CN207003989U - External hanging type scaffold is climbed in one kind - Google Patents

External hanging type scaffold is climbed in one kind Download PDF

Info

Publication number
CN207003989U
CN207003989U CN201720984424.5U CN201720984424U CN207003989U CN 207003989 U CN207003989 U CN 207003989U CN 201720984424 U CN201720984424 U CN 201720984424U CN 207003989 U CN207003989 U CN 207003989U
Authority
CN
China
Prior art keywords
scaffold
locking device
internal upright
hanging type
external hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201720984424.5U
Other languages
Chinese (zh)
Inventor
孟凡林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jilin Jianzhu University
Original Assignee
Jilin Jianzhu University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jilin Jianzhu University filed Critical Jilin Jianzhu University
Priority to CN201720984424.5U priority Critical patent/CN207003989U/en
Application granted granted Critical
Publication of CN207003989U publication Critical patent/CN207003989U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ladders (AREA)

Abstract

External hanging type scaffold is climbed in one kind, belongs to building engineering field, the interior external hanging type scaffold of climbing includes internal upright, horizontal outrigger, pylon, upper locking device and lower locking device, and internal upright is arranged on the inner side of external wall;Horizontal outrigger is arranged at the top of internal upright and chooses building outside;The pylon is external hanging type scaffold, pylon be arranged on horizontal outrigger encorbelment end bottom and be fastenedly connected with it;Lower locking device is arranged in the bottom at internal upright through-flooring hole;Upper locking device is arranged in the top at internal upright through-flooring hole;Scaffold of the present utility model is without through walls and vented fire mouth, without in exterior wall box out mouth, not touching the interior outside of external wall, integral-scaffold is quick and easy for installation, and overall lifting is easy to operate, and scaffold builds saving of labor, time saving, material-saving, and scaffold is safe and reliable.

Description

External hanging type scaffold is climbed in one kind
Technical field
The utility model belongs to building engineering field, is related to construction scaffold, is more particularly to climbed in one kind plug-in Formula scaffold.
Background technology
Scaffold is job site for operation and solves vertically and horizontally to transport the various supports set up.Scaffold It is the generic term of architecture field, exterior wall, inside fitting or the higher ground that can not directly construct of floor height is generally used on construction site Side, in order to which workmen up and down go along with sb. to guard him and high-altitude installation component etc. by operation or perimeter security net.
External wall construction scaffolding, national standard《Construction fastener type steel pipe scaffold technical specification of security》 JGJ130-2011, such as console mode scaffold maximum height is used typically to set up four floors using overhanging scaffold for 50 meters Height, this scaffold sets up time-consuming expense material, and construction cost is high and security incident easily occurs.
The Chinese patent literature of Application No. 200610118946.3, disclose a kind of tool-type hanging integral falsework system The construction method of system, the tool-type hanging integral falsework include scaffold unit, it is characterised in that scaffold unit includes pin Hand cradle over sling, suspension bracket under the scaffold being connected with scaffold over sling, is provided with top walkway board, in pin in scaffold over sling Suspension bracket is provided with bottom walkway board under hand cradle, and the bottom of suspension bracket is provided with bottom plate under scaffold.Scaffold unit after assembling passes through spiral shell Bolt is connected with steel platform, and scaffold realizes Synchronous lifting in steel platform lifting process.All scaffold units are to the end of engineering Reused after dismountable finishing, realize the tool of scaffold.This scaffold is suitable only for concrete shear force wall Core Walls Structure and applied Work, and both sides do not have floor, there is the building of floor a large amount of inner sides and not applied in being constructed for reality, and external scaffolding Highly larger, material usage is big, is not particularly suitable for the construction of assembled architecture.
The Chinese patent literature of Application No. 201620406622.9, disclose a kind of special external hanging type operation horizontal of building Platform, including overlap joint hook, outer framework, protection wire netting, overlap joint link, pedal, inner frame, pillar, support end, overlap railing, Building corner, retractable holder, sleeve, helical axis, expansion link, groove and support slot;The overlap joint hook is arranged on outer Frame right centre position;The outer framework is in matrix pattern, is welded by hollow steel pipe;The protection wire netting is placed in outer On the inside of framework;The overlap joint link is welded on centre position on the left of outer framework, with same horizontal line at overlap joint hook;The inside casing Frame is rectangle, perpendicular to outer framework, is welded by hollow steel pipe;The pedal is laid on inner frame;The support end weldering Posts bottom is connected on, in cylindrical shape;The retractable holder, including sleeve, helical axis, expansion link and groove.It is therein Retractable holder, including sleeve, helical axis and expansion link are required to through walls or window, then necessary in the case of no window Through walls, the later stage can not handle wall-through hole, be only suitable for the maintenance construction of building for having enough windows to pass through, and be not suitable for newly-built The construction usage of engineering.
Existing new construction exterior wall scaffold, either overhanging type or external hanging type, are required for through walls or window, are not having Can only be through walls in the case of window, cause hole on wall, post-processing get up it is pretty troublesome, especially for the outer of assembled architecture Wall, even more it is difficult to handle, therefore, it is necessary to a kind of new technical scheme solves this problem, to meet the needs of construction.
Utility model content
Technical problem to be solved in the utility model:For existing scaffold during building construction process use Be required for through walls or window, can only be through walls in the case of no window, cause hole on wall, post-processing get up it is pretty troublesome, especially It is the exterior wall for assembled architecture, is even more difficult to handle, using a kind of scaffold that need not wear external wall and window, solution The certainly constructing operation problem of external wall.
The utility model adopts the following technical scheme that:External hanging type scaffold is climbed in one kind, it is characterized in that:It is vertical including inside Post, horizontal outrigger, pylon, lower locking device and upper locking device, the internal upright are arranged on the inner side of external wall;It is described Horizontal outrigger is arranged at the top of internal upright and chooses building outside;The pylon is external hanging type scaffold, and pylon is arranged on Horizontal outrigger encorbelment end bottom and be fastenedly connected with horizontal outrigger;The lower locking device is arranged in internal upright through-flooring hole Bottom, and be fastenedly connected by fastening bolt and internal upright;The upper locking device is arranged in internal upright through-flooring hole Top, and be fastenedly connected by fastening bolt and internal upright.
By above-mentioned design, the utility model can bring following beneficial effect:The utility model proposes one kind Inside climb external hanging type scaffold, the use process of scaffold is without through walls and vented fire mouth, without in exterior wall box out mouth, not touching building The interior outside of exterior wall, integral-scaffold is quick and easy for installation, and overall lifting is easy to operate, and scaffold builds saving of labor, time saving, material-saving, Scaffold is safe and reliable, using comfortable, improves the working environment of workmen, the construction for the assembled architecture that is particularly suitable for use in.
Brief description of the drawings
The utility model is described in further detail with embodiment for explanation below in conjunction with the accompanying drawings:
Fig. 1 is the utility model first floor and top first floor plate reserved opening schematic diagram.
Fig. 2 is that the utility model integral-scaffold just fills schematic diagram.
Fig. 3 is using one layer of schematic diagram of construction after the utility model integral-scaffold just fills.
Fig. 4 is that the utility model integral-scaffold is lifted up one layer of schematic diagram.
Fig. 5 is locking device and upper locking device scheme of installation under the utility model.
In figure:Locking device, 5- upper locking devices, 6- floors hole under the horizontal outrigger of 1- internal uprights, 2-, 3- pylons, 4- Mouthful.
Embodiment
The technical scheme in the embodiment of the utility model is carried out below in conjunction with the accompanying drawing in the utility model embodiment Clearly and completely describe, as shown in Figures 1 to 5, the utility model proposes including internal upright 1, horizontal outrigger 2, pylon 3, Lower locking device 4 and upper locking device 5, the internal upright 1 are arranged on the inner side of external wall;The horizontal outrigger 2 is arranged on Simultaneously choose building outside in the top of internal upright 1;The pylon 3 is external hanging type scaffold, and it is outstanding that pylon 3 is arranged on horizontal outrigger 2 Choose the bottom at end and be fastenedly connected with horizontal outrigger 2;The lower locking device 4 is arranged under the through-flooring hole 6 of internal upright 1 Portion, and be fastenedly connected by fastening bolt and internal upright 1;The upper locking device 5 is arranged in the through-flooring hole of internal upright 1 6 top, and be fastenedly connected by fastening bolt and internal upright 1.
