CN106088564A - Track climbing type monolithic architecture construction scaffolding - Google Patents

Track climbing type monolithic architecture construction scaffolding Download PDF

Info

Publication number
CN106088564A
CN106088564A CN201610669466.XA CN201610669466A CN106088564A CN 106088564 A CN106088564 A CN 106088564A CN 201610669466 A CN201610669466 A CN 201610669466A CN 106088564 A CN106088564 A CN 106088564A
Authority
CN
China
Prior art keywords
support
support body
construction
backgear
climbing type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610669466.XA
Other languages
Chinese (zh)
Inventor
桑印祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianli Boda Science And Technology Co Ltd
Original Assignee
Tianli Boda Science And Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianli Boda Science And Technology Co Ltd filed Critical Tianli Boda Science And Technology Co Ltd
Priority to CN201610669466.XA priority Critical patent/CN106088564A/en
Publication of CN106088564A publication Critical patent/CN106088564A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/20Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Types And Forms Of Lifts (AREA)

Abstract

The present invention relates to the realm of building construction, specifically a kind of track climbing type monolithic architecture construction scaffolding.Including support body, also include rack support, rack support is bolted on construction wall, support body is slidably connected with rack support by fixed block, support body is provided with electric machine support, electric machine support is provided with motor, and the power transmission shaft of motor is provided with the travelling gear that the tooth bar with rack support coordinates.The present invention is mounted directly use with building body construction, increases the lifting speed of scaffold, shortens construction period, improves production efficiency, and support body stability in the large is strong, adds the working range of personnel's construction, convenient construction.

