CN115538792A - Residential building machine installation construction method and structure - Google Patents

Residential building machine installation construction method and structure Download PDF

Info

Publication number
CN115538792A
CN115538792A CN202211210425.6A CN202211210425A CN115538792A CN 115538792 A CN115538792 A CN 115538792A CN 202211210425 A CN202211210425 A CN 202211210425A CN 115538792 A CN115538792 A CN 115538792A
Authority
CN
China
Prior art keywords
residential building
building machine
hanging
construction
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211210425.6A
Other languages
Chinese (zh)
Inventor
王军
廖继
胡智明
李劲
刘恒
张步月
王嗣宗
杨涛
康克巍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Co Ltd of China Construction Third Engineering Division
Original Assignee
Third Construction Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Co Ltd of China Construction Third Engineering Division filed Critical Third Construction Co Ltd of China Construction Third Engineering Division
Priority to CN202211210425.6A priority Critical patent/CN115538792A/en
Publication of CN115538792A publication Critical patent/CN115538792A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/167Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3577Extraordinary methods of construction, e.g. lift-slab, jack-block prefabricating a building and moving it as a whole to the erection site
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3588Extraordinary methods of construction, e.g. lift-slab, jack-block using special lifting or handling devices, e.g. gantries, overhead conveying rails

Abstract

The invention relates to the technical field of installation and construction of residential building machines, in particular to an installation and construction method and a structure of a residential building machine, wherein a construction structure comprises the residential building machine and an external protection hanging frame, the external protection hanging frame comprises a hanging rod, a cross beam is installed on the hanging rod, a walkway plate is installed on the cross beam, one end of the hanging rod is connected with a wall body through a wall connecting piece, and the structures are a Bailey truss, a hanging hook, an electric hoist, an upper hanging rod, a middle hanging rod and a lower hanging rod which are sequentially connected from top to bottom; the lifting device of the residential building machine is used for lifting the external protective hanging frame in sections. The residential building machine hanging frame is adopted to replace a floor type steel pipe scaffold, so that the construction efficiency of the residential building machine can be improved, the construction period is shortened, the safety risk of the construction process is reduced, and the construction economic cost is saved. The construction method is simple to operate, high in reliability and strong in realizability, and is beneficial to further improving the adaptability of the residential building machine in residential engineering and improving the industrial competitiveness of the residential building machine in the field of residential construction equipment.

