CN209145256U - The dedicated climbing frame of assembled architecture - Google Patents

The dedicated climbing frame of assembled architecture Download PDF

Info

Publication number
CN209145256U
CN209145256U CN201821913110.7U CN201821913110U CN209145256U CN 209145256 U CN209145256 U CN 209145256U CN 201821913110 U CN201821913110 U CN 201821913110U CN 209145256 U CN209145256 U CN 209145256U
Authority
CN
China
Prior art keywords
jack
guide rail
climbing frame
construction
turnover panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821913110.7U
Other languages
Chinese (zh)
Inventor
刘志坚
李学峰
吴仍辉
要志东
张庆云
豆笑笑
赵坤
许梦菲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING ZHUOLIANG SHUTTERING Co Ltd
Original Assignee
BEIJING ZHUOLIANG SHUTTERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING ZHUOLIANG SHUTTERING Co Ltd filed Critical BEIJING ZHUOLIANG SHUTTERING Co Ltd
Priority to CN201821913110.7U priority Critical patent/CN209145256U/en
Application granted granted Critical
Publication of CN209145256U publication Critical patent/CN209145256U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses a kind of dedicated climbing frames of assembled architecture, including guide rail and outer builder's jack, the top of outer builder's jack is fixed on guide rail and is suspended on the outside in external structure face, guide rail is mounted on internal floor, it is not provided with hanging seat and hanging point between outer builder's jack and external structure face, which uses fabricated construction.The lower part of outer builder's jack is equipped with turnover panel, opens turnover panel in construction, the turnover panel other side rides on external structure face, and turnover panel shelters from the gap between external structure face and climbing frame, and turnover panel is packed up when climbing.The floor support of installation guide rail is equipped on internal floor, equipped with lifting body, load-bearing bolt or overturn-preventing bolt etc. on floor support.The dedicated climbing frame is equipped with from the power-equipment that climbs.For completing in fabricated construction work progress peripheral maintenance work, completion engineering construction that can be efficient, flexible, easy to operate and safe.It is easy to operate efficient, the construction time is greatlyd save, construction efficiency is improved, has saved construction cost.

Description

The dedicated climbing frame of assembled architecture
Technical field
The utility model relates to a kind of architectural furniture more particularly to a kind of dedicated climbing frames of assembled architecture.
Background technique
In existing building climbing frame, including common console mode scaffold, attached lifting scaffold, overhanging scaffold, Attached wall climbing support, attachment point will be arranged in construction and installation process in most of they on wall face, and fabricated construction Wall be all it is prefabricated, wall carried out before construction alien invasion decoration and internal insulation processing, it is pre- to avoid damage to The outer wall body made, it is desirable to attachment point cannot be set in wall face when using climbing frame.
Attached wall climbing support possesses biggish rigidity and self weight, in bearing capacity requirement of the structure construction procedure to attaching structure Higher, attachment point setting requirements are higher, and it is complicated that frame structure composition is more complicated, and when spelling assembly and disassembly, process is tedious, investment Manpower it is larger.
Common builder's jack itself needs other hanging devices auxiliary to climb without climbing device, when climbing, and it is numerous to hang liter process Trivial, there are biggish security risk, each rigging outs to re-start reinforcing for hoisting process, increases construction week to a certain degree Phase.
When assembled public affairs are rented a house, house, office building contour level or Super High fabricated construction are constructed, although also there is landing The protective frames such as formula scaffold, suspension scaffold are constructed, but because of the limitation of technology and the not specific aim of specialty work, no Can the time saving and energy saving effective construction of prevention work for completing engineering, due to assembled wall find suitable frame body attachment point difficulty compared with Greatly, existing technological deficiency when construction, leads to the disadvantages of construction efficiency is low, flexibility is low, inconvenient.
Utility model content
The purpose of the utility model is to provide a kind of assembled public affairs to rent a house, house, office building contour level or Super High are constructed When, structure is gone along with sb. to guard him when not destroying wall face the dedicated climbing frame of assembled architecture.
The purpose of this utility model is achieved through the following technical solutions:
The dedicated climbing frame of the assembled architecture of the utility model, including guide rail and outer builder's jack, the top of the outer builder's jack are fixed On guide rail and it is suspended on the outside in external structure face, the guide rail is mounted on internal floor, the outer builder's jack and external structure face Between be not provided with hanging seat and hanging point, the dedicated climbing frame use fabricated construction.
Assembled provided by the embodiment of the utility model is built it can be seen from above-mentioned technical solution provided by the utility model Dedicated climbing frame is built, outer builder's jack is mounted on internal floor by guide rail, hanging seat, hanging point is not arranged in outer structural plane, is prevented to building The destruction of building structure wall face and facing of dispatching workers to do on-site repairs;The dedicated climbing frame frame body of assembled architecture uses assembled design method, facilitates dress The combination and separation of dedicated climbing frame body are built with formula.Completion engineering construction that can be efficient, flexible, easy to operate and safe.
Detailed description of the invention
Fig. 1 a and Fig. 1 b are respectively the dedicated climbing frame rail sections of assembled architecture and outer builder's jack in the utility model embodiment Partial component schematic diagram;
Fig. 2 is the combination signal of the guide rail of the dedicated climbing frame of assembled architecture and outer builder's jack body in the utility model embodiment Figure;
Fig. 3 a, Fig. 3 b, which are respectively that the dedicated climbing frame arrangement of assembled architecture is exemplary in the utility model embodiment, to be faced and bows Depending on schematic diagram;
In figure:
Platform board 1;Sunpender 2;Go along with sb. to guard him web plate 3;Hanger rod connecting piece 4;Platform truss 5;C-type steel hanging beam 6;Truss frame for connecting 7;It turns over Plate 8;Guide rail 9;Floor support 10;Lifting body 11;Load-bearing bolt 12;Overturn-preventing bolt 13;Precast floor slab 14;Precast wall body 15。
Specific embodiment
The utility model embodiment will be described in further detail below.Do not make in the utility model embodiment in detail The content of description belongs to the prior art well known to professional and technical personnel in the field.
The dedicated climbing frame of the assembled architecture of the utility model, preferable specific embodiment is:
Including guide rail and outer builder's jack, the top of the outer builder's jack is fixed on guide rail and is suspended on the outside in external structure face, The guide rail is mounted on internal floor, is not provided with hanging seat and hanging point between the outer builder's jack and external structure face, the dedicated climbing frame Using fabricated construction.
The lower part of the outer builder's jack is equipped with turnover panel, and the side of the turnover panel and the outer builder's jack are hinged, opens in construction Turnover panel, the turnover panel other side ride on external structure face, and turnover panel shelters from the gap between external structure face and climbing frame, pack up when climbing Turnover panel.
It is equipped with the floor support of installation guide rail on internal floor, is furnished with lifting body, load-bearing bolt on floor support Or overturn-preventing bolt.
The dedicated climbing frame is equipped with from the power-equipment that climbs.
The outer builder's jack includes platform board, sunpender, goes along with sb. to guard him web plate, hanger rod connecting piece, platform truss, C-type steel hanging beam, connection Truss.
The dedicated climbing frame of the assembled architecture of the utility model, outer builder's jack are mounted on internal floor by guide rail, not outside Hanging seat, hanging point is arranged in structural plane, prevents the destruction to building structure wall face and facing of dispatching workers to do on-site repairs;The assembled architecture is dedicated to climb Frame frame body uses assembled design method, and formula convenient for assembly builds the combination and separation of dedicated climbing frame body, and the assembled architecture is special Possess power-equipment with climbing frame, the self-climbing of frame body, the length of the dedicated climbing frame protection of the assembled architecture can be completed Degree can be adjusted flexibly according to actual needs;
The length of the dedicated climbing frame protection of assembled architecture and the quantitative proportion of guide rail are reasonable, are not influencing safety and are applying The configuration for reducing guide rail under the premise of work as far as possible can complete self-climbing with seldom power-equipment;
The bottom platform of the dedicated climbing frame frame body of assembled architecture and building structure face contact side are equipped with turnover panel, turn over Plate can block the gap between building structure face and climbing frame, prevent top construction falling object from high altitude bring security risk, turnover panel It can be opened at construction with free-open-close, turnover panel is packed up when climbing;
The dedicated climbing frame of assembled architecture is furnished with anti-dumping bolt on the support of floor, and anti-dumping bolt can guarantee climbing frame Guide rail vertical shift in floor support during climbing prevents guide rail from carrying out front and back and topples;
The utility model can be efficient, flexible, easy to operate and safe completion engineering construction.Construction method include with Lower step:
The assembled arthitecutral structure has been reserved before precast floor slab factory and has wanted erection support progress guide rail perpendicular on floor To the notch to climb.
The floor support of the dedicated climbing frame of the assembled architecture floor is fixed on after preceding two layers of the floor slab construction of completion to reserve Notch on, then by guide rail lifting be fixed on floor support, external suspension scaffold is good in installation on ground, using auxiliary lift The lifting of external suspension scaffold is fixed on guide rail builder's jack by equipment, completes the lifting of the dedicated climbing frame of entire assembled architecture;
All turnover panels are opened, carry out next layer of structure by the outer protection and operating platform of the dedicated climbing frame of assembled architecture Construction;
After completing this layer of structure construction, turnover panel is packed up, lifting body is installed on floor support, is carried out by lifting body Frame body climbs, and is ready work after climbing in place, recycles into subsequent work.
The utility model is the dedicated climbing frame of assembled architecture, for completing peripheral maintenance workers in fabricated construction work progress Make, including track-type facilities, outer builder's jack body, install the operating platform peripheral protective on the outer builder's jack body, is driven by track-type facilities outer Builder's jack body climbs, thus the dedicated climbing frame of the assembled architecture not only possess common climbing frame climb ability certainly, while also having The characteristic of operating platform and external protection that other climbing frames are possessed, is omitted that common suspension scaffold is required when climbing to hang liter Equipment, can flexibly, safety completion engineering construction, it is easy to operate efficiently, greatly save the construction time, improve construction effect Rate has saved construction cost.
The dedicated climbing frame of assembled architecture in use, its guide rail is on the floor being fixed on inside building structure, rather than On wall.The guide rail of the dedicated climbing frame of assembled architecture, guide rail are equipped with self-climbing mechanism, and self-climbing mechanism mainly takes hydraulic oil The form of cylinder, more safety and stability of climbing and climbs high-efficient.Climbing device is fixed on floor every time, this allows for climbing Rise the more firm safety of mechanism.
Upper on guide rail that overturn-preventing mechanism is arranged, during jacking, guide rail and frame body can only climb along the vertical direction, no Toppling for front and back can occur, the springboard and web plate of the dedicated climbing frame of assembled architecture take modularization, standardization, lightweight, in this way The number that is used in turn of component can be increased, and it is more safe and efficient, simple so that frame body is spelled assembly and disassembly.
The construction method of the utility model offer dedicated climbing frame of assembled architecture:
1. guide rail is fixedly mounted on floor after double-layer structure construction before completion;
2. lifting is external to overhang frame body, the overhanging device drawn with guide rail is attached fixation.
3. checking the fixing situation of guide rail and external suspension scaffold, turnover panel is opened, next layer of construction is carried out after confirmation is errorless.
4. installing lifting body on guide rail after the completion of construction layer construction, packing up turnover panel, it is laggard to carry out preparation of climbing Row climbs, and enters subsequent work after in place and recycles.
The utility model is using existing from the protecting screen that climbs, and innovative proposition is by climbing frame installation fixed form by exterior wall Face is changed to the fixed form of interior floor, the problem of attachment point cannot be arranged in fabricated construction precast wall body has been solved perfectly, simultaneously Due to combining from the function of protecting screen and common climbing frame of climbing, the dedicated climbing frame of assembled architecture is provided with from climbing mechanism, can be with The increase of engineering structure height oneself is climbed, and is simplified the structure, modularization, lightweight, and integrally-built weight becomes smaller.? Protecting screen and the existing superiority of common climbing frame have been played in use process completely, has set up that simple and convenient, easy to operate, platform is complete Link up and convenient channel, safety economy are provided.
Specific embodiment:
The dedicated climbing frame of assembled architecture used in the utility model is the prior art, and those skilled in the art can basis Construction Object Selection suitably from climbing device such as hydraulic climbing, electronic climb and guide rail, guide rail can have various shapes Suspension scaffold is mounted on guide rail by formula, and the specific installation connection type of guide rail and external overhanging frame body has various forms, this field Technical staff uses different installation connection types according to the different structure of its selected guide rail and external suspension scaffold, passes through top Rise the automatic climbing that mechanism drives guide rail to realize the dedicated climbing frame of assembled architecture.
As shown in Fig. 2, external builder's jack is mounted on guide rail builder's jack, external builder's jack is formed, guide rail is jacked by lifting body Completion is climbed.
As shown in Figure 1 b, for external builder's jack installation connection one embodiment, using connector such as bolt by sunpender 2, Platform board 1, platform truss 5 and C-type steel hanging beam 6 are gone along with sb. to guard him web plate 3 and are connected;
Guide rail 9 is fixed on the support being fixed by bolts on floor with connector such as load-bearing bolt;
Guide rail is connect with external builder's jack, the truss being fixedly connected on outer builder's jack using connector such as bolt on guide rail On;
Load-bearing bolt and each connector are critically important, therefore inspection that will be conscientious during installation pays attention to installation situation;
After completing guide rail assembly and the assembly of external builder's jack, two parts are fixedly connected with connector, complete single assembled Build the assembly of dedicated climbing frame;
Floor support is hung over frame body in building structure using lifting means loaded on after floor with expansion bolt;
It as shown in Figure 3a, is the installation number schematic diagram of the dedicated climbing frame of assembled architecture, those skilled in the art can root It is led according to the dedicated climbing frame guide rail quantity of construction demand setting assembled architecture and platform and the length gone along with sb. to guard him, such as setting 2 3 layers of platform are arranged in rail altogether on 2 guide rails, go along with sb. to guard him length and are arranged 6 meters.Certainly, safeguard that length and springboard length can also bases It actually increases or decreases, equally, when going along with sb. to guard him extended length to certain length, the quantity of guide rail will also be accordingly increased, for section About cost and raising construction efficiency can be with very as long as the quantity that stress meets construction safety requirement guide rail is reduced as far as possible Few power-equipment can complete self-climbing.
After engineering is fully completed, completes to remove work under the cooperation of lifting equipment at the scene, be taken as dismounting mode Certainly idle place on site is disintegrated again if place allows integrally to hang down, can utilized if place is impermissible for Tower crane disintegrates in top:
(1) tower crane steel strand wires are hung in the top C-type steel of outer builder's jack, builder's jack and guide rail is fixedly connected with bolt pine It opens, outer builder's jack is hung down, the fixedly connected part for unclamping each framework on outer builder's jack carries out outer builder's jack and disintegrates;
(2) tower crane steel strand wires are hung on guide rail suspension hook, will be extracted with the fixed load-bearing bolt of floor support, guide rail is hung Under;
(3) steel strand wires are hung on floor support, unclamps the fixing bolt on floor, support is hung down;
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not It is confined to this, anyone skilled in the art can readily occur in the technical scope that the utility model discloses Change or replacement, should be covered within the scope of the utility model.Therefore, the protection scope of the utility model should Subject to the scope of protection of the claims.

Claims (5)

1. a kind of dedicated climbing frame of assembled architecture, which is characterized in that including guide rail and outer builder's jack, the top of the outer builder's jack is fixed On guide rail and it is suspended on the outside in external structure face, the guide rail is mounted on internal floor, the outer builder's jack and external structure face Between be not provided with hanging seat and hanging point, the dedicated climbing frame use fabricated construction.
2. the dedicated climbing frame of assembled architecture according to claim 1, which is characterized in that the lower part of the outer builder's jack is equipped with and turns over Plate, the side of the turnover panel and the outer builder's jack are hinged, open turnover panel in construction, and the turnover panel other side rides on external structure face, Turnover panel shelters from the gap between external structure face and climbing frame, and turnover panel is packed up when climbing.
3. the dedicated climbing frame of assembled architecture according to claim 2, which is characterized in that be equipped with installation on internal floor and lead The floor support of rail is furnished with lifting body, load-bearing bolt or overturn-preventing bolt on floor support.
4. the dedicated climbing frame of assembled architecture according to claim 3, which is characterized in that the dedicated climbing frame is equipped with dynamic from climbing Power equipment.
5. the dedicated climbing frame of assembled architecture according to any one of claims 1 to 4, which is characterized in that the outer builder's jack packet It includes platform board, sunpender, go along with sb. to guard him web plate, hanger rod connecting piece, platform truss, C-type steel hanging beam, truss frame for connecting.
CN201821913110.7U 2018-11-20 2018-11-20 The dedicated climbing frame of assembled architecture Active CN209145256U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821913110.7U CN209145256U (en) 2018-11-20 2018-11-20 The dedicated climbing frame of assembled architecture

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821913110.7U CN209145256U (en) 2018-11-20 2018-11-20 The dedicated climbing frame of assembled architecture

Publications (1)

Publication Number Publication Date
CN209145256U true CN209145256U (en) 2019-07-23

Family

ID=67286606

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821913110.7U Active CN209145256U (en) 2018-11-20 2018-11-20 The dedicated climbing frame of assembled architecture

Country Status (1)

Country Link
CN (1) CN209145256U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236614A (en) * 2020-02-27 2020-06-05 杭州昂创科技有限公司 Construction method of externally-hung self-climbing type triangular support protective scaffold system
CN114541728A (en) * 2022-02-28 2022-05-27 中建三局集团有限公司 Lightweight and modular self-climbing external frame system for assembled structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236614A (en) * 2020-02-27 2020-06-05 杭州昂创科技有限公司 Construction method of externally-hung self-climbing type triangular support protective scaffold system
CN114541728A (en) * 2022-02-28 2022-05-27 中建三局集团有限公司 Lightweight and modular self-climbing external frame system for assembled structure

Similar Documents

Publication Publication Date Title
CN101514586B (en) Hanger rail type electric hanging boat and construction method thereof
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
CN104074349B (en) A kind of new-type protection type attachment type raise scaffold
CN205077845U (en) Building core section of thick bamboo well hydraulic pressure intelligence operation scaffold that climbs
CN205077885U (en) Building core section of thick bamboo hydraulic pressure intelligence protection platform that climbs
CN215291318U (en) Mounting structure of attached lifting scaffold
CN201826516U (en) Novel attached lifting scaffold
CN211524016U (en) Double-working-surface guide frame climbing type working platform and system
CN206233541U (en) A kind of interior top external climbing mould bases operation platform for construction of super highrise building
CN109779244A (en) A kind of self-elevating type elevator hoistway exterior wall creeping formwork operating platform construction
CN209145256U (en) The dedicated climbing frame of assembled architecture
CN109184190A (en) It climbs and carries integrated beam type hydraulic climbing platform and its installation method
CN107476561A (en) A kind of attachment type raise scaffold and its construction
CN206636173U (en) Curved surface high-rise building intellectuality attached lifting scaffold equipment
CN115538792A (en) Residential building machine installation construction method and structure
CN102287045B (en) Square steel tube lifting outside scaffold
CN203924662U (en) A kind of attaching integral lifting scaffold
CN105625732B (en) Superelevation overhanging steel structure truss support free construction method
CN109653484B (en) Roofing superelevation faces external hanging flower basket mounting structure of empty curtain engineering
CN204850469U (en) Commercial mansion system that builds
CN110552495A (en) assembled building combined tool type outer protective frame system and construction method thereof
CN204754150U (en) Dish -type node formula scaffold
CN207003989U (en) External hanging type scaffold is climbed in one kind
CN208039787U (en) The assembled operating platform of side operation is faced in a kind of high-altitude
CN104675093B (en) Dish-type node type scaffold