Description

Track climbing type monolithic architecture construction scaffolding
Technical field
The present invention relates to the realm of building construction, specifically a kind of track climbing type monolithic architecture construction scaffolding.
Background technology
Existing construction scaffolding mounting means be mostly after main building construction speed reaches index bed to start to assemble Support body, support body utilizes electric hoist to promote, and is also movable Scaffold, only possesses operation platform function, and it is slow that electric hoist promotes speed And unstable, increase the engineering time, extend man-hour, utilize some seats in the plane, somewhat expensive, produce and set up sufficiently complex, building site It is difficult to dismantle, and another kind of method is that I-steel is beaten in body of wall, then scaffold tube is placed on I-steel front end as support, Then set up scaffold above, starting when the method is built can be Tong Bu with main body, more than three layers need dismounting after build again, secondary Taking a lot of work, increase cost, both the above method uses function singleness, without water supply capacity, scaffold frame nonintegrated structure, Gong Ren Can not change smoothly between in each several part construction, work progress causes inconvenience and potential safety hazard.
Summary of the invention
Present invention seek to address that the problems referred to above, thus provide a kind of and be mounted directly use, Neng Gouzeng with building body construction Add support body promote speed and workmen's working range, improve production efficiency, track climbing type entirety that stability in the large is strong is built Build construction scaffolding.
The present invention solves described problem, the technical scheme is that
A kind of track climbing type monolithic architecture construction scaffolding, including support body, also includes rack support, and rack support passes through bolt Being fixed on construction wall, support body is slidably connected with rack support by fixed block, and support body is provided with electric machine support, and motor props up Frame is provided with motor, and the power transmission shaft of motor is provided with the travelling gear that the tooth bar with rack support coordinates.
Using the present invention of technique scheme, compared with prior art, its prominent feature is:
1. it is mounted directly use with building body construction, changes into being carried by rack gear by the mode that electric hoist in prior art promotes The mode of liter, overall increasing promotes speed and the degree of stability of full building scaffold support body, shortens construction period, improve and produce effect Rate, when building body high level needs scaffold, the time of entirety 5-10 minute climbs one layer, does not affect the construction period.
2. support body stability in the large is strong, adds the working range of personnel's construction, convenient construction.
As preferably, the present invention further technical scheme is:
Support body includes that crossbeam, vertical beam, crossbeam, vertical beam connect and compose frame structure by connector and bolt, and frame structure is divided Be not provided with bridging, top layer guardrail diagonal brace, top layer guardrail directly support, flat bed diagonal brace.
Crossbeam includes scaffold top guardrail cross beams, Horizontal load-bearing beam, flat bed load-bearing straight beam.
Support body is provided with the electrical control cabinet electrically connected with motor, it is achieved centralized Control motor drives support body lifting.
Each layer of work platforms of support body is provided with fire water box, and support body is provided with and is placed in above each layer of work platforms Fire extinguisher canvas hose bracing frame, the fire extinguisher canvas hose bracing frame above each layer of work platforms is provided with and disappearing that corresponding fire water box connects Guard tube, once breaking out of fire can be put out a fire rescue in time, improves monolithic architecture safety coefficient greatly.
Fixed block is arranged on support body, including being respectively placed on front side of rack support support beam, rear side and the front back of the body in outside Wheel, rear backgear and side backgear, support body is slided up and down on rack support by front backgear, rear backgear and side backgear, fixed block Effect be to realize being slidably connected of support body and rack support.
Accompanying drawing explanation
Fig. 1 is the embodiment of the present invention main TV structure schematic diagram;
Fig. 2 is the partial enlarged drawing of A in Fig. 1;
Fig. 3 is B-B cross-sectional view in Fig. 1;
Fig. 4 is embodiment of the present invention side-looking structural representation;
Fig. 5 is the partial enlarged drawing of B in Fig. 4;
In figure: rack support 1;Tooth bar 2;Body of wall 3;Travelling gear 4;Motor 5;Electric machine support 6;Scaffold top guardrail cross beams 7; Horizontal load-bearing beam 8;Flat bed load-bearing straight beam 9;Vertical beam 10;Bridging 11;Top layer guardrail diagonal brace 12;Top layer guardrail directly supports 13;Flat bed Diagonal brace 14;Fire water box 15;Electrical control cabinet 16;Front backgear 17;Rear backgear 18;Side backgear 19;Fire extinguisher canvas hose 20;Fire water Pipe bracing frame 21;Support body 22.
Detailed description of the invention:
Below in conjunction with embodiment, the invention will be further described, and purpose is only that and is more fully understood that present invention, therefore, and institute The example of act is not limiting as protection scope of the present invention.
Seeing Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, rack support 1 is fixed on body of wall 3 by bolt by the bolt hole on body of wall 3 On, support body 22 is slidably connected with rack support 1 by fixed block, and fixed block is arranged on support body 22, including being respectively placed in On front side of rack support 1 support beam, rear side and the front backgear 17 in outside, rear backgear 18 and side backgear 19, support body 22 is by front backgear 17, rear backgear 18 and side backgear 19 slide up and down on rack support 1, and the effect of fixed block is to realize support body 22 to prop up with tooth bar Being slidably connected of frame 1, motor 5 is bolted on electric machine support 6, and electric machine support 6 is bolted on support body 22, electricity The power transmission shaft of motivation 5 is provided with the travelling gear 4 that the tooth bar 2 with rack support 1 coordinates, and support body 22 is horizontal by scaffold top guardrail Beam 7, Horizontal load-bearing beam 8, flat bed load-bearing straight beam 9, vertical beam 10 and bridging 11, top layer guardrail diagonal brace 12, top layer guardrail directly support 13, flat bed diagonal brace 14 passes through connector and is bolted together the frame structure of composition, after support body 22 holistic conformation completes, often Covering platform liner plate on the Horizontal load-bearing beam 8 of layer, each layer of work platforms of support body 22 is provided with fire water box 15, on support body 22 Being provided with the fire extinguisher canvas hose bracing frame 21 being placed in above each layer of work platforms, the fire extinguisher canvas hose above each layer of work platforms supports The fire extinguisher canvas hose 20 that frame 21 is provided with and corresponding fire water box 15 connects, once breaking out of fire can be put out a fire rescue in time, greatly Improving monolithic architecture safety coefficient, support body 22 is provided with the electrical control cabinet 16 electrically connected with motor 5, it is achieved centralized Control electricity Motivation 5 drives support body 22 to lift.
Start to build this device while building body starts to build, steel pipe and the connecting rod of support body 22 are utilized and connect Part couples together, and lays platform liner plate, can directly supply after having built on the horizontal support framework of overall support body 22 1 layers Workmen uses, and installs electrical control cabinet 16 and fire water box 15 simultaneously, and owner's body to be built a layer has been built outside pulling down After boxing plate, bore the fixing hole of rack support in body of wall 3 appropriate location, rack support 1 is installed, simultaneously at overall support body 22 1 Layer electric machine support 6 installed above and motor 5, after building main body starts to build the second layer, also with the steel pipe of support body 22 Building overall support body 22 second layer with connecting rod, the same ground floor of form of construction work, owner's body to be built two layers has been built limit mould and has been torn open Boring the fixing hole of rack support after removing in body of wall 3 appropriate location, install rack support 1, building main body starts to build third layer Time start simultaneously at and build support body 22 third layer, mode of building is the same, afterwards with the increase of building main body construction height, support body 22 Driven by motor 5 and promote, coordinate the increase of building main body construction height, after support body 22 promotes, can be by Idle rack support 1 below support body 22 working lining is removed from the body of wall 3 of building main body, and the upper strata being installed to need to promote is built Building on thing body of wall 3, after building main body construction completes, support body 22 can be along with the carrying out of secondary construction, and support body 22 declines simultaneously, with Time remove support body 22 working lining upper strata rack support 1, attach it on support body 22 gravitating bed, along with secondary construction downward Carrying out, support body 22 drops to ground the most completely, until support body 22 can be carried out after having constructed removing operation by secondary.
This device is mounted directly use with building body construction, increases the lifting speed of support body 22, increases on support body 22 Fire water box 15, can improve safety coefficient, and support body 22 is general frame structure, increases the working range of personnel's construction, conveniently executes Work, it is to avoid arrange I-steel on body of wall 3 and cause secondary to construct, shortens construction period, and simple in construction, quick for installation, minimizing is executed Between man-hour, improve work efficiency.
The foregoing is only the embodiment that the present invention is the most feasible, not thereby limit to the interest field of the present invention, The equivalence change that all utilization description of the invention and accompanying drawing content thereof are made, within being both contained in the interest field of the present invention.