Description

Residential building machine installation construction method and structure
Technical Field
The invention relates to the technical field of installation and construction of residential building machines, in particular to an installation and construction method and structure of a residential building machine.
Background
The hanging frame system of the residential building machine mainly comprises a hanging head, a hanging rod, a connecting clamp plate, a walkway plate, a cross beam and the like. Different from the climbing frame, the external protective frame of the residential building machine adopts a hanging design, and the whole frame body is hung on the lower chord of the bailey truss through a hanging head. The traditional hanger rod is designed to be 50 multiplied by 4, and the walkway plate is designed to be divided into two forms of a prismatic steel plate net and a hyacinth bean pattern steel plate.
Traditional stores pylon system is when the design, in order to satisfy major structure construction and lean construction requirement, and whole support body overall height is 17.23m, sets up 8 layers altogether and walks the guidance tape, and each layer stores pylon (from last down) first floor 2m, second floor 2.23m, third layer 2m, fourth layer 2m, fifth layer 3m, sixth layer 2m, seventh layer 2m, eighth layer 2m. The hanger rod is formed by butting 3 square tubes.
The installation sequence is as follows: hanging head → hanging rod → crossbeam → walkway plate → outer protective net piece. The external protection hanging frame needs to be installed after the Bailey truss of the residential building machine is installed, and the residential building machine is usually installed after the second-layer structure of the main structure is constructed. Therefore, when the main structure construction of one floor and two floors is carried out, the outer protection floor type steel pipe scaffold needs to be erected firstly to carry out the main structure construction, and when the house building machine begins to install the outer protection hanging frame, the floor type scaffold is dismantled. The construction method has the following problems:
1) The hanging frame is designed in a hanging mode, a winch or a pulley is needed to be manually adopted to lift the hanging rod upwards from the ground during installation, then constructors operate in the bailey truss to carry out combined installation of the hanging rod and the hanging head, and the construction process is complicated and the risk coefficient is high;
2) When the hanging frame is installed, a floor type scaffold needs to be dismantled in advance, and at the moment, protective facilities are not arranged on the periphery of a floor, the edge of a balcony and the like, so that certain potential safety hazards exist;
3) The hanger rod is installed manually by adopting a pulley manual lifting mode, the number of required constructors is large, 2-3 persons are required in the truss under normal conditions, 5-7 persons are required for lifting the ground, the construction cost is high, and the installation time is long;
4) When the stores pylon was installed, the console mode scaffold frame need be demolishd, and the stores pylon installation time is longer, and this process major structure can't be under construction, influences major structure construction period, causes later stage main part labour claim condition easily.
To sum up, the outer protection stores pylon of traditional suspension type installation house building machine, the stores pylon easily conflicts with console mode steel pipe scaffold, influences jib installation construction, and the high altitude construction volume is big, and the construction is inconvenient, and the safety risk is big.
Disclosure of Invention
The invention provides a residential building machine installation construction method and a residential building machine installation construction structure, and solves the technical problems that the traditional hanging type residential building machine installation external protection hanging frame is easy to collide with a floor type steel pipe scaffold, the hanging frame influences the hanging rod installation construction, the high-altitude operation amount is large, the construction is inconvenient, and the safety risk is large.
The invention provides a residential building machine installation construction method for solving the technical problems, which comprises the following steps:
s1, after the top plate construction is finished, positioning and paying off, marking the position of each suspender, and setting suspender installation positions according to the projection position of a suspender head;
s2, placing a middle suspension rod according to the paying-off positioning position, installing a walkway cross beam, and installing a walkway plate after the cross beam is installed;
s3, reserving sleeve holes at the positions of the shear walls and/or the balconies at the segmented positions for installing wall connecting pieces;
s4, after the construction of the first-layer structure is completed, installing a suspender, a corresponding cross beam and a corresponding walkway plate, and then constructing a second-layer main structure;
s5, after the construction of the main structure of the second floor is finished, the installation work of the residential building machine is started;
s6, after the installation of the Bailey truss and the hanging head of the residential building machine is finished, the outer protective hanging frame is lifted up in sections by utilizing a lifting device, and then the upper hanging rod is connected with the hanging head;
s7, constructing a three-layer structure, and lifting the residential building machine for the first time after the construction is finished;
s8, mounting a lower suspender;
s9, lifting the residential building machine for the second time, and mounting the cross beam, the walkway plate and the outer protection net piece of the lower suspender after the lifting is finished, namely mounting all the outer protection hangers; and then carrying out the normal construction stage of the main structure.
Preferably, the S2 specifically includes: and installing a standard walkway plate and corresponding suspenders, continuously installing 3 spans to ensure the stability of the external protection hanging rack, and installing the walkway plate and the external protection net piece layer by layer from bottom to top.
Preferably, the installation work of the residential building machine in S5 specifically includes: the device comprises an installation supporting system, a power and control system, a steel platform system, a template system and a safety protection system, wherein a hanging head connected with a hanging rod of an external protection hanging rack is installed on the lower chord of the Bailey truss.
Preferably, the lifting device comprises an electric hoist and a lifting hook, the upper end of the electric hoist is hung under the bailey truss through the lifting hook, and the lower end of the electric hoist is tied at the joint position of an upper lifting rod and a cross beam on the inner side and the outer side of the hanger.
Preferably, S6 specifically includes: the mode that the segmentation upwards promoted is taken to the outer protection stores pylon, and 4 electric block are installed to each section stores pylon, are located four angles of stores pylon respectively, and the electric block lower extreme all is connected with the handing-over position of jib and crossbeam, needs synchronous operation during the promotion, guarantees the stability of support body.
Preferably, the length of the upper suspender is 5.5m, the length of the middle suspender is 6m, and the length of the lower suspender is 6m.
Preferably, the upper end of the lower suspender is hung at the lower end of the middle suspender, the upper end of the middle suspender is hung at the lower end of the upper suspender, and the upper end of the upper suspender is hung with the hanging head.
Preferably, the middle suspension rod and the upper suspension rod are tied with the shear wall through the wall connecting piece, and the lower suspension rod is free of the wall connecting piece.
The invention also provides a residential building machine installation construction structure, which comprises a residential building machine and an external protection hanging frame, wherein the external protection hanging frame comprises a hanging rod, a cross beam is arranged on the hanging rod, a walkway plate is arranged on the cross beam, one end of the hanging rod is connected with a wall body through a wall connecting piece, and the hanging rod comprises an upper hanging rod, a middle hanging rod and a lower hanging rod which are sequentially connected from top to bottom;
and the lifting device of the residential building machine is used for lifting the outer protective hanging frame in sections.
Preferably, each hanger rod is provided with a cross beam, a walkway plate and an outer protective net sheet.
Has the advantages that: the invention provides a residential building machine installation construction method and a residential building machine installation construction structure, wherein the construction structure comprises a residential building machine and an external protection hanging frame, the external protection hanging frame comprises a hanging rod, a cross beam is installed on the hanging rod, a walkway plate is installed on the cross beam, one end of the hanging rod is connected with a wall body through a wall connecting piece, and the hanging rod comprises an upper hanging rod, a middle hanging rod and a lower hanging rod which are sequentially connected from top to bottom; the lifting device of the residential building machine is used for lifting the external protective hanging frame in sections. The residential building machine hanging frame is adopted to replace a floor type steel pipe scaffold, so that the construction efficiency of the residential building machine can be improved, the construction period is shortened, the safety risk of the construction process is reduced, and the construction economic cost is saved. The construction method is simple to operate, high in reliability and strong in realizability, and is beneficial to further improving the adaptability of the residential building machine in residential engineering and improving the industrial competitiveness of the residential building machine in the field of residential construction equipment.
The foregoing description is only an overview of the technical solutions of the present invention, and in order to make the technical solutions of the present invention more clearly understood and to implement them in accordance with the contents of the description, the following detailed description is given with reference to the preferred embodiments of the present invention and the accompanying drawings. The detailed description of the present invention is given in detail by the following examples and the accompanying drawings.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this application, illustrate embodiment(s) of the invention and together with the description serve to explain the invention without limiting the invention. In the drawings:
FIG. 1 is a flow chart of a method for installing and constructing a residential building machine according to the present invention;
FIG. 2 is a schematic view of a middle boom installation provided by the present invention;
FIG. 3 is a construction drawing of the upper hanger bar installation and the two-layer structure provided by the present invention;
fig. 4 is an installation diagram of the main body structure of the building construction machine provided by the invention;
FIG. 5 is a schematic view of the first lifting of the outer protective hanger according to the present invention;
FIG. 6 is a schematic view of a hanger according to the present invention;
fig. 7 is a schematic view of a first jacking of the building construction machine provided by the invention;
FIG. 8 is a schematic view of a lower boom installation provided by the present invention;
FIG. 9 is a schematic view of a second lift of the residential building machine according to the present invention;
FIG. 10 is a schematic view of a cross beam mounting of the lower boom provided by the present invention;
description of reference numerals:
the building frame comprises a middle suspender 1, a cross beam 2, a wall connecting piece 3, a building machine 4, an upper suspender 5, an electric hoist 6, a lower suspender 7, a bailey truss 8 and a hanging head 9.
Detailed Description
The principles and features of this invention are described below in conjunction with the following drawings, which are set forth by way of illustration only and are not intended to limit the scope of the invention. The invention is described in more detail in the following paragraphs by way of example with reference to the accompanying drawings. Advantages and features of the present invention will become apparent from the following description and from the claims. It is to be noted that the drawings are in a very simplified form and are not to precise scale, which is provided for the purpose of facilitating and clearly illustrating embodiments of the present invention.
It will be understood that when an element is referred to as being "secured to" another element, it can be directly on the other element or intervening elements may also be present. When a component is referred to as being "connected" to another component, it can be directly connected to the other component or intervening components may also be present. When a component is referred to as being "disposed on" another component, it can be directly on the other component or intervening components may also be present. The terms "vertical," "horizontal," "left," "right," and the like as used herein are for illustrative purposes only.
Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs. The terminology used in the description of the invention herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.
As shown in fig. 1 to 10, the present invention provides a residential building machine installation construction method, including the steps of:
s1, after the top plate construction is finished, positioning and paying off, marking the position of each suspender, and setting suspender installation positions according to the projection position of a hanging head 9;
s2, placing the middle suspension rod 1 according to the paying-off positioning position, installing a walkway crossbeam 2, and installing a walkway plate after the crossbeam 2 is installed;
s3, reserving sleeve holes at the positions of the shear walls and/or the balconies at the segmented positions for installing the wall connecting pieces 3;
s4, after the construction of the first-layer structure is completed, installing the hanger rods 5, the corresponding cross beams and the corresponding walkway plates, and then constructing a second-layer main body structure;
s5, after the construction of the second-layer main structure is finished, the installation work of the residential building machine 4 is started;
s6, after the installation of the Bailey truss and the hanging head of the residential building machine is finished, the outer protective hanging frame is lifted up in sections by utilizing a lifting device, and then the upper hanging rod is connected with the hanging head;
s7, constructing a three-layer structure, and lifting the residential building machine 4 for the first time after the construction is finished;
s8, mounting a lower suspender 7;
s9, lifting the building machine 4 for the second time, and completing the installation of the cross beam 2, the walkway plate and the outer protection net of the lower suspender 7 after lifting, namely completing the installation of all the outer protection hangers; then the normal construction stage of the main structure is carried out.
The scheme changes the installation mode of the prior external protection hanging rack (hanging rack for short), and the hanging rack is used for replacing a floor type scaffold, namely, the external protection hanging rack of the residential building machine 4 is used as a floor type external protection operation rack during the construction of a main body structure. The outer frame of the residential building machine 4 mainly comprises a suspender, a beam 2 and a walkway plate; the suspender comprises an upper suspender, a middle suspender and a lower suspender which are combined and connected, wherein the length of the upper suspender 5 is 5.5m, the middle suspender is 6m, and the lower suspender is 6m. The concrete construction steps are as follows:
1) Positioning and paying off: according to the design drawing of the outer frame, after the construction of the top plate is completed, positioning and paying off are carried out, the mounting point position of the hanging rod is arranged according to the projection position of the hanging head 9, and when on-site paying off is required, the position of each hanging rod is marked.
2) Mounting a hanging rack: only installing middle suspender 1 during the first installation, wherein the length of the suspender is 6m, placing the middle suspender 1 according to the position of paying off and positioning, installing a walkway beam 2 at the same time, and installing a walkway plate after the installation of the beam 2 is finished. The installation process requires that a standard walkway plate and a corresponding suspender are installed first, and requires that 3 spans are continuously installed to ensure the stability of the frame body. And the walkway plates and the outer side protection net sheets are installed layer by layer from bottom to top.
3) The wall connecting piece 3 is provided with: the wall connecting piece 3 is arranged by considering two-step two-span arrangement and simultaneously considering temporary tying measures during later-stage hanging rack subsection lifting, and sleeve holes are reserved in positions such as a shear wall and a balcony of the position needing to be sectioned for installing the wall connecting piece 3.
4) The upper suspender 5 is installed: after the construction of the first-layer structure is completed, the upper suspender 5 is installed, and then the construction of the second-layer structure is carried out.
5) The residential building machine 4 is installed: after the construction of the second-floor main structure is completed, the installation work of the residential building machine 4 is started, including the installation of a support system, a power and control system, a steel platform system, a template system, a safety protection system and the like. And a lifting device is arranged at the lower end of the bailey truss 8.
6) Lifting the hanging rack: after the installation of the residential building machine 4 Bailey frame is completed, the external protection hanging frame is lifted by the lifting device. Specifically, hoisting device mainly is electric block 6, and this 6 upper ends of electric block hang under bailey truss through the lifting hook, and the position department is handed over with crossbeam 2 to the last jib 5 of 6 lower extreme drawknot of electric block in the stores pylon inside and outside, promotes the stores pylon segmentation upwards under the drive of electric block 6. In the installation process, the frame body of the external protection hanging frame cannot be lifted upwards synchronously, and only after one section is installed, the next section is lifted and installed. However, each section of the frame body is lifted by 4 electric hoists 6, and the electric hoists 6 need to be lifted synchronously to ensure the stability of the frame body. After the first section, namely the section where the upper suspender 5 is located, is lifted, the upper suspender 5 is connected with the corresponding suspension heads 9, the suspension heads 9 are all arranged at the lower chord of the bailey truss 8 and are connected with the upper suspender 5, and the function of the suspension heads is to suspend the upper suspender 5 below the bailey truss 8.
The mode that the outer protection stores pylon adopted the segmentation to promote upwards, and 4 electric block 6 are installed to every section outer protection stores pylon, are located four angles of outer protection stores pylon respectively. Namely, the upper ends of the upper booms 5 and the lower booms are provided with electric hoists 6. The lower end of the electric hoist 6 is connected with the handing-over positions of the suspenders and the cross beam, and the synchronous operation is needed during lifting, so that the stability of the frame body is ensured.
7) And (3) constructing a three-layer structure: and (4) carrying out three-layer structure construction after the hanging frame is lifted, and carrying out first lifting on the residential building machine 4 after the construction is finished.
8) The lower suspender 7 is installed: after the house building machine 4 is lifted for the first time, the hanger lower suspender 7 is installed, only the suspender is installed in the installation, and the beam 2 and the walkway plate are not installed. The upper end of the lower suspender 7 is hung at the lower end of the middle suspender 1, the upper end of the middle suspender 1 is hung at the lower end of the upper suspender 5, and the upper end of the upper suspender 5 is hung with the hanging head 9. The hanger rods include a hanger head 9, an upper hanger rod 5, a middle hanger rod 1 and a lower hanger rod 7 which are sequentially hung from top to bottom.
9) Jacking the building machine: after the construction of each layer of structure is completed, the house building machine 4 is lifted for the second time, the installation of the lower suspender 7, the beam 2 and the walkway plate is completed after the lifting, the integral installation of the house building machine 4 is completed after the installation, and the normal construction stage is entered.
The embodiment of the invention also provides a residential building machine 4 installation construction structure, which comprises a residential building machine 4 and a suspender, wherein the suspender is provided with the beam 2, the beam 2 is provided with the walkway plate, one end of the beam 2 is connected with a wall body through the wall connecting piece 3, and the suspender comprises an upper suspender 5, a middle suspender 1 and a lower suspender 7 which are sequentially hung from top to bottom.
Wherein, each suspender is provided with a beam, a walkway plate and an outer protective net sheet. The crossbeam plays the transverse connection effect, and the guidance tape is used for the staff to walk, and outer protection net piece is used for the protection safety to prevent that the object from falling to the outside.
Has the advantages that:
1) The external protective hanging frame of the residential building is adopted to replace a floor type steel pipe scaffold, so that the building and dismantling processes of the steel pipe scaffold can be reduced, and the steel pipe lease and construction cost can be reduced;
2) After the external frame of the residential building machine is used as a ground falling frame, the electric hoist is only needed to be utilized to integrally lift the hanging frame upwards in a segmented manner after the Bailey frame truss of the residential building machine is installed in the later period, so that the construction period of the residential building machine can be greatly shortened;
3) The outer protection stores pylon of house building machine adopts hanging design down, adopts the stores pylon to replace the outrigger after, can avoid later stage from the top down to install the stores pylon, reduces later stage high altitude construction volume, reduces work progress safety risk.
The foregoing is merely a preferred embodiment of the invention and is not intended to limit the invention in any manner; the present invention may be readily implemented by those of ordinary skill in the art as illustrated in the accompanying drawings and described above; however, those skilled in the art should appreciate that they can readily use the disclosed conception and specific embodiments as a basis for designing or modifying other structures for carrying out the same purposes of the present invention without departing from the scope of the invention as defined by the appended claims; meanwhile, any equivalent changes, modifications and evolutions made to the above embodiments according to the substantial technology of the present invention are still within the protection scope of the technical solution of the present invention.

Claims (10)

1. A residential building machine installation and construction method is characterized by comprising the following steps:
s1, after the top plate construction is finished, positioning and paying off, marking the position of each suspender, and setting suspender installation positions according to the projection position of a suspender head;
s2, placing a middle suspension rod according to the paying-off positioning position, installing a walkway cross beam, and installing a walkway plate after the cross beam is installed;
s3, reserving sleeve holes at the positions of the shear walls and/or the balconies at the segmented positions for installing wall connecting pieces;
s4, after the construction of the first-layer structure is completed, installing the hanger rods, the corresponding cross beams and the corresponding walkway plates, and then constructing a second-layer main body structure;
s5, after the construction of the main structure of the second floor is finished, the installation work of the residential building machine is started;
s6, after the installation of the Bailey truss and the hanging head of the residential building machine is finished, the outer protective hanging frame is lifted up in sections by utilizing a lifting device, and then the upper hanging rod is connected with the hanging head;
s7, constructing a three-layer structure, and lifting the residential building machine for the first time after the construction is finished;
s8, mounting a lower suspender;
s9, lifting the residential building machine for the second time, and mounting the cross beam, the walkway plate and the outer protection net piece of the lower suspender after the lifting is finished, namely mounting all the outer protection hangers; then the normal construction stage of the main structure is carried out.
2. The residential building machine installation and construction method according to claim 1, wherein said S2 specifically comprises: and installing a standard walkway plate and corresponding suspenders, continuously installing 3 spans to ensure the stability of the external protection hanging rack, and installing the walkway plate and the external protection net piece layer by layer from bottom to top.
3. The residential building machine installation and construction method according to claim 1, wherein the installation work of the residential building machine in S5 specifically includes: the device comprises an installation supporting system, a power and control system, a steel platform system, a template system and a safety protection system, wherein a hanging head connected with a hanging rod of an external protection hanging rack is installed on the lower chord of the Bailey truss.
4. The residential building machine installation and construction method according to claim 1, wherein the lifting device comprises an electric hoist and a lifting hook, the upper end of the electric hoist is hung under the bailey truss through the lifting hook, and the lower end of the electric hoist is tied at the joint position of the upper hanger rod and the cross beam inside and outside the hanger.
5. The residential building machine installation and construction method according to claim 4, wherein said S6 specifically comprises: the mode that the segmentation upwards promoted is taken to the outer protection stores pylon, and 4 electric block are installed to each section stores pylon, are located four angles of stores pylon respectively, and the electric block lower extreme all is connected with the handing-over position of jib and crossbeam, needs synchronous operation during the promotion, guarantees the stability of support body.
6. The residential building machine installation method of claim 1, wherein said upper boom is 5.5m long, said middle boom is 6m long, and said lower boom is 6m long.
7. The residential building machine installation and construction method according to claim 1, wherein an upper end of said lower boom is hung on a lower end of said middle boom, an upper end of said middle boom is hung on a lower end of said upper boom, an upper end of said upper boom is hung on a lower end of a hanging head, and an upper end of said hanging head is connected to a lower chord of a bailey truss.
8. The residential building machine installation and construction method according to claim 1, wherein the middle and upper booms are each tied to the shear wall by a wall connecting member, and the wall connecting member is absent at the lower boom.
9. The mounting construction structure of the residential building machine comprises the residential building machine and an outer protective hanging frame, and is characterized in that the outer protective hanging frame comprises a hanging head and a hanging rod, wherein a cross beam is arranged on the hanging rod, a walkway plate is arranged on the cross beam, one end of the hanging rod is connected with a wall body through a wall connecting piece, the hanging rod comprises an upper hanging rod, a middle hanging rod and a lower hanging rod which are sequentially connected from top to bottom, and the upper hanging rod is connected with the lower chord of a Bailey truss through the hanging head;
the lifting device of the residential building machine is used for lifting the external protective hanging frame in sections.
10. The residential building machine installation construction structure of claim 9, wherein each said boom is provided with a cross member, a walkway plate and an outer protective mesh.
CN202211210425.6A 2022-09-30 2022-09-30 Residential building machine installation construction method and structure Pending CN115538792A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211210425.6A CN115538792A (en) 2022-09-30 2022-09-30 Residential building machine installation construction method and structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211210425.6A CN115538792A (en) 2022-09-30 2022-09-30 Residential building machine installation construction method and structure

Publications (1)

Publication Number Publication Date
CN115538792A true CN115538792A (en) 2022-12-30

Family

ID=84731963

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211210425.6A Pending CN115538792A (en) 2022-09-30 2022-09-30 Residential building machine installation construction method and structure

Country Status (1)

Country Link
CN (1) CN115538792A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116181041A (en) * 2023-04-25 2023-05-30 中铁建工集团有限公司 Building machine of multilayer quick construction
CN116335398A (en) * 2023-04-25 2023-06-27 中铁建工集团有限公司 Multilayer rapid construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116181041A (en) * 2023-04-25 2023-05-30 中铁建工集团有限公司 Building machine of multilayer quick construction
CN116335398A (en) * 2023-04-25 2023-06-27 中铁建工集团有限公司 Multilayer rapid construction method
CN116181041B (en) * 2023-04-25 2023-08-15 中铁建工集团有限公司 Building machine of multilayer quick construction
CN116335398B (en) * 2023-04-25 2023-11-03 中铁建工集团有限公司 Multilayer rapid construction method

Similar Documents

Publication Publication Date Title
CN115538792A (en) Residential building machine installation construction method and structure
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
CN106400951B (en) A kind of level and vertical structure method for synchronously constructing of super high-rise building
CN103603504B (en) The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction
CN106241618A (en) A kind of curtain wall profiles boom hoisting
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN114197634B (en) Construction method of high-rise conjoined large steel structure installation monitoring system
CN105442839A (en) Erecting method of cantilever structure formwork bent
CN103883128B (en) Multi-tier large-span steel structure mounting method
CN204781927U (en) Elevartor shaft formwork and elevartor shaft concrete placement operation platform
CN205502551U (en) Platform is suspended in midair in high altitude large -span vestibule construction
CN105839907A (en) Suspension type steel platform scaffold foundation and method for mounting same
CN113062584A (en) Multipoint elevator shaft construction lifting platform and construction method
CN112267692A (en) Assembly type building component hoisting comprehensive equipment and construction method thereof
CN216616216U (en) Large-scale high-rise steel truss disjunctor structure
CN216787874U (en) Large-scale ring type truss hoisting structure in large-span high altitude
CN113445723A (en) Construction platform for mounting overhanging structure curtain wall and mounting method
CN215107152U (en) High-altitude lateral angle control overhanging operation platform
CN107035037A (en) High building top layer curtain wall frame and its installation method
CN109972845B (en) Method for mounting steel roof truss
CN207003989U (en) External hanging type scaffold is climbed in one kind
CN206397107U (en) Armored concrete construction of lift well operating platform bracket
CN116181041B (en) Building machine of multilayer quick construction
CN114197633B (en) Construction method of large-span high-altitude annular truss lifting and mounting structure
CN116335398B (en) Multilayer rapid construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination