.
The present invention is further arranged to:The platform building of the S2 comprises the following steps:S21, layer doorway lay anchor position, Safety rope;S22, column is installed on the wall of layer door;S23, assembling load-bearing channel-section steel, transverse slat and brace, combined bay is formed, And combined bay is moved into hoistway;S24, brace and column fixed, load-bearing channel-section steel is fixed with column, column, load-bearing Channel-section steel and brace form triangular structure;S25, installation pedal;S26, turnbuckle, support bar, fender rod, shield are installed successively Column and toeguard.
Pass through above-mentioned technical proposal, by above-mentioned steps, top layer platform can be allowed smoothly to build.
The present invention is further arranged to:Warning sign is installed on the fender rod being connected with column.
Pass through above-mentioned technical proposal, the setting of warning sign can allow it to be indicated, prevent the generation of fortuitous event.
The present invention is further arranged to:Alarm for counterweight proximity test is installed between the layer door and compartment system Device, the warning device include the first detector being arranged on compartment system and the second detection installed in hoistway wall Head and the 3rd detector, first detector coordinates with the second detector and the 3rd detector respectively carries out proximity test Alarm.
Pass through above-mentioned technical proposal, when operation elevator car systems are installed, due between counterweight and compartment system Do not accomplish complete stability, accordingly, it is possible to which situation about being collided between counterweight and compartment system occurs, therefore alarm is set Device can allow operating personnel to prevent it, due to when elevator carries out up or descending, can be carried out with counterweight It is close, therefore, set the first detector to coordinate respectively with the second detector and the 3rd detector, can identify that elevator exists respectively Close signal is carried out when up and with counterweight when descending.
The present invention is further arranged to:The compartment system includes car and the protective cover on car, car With to reconnection.
Pass through above-mentioned technical proposal, the setting of protective cover can allow operating personnel at work will not be by elevator hoistways Debris drop caused by influence or safety problem.
The present invention is further arranged to:After S6 steps, the top layer platform that step 2 is built is removed.
Pass through above-mentioned technical proposal, installed, it is necessary to run elevator after S6 steps, therefore, top layer platform is carried out Remove, the operation of elevator can be facilitated.
In summary, the invention has the advantages that:
(1)By the way that scaffold need not be installed in whole process in elevator hoistways, so as to after the completion of construction or construct During need not carry out dismounting scaffold, entirely construct simpler, conveniently;
(2)By using the close warning device of protective cover, counterweight, make workmen safer in work progress.
Brief description of the drawings
Fig. 1 is structure diagram when elevator is installed;
Fig. 2 is the overall schematic of top layer platform;
Fig. 3 is structure chart of the top layer platform building in hoistway.
Reference:100th, baffle plate;101st, traction machine;102nd, directive wheel;103rd, steel wire rope;200th, top layer platform;1st, hold Baking soda steel;2nd, transverse slat;3rd, column;4th, pedal;5th, brace;6th, support bar;7th, fender rod;8th, guardrail;9th, toeguard;10th, it is tight Line device;300th, first guide rail;400th, compartment system;401st, car;402nd, protective cover;500th, counterweight;600th, stretcher;701、 First detector;702nd, the second detector;703rd, the 3rd detector.
Embodiment
The present invention will be described in detail below in conjunction with the accompanying drawings.
A kind of installation construction method for elevator, comprises the following steps:S1, by layer door door opening block, using baffle plate 100, to every One layer of layer door is blocked, and leaves top layer layer door;S2, top layer platform 200 is built, build top layer in the layer door position of top layer and put down Platform 200;S3, computer room mechanism installed, first guide rail 300 is installed, using the top layer platform 200 built, by computer room and the A piece guide rail 300 carries out installation fixation;S4, installation buffer and stretcher 600;S5, installation compartment system 400, pass through top Layer platform 200, sedan-chair frame and compartment system 400 are installed, wherein, compartment system 400 includes car 401;S6, installation counterweight 500, using top layer platform 200, counterweight 500 is installed, and allow it to be docked with car 401, allow car 401 can be in elevator Interior movement, form mobile construction platform;S7, operation car 401 install other guide rails, the mobile construction formed by car 401 Platform installs other guide rails successively;S8, mounting layer door, the mobile construction platform mounting layer door formed again by car 401; S9, installation gate, gate is finally installed, allow elevator to assemble substantially and finish;S10, debugging, miscellaneous part is installed, and And unnecessary structure is removed, finally carry out the detection debugging of elevator operation.Its structure is referred to Fig. 1.
Wherein, in above-mentioned steps, S2 top layer platform 200 is built as construction basis, and its structure and mounting structure can be with Reference picture 2 and Fig. 3.
Top layer platform 200 includes overlap joint load-bearing channel-section steel 1 on the wall, fixed with load-bearing channel-section steel 1 and is that load-bearing channel-section steel 1 provides The column 3 of pulling force, the transverse slat 2 fixed with load-bearing channel-section steel 1 and the pedal 4 on load-bearing channel-section steel 1 and transverse slat 2, load-bearing groove Brace 5 is provided between steel 1 and column 3, is provided with the support bar 6 corresponding with column 3 on load-bearing channel-section steel 1, support bar 6 with And fender rod 7 is provided with column 3, guardrail 8 is provided between column 3 and support bar 6.Set between load-bearing channel-section steel 1 and wall It is equipped with turnbuckle 10.The surrounding of pedal 4 is mounted on toeguard 9.
Top layer platform 200, which is built, to be comprised the following steps:S21, layer doorway lay anchor position, safety rope;S22, in layer door Column 3 is installed on wall;S23, assembling load-bearing channel-section steel 1, transverse slat 2 and brace 5, combined bay is formed, and combined bay is moved Enter in hoistway;S24, brace 5 and column 3 fixed, load-bearing channel-section steel 1 and column 3 fixed, column 3, load-bearing channel-section steel 1 and Brace 5 forms triangular structure;S25, installation pedal 4;S26, turnbuckle 10, support bar 6, fender rod 7, guardrail are installed successively 8 and toeguard 9.Warning sign finally is installed on the fender rod 7 being connected with column 3.
Reference picture 1, after the completion of top layer platform 200 is built, then pass through top layer platform 200, the installation of Auxiliary Machinery Rooms equipment. Workmen stands on top layer platform 200, installs traction machine 101, directive wheel 102 and steel wire rope 103 etc. successively, completes computer room Assembling.After the assembling for completing computer room, decelerator, stretcher 600 etc. are installed in shaft bottom, and first guide rail 300 is pacified In elevator hoistways.Compartment system 400 finally can equally be built into completion on top layer platform 200, and by steel wire rope 103 are attached with counterweight 500, and now, elevator can carry out preliminary movement.Top layer platform 200 is removed, by controlling electricity Terraced car 401 is slowly lifted, and guide rail is reinforced, while installing other guide rails and layer door.Due to elevator car The running and comparing of railway carriage or compartment 401 is slow, and counterweight 500 is not limited in this process, therefore, in order to prevent counterweight 500 for sedan-chair Collide between railway carriage or compartment 401 and warned, it is necessary to install warning device between hoistway on lift car 401 in the process of running Show.
Reference picture 1, warning device include the first detector 701, the second detector 702 and the 3rd detector 703, and first Detector 701 is arranged on car 401, and the second detector 702 and the 3rd detector 703 are separately mounted in hoistway, in order to Convenient installation, is typically mounted at layer door position, in the upper and lower for the position that lift car 401 and counterweight 500 meet successively Second detector 702 and the 3rd detector 703 are installed.Send the signal that the first detector 701 detects to controller, lead to Cross controller control buzzer or warning light is alarmed, so as in the running of car 401, in block close to counterweight 500 When, it can be alarmed.Controller can use PLC or central processing unit to form.
Reference picture 1, typically in mounting layer door and track, operate for convenience, workmen is usually to stand in car 401 Push up what position was carried out, therefore, in this process, easily drop debris above elevator hoistways, may influence workmen and apply Work, or even security incident is caused, therefore, in order to make workmen's construction safer, protection is installed on lift car 401 Cover 402.
Described above is only the preferred embodiment of the present invention, and protection scope of the present invention is not limited merely to above-mentioned implementation Example, all technical schemes belonged under thinking of the present invention belong to protection scope of the present invention.It should be pointed out that for the art Those of ordinary skill for, some improvements and modifications without departing from the principles of the present invention, these improvements and modifications It should be regarded as protection scope of the present invention.

Claims (9)

1. a kind of installation construction method for elevator, it is characterised in that comprise the following steps:S1, by layer door door opening block;S2, build top Layer platform(200);S3 and computer room mechanism is installed, first guide rail is installed(300);S4, installation buffer and stretcher (600);S5, installation compartment system(400);S6, installation counterweight(500);S7, operation compartment system(400)Other guide rails are installed; S8, mounting layer door;S9, installation gate;S10, debugging.
2. installation construction method for elevator according to claim 1, it is characterised in that the top layer platform(200)Including taking Connect load-bearing channel-section steel on the wall(1)And load-bearing channel-section steel(1)It is fixed and be load-bearing channel-section steel(1)The column of pulling force is provided(3), with holding Baking soda steel(1)Fixed transverse slat(2)And installed in load-bearing channel-section steel(1)And transverse slat(2)On pedal(4), the load-bearing channel-section steel (1)With column(3)Between be provided with brace(5), the load-bearing channel-section steel(1)On be provided with and column(3)Corresponding support Bar(6), the support bar(6)And column(3)On be provided with fender rod(7), the column(3)With support bar(6)Between It is provided with guardrail(8).
3. installation construction method for elevator according to claim 2, it is characterised in that the load-bearing channel-section steel(1)With wall it Between be provided with turnbuckle(10).
4. installation construction method for elevator according to claim 3, it is characterised in that the pedal(4)Surrounding is mounted on Toeguard(9).
5. installation construction method for elevator according to claim 4, it is characterised in that the platform building of the S2 includes as follows Step:S21, layer doorway lay anchor position, safety rope;S22, column is installed on the wall of layer door(3);S23, assembling load-bearing groove Steel(1), transverse slat(2)And brace(5), combined bay is formed, and combined bay is moved into hoistway;S24, by brace(5) With column(3)It is fixed, by load-bearing channel-section steel(1)With column(3)It is fixed, column(3), load-bearing channel-section steel(1)And brace(5)Formed Triangular structure;S25, installation pedal(4);S26, turnbuckle is installed successively(10), support bar(6), fender rod(7), guardrail(8) And toeguard(9).
6. installation construction method for elevator according to claim 4, it is characterised in that with column(3)The fender rod of connection(7) On warning sign is installed.
7. installation construction method for elevator according to claim 1, it is characterised in that the layer door and compartment system(400) Between be provided with for counterweight(500)The warning device of proximity test, the warning device include being arranged on compartment system(400) On the first detector(701)And the second detector installed in hoistway wall(702)And the 3rd detector(703), institute State the first detector(701)Respectively with the second detector(702)And the 3rd detector(703)Coordinate and carry out proximity test report It is alert.
8. installation construction method for elevator according to claim 1, it is characterised in that the compartment system(400)Including sedan-chair Railway carriage or compartment(401)And installed in car(401)On protective cover(402), car(401)With counterweight(500)Connection.
9. installation construction method for elevator according to claim 1, it is characterised in that after S6 steps, step 2 is built Platform is removed.
CN201710965671.5A 2017-10-17 2017-10-17 A kind of installation construction method for elevator Pending CN107522062A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710965671.5A CN107522062A (en) 2017-10-17 2017-10-17 A kind of installation construction method for elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710965671.5A CN107522062A (en) 2017-10-17 2017-10-17 A kind of installation construction method for elevator

Publications (1)

Publication Number Publication Date
CN107522062A true CN107522062A (en) 2017-12-29

Family

ID=60684652

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710965671.5A Pending CN107522062A (en) 2017-10-17 2017-10-17 A kind of installation construction method for elevator

Country Status (1)

Country Link
CN (1) CN107522062A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109368446A (en) * 2018-12-12 2019-02-22 北京顺迅电梯设备工程有限公司 A kind of elevator lifting system and its installation method
CN109626190A (en) * 2018-12-12 2019-04-16 北京顺迅电梯设备工程有限公司 A kind of mounting device and its installation method of car guide rail
CN110980478A (en) * 2019-12-30 2020-04-10 江苏阿尔法电梯制造有限公司 Construction lifting system
CN111119461A (en) * 2020-01-10 2020-05-08 日立电梯(中国)有限公司 A operation platform that is used for steel construction elevator well installation top hoisting point
CN113636435A (en) * 2021-08-12 2021-11-12 中国华能集团清洁能源技术研究院有限公司 Vertical conveying device for maintenance personnel of wind power generation equipment
CN114269673A (en) * 2019-08-23 2022-04-01 株式会社日立制作所 Elevator device for construction
CN115159300A (en) * 2022-07-14 2022-10-11 广州市机电安装有限公司 Elevator installation construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004189367A (en) * 2002-12-09 2004-07-08 Hitachi Building Systems Co Ltd Installation method of elevator
CN1990371A (en) * 2005-12-27 2007-07-04 上海三菱电梯有限公司 Elevator installation method and up-down system used therein
CN101134548A (en) * 2006-08-31 2008-03-05 因温特奥股份公司 Lift facility with cabin and counterweight and method for arranging a lift facility
CN103025640A (en) * 2010-05-28 2013-04-03 通力股份公司 Method and elevator arrangement
CN104477736A (en) * 2012-10-12 2015-04-01 广州广日电梯工程有限公司 Shaft elevator installation method
CN104528500A (en) * 2014-12-29 2015-04-22 中国建筑股份有限公司 Double-platform scaffold-free elevator installation method
CN204626921U (en) * 2015-05-13 2015-09-09 巨人通力电梯有限公司 A kind of fixed working platform without scaffold construction elevator

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004189367A (en) * 2002-12-09 2004-07-08 Hitachi Building Systems Co Ltd Installation method of elevator
CN1990371A (en) * 2005-12-27 2007-07-04 上海三菱电梯有限公司 Elevator installation method and up-down system used therein
CN101134548A (en) * 2006-08-31 2008-03-05 因温特奥股份公司 Lift facility with cabin and counterweight and method for arranging a lift facility
CN103025640A (en) * 2010-05-28 2013-04-03 通力股份公司 Method and elevator arrangement
CN104477736A (en) * 2012-10-12 2015-04-01 广州广日电梯工程有限公司 Shaft elevator installation method
CN104528500A (en) * 2014-12-29 2015-04-22 中国建筑股份有限公司 Double-platform scaffold-free elevator installation method
CN204626921U (en) * 2015-05-13 2015-09-09 巨人通力电梯有限公司 A kind of fixed working platform without scaffold construction elevator

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
李勇: "无脚手架电梯自导式安装施工工艺", 《安装》 *
林仕超: "无脚手架电梯安装施工技术", 《施工技术》 *
王应等: "《垂直电梯安装维护与保养》", 31 January 2017, 中国轻工业出版社 *
许林等: "《电梯安装维修与保养安全技术》", 30 June 2011, 安徽科学技术出版社 *
邵永青: "电梯无脚手架安装工艺探讨及优化", 《中国新技术新产品》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109368446A (en) * 2018-12-12 2019-02-22 北京顺迅电梯设备工程有限公司 A kind of elevator lifting system and its installation method
CN109626190A (en) * 2018-12-12 2019-04-16 北京顺迅电梯设备工程有限公司 A kind of mounting device and its installation method of car guide rail
CN114269673A (en) * 2019-08-23 2022-04-01 株式会社日立制作所 Elevator device for construction
CN110980478A (en) * 2019-12-30 2020-04-10 江苏阿尔法电梯制造有限公司 Construction lifting system
CN110980478B (en) * 2019-12-30 2021-04-20 江苏阿尔法电梯制造有限公司 Construction lifting system
CN111119461A (en) * 2020-01-10 2020-05-08 日立电梯(中国)有限公司 A operation platform that is used for steel construction elevator well installation top hoisting point
CN113636435A (en) * 2021-08-12 2021-11-12 中国华能集团清洁能源技术研究院有限公司 Vertical conveying device for maintenance personnel of wind power generation equipment
CN113636435B (en) * 2021-08-12 2023-01-03 中国华能集团清洁能源技术研究院有限公司 Vertical conveying device for maintenance personnel of wind power generation equipment
CN115159300A (en) * 2022-07-14 2022-10-11 广州市机电安装有限公司 Elevator installation construction method

Similar Documents

Publication Publication Date Title
CN107522062A (en) A kind of installation construction method for elevator
US9382099B2 (en) Motorized height access device for tower cranes
CN105377738B (en) For the falling-prevention protecting device of platform
CN104477736A (en) Shaft elevator installation method
CN201714054U (en) Climbing platform system for construction of elevator shaft of high-rise building
CN106638299B (en) Multifunction working platform and construction method
CN110528863B (en) Hanging basket device for outer inclined plane construction and construction method
CN101845883A (en) Climbing scaffold system and construction method
JP2011178496A (en) Control device for elevator
CN205709568U (en) A kind of intelligent remote controls full-automatic explosion-proof type tank container gantry
CN103193137B (en) High-altitude full automatic lifting and using method thereof
CN208235927U (en) All steel intelligent building construction lifting platform
CN103912128B (en) The construction method of high-altitude disjunctor steel truss
CN110171759B (en) Method for disassembling elevator with machine room
JP5105146B2 (en) Gondola device and method for constructing exterior of building using gondola device
CN103011031A (en) Stand column type 360-degree rotary oil tank maintenance platform
CN109763638A (en) A kind of high-altitude overhanging facade special type working vehicle and its construction method
CN111287498B (en) Protective shed frame for construction of overhead bridge box girder crossing railway and erection method
CN107215748A (en) The special building hoist of hoistway and its installation method
CN106088564A (en) Track climbing type monolithic architecture construction scaffolding
CN105776092A (en) Stretching type basket device and construction method thereof
CN104973515B (en) A kind of crane more piece safety operation room and its method of operating
CN205369033U (en) Gallows formula bridge tool car
CN108035530A (en) A kind of inner wall of oil tank construction hanging basket
CN211037771U (en) Hanging basket device for outer slope construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171229