CN103912128B - The construction method of high-altitude disjunctor steel truss - Google Patents
The construction method of high-altitude disjunctor steel truss Download PDFInfo
- Publication number
- CN103912128B CN103912128B CN201410070549.8A CN201410070549A CN103912128B CN 103912128 B CN103912128 B CN 103912128B CN 201410070549 A CN201410070549 A CN 201410070549A CN 103912128 B CN103912128 B CN 103912128B
- Authority
- CN
- China
- Prior art keywords
- platform
- steelframe
- construction
- protective platform
- sides
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
技术领域technical field
本发明涉及建筑技术领域,具体涉及一种高空连体钢桁架的施工方法。The invention relates to the field of building technology, in particular to a construction method of a high-altitude conjoined steel truss.
背景技术Background technique
近年来,出现了较多高空连体结构的大楼,这些大楼在施工时,通常是先进行两侧建筑主体结构施工,然后,在两侧建筑主体顶部之间搭建连廊。In recent years, there have been many high-altitude conjoined buildings. During the construction of these buildings, the main structure of the two sides of the building is usually constructed first, and then a corridor is built between the tops of the main buildings on both sides.
目前,高空连廊的搭建过程通常是采用传统搭建落地式支撑体系或者整体提升及滑移的方式进行,具体的是,从地面开始在两侧建筑主体之间搭接脚手架,将脚手架搭建至连廊预定的位置,在脚手架上形成一个用于放置设备以及供施工人员站立的承载平台,在承载平台侧面设置立面防护;在完成承载平台搭建后,设备以及工人在承载平台上施工,在两侧建筑主体之间搭建钢桁架,形成高空连廊的主体梁结构,然后以钢桁架为基础进行承板安装、幕墙施工等建筑后续施工,完成连廊的搭建。这种采用搭建脚手架辅助完成高空连体钢桁架搭建的施工方法,虽然能够确保施工安全,但是,搭建以及拆除脚手架的过程较为麻烦,使整个连廊搭建的工期较长,在两侧建筑主体跨度及高度较大时,脚手架的整体强度相对较低,安全隐患较严重且成本较高。因此,限制了承载平台上施工设备的吨位,一些大型设备还需要通过其他方式来安置。整体提升及整体滑移的安装方法则是,在地面预先拼装完成后,通过大吨位或长行程顶升设备,将建筑构件整体安装就位,此方法主要受到施工高度的限制,且要求提升通道空间规整,无碰撞且具有可通过性,同时成本较高,安全隐患难以控制。At present, the construction process of high-altitude corridors is usually carried out by using the traditional method of building a floor-standing support system or the overall lifting and sliding. Specifically, starting from the ground, scaffolding is overlapped between the main bodies of the buildings on both sides, and the scaffolding is built to the connection. At the predetermined position of the corridor, a bearing platform for placing equipment and standing on the scaffold is formed on the scaffold, and facade protection is set on the side of the bearing platform; Steel trusses are built between the main bodies of the side buildings to form the main beam structure of the high-altitude corridor, and then the steel trusses are used as the basis for the subsequent construction of the building, such as the installation of the bearing plate and the construction of the curtain wall, to complete the construction of the corridor. Although this construction method using scaffolding to assist in the construction of high-altitude conjoined steel trusses can ensure construction safety, the process of erecting and dismantling the scaffolding is cumbersome, which makes the construction period of the entire corridor longer, and the main span of the building on both sides And when the height is large, the overall strength of the scaffold is relatively low, the safety hazard is serious and the cost is high. Therefore, the tonnage of construction equipment on the carrying platform is limited, and some large equipment needs to be placed in other ways. The installation method of overall lifting and overall sliding is to install the building components in place through large tonnage or long-stroke jacking equipment after the pre-assembly on the ground is completed. This method is mainly limited by the construction height and requires a lifting channel The space is regular, collision-free and passable, but at the same time, the cost is high, and safety hazards are difficult to control.