Embodiment one:It is adapted to the construction of cast-in-place concrete structure
Inside climb the installation method of external hanging type scaffold, this method uses in described and climbs external hanging type scaffold, specifically includes Following steps:
Step 1: climb external hanging type scaffold in preparing
Internal upright 1 is prepared using steel profile or aluminium alloy extrusions, and the section form of internal upright 1 and size are according to technology Standard design, which calculates, to be determined, the height of internal upright 1 determines according to the story height of construction building, at least to pass through two floors Height, and prominent top construction flooring;Horizontal outrigger 2 is prepared using steel profile or aluminium alloy extrusions, the length of horizontal outrigger 2 according to Practice of construction operation it needs to be determined that, the section form and size of horizontal outrigger 2 are calculated according to technical standard design and determined;Pylon 3, using conventional external hanging type scaffold, prepare lower locking device 4, it can be with internal upright 1 by fastening bolt using shaped steel Locking, the outer profile size of lower locking device 4 are greater than the size at floor hole 6;Upper locking device 5 is prepared using shaped steel, led to Crossing fastening bolt can lock with internal upright 1, and the outer profile size of upper locking device 5 is greater than the size at floor hole 6;
Step 2: floor hole 6 is reserved in construction
During first floor floor slab construction, floor hole 6 is being reserved by the sectional dimension of internal upright 1 close to the side of exterior wall;It is first During the last layer floor slab construction of floor plate, floor hole 6 is being reserved by the sectional dimension of internal upright 1 close to the side of exterior wall, And ensure the consistency from top to bottom of floor hole 6 of two floors;
Step 3: climb external hanging type scaffold in installation
After the completion of bottom two layers floor slab construction, start to climb external hanging type scaffold in installation, handling internal upright 1, from upper Lower insertion floor hole 6, after passing through the floor hole 6 of two floors, internally the lower locking device 4 of the bottom installation of column 1, leads to Overwinding tightly fixing bolt tightens together it with internal upright 1;Lift internal upright 1 so that the installation of the bottom of internal upright 1 Lower locking device 4 is close to the bottom of first floor floor;Install first floor floor upper locking device 5, by screw fastening bolt by its Tightened together with internal upright 1;And ensure that inside that can be by upper locking device 5 and lower locking device 4 is stood herein Post 1 is in each to constrained state;The upper locking device 5 of the last layer floor of first floor floor is installed, it is fastened with internal upright 1 Together, and ensure by the lower locking device 4 of upper locking device 5 and first floor floor can be herein internal upright 1 at In each to constrained state;According to being actually needed for engineering construction, installed along external wall inner side through floor in even number Portion's column 1, the one group of pylon 3 of corresponding installation of each two internal upright 1, each group of pylon 3 are connected to by two horizontal outriggers 2 The top of internal upright 1;This step is repeated, until climbing external hanging type scaffold installation in whole, you can for applying for this layer Work operates;
Step 4: climb external hanging type scaffold in lifting
After the completion of the construction of this layer, external hanging type scaffold is climbed in segmentation or overall lifting, for one layer of the construction in top;Using Conventional method, which hangs or withstood, climbs external hanging type scaffold in the entirety including internal upright 1, open the lower He of locking device 4 Upper locking device 5, sling or jack up and external hanging type scaffold is climbed in entirety to the construction station on one layer of top, according to the side of step 3 Formula installs lower locking device 4 and upper locking device 5, and the construction behaviour that external hanging type scaffold can be used to one layer of top is climbed in entirety Make;This step is repeated, until top completes the interior of Zheng Zhuan buildings and climbs external hanging type scaffold construction usage.
Embodiment two:It is adapted to the construction of prefabricated concrete structure
Inside climb the installation method of external hanging type scaffold, this method uses in described and climbs external hanging type scaffold, specifically includes Following steps:
Step 1 is to step 3, with embodiment one;
Step 4: climb external hanging type scaffold in lifting
After the completion of the construction of this layer, horizontal outrigger 2 is hung with tower crane, the connection opened between internal upright 1 and horizontal outrigger 2 makes two Person separates, and horizontal outrigger 2 and pylon 3 are hoisted into top construction floor temporarily puts;At this moment prefabricated concrete structure is first installed Exterior wall, after the external wall structure installation of prefabricated concrete structure, internal upright 1 is hung with tower crane, open lower locking device 4 With upper locking device 5, internal upright 1 is sling to the construction station on one layer of top, lower locking dress is installed in the way of step 3 Put 4 and upper locking device 5;The horizontal outrigger 2 of handling and pylon 3, make horizontal outrigger 2 and internal upright 1 be reliably connected again;In entirety Climb the constructing operation that external hanging type scaffold can be used to one layer of top;This step is repeated, until top completes the interior of Zheng Zhuan buildings Climb external hanging type scaffold construction usage.
External hanging type scaffold installation is climbed in entirety and removes convenient and swift, it is as follows that external hanging type scaffold process is climbed in dismounting:
Inside climb after the completion of the use function of external hanging type scaffold, you can remove in entirety and climb external hanging type scaffold, using normal The method of rule hangs horizontal outrigger 2, opens the connection of horizontal outrigger 2 and internal upright 1, and horizontal outrigger 2 and pylon 3 are hoisted into ground Piled up after further disassembling arrangement;Internal upright 1 is hung using the method for routine, opens lower locking device 4 and upper locking device 5, internal upright 1 is hoisted to ground, together with connecting material, locking device, piled up after collated, until interior climb external hanging type Scaffold is removed and finished.
Climbed in dismounting after the completion of external hanging type scaffold block reserved floor hole 6 process it is as follows:
After internal upright 1 is boosted leaves floor hole 6, when floor hole 6 need not reuse, using concrete by building Plate hole 6 blocks closely knit.
Preferable two embodiments of the utility model are the foregoing is only, are not limited to the utility model, it is right For those skilled in the art, the utility model can have various modifications and variations.It is all it is of the present utility model spirit and Within principle, any modification, equivalent substitution and improvements made etc., it should be included within the scope of protection of the utility model.