Claims (6)

1. a track climbing type monolithic architecture construction scaffolding, including support body, it is characterised in that: also include rack support, tooth Bar support is bolted on construction wall, and support body is slidably connected with rack support by fixed block, and support body is provided with Electric machine support, electric machine support is provided with motor, and the power transmission shaft of motor is provided with the transmission that the tooth bar with rack support coordinates Gear.
Track climbing type monolithic architecture construction scaffolding the most according to claim 1, it is characterised in that: support body includes horizontal stroke Beam, vertical beam, crossbeam, vertical beam connect and compose frame structure by connector and bolt, frame structure are respectively equipped with bridging, top Layer guardrail diagonal brace, top layer guardrail directly support, flat bed diagonal brace.
Track climbing type monolithic architecture construction scaffolding the most according to claim 2, it is characterised in that: crossbeam includes foot hands Frame top guardrail cross beams, Horizontal load-bearing beam, flat bed load-bearing straight beam.
Track climbing type monolithic architecture construction scaffolding the most according to claim 1, it is characterised in that: support body be provided with The electrical control cabinet of motor electrical connection.
Track climbing type monolithic architecture construction scaffolding the most according to claim 1, it is characterised in that: each layer of support body Work platforms is provided with fire water box, and support body is provided with the fire extinguisher canvas hose bracing frame being placed in above each layer of work platforms, each Fire extinguisher canvas hose bracing frame above layer work platforms is provided with the fire extinguisher canvas hose connected with corresponding fire water box.
Track climbing type monolithic architecture construction scaffolding the most according to claim 1, it is characterised in that: fixed block is installed On support body, including being respectively placed on front side of rack support support beam, rear side and the front backgear in outside, rear backgear and side backgear, frame Body is slided up and down on rack support by front backgear, rear backgear and side backgear.
CN201610669466.XA 2016-08-16 2016-08-16 Track climbing type monolithic architecture construction scaffolding Pending CN106088564A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610669466.XA CN106088564A (en) 2016-08-16 2016-08-16 Track climbing type monolithic architecture construction scaffolding

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610669466.XA CN106088564A (en) 2016-08-16 2016-08-16 Track climbing type monolithic architecture construction scaffolding

Publications (1)

Publication Number Publication Date
CN106088564A true CN106088564A (en) 2016-11-09

Family

ID=58069267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610669466.XA Pending CN106088564A (en) 2016-08-16 2016-08-16 Track climbing type monolithic architecture construction scaffolding

Country Status (1)

Country Link
CN (1) CN106088564A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424543A (en) * 2019-07-24 2019-11-08 中冶天工集团有限公司 A kind of motor driven building module structure and construction method
CN112376885A (en) * 2020-11-17 2021-02-19 浙江铠甲建筑科技有限公司 Track climbing type integral building construction scaffold convenient to disassemble

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090080613A (en) * 2008-01-22 2009-07-27 최순복 Building outer wall construction equipment system
CN102704664A (en) * 2012-05-30 2012-10-03 深圳市特辰科技股份有限公司 Self-lifting quick transferring platform
CN102747831A (en) * 2012-06-19 2012-10-24 张玉家 Sleeve rail type electric attachment lifting scaffold
CN105401714A (en) * 2015-10-27 2016-03-16 重庆东辰建筑机械安装工程有限公司 Attachment type lifting scaffold and lifting method
CN105715028A (en) * 2015-06-26 2016-06-29 王积政 Successive lifting device and lifting scaffold with same
CN206091254U (en) * 2016-08-16 2017-04-12 天力博达科技有限公司 Whole construction scaffold frame of track formula of climbing

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090080613A (en) * 2008-01-22 2009-07-27 최순복 Building outer wall construction equipment system
CN102704664A (en) * 2012-05-30 2012-10-03 深圳市特辰科技股份有限公司 Self-lifting quick transferring platform
CN102747831A (en) * 2012-06-19 2012-10-24 张玉家 Sleeve rail type electric attachment lifting scaffold
CN105715028A (en) * 2015-06-26 2016-06-29 王积政 Successive lifting device and lifting scaffold with same
CN105401714A (en) * 2015-10-27 2016-03-16 重庆东辰建筑机械安装工程有限公司 Attachment type lifting scaffold and lifting method
CN206091254U (en) * 2016-08-16 2017-04-12 天力博达科技有限公司 Whole construction scaffold frame of track formula of climbing

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424543A (en) * 2019-07-24 2019-11-08 中冶天工集团有限公司 A kind of motor driven building module structure and construction method
CN112376885A (en) * 2020-11-17 2021-02-19 浙江铠甲建筑科技有限公司 Track climbing type integral building construction scaffold convenient to disassemble
CN112376885B (en) * 2020-11-17 2022-05-17 浙江铠甲建筑科技有限公司 Track climbing type integral building construction scaffold convenient to disassemble

Similar Documents

Publication Publication Date Title
CN103635643B (en) The construction method of nigh-level synthesis steel bar concrete cylindrical shell
CN201826525U (en) Climbing shuttering system device for buildings
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
CN203531344U (en) Tool type scaffold
CN201158933Y (en) High-rise maintaining scaffold device with extruding structure
CN106400951B (en) A kind of level and vertical structure method for synchronously constructing of super high-rise building
CN103206074B (en) Elevator shaft template construction method, platform and support
CN206233541U (en) A kind of interior top external climbing mould bases operation platform for construction of super highrise building
CN201125524Y (en) Construction site climbing mobile platform
CN203097316U (en) Foldable hydraulic lifting support secure channel for high altitude construction
CN106088564A (en) Track climbing type monolithic architecture construction scaffolding
CN107514145A (en) A kind of removable steel roofing liner installation construction device and method
CN212957538U (en) Roof flower frame beam and outer wall decoration construction movable operation platform
CN203452375U (en) Hydraulic self-jacking oblique creeping formwork
CN205713096U (en) A kind of roofing cantilevered structure form bracing system
CN209568688U (en) A kind of elevating construction platform
CN209145256U (en) The dedicated climbing frame of assembled architecture
CN206091254U (en) Whole construction scaffold frame of track formula of climbing
CN204754150U (en) Dish -type node formula scaffold
CN205976412U (en) Integrated platform of encorbelmenting of boundary beam formwork protection
CN212613606U (en) Adjustable drilling and blasting trolley convenient to move
CN104594631B (en) The construction technology of sliding form apparatus traction operation platform construction granulation tower spraying layer
CN211622512U (en) Modular aerial working safety protection platform
CN204038917U (en) Dismountable external hanging service platform
CN202831591U (en) Special-shaped truss operation platform capable of hoisting to super high space

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161109