发明内容Contents of the invention
针对现有技术的不足,本发明的目的旨在于提供一种高空连体钢桁架的施工方法,其无需搭建脚手架,在满足施工安全以及施工强度要求的同时,能够提高施工的效率、缩短施工工期。Aiming at the deficiencies of the prior art, the object of the present invention is to provide a construction method for high-altitude conjoined steel trusses, which does not require scaffolding, and can improve construction efficiency and shorten the construction period while meeting construction safety and construction strength requirements .
为实现上述目的,本发明采用如下技术方案:To achieve the above object, the present invention adopts the following technical solutions:
高空连体钢桁架的施工方法,包括如下步骤:The construction method of high-altitude conjoined steel truss includes the following steps:
A、在两侧建筑主体上分别预埋支承件,支承件的高度位于预搭建钢桁架位置的下方;A. Pre-embed supporting parts on the main body of the building on both sides, and the height of the supporting parts is located below the position of the pre-built steel truss;
B、在两侧建筑主体之间的裙楼屋面搭建钢架防护平台,在钢架防护平台的两端分别设置支撑梁;B. Build a steel frame protection platform on the podium roof between the main buildings on both sides, and set support beams at both ends of the steel frame protection platform;
C、利用塔吊将钢架防护平台吊装至支承件的高度,将钢架防护平台的两端的支撑梁分别连接固定在两侧建筑主体上预埋的支承件上;C. Use a tower crane to hoist the steel frame protection platform to the height of the support, and connect and fix the support beams at both ends of the steel frame protection platform to the pre-embedded supports on the main body of the building on both sides;
D、在固定好的钢架防护平台上铺设胶合板,钢架防护平台的四周搭设防护栏杆,使得钢架防护平台形成完整的施工活动平台;D. Lay plywood on the fixed steel frame protection platform, and set up protective railings around the steel frame protection platform, so that the steel frame protection platform forms a complete construction activity platform;
E、利用塔吊将钢桁架的底部主梁吊装至施工活动平台上方,施工活动平台上方的施工人员对底部主梁端部与两侧建筑主体的钢结构进行焊接,底部主梁的外侧焊接悬挑梁,在悬挑梁上搭建脚手架,形成施工通道和操作平台;E. Use the tower crane to hoist the bottom main girder of the steel truss above the construction activity platform. The construction workers above the construction activity platform weld the end of the bottom main girder and the steel structure of the main body of the building on both sides. The outer welding of the bottom main girder is overhanging Beams, build scaffolding on the cantilever beams to form construction passages and operating platforms;
F、在底部主梁上分段拼接承重贝雷架,拼接的贝雷架端部固定于两侧建筑主体的钢结构上,形成贝雷架操作平台;F. The load-bearing Bailey frame is spliced in sections on the main beam at the bottom, and the ends of the spliced Bailey frame are fixed on the steel structures of the main buildings on both sides to form the Bailey frame operating platform;
G、在贝雷架操作平台上搭建钢桁架的其他钢构件;G. Build other steel components of the steel truss on the Bailey frame operating platform;
H、钢桁架整体施工完成后,切割支承件,将钢架防护平台吊装至地面。H. After the overall construction of the steel truss is completed, the supporting parts are cut, and the steel frame protection platform is hoisted to the ground.
步骤H中,在两侧建筑主体上与钢架防护平台高度相同的位置分别安装一卷扬机,利用卷扬机牵引钢架防护平台的端部,切割支承件后,利用卷扬机将钢架防护平台整体牵引下降。In step H, install a winch on the main body of the building on both sides at the same height as the steel frame protection platform, use the winch to pull the end of the steel frame protection platform, cut the support, use the winch to pull the steel frame protection platform down as a whole .
步骤B中,钢架防护平台分左右两部分,在步骤C将钢架防护平台的两部分吊装完成后,将钢架防护平台的两部分横向靠拢并焊接固定。In step B, the steel frame protective platform is divided into left and right parts, and in step C, after the two parts of the steel frame protective platform are hoisted, the two parts of the steel frame protective platform are laterally moved closer and fixed by welding.
在步骤E进行完之后,底部主梁端两端底部与两侧建筑主体的钢结构之间设置斜支撑梁。After step E is completed, diagonal support beams are set between the bottom of the two ends of the bottom main girder and the steel structures of the building main bodies on both sides.
本发明的有益效果在于:The beneficial effects of the present invention are:
相比于现有技术,本发明采用直接吊装的方式安装钢架防护平台,从而在施工位置形成供设备和工人活动的安全平台,相比于现有搭建脚手架建立安全平台的方法,本发明的方法简单,能够提高施工效率、缩短施工工期;此外,采用贝雷架操作平台承重,能够确保施工强度。Compared with the prior art, the present invention adopts the method of direct hoisting to install the steel frame protective platform, thereby forming a safe platform for equipment and workers to move about at the construction site. The method is simple, can improve the construction efficiency and shorten the construction period; in addition, the use of the Bailey frame operating platform for load bearing can ensure the construction strength.
具体实施方式detailed description
下面,结合具体实施方式,对本发明做进一步描述:Below, in conjunction with specific embodiment, the present invention is described further:
本发明高空连体钢桁架的施工方法包括如下步骤:The construction method of high-altitude conjoined steel truss of the present invention comprises the following steps:
A、在两侧建筑主体上相对的面上分别预埋支承件,支承件的高度位于预搭建钢桁架位置的下方;A. Pre-embed supporting parts on the opposite surfaces of the main body of the building on both sides, and the height of the supporting parts is located below the position of the pre-built steel truss;
B、在两侧建筑主体之间的裙楼屋面搭建钢架防护平台,在钢架防护平台的两端分别设置支撑梁;防护平台的强度要能够满足施工设备以及人工操作的要求,防护平台的长度等于两侧建筑主体之间的楼距;B. Build a steel-frame protective platform on the podium roof between the main building bodies on both sides, and set support beams at both ends of the steel-frame protective platform; the strength of the protective platform must be able to meet the requirements of construction equipment and manual operation. The length is equal to the building distance between the building bodies on both sides;
C、利用塔吊将钢架防护平台吊装至支承件的高度,将钢架防护平台的两端的支撑梁分别连接固定在两侧建筑主体上预埋的支承件上;C. Use a tower crane to hoist the steel frame protection platform to the height of the support, and connect and fix the support beams at both ends of the steel frame protection platform to the pre-embedded supports on the main body of the building on both sides;
D、在固定好的钢架防护平台上铺设胶合板,钢架防护平台的四周搭设防护栏杆,使得钢架防护平台形成完整的施工活动平台,该施工活动平台用于放置施工设备以及工人施工时活动,同时可以防止施工时造成的高空坠物掉落至地面;D. Lay plywood on the fixed steel frame protection platform, and set up protective railings around the steel frame protection platform, so that the steel frame protection platform forms a complete construction activity platform. The construction activity platform is used to place construction equipment and workers during construction. , At the same time, it can prevent the falling objects caused by the construction from falling to the ground;
E、利用塔吊将钢桁架的底部主梁吊装至施工活动平台上方,施工活动平台上方的施工人员对底部主梁端部与两侧建筑主体的钢结构进行焊接,底部主梁的外侧焊接悬挑梁,在悬挑梁上搭建脚手架,形成施工通道和操作平台;E. Use the tower crane to hoist the bottom main girder of the steel truss above the construction activity platform. The construction workers above the construction activity platform weld the end of the bottom main girder and the steel structure of the main body of the building on both sides. The outer welding of the bottom main girder is overhanging Beams, build scaffolding on the cantilever beams to form construction passages and operating platforms;
F、在底部主梁上分段拼接承重贝雷架,拼接的贝雷架端部固定于两侧建筑主体的钢结构上,形成贝雷架操作平台;F. The load-bearing Bailey frame is spliced in sections on the main beam at the bottom, and the ends of the spliced Bailey frame are fixed on the steel structures of the main buildings on both sides to form the Bailey frame operating platform;
G、在贝雷架操作平台上搭建钢桁架的其他钢构件;G. Build other steel components of the steel truss on the Bailey frame operating platform;
H、钢桁架整体施工完成后,切割支承件,将钢架防护平台吊装至地面。H. After the overall construction of the steel truss is completed, the supporting parts are cut, and the steel frame protection platform is hoisted to the ground.
上述方法相比于现有搭建脚手架施工的方式,其采用塔吊吊装钢架防护平台,可以简化施工过程,提高施工效率,缩短施工周期,此外,采用贝雷架操作平台承重,能够确保施工强度。Compared with the existing construction method of scaffolding, the above method uses a tower crane to hoist the steel frame protection platform, which can simplify the construction process, improve construction efficiency, and shorten the construction period. In addition, the use of the Bailey frame operation platform for load bearing can ensure construction strength.
为了便于操作,在上述的步骤H中,可以在两侧建筑主体上与钢架防护平台高度相同的位置分别安装一卷扬机,利用卷扬机牵引钢架防护平台的端部,之后切割支承件,利用卷扬机将钢架防护平台整体牵引,使钢架防护平台缓慢下降至地面。For the convenience of operation, in the above step H, a hoist can be installed on the main body of the building on both sides at the same height as the steel frame protection platform, and the end of the steel frame protection platform can be pulled by the hoist, and then the support is cut, and the hoist can be used to Pull the steel frame protection platform as a whole, so that the steel frame protection platform slowly descends to the ground.
在上述的步骤B中,钢架防护平台分左右两部分分别焊接完成,在步骤C将钢架防护平台的两部分吊装完成后,将钢架防护平台的两部分横向靠拢并焊接固定,如此,可以减少塔吊的负重力。In the above-mentioned step B, the steel frame protection platform is divided into left and right parts and welded respectively. After the two parts of the steel frame protection platform are hoisted in step C, the two parts of the steel frame protection platform are horizontally moved closer and fixed by welding. In this way, It can reduce the load of the tower crane.
在步骤E进行完之后,底部主梁两端底部与两侧建筑主体的钢结构之间设置斜支撑梁,用于增加底部主梁与两侧建筑主体钢结构的连接强度。After step E is completed, diagonal support beams are set between the bottom of the main beam at both ends and the steel structures of the main buildings on both sides to increase the connection strength between the main beam at the bottom and the steel structures of the main buildings on both sides.
对本领域的技术人员来说,可根据以上描述的技术方案以及构思,做出其它各种相应的改变以及形变,而所有的这些改变以及形变都应该属于本发明权利要求的保护范围之内。Those skilled in the art can make various other corresponding changes and deformations according to the above-described technical solutions and concepts, and all these changes and deformations should fall within the protection scope of the claims of the present invention.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410070549.8A CN103912128B (en) | 2014-02-28 | 2014-02-28 | The construction method of high-altitude disjunctor steel truss |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410070549.8A CN103912128B (en) | 2014-02-28 | 2014-02-28 | The construction method of high-altitude disjunctor steel truss |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN103912128A CN103912128A (en) | 2014-07-09 |
| CN103912128B true CN103912128B (en) | 2015-12-30 |
Family
ID=51038097
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201410070549.8A Expired - Fee Related CN103912128B (en) | 2014-02-28 | 2014-02-28 | The construction method of high-altitude disjunctor steel truss |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN103912128B (en) |
Families Citing this family (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104818859B (en) * | 2015-05-27 | 2017-01-04 | 中冶建工集团有限公司 | The installation method of orbit traffic overhead station operation platform |
| CN106522361A (en) * | 2016-12-07 | 2017-03-22 | 上海市机械施工集团有限公司 | Combined installation method for multi-layer heavy steel space corridor |
| CN107012949B (en) * | 2017-05-10 | 2019-06-07 | 中国建筑第二工程局有限公司 | Lifting method of large-span steel corridor |
| CN110439305A (en) * | 2019-05-24 | 2019-11-12 | 上海建工七建集团有限公司 | Steel vestibule integrally promotes high-altitude translation installation safety protection structure and its installation method |
| CN110952786B (en) * | 2019-12-25 | 2022-07-15 | 中建国厦集团股份有限公司 | Truss structure and installation method thereof |
| CN111456400A (en) * | 2020-03-24 | 2020-07-28 | 中国五冶集团有限公司 | A high-altitude temporary operating platform structure |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH04146343A (en) * | 1990-10-09 | 1992-05-20 | Shimizu Corp | Column/beam jointing construction |
| CN100557168C (en) * | 2008-03-21 | 2009-11-04 | 宁波建工集团有限公司 | A high-altitude installation method for long-span steel truss |
| CN101845849B (en) * | 2010-06-22 | 2011-08-24 | 中国建筑第二工程局有限公司 | Large-span steel structure corridor erected between new and old buildings and construction method thereof |
| CN101845848B (en) * | 2010-06-22 | 2011-08-24 | 中国建筑第二工程局有限公司 | Large-span steel connecting bridge and integral hoisting method thereof |
| CN103061514B (en) * | 2012-11-09 | 2015-12-02 | 浙江八达建设集团有限公司 | Long-span steel structure corridor construction method |
-
2014
- 2014-02-28 CN CN201410070549.8A patent/CN103912128B/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| CN103912128A (en) | 2014-07-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103912128B (en) | The construction method of high-altitude disjunctor steel truss | |
| CN203867216U (en) | Detachable steel frame supporting structure for ultra-high-rise building cantilevered plate | |
| CN201158933Y (en) | High-rise maintaining scaffold device with extruding structure | |
| CN102864936B (en) | Combination lifting construction method for large-scale high hollow building roof of steel structure | |
| CN102877637B (en) | Method for implementing operating platform in bottom wall construction of cantilever beam | |
| CN103711301A (en) | Construction method and device for two-track movable electric basket and lifting hoist | |
| CN202194365U (en) | Hydraulic self-climbing type discharging platform | |
| CN207144449U (en) | A kind of hoistway operation platform | |
| CN204781887U (en) | Prefabricated assembly type structure's no outrigger construction platform | |
| CN203654702U (en) | Operating platform for construction of reinforced concrete chimney | |
| CN205296803U (en) | Elevator automatic lifting operation panel | |
| CN115538792B (en) | Building construction method and building construction structure by using residential building machine | |
| CN105350760B (en) | A kind of construction method of suspending scaffold | |
| CN207609153U (en) | A kind of elevator liftable construction operation platform | |
| CN201695668U (en) | An assembled slow-walking platform | |
| CN105442773A (en) | Technology and construction platform for installing and constructing inner plates of metal roof | |
| CN204753397U (en) | Temporary mounting hanger for steel box bridge | |
| CN203947755U (en) | A kind of large Steel Cantilever trussed construction high-altitude construction first floor steel truss erecting device | |
| CN106968371B (en) | A kind of construction method of the high wing articulated structure drifted by wind of curtain wall construction | |
| CN103375022A (en) | Multifunctional movable-rail attachment lifting scaffold | |
| CN108487621A (en) | Assembled movement shield cage and its construction method | |
| CN108277994A (en) | On across the high ferro safe guarding shed quick method for dismounting of operation line | |
| CN104060809B (en) | A kind of roofing daylighting glass steelframe installs equipment and operation method thereof | |
| CN102733612B (en) | Mounting method of electric hoist orbit | |
| CN201915630U (en) | Combined platform of fire control joint gallery form supporting steel beam |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20151230 Termination date: 20170228 |