CN107522062A - A kind of installation construction method for elevator - Google Patents
A kind of installation construction method for elevator Download PDFInfo
- Publication number
- CN107522062A CN107522062A CN201710965671.5A CN201710965671A CN107522062A CN 107522062 A CN107522062 A CN 107522062A CN 201710965671 A CN201710965671 A CN 201710965671A CN 107522062 A CN107522062 A CN 107522062A
- Authority
- CN
- China
- Prior art keywords
- load
- column
- installation
- section steel
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B7/00—Other common features of elevators
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B11/00—Main component parts of lifts in, or associated with, buildings or other structures
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B5/00—Applications of checking, fault-correcting, or safety devices in elevators
Landscapes
- Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Mechanical Engineering (AREA)
- Structural Engineering (AREA)
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
Abstract
The invention discloses a kind of installation construction method for elevator, it first blocks layer door door opening, carry out security protection, then top layer platform is built, computer room installation is carried out by top layer platform, then first guide rail is fixed, it can allow two of guide rail to be fixed, and stretcher and buffer are installed in shaft bottom, sedan-chair frame and compartment system are correspondingly installed, then the counterweight for being used to balance between compartment system is installed, finally, control the height of car, other guide rails are installed, simultaneously, also first guide rail is reinforced, and, when reaching designated layer door position, layer door is installed, after integral installation, finally the gate of compartment system is installed, finally debug, in whole process, scaffold need not be increased in elevator, it is more convenient so as to be installed in whole process.
Description
Technical field
The present invention relates to architecture storey means of transport construction method, more specifically, it relates to a kind of elevator installation
Method.
Background technology
Elevator is the nowadays indispensable instrument of skyscraper, and it can allow people to be rapidly performed by the shuttle of floor part,
Therefore, in order to configure elevator to high-rise building, when high-rise building is built, elevator is left, after the completion of building, in electricity
Stair shaft position is installed by elevator.
When elevator hoistways install elevator, it is necessary to build scaffold, by scaffold by the track of elevator, layer door and sedan-chair
Railway carriage or compartment etc. is installed, and finally again removes scaffold, and then elevator is debugged again, it is necessary to enter in this work progress
Hand cradle of traveling far and wide being built and removing, and inside hoistway, it is relatively difficult.
The content of the invention
For existing technical problem, the present invention provides a kind of installation construction method for elevator, and it need not build scaffold
Elevator installation can be just carried out, it is more convenient so as to install.
To achieve the above object, the invention provides following technical scheme:
A kind of installation construction method for elevator, comprises the following steps:S1, by layer door door opening block;S2, build top layer platform;S3, simultaneously
And computer room mechanism is installed, first guide rail is installed;S4, installation buffer and stretcher;S5, installation compartment system;S6, peace
Fill counterweight;S7, operation compartment system install other guide rails;S8, mounting layer door;S9, installation gate;S10, debugging.
Pass through above-mentioned technical proposal, first layer door door opening is blocked, carry out security protection, then build top layer platform, pass through
Top layer platform carries out computer room installation, and then first guide rail is fixed, and it can allow two of guide rail to be fixed, and
Stretcher and buffer are installed in shaft bottom, sedan-chair frame and compartment system are correspondingly installed, then with compartment system it
Between be used for balance counterweight installed, finally, control the height of car, other guide rails installed, meanwhile, also to first
Root guide rail is reinforced, also, when reaching designated layer door position, layer door is installed, after integral installation, finally by sedan-chair
The gate of railway carriage or compartment system is installed, and is finally debugged, in whole process, it is not necessary to increases scaffold in elevator, so as to whole
Installed during individual more convenient.
The present invention is further arranged to:The top layer platform includes overlap joint load-bearing channel-section steel on the wall, consolidated with load-bearing channel-section steel
Determine and provide the column of pulling force, with the transverse slat of load-bearing channel-section steel fixation and on load-bearing channel-section steel and transverse slat for load-bearing channel-section steel
Pedal, brace is provided between the load-bearing channel-section steel and column, the branch corresponding with column is provided with the load-bearing channel-section steel
Strut, fender rod is provided with the support bar and column, guardrail is provided between the column and support bar.
Pass through above-mentioned technical proposal, load-bearing channel-section steel can allow the stress intensity of whole top layer platform high, column and brace
Setting, make the horizontal level of whole load-bearing channel-section steel more stable, the setting of pedal can allow people stand it is convenient, so as to right
The installation of computer room is more convenient, and the setting of fender rod and guardrail can allow whole top layer platform safer.
The present invention is further arranged to:Turnbuckle is provided between the load-bearing channel-section steel and wall.
Pass through above-mentioned technical proposal, the setting of turnbuckle allow load-bearing channel-section steel further to be protected with wall, improve
The security of top layer platform.
The present invention is further arranged to:The pedal surrounding is mounted on toeguard.
Pass through above-mentioned technical proposal, the setting of toeguard can place pin and extend into elevator.
The present invention is further arranged to:The platform building of the S2 comprises the following steps:S21, layer doorway lay anchor position,
Safety rope;S22, column is installed on the wall of layer door;S23, assembling load-bearing channel-section steel, transverse slat and brace, combined bay is formed,
And combined bay is moved into hoistway;S24, brace and column fixed, load-bearing channel-section steel is fixed with column, column, load-bearing
Channel-section steel and brace form triangular structure;S25, installation pedal;S26, turnbuckle, support bar, fender rod, shield are installed successively
Column and toeguard.
Pass through above-mentioned technical proposal, by above-mentioned steps, top layer platform can be allowed smoothly to build.
The present invention is further arranged to:Warning sign is installed on the fender rod being connected with column.
Pass through above-mentioned technical proposal, the setting of warning sign can allow it to be indicated, prevent the generation of fortuitous event.
The present invention is further arranged to:Alarm for counterweight proximity test is installed between the layer door and compartment system
Device, the warning device include the first detector being arranged on compartment system and the second detection installed in hoistway wall
Head and the 3rd detector, first detector coordinates with the second detector and the 3rd detector respectively carries out proximity test
Alarm.
Pass through above-mentioned technical proposal, when operation elevator car systems are installed, due between counterweight and compartment system
Do not accomplish complete stability, accordingly, it is possible to which situation about being collided between counterweight and compartment system occurs, therefore alarm is set
Device can allow operating personnel to prevent it, due to when elevator carries out up or descending, can be carried out with counterweight
It is close, therefore, set the first detector to coordinate respectively with the second detector and the 3rd detector, can identify that elevator exists respectively
Close signal is carried out when up and with counterweight when descending.
The present invention is further arranged to:The compartment system includes car and the protective cover on car, car
With to reconnection.
Pass through above-mentioned technical proposal, the setting of protective cover can allow operating personnel at work will not be by elevator hoistways
Debris drop caused by influence or safety problem.
The present invention is further arranged to:After S6 steps, the top layer platform that step 2 is built is removed.
Pass through above-mentioned technical proposal, installed, it is necessary to run elevator after S6 steps, therefore, top layer platform is carried out
Remove, the operation of elevator can be facilitated.
In summary, the invention has the advantages that:
(1)By the way that scaffold need not be installed in whole process in elevator hoistways, so as to after the completion of construction or construct
During need not carry out dismounting scaffold, entirely construct simpler, conveniently;
(2)By using the close warning device of protective cover, counterweight, make workmen safer in work progress.
Brief description of the drawings
Fig. 1 is structure diagram when elevator is installed;
Fig. 2 is the overall schematic of top layer platform;
Fig. 3 is structure chart of the top layer platform building in hoistway.
Reference:100th, baffle plate;101st, traction machine;102nd, directive wheel;103rd, steel wire rope;200th, top layer platform;1st, hold
Baking soda steel;2nd, transverse slat;3rd, column;4th, pedal;5th, brace;6th, support bar;7th, fender rod;8th, guardrail;9th, toeguard;10th, it is tight
Line device;300th, first guide rail;400th, compartment system;401st, car;402nd, protective cover;500th, counterweight;600th, stretcher;701、
First detector;702nd, the second detector;703rd, the 3rd detector.
Embodiment
The present invention will be described in detail below in conjunction with the accompanying drawings.
A kind of installation construction method for elevator, comprises the following steps:S1, by layer door door opening block, using baffle plate 100, to every
One layer of layer door is blocked, and leaves top layer layer door;S2, top layer platform 200 is built, build top layer in the layer door position of top layer and put down
Platform 200;S3, computer room mechanism installed, first guide rail 300 is installed, using the top layer platform 200 built, by computer room and the
A piece guide rail 300 carries out installation fixation;S4, installation buffer and stretcher 600;S5, installation compartment system 400, pass through top
Layer platform 200, sedan-chair frame and compartment system 400 are installed, wherein, compartment system 400 includes car 401;S6, installation counterweight
500, using top layer platform 200, counterweight 500 is installed, and allow it to be docked with car 401, allow car 401 can be in elevator
Interior movement, form mobile construction platform;S7, operation car 401 install other guide rails, the mobile construction formed by car 401
Platform installs other guide rails successively;S8, mounting layer door, the mobile construction platform mounting layer door formed again by car 401;
S9, installation gate, gate is finally installed, allow elevator to assemble substantially and finish;S10, debugging, miscellaneous part is installed, and
And unnecessary structure is removed, finally carry out the detection debugging of elevator operation.Its structure is referred to Fig. 1.
Wherein, in above-mentioned steps, S2 top layer platform 200 is built as construction basis, and its structure and mounting structure can be with
Reference picture 2 and Fig. 3.
Top layer platform 200 includes overlap joint load-bearing channel-section steel 1 on the wall, fixed with load-bearing channel-section steel 1 and is that load-bearing channel-section steel 1 provides
The column 3 of pulling force, the transverse slat 2 fixed with load-bearing channel-section steel 1 and the pedal 4 on load-bearing channel-section steel 1 and transverse slat 2, load-bearing groove
Brace 5 is provided between steel 1 and column 3, is provided with the support bar 6 corresponding with column 3 on load-bearing channel-section steel 1, support bar 6 with
And fender rod 7 is provided with column 3, guardrail 8 is provided between column 3 and support bar 6.Set between load-bearing channel-section steel 1 and wall
It is equipped with turnbuckle 10.The surrounding of pedal 4 is mounted on toeguard 9.
Top layer platform 200, which is built, to be comprised the following steps:S21, layer doorway lay anchor position, safety rope;S22, in layer door
Column 3 is installed on wall;S23, assembling load-bearing channel-section steel 1, transverse slat 2 and brace 5, combined bay is formed, and combined bay is moved
Enter in hoistway;S24, brace 5 and column 3 fixed, load-bearing channel-section steel 1 and column 3 fixed, column 3, load-bearing channel-section steel 1 and
Brace 5 forms triangular structure;S25, installation pedal 4;S26, turnbuckle 10, support bar 6, fender rod 7, guardrail are installed successively
8 and toeguard 9.Warning sign finally is installed on the fender rod 7 being connected with column 3.
Reference picture 1, after the completion of top layer platform 200 is built, then pass through top layer platform 200, the installation of Auxiliary Machinery Rooms equipment.
Workmen stands on top layer platform 200, installs traction machine 101, directive wheel 102 and steel wire rope 103 etc. successively, completes computer room
Assembling.After the assembling for completing computer room, decelerator, stretcher 600 etc. are installed in shaft bottom, and first guide rail 300 is pacified
In elevator hoistways.Compartment system 400 finally can equally be built into completion on top layer platform 200, and by steel wire rope
103 are attached with counterweight 500, and now, elevator can carry out preliminary movement.Top layer platform 200 is removed, by controlling electricity
Terraced car 401 is slowly lifted, and guide rail is reinforced, while installing other guide rails and layer door.Due to elevator car
The running and comparing of railway carriage or compartment 401 is slow, and counterweight 500 is not limited in this process, therefore, in order to prevent counterweight 500 for sedan-chair
Collide between railway carriage or compartment 401 and warned, it is necessary to install warning device between hoistway on lift car 401 in the process of running
Show.
Reference picture 1, warning device include the first detector 701, the second detector 702 and the 3rd detector 703, and first
Detector 701 is arranged on car 401, and the second detector 702 and the 3rd detector 703 are separately mounted in hoistway, in order to
Convenient installation, is typically mounted at layer door position, in the upper and lower for the position that lift car 401 and counterweight 500 meet successively
Second detector 702 and the 3rd detector 703 are installed.Send the signal that the first detector 701 detects to controller, lead to
Cross controller control buzzer or warning light is alarmed, so as in the running of car 401, in block close to counterweight 500
When, it can be alarmed.Controller can use PLC or central processing unit to form.
Reference picture 1, typically in mounting layer door and track, operate for convenience, workmen is usually to stand in car 401
Push up what position was carried out, therefore, in this process, easily drop debris above elevator hoistways, may influence workmen and apply
Work, or even security incident is caused, therefore, in order to make workmen's construction safer, protection is installed on lift car 401
Cover 402.
Described above is only the preferred embodiment of the present invention, and protection scope of the present invention is not limited merely to above-mentioned implementation
Example, all technical schemes belonged under thinking of the present invention belong to protection scope of the present invention.It should be pointed out that for the art
Those of ordinary skill for, some improvements and modifications without departing from the principles of the present invention, these improvements and modifications
It should be regarded as protection scope of the present invention.
Claims (9)
1. a kind of installation construction method for elevator, it is characterised in that comprise the following steps:S1, by layer door door opening block;S2, build top
Layer platform(200);S3 and computer room mechanism is installed, first guide rail is installed(300);S4, installation buffer and stretcher
(600);S5, installation compartment system(400);S6, installation counterweight(500);S7, operation compartment system(400)Other guide rails are installed;
S8, mounting layer door;S9, installation gate;S10, debugging.
2. installation construction method for elevator according to claim 1, it is characterised in that the top layer platform(200)Including taking
Connect load-bearing channel-section steel on the wall(1)And load-bearing channel-section steel(1)It is fixed and be load-bearing channel-section steel(1)The column of pulling force is provided(3), with holding
Baking soda steel(1)Fixed transverse slat(2)And installed in load-bearing channel-section steel(1)And transverse slat(2)On pedal(4), the load-bearing channel-section steel
(1)With column(3)Between be provided with brace(5), the load-bearing channel-section steel(1)On be provided with and column(3)Corresponding support
Bar(6), the support bar(6)And column(3)On be provided with fender rod(7), the column(3)With support bar(6)Between
It is provided with guardrail(8).
3. installation construction method for elevator according to claim 2, it is characterised in that the load-bearing channel-section steel(1)With wall it
Between be provided with turnbuckle(10).
4. installation construction method for elevator according to claim 3, it is characterised in that the pedal(4)Surrounding is mounted on
Toeguard(9).
5. installation construction method for elevator according to claim 4, it is characterised in that the platform building of the S2 includes as follows
Step:S21, layer doorway lay anchor position, safety rope;S22, column is installed on the wall of layer door(3);S23, assembling load-bearing groove
Steel(1), transverse slat(2)And brace(5), combined bay is formed, and combined bay is moved into hoistway;S24, by brace(5)
With column(3)It is fixed, by load-bearing channel-section steel(1)With column(3)It is fixed, column(3), load-bearing channel-section steel(1)And brace(5)Formed
Triangular structure;S25, installation pedal(4);S26, turnbuckle is installed successively(10), support bar(6), fender rod(7), guardrail(8)
And toeguard(9).
6. installation construction method for elevator according to claim 4, it is characterised in that with column(3)The fender rod of connection(7)
On warning sign is installed.
7. installation construction method for elevator according to claim 1, it is characterised in that the layer door and compartment system(400)
Between be provided with for counterweight(500)The warning device of proximity test, the warning device include being arranged on compartment system(400)
On the first detector(701)And the second detector installed in hoistway wall(702)And the 3rd detector(703), institute
State the first detector(701)Respectively with the second detector(702)And the 3rd detector(703)Coordinate and carry out proximity test report
It is alert.
8. installation construction method for elevator according to claim 1, it is characterised in that the compartment system(400)Including sedan-chair
Railway carriage or compartment(401)And installed in car(401)On protective cover(402), car(401)With counterweight(500)Connection.
9. installation construction method for elevator according to claim 1, it is characterised in that after S6 steps, step 2 is built
Platform is removed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710965671.5A CN107522062A (en) | 2017-10-17 | 2017-10-17 | A kind of installation construction method for elevator |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710965671.5A CN107522062A (en) | 2017-10-17 | 2017-10-17 | A kind of installation construction method for elevator |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107522062A true CN107522062A (en) | 2017-12-29 |
Family
ID=60684652
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710965671.5A Pending CN107522062A (en) | 2017-10-17 | 2017-10-17 | A kind of installation construction method for elevator |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107522062A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109368446A (en) * | 2018-12-12 | 2019-02-22 | 北京顺迅电梯设备工程有限公司 | A kind of elevator lifting system and its installation method |
CN109626190A (en) * | 2018-12-12 | 2019-04-16 | 北京顺迅电梯设备工程有限公司 | A kind of mounting device and its installation method of car guide rail |
CN110980478A (en) * | 2019-12-30 | 2020-04-10 | 江苏阿尔法电梯制造有限公司 | Construction lifting system |
CN111119461A (en) * | 2020-01-10 | 2020-05-08 | 日立电梯(中国)有限公司 | A operation platform that is used for steel construction elevator well installation top hoisting point |
CN113636435A (en) * | 2021-08-12 | 2021-11-12 | 中国华能集团清洁能源技术研究院有限公司 | Vertical conveying device for maintenance personnel of wind power generation equipment |
CN114269673A (en) * | 2019-08-23 | 2022-04-01 | 株式会社日立制作所 | Elevator device for construction |
CN115159300A (en) * | 2022-07-14 | 2022-10-11 | 广州市机电安装有限公司 | Elevator installation construction method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004189367A (en) * | 2002-12-09 | 2004-07-08 | Hitachi Building Systems Co Ltd | Installation method of elevator |
CN1990371A (en) * | 2005-12-27 | 2007-07-04 | 上海三菱电梯有限公司 | Elevator installation method and up-down system used therein |
CN101134548A (en) * | 2006-08-31 | 2008-03-05 | 因温特奥股份公司 | Lift facility with cabin and counterweight and method for arranging a lift facility |
CN103025640A (en) * | 2010-05-28 | 2013-04-03 | 通力股份公司 | Method and elevator arrangement |
CN104477736A (en) * | 2012-10-12 | 2015-04-01 | 广州广日电梯工程有限公司 | Shaft elevator installation method |
CN104528500A (en) * | 2014-12-29 | 2015-04-22 | 中国建筑股份有限公司 | Double-platform scaffold-free elevator installation method |
CN204626921U (en) * | 2015-05-13 | 2015-09-09 | 巨人通力电梯有限公司 | A kind of fixed working platform without scaffold construction elevator |
-
2017
- 2017-10-17 CN CN201710965671.5A patent/CN107522062A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004189367A (en) * | 2002-12-09 | 2004-07-08 | Hitachi Building Systems Co Ltd | Installation method of elevator |
CN1990371A (en) * | 2005-12-27 | 2007-07-04 | 上海三菱电梯有限公司 | Elevator installation method and up-down system used therein |
CN101134548A (en) * | 2006-08-31 | 2008-03-05 | 因温特奥股份公司 | Lift facility with cabin and counterweight and method for arranging a lift facility |
CN103025640A (en) * | 2010-05-28 | 2013-04-03 | 通力股份公司 | Method and elevator arrangement |
CN104477736A (en) * | 2012-10-12 | 2015-04-01 | 广州广日电梯工程有限公司 | Shaft elevator installation method |
CN104528500A (en) * | 2014-12-29 | 2015-04-22 | 中国建筑股份有限公司 | Double-platform scaffold-free elevator installation method |
CN204626921U (en) * | 2015-05-13 | 2015-09-09 | 巨人通力电梯有限公司 | A kind of fixed working platform without scaffold construction elevator |
Non-Patent Citations (5)
Title |
---|
李勇: "无脚手架电梯自导式安装施工工艺", 《安装》 * |
林仕超: "无脚手架电梯安装施工技术", 《施工技术》 * |
王应等: "《垂直电梯安装维护与保养》", 31 January 2017, 中国轻工业出版社 * |
许林等: "《电梯安装维修与保养安全技术》", 30 June 2011, 安徽科学技术出版社 * |
邵永青: "电梯无脚手架安装工艺探讨及优化", 《中国新技术新产品》 * |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109368446A (en) * | 2018-12-12 | 2019-02-22 | 北京顺迅电梯设备工程有限公司 | A kind of elevator lifting system and its installation method |
CN109626190A (en) * | 2018-12-12 | 2019-04-16 | 北京顺迅电梯设备工程有限公司 | A kind of mounting device and its installation method of car guide rail |
CN114269673A (en) * | 2019-08-23 | 2022-04-01 | 株式会社日立制作所 | Elevator device for construction |
CN110980478A (en) * | 2019-12-30 | 2020-04-10 | 江苏阿尔法电梯制造有限公司 | Construction lifting system |
CN110980478B (en) * | 2019-12-30 | 2021-04-20 | 江苏阿尔法电梯制造有限公司 | Construction lifting system |
CN111119461A (en) * | 2020-01-10 | 2020-05-08 | 日立电梯(中国)有限公司 | A operation platform that is used for steel construction elevator well installation top hoisting point |
CN113636435A (en) * | 2021-08-12 | 2021-11-12 | 中国华能集团清洁能源技术研究院有限公司 | Vertical conveying device for maintenance personnel of wind power generation equipment |
CN113636435B (en) * | 2021-08-12 | 2023-01-03 | 中国华能集团清洁能源技术研究院有限公司 | Vertical conveying device for maintenance personnel of wind power generation equipment |
CN115159300A (en) * | 2022-07-14 | 2022-10-11 | 广州市机电安装有限公司 | Elevator installation construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107522062A (en) | A kind of installation construction method for elevator | |
US9382099B2 (en) | Motorized height access device for tower cranes | |
CN105377738B (en) | For the falling-prevention protecting device of platform | |
CN104477736A (en) | Shaft elevator installation method | |
CN201714054U (en) | Climbing platform system for construction of elevator shaft of high-rise building | |
CN106638299B (en) | Multifunction working platform and construction method | |
CN110528863B (en) | Hanging basket device for outer inclined plane construction and construction method | |
CN101845883A (en) | Climbing scaffold system and construction method | |
JP2011178496A (en) | Control device for elevator | |
CN205709568U (en) | A kind of intelligent remote controls full-automatic explosion-proof type tank container gantry | |
CN103193137B (en) | High-altitude full automatic lifting and using method thereof | |
CN208235927U (en) | All steel intelligent building construction lifting platform | |
CN103912128B (en) | The construction method of high-altitude disjunctor steel truss | |
CN110171759B (en) | Method for disassembling elevator with machine room | |
JP5105146B2 (en) | Gondola device and method for constructing exterior of building using gondola device | |
CN103011031A (en) | Stand column type 360-degree rotary oil tank maintenance platform | |
CN109763638A (en) | A kind of high-altitude overhanging facade special type working vehicle and its construction method | |
CN111287498B (en) | Protective shed frame for construction of overhead bridge box girder crossing railway and erection method | |
CN107215748A (en) | The special building hoist of hoistway and its installation method | |
CN106088564A (en) | Track climbing type monolithic architecture construction scaffolding | |
CN105776092A (en) | Stretching type basket device and construction method thereof | |
CN104973515B (en) | A kind of crane more piece safety operation room and its method of operating | |
CN205369033U (en) | Gallows formula bridge tool car | |
CN108035530A (en) | A kind of inner wall of oil tank construction hanging basket | |
CN211037771U (en) | Hanging basket device for outer slope construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171229 |