Claims (1)

1. external hanging type scaffold is climbed in one kind, it is characterized in that:Including internal upright (1), horizontal outrigger (2), pylon (3), lower lock Tight device (4) and upper locking device (5), the internal upright (1) are arranged on the inner side of external wall;The horizontal outrigger (2) sets Put at the top of column (1) internally and choose building outside;The pylon (3) is external hanging type scaffold, and pylon (3) is arranged on Horizontal outrigger (2) encorbelment end bottom and be fastenedly connected with horizontal outrigger (2);The lower locking device (4) is arranged in internal upright (1) The bottom at through-flooring hole (6), and be fastenedly connected by fastening bolt and internal upright (1);Upper locking device (5) arrangement The top at column (1) through-flooring hole (6) internally, and be fastenedly connected by fastening bolt and internal upright (1).
CN201720984424.5U 2017-08-08 2017-08-08 External hanging type scaffold is climbed in one kind Withdrawn - After Issue CN207003989U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720984424.5U CN207003989U (en) 2017-08-08 2017-08-08 External hanging type scaffold is climbed in one kind

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720984424.5U CN207003989U (en) 2017-08-08 2017-08-08 External hanging type scaffold is climbed in one kind

Publications (1)

Publication Number Publication Date
CN207003989U true CN207003989U (en) 2018-02-13

Family

ID=61459242

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720984424.5U Withdrawn - After Issue CN207003989U (en) 2017-08-08 2017-08-08 External hanging type scaffold is climbed in one kind

Country Status (1)

Country Link
CN (1) CN207003989U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107268972A (en) * 2017-08-08 2017-10-20 吉林建筑大学 External hanging type scaffold and its installation method are climbed in one kind

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107268972A (en) * 2017-08-08 2017-10-20 吉林建筑大学 External hanging type scaffold and its installation method are climbed in one kind

Similar Documents

Publication Publication Date Title
CN205077845U (en) Hydraulic intelligent climbing operation scaffold for core barrel well of building
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
CN103758341B (en) Steel column drum rack support type hydraulic lifting overall steel platform cross truss layer construction method
CN102839812B (en) Intelligent construction platform for construction of super high-rise building
CN106400951B (en) A kind of level and vertical structure method for synchronously constructing of super high-rise building
WO2011002120A1 (en) Composite cage for construction
CN103741947B (en) Tube-frame-supporting type hydraulic climbing integral steel platform formwork truss layer construction method
CN209482679U (en) Tub brace type integral steel platform suitable for sloping core construction
CN109457931A (en) Tub brace type integral steel platform and its construction method suitable for sloping core construction
CN206233541U (en) A kind of interior top external climbing mould bases operation platform for construction of super highrise building
CN108331336A (en) The integrated lifting steel plateform system and its construction method of floor synchronous construction
CN208056596U (en) A kind of Novel engineering exterior wall scaffold
CN107100361B (en) Inner support aluminum dipping form device and its installation method are climbed outside a kind of
CN112112418B (en) Construction method of high-rise building aluminum formwork climbing frame combined system
CA3108857A1 (en) Method of erecting a multi-storey structure with a safety barrier facade
CN204781927U (en) Elevartor shaft formwork and elevartor shaft concrete placement operation platform
CN102733608B (en) Construction method for spray head layer of granulation tower
CN209145256U (en) The dedicated climbing frame of assembled architecture
CN115788012A (en) Hydraulic climbing formwork integral climbing and sliding device and method suitable for inclined wall construction
JP3179045B2 (en) Wall construction method with work scaffold
CN207003989U (en) External hanging type scaffold is climbed in one kind
CN107268972A (en) External hanging type scaffold and its installation method are climbed in one kind
CN106193586A (en) Elevator Telescopic folding Integral lifting core
CN214576004U (en) Staircase regularization platform of going up people
CN205134921U (en) Building outer wall concrete constructional column hangs construction platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned