CN103603504B - The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction - Google Patents

The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction Download PDF

Info

Publication number
CN103603504B
CN103603504B CN201310603893.4A CN201310603893A CN103603504B CN 103603504 B CN103603504 B CN 103603504B CN 201310603893 A CN201310603893 A CN 201310603893A CN 103603504 B CN103603504 B CN 103603504B
Authority
CN
China
Prior art keywords
heavy caliber
standpipe
construction
caliber standpipe
diameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310603893.4A
Other languages
Chinese (zh)
Other versions
CN103603504A (en
Inventor
王晓林
赵玉文
朱喆
范贵元
李�瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Original Assignee
Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd filed Critical Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority to CN201310603893.4A priority Critical patent/CN103603504B/en
Publication of CN103603504A publication Critical patent/CN103603504A/en
Application granted granted Critical
Publication of CN103603504B publication Critical patent/CN103603504B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明提供了一种超高层建筑机电大口径立管随主体进度吊装施工的方法,在主体结构每施工40~50米后,即利用塔吊进行一次大口径立管的整管吊装施工,施工中大口径立管整管的长度为10~15米,分层吊装,以塔吊为主要施工机具,将大口径立管由上至下吊装到位。本发明采用整管吊装,解决了常规卷扬机倒装法施工中需根据楼层标高将大口径立管进行切割分段,焊口数量多,施工量大的问题,同时解决了现有卷扬机倒装法的焊口高度不定、焊接难度大、施工效率低、成本高的问题,和易存在安全隐患、难以满足现代建筑施工高效率高标准的综合要求的问题,本发明提高了大口径立管施工的稳定性、安全性和经济性,特别适用于超高层建筑大口径立管的安装施工。

The invention provides a method for hoisting and constructing the electromechanical large-diameter riser of a super high-rise building according to the progress of the main body. After the main structure is constructed every 40 to 50 meters, the tower crane is used to carry out the whole pipe hoisting construction of the large-diameter riser. During construction The length of the large-diameter riser is 10 to 15 meters, and it is hoisted in layers. The tower crane is used as the main construction tool to hoist the large-diameter riser in place from top to bottom. The invention adopts the hoisting of the whole pipe, which solves the problems that the large-diameter standpipe needs to be cut and segmented according to the floor elevation in the construction of the conventional winch upside-down method, the number of welding joints is large, and the problem of large construction volume is solved. The height of the welding joint is not fixed, the welding is difficult, the construction efficiency is low, the cost is high, and there are potential safety hazards, and it is difficult to meet the comprehensive requirements of modern building construction with high efficiency and high standards. The present invention improves the construction efficiency of large-diameter risers. Stability, safety and economy, especially suitable for the installation and construction of large-diameter risers in super high-rise buildings.

Description

超高层建筑机电大口径立管随主体进度吊装施工的方法Method for Hoisting and Construction of Electromechanical Large-diameter Standpipes of Super High-Rise Buildings Following the Progress of the Main Body

技术领域 technical field

本发明涉及大口径立管吊装施工技术领域,特别涉及一种随主体施工进行、适用于超高层建筑的大口径立管安装的吊装施工方法。 The invention relates to the technical field of large-diameter standpipe hoisting construction, in particular to a hoisting construction method that is carried out along with the construction of the main body and is suitable for the installation of large-diameter riser pipes in super high-rise buildings.

背景技术 Background technique

超高层建筑施工中的大口径立管的安装一直是施工的难点,目前一般采用传统的卷扬机倒装法,但倒装法施工中需根据楼层标高将大口径立管进行切割分段,大口径立管切割吊装,焊口数量增加,施工量大,且焊口高度不定,焊接难度大,施工效率低,成本明显增加;卷扬机自重小,为达到吊装目的增加配重,这样在管井内难以固定,且施工中,大口径立管离地的瞬间摇摆剧烈难以控制,容易与结构产生撞击,卷扬机开关操作难度高,骤起骤停对钢丝绳及其卡环冲击力大,卷扬机的固定及大口径立管离地时的防晃措施一直是倒装法的最大难题。综上,卷扬机倒装法成本高、工效低、难度大,且存在较多的安全隐患,难以满足现代建筑施工高效率、高标准的综合要求,目前急需一种新型的大口径立管的施工安装技术,提高现有施工技术的稳定性、安全性和经济性。 The installation of large-diameter risers in the construction of super high-rise buildings has always been a difficult point in construction. At present, the traditional winch inversion method is generally used, but in the inversion method construction, the large-diameter risers need to be cut into sections according to the floor elevation. Cutting and hoisting of standpipes increases the number of welding joints, requires a large amount of construction, and the height of the welding joints is uncertain. The welding is difficult, the construction efficiency is low, and the cost increases significantly. , and during construction, the momentary swing of the large-diameter standpipe off the ground is difficult to control, and it is easy to collide with the structure. The anti-shake measures when the standpipe is off the ground have always been the biggest problem of the inversion method. To sum up, the hoist upside-down method is high in cost, low in efficiency, difficult, and has many potential safety hazards. It is difficult to meet the comprehensive requirements of modern building construction with high efficiency and high standards. At present, there is an urgent need for a new type of large-diameter riser construction. Installation technology to improve the stability, safety and economy of existing construction technology.

发明内容 Contents of the invention

本发明在于提供一种超高层建筑机电大口径立管随主体进度吊装施工的方法,本发明采用整管吊装,解决了常规卷扬机倒装法施工中需根据楼层标高将大口径立管进行切割分段,焊口数量多,施工量大的问题,同时解决了现有卷扬机倒装法的焊口高度不定、焊接难度大、施工效率低、成本高的问题,和易存在安全隐患、难以满足现代建筑施工高效率高标准的综合要求的问题。 The present invention is to provide a method for hoisting and constructing electromechanical large-diameter risers of super high-rise buildings along with the progress of the main body. At the same time, it solves the problems of indeterminate welding height, difficult welding, low construction efficiency and high cost of the existing winch flip-chip method, and it is prone to safety hazards and difficult to meet modern requirements. The problem of comprehensive requirements for high efficiency and high standards in building construction.

为实现上述技术目的,本发明采用的具体技术方案是: For realizing above-mentioned technical purpose, the concrete technical scheme that the present invention adopts is:

一种超高层建筑机电大口径立管随主体进度吊装施工的方法,其特征在于:在主体结构每施工40~50米时,即利用塔吊进行一次大口径立管的整管吊装施工,所述大口径立管的整管的长度为10~15米,其操作步骤包括: A method for hoisting construction of electromechanical large-diameter risers of super high-rise buildings along with the progress of the main body, characterized in that: when the main structure is constructed every 40 to 50 meters, the entire pipe hoisting construction of the large-diameter riser is carried out by using a tower crane. The length of the whole pipe of the large-diameter riser is 10 to 15 meters, and the operation steps include:

步骤一、确定大口径立管的安装位置及安装顺序:绘制管井内大口径立管的平面布置图及竖向排布图,对待安装的大口径立管进行竖向及平面排布,确定其安装位置及安装顺序; Step 1. Determine the installation position and installation sequence of the large-diameter riser: draw the planar layout and vertical layout of the large-diameter riser in the tube well, arrange the vertical and plane arrangement of the large-diameter riser to be installed, and determine its Installation location and installation sequence;

步骤二、确定大口径立管吊装施工时间:确定施工时间,使施工时塔吊的有效起吊高度距结构顶板的高度大于加工后的大口径立管的长度; Step 2. Determine the construction time for hoisting the large-diameter riser: determine the construction time so that the height of the effective lifting height of the tower crane from the structural roof during construction is greater than the length of the processed large-diameter riser;

步骤三、施工前对大口径立管进行加工处理:清理出大口径立管堆放及加工场地,对大口径立管进行加工,包括大口径立管的除锈、坡口修整、吊耳焊接、部分大口径立管的切割与焊接、刷漆和最后的标号码放; Step 3. Process the large-diameter riser before construction: clean up the stacking and processing site of the large-diameter riser, and process the large-diameter riser, including derusting of the large-diameter riser, bevel trimming, lug welding, Cutting and welding, painting and final labeling of some large-diameter risers;

步骤四、管井的清理:保证竖向管井上下畅通无阻; Step 4, cleaning of the tube well: ensure that the vertical tube well is unimpeded up and down;

步骤五、制作并安装管井内的立管支架:按照规范要求在每层管井内安装立管支架,用于吊装完成后及对口焊接完成后的大口径立管固定,其与墙体内的预埋钢板焊接在一起,其上开有预留孔,用于安装直径与立管直径相适应的环形的临时卡箍和正式卡箍; Step 5. Make and install the standpipe support in the tube well: install the standpipe support in each layer of the tube well according to the specification requirements, and use it to fix the large-diameter standpipe after the hoisting and welding. The buried steel plates are welded together, and there are reserved holes on them, which are used to install ring-shaped temporary clamps and formal clamps whose diameter is compatible with the diameter of the standpipe;

步骤六、底部承重支架的制作与安装:在本次吊装施工的最底层安装大口径立管的承重支架,用于大口径立管对口焊接施工完毕后对大口径立管的承重与固定; Step 6. Fabrication and installation of the bottom load-bearing bracket: Install the load-bearing bracket of the large-diameter riser at the bottom of this hoisting construction, which is used for the load-bearing and fixing of the large-diameter riser after the butt-welding construction of the large-diameter riser is completed;

步骤七、管井内临时照明灯的布置与安装:照明灯用于保证管井内施工的亮度,提高施工质量及施工安全性; Step 7. Arrangement and installation of temporary lighting in the tube well: the lighting is used to ensure the brightness of the construction in the tube well and improve the construction quality and construction safety;

步骤八、准备搭设临时支撑架的材料:所述临时支撑架是大口径立管吊装过程中塔吊需要更换钢丝绳时临时搭建的用于临时固定立管的架体,将搭设临时支撑架所用的材料运至所需楼层; Step 8. Prepare the materials for erecting the temporary support frame: the temporary support frame is a temporary frame for temporarily fixing the riser when the tower crane needs to replace the steel wire rope during the hoisting process of the large-diameter riser, and the materials used for erecting the temporary support frame Transport to the desired floor;

步骤九、将大口径立管吊至结构顶板上:根据编号顺序,将大口径立管分批吊至结构顶板上; Step 9. Lift the large-diameter risers to the structural roof: according to the sequence of numbers, lift the large-diameter risers to the structural roof in batches;

步骤十、大口径立管的预吊装:用塔吊吊住大口径立管的吊耳缓慢起吊,在提起及移动过程中检测设备及技术方案的安全性;若存在技术或安全方面的隐患,立即停止吊装进行整改,整改之后再次进行预吊装,直至无安全隐患; Step 10. Pre-hoisting of the large-diameter riser: Use a tower crane to hang the lifting lugs of the large-diameter riser and lift slowly, and check the safety of the equipment and technical solutions during the lifting and moving process; if there are technical or safety hazards, immediately Stop hoisting for rectification, and perform pre-hoisting again after rectification until there are no potential safety hazards;

步骤十一、大口径立管的正式吊装,其方法如下: Step eleven, the formal hoisting of the large-diameter riser, the method is as follows:

1)用塔吊吊住大口径立管的吊耳缓慢起吊,使大口径立管水平向管井移动,至管井正上方后,缓慢下吊; 1) Use the tower crane to hang the lifting lug of the large-diameter riser and lift it slowly, so that the large-diameter riser moves horizontally to the tube well, and after reaching the top of the tube well, slowly lower it;

2)搭设临时支撑架:当塔吊吊钩已经接近结构顶板上的管井开口或塔吊剩余钢丝绳的长度不足以使吊钩下降至预期高度时,暂停塔吊,迅速搭设临时支撑架,将大口径立管缓慢放置到临时支撑架上后,塔吊再缓缓下落; 2) Set up a temporary support frame: When the hook of the tower crane is close to the opening of the tube well on the roof of the structure or the length of the remaining wire rope of the tower crane is not enough to lower the hook to the expected height, stop the tower crane, quickly set up a temporary support frame, and place the large-diameter riser After slowly placing it on the temporary support frame, the tower crane slowly descends;

3)加接钢丝绳:待确定大口径立管不受塔吊作用仍安全稳定后,迅速在结构顶板上进行钢丝绳的加接工作; 3) Adding steel wire ropes: After confirming that the large-diameter riser is safe and stable without being affected by the tower crane, quickly add the steel wire ropes on the structural roof;

4)拆除临时支撑架:连接完毕后,重新起吊,当大口径立管离开临时支撑架1米左右时,暂停塔吊,迅速将临时支撑架管移开; 4) Remove the temporary support frame: After the connection is completed, re-lift it. When the large-diameter standpipe is about 1 meter away from the temporary support frame, stop the tower crane and quickly remove the temporary support frame tube;

5)塔吊再次下落,直至吊装至预定位置; 5) The tower crane falls again until it is hoisted to the predetermined position;

步骤十二、大口径立管的固定:大口径立管吊装至预定位置后,立即用临时卡箍将大口径立管固定在立管支架上,固定完毕后,塔吊继续缓慢下降,至钢丝绳处于松弛状态,确定大口径立管固定良好后,解除钢丝绳; Step 12. Fixing of the large-diameter standpipe: After the large-diameter standpipe is hoisted to the predetermined position, immediately fix the large-diameter standpipe on the standpipe support with a temporary clamp. After the fixation is completed, the tower crane continues to slowly descend until the wire rope is in In the loose state, after confirming that the large-diameter riser is well fixed, release the wire rope;

步骤十三、进行同一高度其他大口径立管吊装固定:重复步骤十一和步骤十二,进行同一高度其他大口径立管的吊装施工; Step 13. Carry out hoisting and fixing of other large-diameter risers at the same height: Repeat steps 11 and 12 to carry out hoisting construction of other large-diameter risers at the same height;

步骤十四、其他高度大口径立管的吊装固定:管井中同一高度的大口径立管吊装完成后,重复步骤十一到步骤十三,进行另一高度大口径立管的吊装,整体吊装顺序是从下层至上层,直至待安装立管的主体部分的大口径立管全部吊装到位; Step 14. Hoisting and fixing of large-diameter risers of other heights: After the hoisting of large-diameter risers of the same height in the tube well is completed, repeat steps 11 to 13 to carry out hoisting of another height of large-diameter risers. The overall hoisting sequence It is from the lower layer to the upper layer, until all the large-diameter risers of the main part of the riser to be installed are hoisted in place;

步骤十五、焊接大口径立管:通过挡板将最底层大口径立管与承重支架焊接为一体,并切除大口径立管的吊耳,将本次吊装施工中已经吊装到位的大口径立管进行对口焊接; Step 15. Welding the large-diameter standpipe: Weld the bottom large-diameter standpipe and the load-bearing support through the baffle, and cut off the lifting lugs of the large-diameter standpipe. Butt welding of the pipe;

步骤十六、用正式卡箍固定大口径立管:将临时卡箍换成用扁钢及较粗圆钢制成的环形的正式卡箍用于对大口径立管的固定; Step sixteen, fix the large-diameter standpipe with a formal clamp: replace the temporary clamp with a ring-shaped formal clamp made of flat steel and thicker round steel for fixing the large-diameter standpipe;

步骤十七、待主体结构再次施工完成40~50米左右时,重复步骤一到步骤十六,进行下一次的大口径立管吊装施工。 Step 17. When the main structure is re-constructed for about 40 to 50 meters, repeat steps 1 to 16 to carry out the next large-diameter standpipe hoisting construction.

所述步骤二中大口径立管吊装施工时间在结构顶板浇筑完成12小时左右,此时交叉作业量较少,为大口径立管吊装的最佳时机。 The hoisting construction time of the large-diameter riser in the step 2 is about 12 hours after the pouring of the structural roof is completed. At this time, the amount of cross work is less, which is the best time for the hoisting of the large-diameter riser.

所述步骤四管井的清理的具体步骤包括:拆除管井部位的模板及脚手架,同时针对现场实际情况对管井周围进行局部加固,确保结构及施工安全。 The specific steps of cleaning the tube well in the step four include: removing the formwork and scaffolding at the tube well part, and at the same time locally reinforcing the surrounding tube well according to the actual situation on site to ensure structural and construction safety.

所述步骤七中管井内临时照明灯的安装与布置的具体方法为:在每层管井中安装低压照明灯,并在正式施工时,每隔两层安装1盏LED工矿灯,保证正常施工照明,后期管井中的大口径立管焊接时不再重复安装照明灯具。 The specific method of installing and arranging the temporary lighting in the tube well in step 7 is: install a low-voltage lighting in each layer of the tube well, and during the formal construction, install an LED industrial and mining lamp every two floors to ensure normal construction lighting , No need to repeat the installation of lighting fixtures when the large-diameter riser in the tube well is welded in the later stage.

所述步骤十一中临时支撑架是由架管和木板搭设成的临时架体,搭设时将若干根架管的两端搭在两侧的楼板上,架管之上铺设木板。 In the eleventh step, the temporary support frame is a temporary frame body built by frame tubes and planks. When erecting, the two ends of several frame tubes are placed on the floor slabs on both sides, and planks are laid on the frame tubes.

所述步骤六中涉及的承重支架为格状矩形钢架,包括矩形框架支撑、横支撑和斜支撑,所述格状矩形框架的一个格子对应一个大口径立管,总格数与待安装大口径立管数目想适应,所述框架支撑、横支撑、和斜支撑均与墙体内的预埋钢板焊接连接。 The load-bearing support involved in the step six is a grid-like rectangular steel frame, including rectangular frame support, horizontal support and oblique support. The number of caliber risers is suitable, and the frame support, horizontal support, and oblique support are all welded and connected to the embedded steel plate in the wall.

所述承重支架与大口径立管的上底面之间焊接有起三角固定作用的挡板。 A baffle plate for triangular fixing is welded between the load-bearing bracket and the upper bottom surface of the large-diameter riser.

所述挡板为直角三角形,其一边焊接在大口径立管上,相邻一边焊接在大口径立管承重支架。 The baffle is a right-angled triangle, one side of which is welded on the large-diameter standpipe, and the adjacent side is welded to the load-bearing support of the large-diameter standpipe.

与现有技术相比,本发明的优势在于:本发明提供了一种超高层建筑机电大口径立管随主体进度吊装施工的方法,在主体结构每施工40~50米后,即利用塔吊进行一次大口径立管的整管吊装施工,施工中大口径立管整管的长度为10~15米,分层吊装,以塔吊为主要施工机具,将大口径立管由上至下吊装到位。本发明采用整管吊装,解决了常规卷扬机倒装法施工中需根据楼层标高将大口径立管进行切割分段,焊口数量多,施工量大的问题,同时解决了现有卷扬机倒装法的焊口高度不定、焊接难度大、施工效率低、成本高的问题,和易存在安全隐患、难以满足现代建筑施工高效率高标准的综合要求的问题,10层288米空调水大口径立管吊装到位仅用6个小时,本发明提高了大口径立管(1)施工的稳定性、安全性和经济性,方便后期维护与管理,特别适用于超高层建筑大口径立管的安装施工。 Compared with the prior art, the advantage of the present invention is that: the present invention provides a method for hoisting and constructing electromechanical large-diameter risers of super high-rise buildings along with the progress of the main body. A whole-pipe hoisting construction of a large-diameter riser. During construction, the length of the large-diameter riser is 10 to 15 meters, and it is hoisted in layers. The tower crane is used as the main construction tool to hoist the large-diameter riser in place from top to bottom. The invention adopts the hoisting of the whole pipe, which solves the problems that the large-diameter standpipe needs to be cut and segmented according to the floor elevation in the construction of the conventional winch upside-down method, the number of welding joints is large, and the problem of large construction volume is solved. The height of the welding joint is uncertain, the welding is difficult, the construction efficiency is low, the cost is high, and there are potential safety hazards, and it is difficult to meet the comprehensive requirements of modern building construction with high efficiency and high standards. The 10-story 288-meter air-conditioning water large-diameter riser It takes only 6 hours to hoist in place. The invention improves the stability, safety and economy of the large-diameter riser (1) construction, facilitates later maintenance and management, and is especially suitable for the installation and construction of large-diameter risers in super high-rise buildings.

附图说明 Description of drawings

图1是本发明超高层建筑机电大口径立管随主体进度吊装施工的方法的施工流程图; Fig. 1 is the construction flowchart of the method for hoisting construction of super high-rise building electromechanical large-diameter riser with main body progress of the present invention;

图2是本发明超高层建筑机电大口径立管随主体进度吊装施工的方法示意图; Fig. 2 is the method schematic diagram of the hoisting construction of super high-rise building electromechanical large-diameter riser with the progress of the main body of the present invention;

图3是本发明步骤八和步骤十一中涉及的临时支撑架的主视图; Fig. 3 is the front view of the temporary support frame involved in step 8 and step 11 of the present invention;

图4是本发明步骤八和步骤十一中涉及的临时支撑架的俯视图; Fig. 4 is the top view of the temporary support frame involved in step 8 and step 11 of the present invention;

图5是本发明步骤六中涉及的承重支架2的主视图; Fig. 5 is the front view of the load-bearing bracket 2 involved in the sixth step of the present invention;

图6是本发明步骤六中涉及的承重支架2的俯视图; Fig. 6 is a top view of the load-bearing bracket 2 involved in step six of the present invention;

图7是本发明步骤十二中涉及的用临时卡箍14固定大口径立管1的主视图; Fig. 7 is the front view of fixing the large-diameter standpipe 1 with the temporary clamp 14 involved in step 12 of the present invention;

图8是本发明步骤十二中涉及的用临时卡箍14固定大口径立管1的俯视图; Fig. 8 is a top view of fixing the large-diameter standpipe 1 with a temporary clamp 14 involved in step 12 of the present invention;

图9是本发明步骤十六中涉及的用正式卡箍16固定大口径立管1的主视图; Fig. 9 is the front view of fixing the large-diameter standpipe 1 with a formal clamp 16 involved in the sixteenth step of the present invention;

图10是本发明步骤十六中涉及的用正式卡箍16固定大口径立管1的俯视图。 Fig. 10 is a top view of fixing the large-diameter standpipe 1 with a formal clamp 16 involved in step sixteen of the present invention.

附图标记:1-大口径立管、2-承重支架、21-框架支撑、22-横支撑、23-斜支撑、3-楼板、4-架管、5-木板、6-挡板、7-结构顶板、8-钢丝绳、9-管井、10-塔吊、11-混凝土剪力墙、12-槽钢、13-预埋钢板、14-临时卡箍、15-立管支架、16-正式卡箍。 Reference signs: 1-large-diameter standpipe, 2-load-bearing bracket, 21-frame support, 22-horizontal support, 23-oblique support, 3-floor slab, 4-frame pipe, 5-wooden board, 6-baffle plate, 7 -Structure roof, 8-wire rope, 9-tube well, 10-tower crane, 11-concrete shear wall, 12-channel steel, 13-embedded steel plate, 14-temporary clamp, 15-standpipe support, 16-formal clamp hoop.

具体实施方式 Detailed ways

结合图1~6,本实施例机电工程包括给排水、通风空调、强电、消防、弱电等系统施工,其中给排水、空调水、消防专业的大口径立管1数量较多,尤其是子分部工程空调水系统存在大量的大口径焊接大口径立管1,此部分大口径立管1的安装施工给工程增加了很大的难度,且传统吊装施工已难以满足本实施例对进度、安全、成本的高要求,遂采用了大口径大口径立管1随主体施工吊装技术。本实施例大口径立管1的长度为12米,主体施工每完成10层进行一次吊装,分三次吊装后进行相邻层对口焊接。 In combination with Figures 1 to 6, the mechanical and electrical engineering of this embodiment includes the construction of systems such as water supply and drainage, ventilation and air conditioning, strong electricity, fire protection, and weak electricity. There are a large number of large-diameter welded large-diameter risers 1 in the air-conditioning water system of the branch project. The installation and construction of this part of the large-diameter riser 1 has added great difficulty to the project, and the traditional hoisting construction has been difficult to meet the requirements of this embodiment. Due to the high requirements of safety and cost, the large-diameter standpipe 1 was hoisted along with the main construction. The length of the large-diameter riser 1 in this embodiment is 12 meters, and the main body construction is completed every 10 floors, and the hoisting is carried out once, and the adjacent layers are welded after three hoistings.

1 施工重点 1 Construction focus

1.1明确塔吊10顶升时间;保证塔吊10的最大起吊高度满足吊装要求,即塔吊10的有效起吊高度距施工最顶层高度大于12米,12米为大口径立管1的长度,可使大口径立管1垂直吊起。 1.1 Specify the lifting time of the tower crane 10; ensure that the maximum lifting height of the tower crane 10 meets the hoisting requirements, that is, the effective lifting height of the tower crane 10 is greater than 12 meters from the height of the top layer of the construction, and 12 meters is the length of the large-diameter riser 1, which can make the large-diameter Standpipe 1 is vertically suspended.

1.2紧抓混凝土浇筑时间安排;因本实施例混凝土浇筑一般在中午完成,晚上混凝土初凝,达到上人条件,且未搭设脚手架,塔吊10相应比较空闲,最高层施工面一马平川,极利于大口径立管1吊装施工作业,所以尽量在混凝土浇筑完成当晚便开始进行大口径立管1吊装。另,协调塔吊10顶升时间与混凝土浇筑时间相呼应,即确保塔吊10顶升到位的情况下,再确定在哪一层混凝土浇筑完成后进行吊装施工。 1.2 Pay close attention to the timing of concrete pouring; because the concrete pouring in this embodiment is generally completed at noon, and the concrete is initially set at night, which meets the conditions for masters, and no scaffolding is erected, the tower crane 10 is correspondingly idle, and the topmost construction surface is flat, which is very beneficial to large-diameter Standpipe 1 hoisting construction work, so try to start large-diameter riser 1 hoisting on the night when concrete pouring is completed. In addition, coordinate the lifting time of the tower crane 10 to correspond with the concrete pouring time, that is, ensure that the lifting of the tower crane 10 is in place, and then determine which layer of concrete is poured to carry out the lifting construction.

1.3脚手架局部加固;因大口径立管1是从结构已施工完成面最顶端纵向贯穿各楼层至预定位置,管井9部位的模板及脚手架必须拆除,以保证竖向管井9上下畅通无阻,所以需技术部门针对现场实际情况对管井9周围进行局部加固,确保结构及施工安全。 1.3 The scaffolding is partially reinforced; since the large-diameter riser 1 runs through each floor longitudinally from the top of the completed surface of the structure to the predetermined position, the formwork and scaffolding at the tube well 9 must be removed to ensure that the vertical tube well 9 is unimpeded up and down, so it is necessary to The technical department carried out partial reinforcement around the tube well 9 according to the actual situation on site to ensure the safety of the structure and construction.

1.4大口径立管1临时停放;大口径立管1吊装过程中,塔吊10钢丝绳8长度不足以一次性将大口径立管1下放到位,需对钢丝绳8进行加接,此时大口径立管1必须进行临时停放,而本工程空调水大口径立管1整根重量最大可达1380KG, 所以大口径立管1的临时停放方案及措施显得尤其重要。 1.4 Temporary parking of the large-diameter riser 1; during the hoisting process of the large-diameter riser 1, the length of the steel wire rope 8 of the tower crane 10 is not enough to lower the large-diameter riser 1 in place at one time, and the wire rope 8 needs to be added. At this time, the large-diameter riser 1 must be temporarily parked, and the weight of the large-diameter riser 1 of the air-conditioning water in this project can reach up to 1380KG, so the temporary parking plan and measures for the large-diameter riser 1 are particularly important.

2准备工作 2 Preparations

2.1方案准备与完善 2.1 Plan preparation and improvement

①明确塔吊10顶升时间及顶升高度;确保大口径立管1吊装前塔吊10的有效起吊高度满足吊装施工要求; ① Clarify the lifting time and height of the tower crane 10; ensure that the effective lifting height of the tower crane 10 meets the lifting construction requirements before the large-diameter riser 1 is hoisted;

②确定结构顶板7混凝土浇筑时间;在塔吊10的有效起吊高度满足施工要求的前提下,通过确定结构顶板7混凝土浇筑时间来计划大口径立管吊装时间。 ②Determine the concrete pouring time of the structural roof 7; on the premise that the effective lifting height of the tower crane 10 meets the construction requirements, the hoisting time of the large-diameter riser is planned by determining the concrete pouring time of the structural roof 7.

③与技术部沟通对结构顶板7下相邻3层管井9部位的支撑进行局部加固调整,不得影响大口径立管1吊装; ③ Communicate with the technical department to locally reinforce and adjust the support of the adjacent 3-layer tube well 9 under the structural roof 7, without affecting the hoisting of the large-diameter riser 1;

④吊装前,协调土建专业对管井9进行清理,确保管井9上下施工无障碍; ④ Before hoisting, coordinate civil engineering to clean up the tube well 9 to ensure that the upper and lower construction of the tube well 9 is unobstructed;

⑤管井9大口径立管1排布;对管井9大口径立管1进行综合布置,平面排布使大口径立管1施工经济化、最优化,竖向排布的目的主要是使大口径立管1上口离地高度不超过1.5米,便于吊装完成后摘取钢丝绳8,减少安全隐患,并降低压力大口径立管1横向焊口的施工难度。 ⑤Arrangement of 9 large-diameter risers 1 in the tube wells; the comprehensive arrangement of the 9 large-diameter risers 1 in the tube wells, the planar arrangement makes the construction of the large-diameter risers 1 economical and optimized, and the purpose of the vertical arrangement is mainly to make the large-diameter risers 1 The height of the top of the riser 1 from the ground is no more than 1.5 meters, which is convenient for picking up the steel wire rope 8 after the hoisting is completed, reduces potential safety hazards, and reduces the construction difficulty of the horizontal weld of the pressure large-caliber riser 1 .

例:根据管线布置的实际情况,分别将管线竖向排布图及管井9平面布置图深化如图2、图3。 Example: According to the actual situation of the pipeline layout, the vertical pipeline layout diagram and the tube well 9 plane layout diagram are respectively deepened as shown in Figure 2 and Figure 3.

2.2施工准备 2.2 Construction preparation

①大口径立管1运至现场前,应先准备并清理出大口径立管1堆放及加工场地,需现场勘查来确定场地; ① Before the large-diameter riser 1 is transported to the site, the stacking and processing site of the large-diameter riser 1 should be prepared and cleared, and the site needs to be investigated to determine the site;

②将管井9内所需大口径立管1运至加工场地,进行加工处理,包括大口径立管1除锈、坡口修整、吊耳焊接、部分大口径立管1的切割与焊接、大口径立管1刷漆,最后标号码放; ②Transport the large-diameter riser 1 required in the tube well 9 to the processing site for processing, including rust removal of the large-diameter riser 1, bevel trimming, lug welding, cutting and welding of some large-diameter riser 1, large-diameter Caliber riser 1 is painted, and finally marked and numbered;

③立管支架15制作安装;对结构管井9进行偏差测量,严格按照现场实际情况进行立管支架15制作,保证支架竖向成线,避免因支架偏差影响大口径立管1垂直度; ③ Manufacture and install the riser support 15; measure the deviation of the structural pipe well 9, and make the riser support 15 strictly according to the actual situation on site to ensure the vertical alignment of the support and avoid affecting the verticality of the large-diameter riser 1 due to the deviation of the support;

④临时支撑架制作方案确定;因本楼空调水管井9背面为剪力墙,且楼板3处与剪力墙无连接,无法按常规方法在管井上方满铺架管4作为大口径立管1临时支撑,这就给吊装换绳工作造成了很大的难度,后经讨论并现场实践论证,在需加接钢丝绳的楼层剪力墙处焊接槽钢,槽钢顶部与楼板3平,上方可进行架管4铺设,即可按照常规方法进行大口径立管1临时固定,临时支撑架制作如图4; ④The production plan of the temporary support frame is determined; because the back of the air-conditioning water pipe well 9 in this building is a shear wall, and the 3 floors of the floor are not connected to the shear wall, it is impossible to fully lay the frame pipe 4 above the pipe well as a large-diameter standpipe according to the conventional method 1 Temporary support, which has caused great difficulty in hoisting and changing ropes. After discussion and on-site demonstration, channel steel is welded at the floor shear wall where steel wire ropes need to be added. The top of the channel steel is 3 levels from the floor, and The laying of the frame pipe 4 can be carried out, and the large-diameter riser 1 can be temporarily fixed according to the conventional method, and the temporary support frame is made as shown in Figure 4;

⑤临时照明布置;大口径立管1吊装一般为夜间施工,且管井9本身采光效果较差,需在每层管井9中安装低压照明灯,并在正式施工时,每隔两层安装1架碘钨灯,保证正常施工照明,后期管井9中的大口径立管1焊接时可不再重复安装照明灯具; ⑤Temporary lighting layout; the hoisting of large-diameter riser 1 is generally carried out at night, and the lighting effect of tube well 9 itself is poor, so it is necessary to install low-voltage lighting lamps in each layer of tube well 9, and install one frame every two floors during formal construction Iodine tungsten lamps ensure normal construction lighting, and it is no longer necessary to repeatedly install lighting fixtures during the welding of large-diameter standpipes 1 in tube wells 9 in the later stage;

3大口径立管1吊装 3 large diameter riser 1 hoisting

3.1首先对大口径立管1进行预吊装 3.1 First, pre-install the large-diameter riser 1

①根据编号顺序,将大口径立管1分批吊至结构顶板7; ① According to the numbering sequence, hoist the large-diameter risers 1 to the structural roof 7 in batches;

②在施工人员配合下,使用塔吊10吊住大口径立管1的吊耳缓慢起吊,当大口径立管1整体脱离地面30cm时,暂停,观察塔吊10工作是否正常; ② With the cooperation of the construction personnel, use the tower crane 10 to hang the lugs of the large-diameter riser 1 and slowly lift it. When the large-diameter riser 1 is 30cm away from the ground as a whole, pause and observe whether the tower crane 10 is working normally;

③经检查情况良好后,启动塔吊10,使管水平向管井9移动,在工作人员的协助下,缓慢下吊,当大口径立管1上口离结构顶板7上沿10公分左右时,再次暂停塔吊10,观察塔吊10工作是否正常; ③ After the inspection is in good condition, start the tower crane 10 to move the pipe horizontally to the pipe well 9, and slowly lower it with the assistance of the staff. Pause the tower crane 10, and observe whether the tower crane 10 works normally;

④若存在技术或安全方面的隐患,立即停止吊装,在进行彻底整改后,再次进行预吊装,直至一切状况良好后,进行正常吊装施工。 ④ If there are hidden dangers in technology or safety, stop the hoisting immediately, and carry out pre-hoisting again after thorough rectification, and carry out normal hoisting construction until everything is in good condition.

3.2大口径立管1正式吊装 3.2 Formal hoisting of large diameter riser 1

①正式吊装时,用塔吊10吊住大口径立管1的吊耳缓慢起吊,使大口径立管1水平向管井9移动,至管井9正上方后,缓慢下吊,大口径立管1经过每层时,本层的施工人员必须配合校正,尽量减小大口径立管1摆动幅度,避免大口径立管1与周围结构发生碰撞; ① During formal hoisting, use the tower crane 10 to hang the lifting lugs of the large-diameter riser 1 and lift slowly, so that the large-diameter riser 1 moves horizontally to the tube well 9, and after reaching the top of the tube well 9, slowly lower it, and the large-diameter riser 1 passes For each floor, the construction personnel on this floor must cooperate with the calibration to minimize the swing range of the large-diameter riser 1 and avoid collisions between the large-diameter riser 1 and the surrounding structures;

②当塔吊10吊钩已经接近结构顶板7上的管井9开口或塔吊10剩余钢丝绳8的长度不足以使吊钩下降至预期高度时,暂停塔吊10,迅速搭设临时支撑架,将大口径立管1缓慢放置到临时支撑架上后; ② When the hook of the tower crane 10 is close to the opening of the tube well 9 on the structural roof 7 or the length of the remaining wire rope 8 of the tower crane 10 is not enough to lower the hook to the expected height, stop the tower crane 10, quickly set up a temporary support frame, and place the large-diameter standpipe 1 Slowly placed on the temporary support frame;

③当大口径立管1停放到临时支撑架上时,塔吊10再缓缓下落,并确定大口径立管1不受塔吊10作用仍安全稳定后,通知结构顶板7工作人员进行钢丝绳8加接工作,加接完毕,由信号工通知塔吊10上升,大口径立管1底端所在层施工人员配合重新起吊,当大口径立管1离楼板3面1米左右时,暂停,施工人员尽快将临时支撑架移开,并通知塔吊10再次下落; ③ When the large-diameter riser 1 is parked on the temporary support frame, the tower crane 10 will slowly fall again, and after confirming that the large-diameter riser 1 is still safe and stable without being affected by the tower crane 10, notify the staff on the structural roof 7 to connect the wire rope 8 Work, after the connection is completed, the signal worker will notify the tower crane 10 to rise, and the construction personnel on the floor where the bottom end of the large-diameter riser 1 will cooperate with the hoisting again. The temporary support frame is removed, and the tower crane 10 is notified to fall again;

④重复第②③项工作,直至大口径立管1吊装至预定位置; ④ Repeat the work of ② and ③ until the large-diameter riser 1 is hoisted to the predetermined position;

⑤吊至预定位置后,大口径立管1所在层的施工人员立即用临时卡箍14将大口径立管固定在立管支架15上,固定完毕后,塔吊10继续缓慢下降20cm左右,使钢丝绳8处于松弛不受力状态,确定大口径立管1固定良好后,由大口径立管1上口所在层施工人员解除钢丝绳8,并进行下一大口径立管1的吊装施工; ⑤ After hoisting to the predetermined position, the construction personnel on the floor where the large-diameter riser 1 is located immediately fix the large-diameter riser on the standpipe support 15 with a temporary clamp 14. 8 is in a state of relaxation and no force, after confirming that the large-diameter riser 1 is well fixed, the construction personnel on the upper layer of the large-diameter riser 1 release the steel wire rope 8, and carry out the hoisting construction of the next large-diameter riser 1;

   ⑥依照步骤①-⑤,依次将管井9中同一高度的大口径立管1吊入,然后进行下一高度大口径立管1的吊装,直至所有大口径立管1吊装完成; ⑥ According to steps ①-⑤, the large-diameter risers 1 of the same height in the tube well 9 are hoisted in sequence, and then the hoisting of the large-diameter risers 1 at the next height is carried out until all the large-diameter risers 1 are hoisted;

⑦在所有大口径立管1吊装完成后,通过挡板将最底层大口径立管1与承重支架2焊接为一体,并切除大口径立管的吊耳,将本次吊装施工中已经吊装到位的大口径立管(1)进行对口焊接; ⑦ After all the large-diameter risers 1 are hoisted, the bottom large-diameter riser 1 and the load-bearing bracket 2 are welded together through the baffle, and the lifting lugs of the large-diameter risers are cut off, and the hoisting construction has been hoisted in place. The large-diameter standpipe (1) is butt-welded;

⑧将临时卡箍14换成用扁钢及较粗圆钢制成的环形的正式卡箍16用于对大口径立管1的固定; 8. Temporary clamp 14 is replaced with the ring-shaped formal clamp 16 that is made of flat steel and thicker round steel and is used for fixing large-diameter standpipe 1;

⑨待主体结构再次施工完成40~50米左右时,进行下一次的大口径立管1吊装施工。 ⑨ When the re-construction of the main structure is completed for about 40-50 meters, the next large-diameter riser 1 hoisting construction will be carried out.

Claims (8)

1. the dynamo-electric heavy caliber standpipe of a super highrise building is with the method for main body progress lifting construction, it is characterized in that: agent structure often construct 40 ~ 50 meters time, namely tower crane (10) is utilized to carry out the homogeneous tube lifting construction of a heavy caliber standpipe (1), the length of the homogeneous tube of described heavy caliber standpipe (1) is 10 ~ 15 meters, and its operating procedure comprises:
Step one, the installation site determining heavy caliber standpipe (1) and erection sequence: draw the layout plan of pipe well (9) interior heavy caliber standpipe (1) and vertical layout viewing, vertical and planar arrangement are carried out to heavy caliber standpipe (1) to be installed, determines its installation site and erection sequence;
Step 2, determine heavy caliber standpipe (1) the lifting construction time: determine the engineering time, when making construction, effective sling height of tower crane (10) is greater than the length of the heavy caliber standpipe (1) after processing apart from the height of structure roof (7);
Before step 3, construction, processing process is carried out to heavy caliber standpipe (1): clean out heavy caliber standpipe and stack and processing place, heavy caliber standpipe is processed, comprise the rust cleaning of heavy caliber standpipe, groove finishing, hanger welding, part heavy caliber standpipe cutting with weld, mopping and last label pile up;
The cleaning of step 4, pipe well (9): ensure that vertical pipe well (9) is unblocked up and down;
Step 5, making install the riser cradle (15) of in pipe well (9) every layer: in every stove pipe well (9), riser cradle (15) is installed according to code requirement, for after having lifted and butt welding complete after heavy caliber standpipe (1) fix, pre-embedded steel slab (13) in itself and body of wall welds together, it has preformed hole, for installing interim clip (14) and the formal clip (16) of the annular that diameter and standpipe diameter adapt;
The manufacture and installation of step 6, bottom support bracket (2): the support bracket (2) installing heavy caliber standpipe (1) at the bottom of this lifting construction, for after the construction of heavy caliber standpipe (1) butt welding to the load-bearing of heavy caliber standpipe (1) with fixing;
The layout of step 7, pipe well (9) interior temporary illuminating lamp and installation: illuminating lamp, for ensureing the brightness of constructing in pipe well (9), improves construction quality and working security;
Step 8, prepare to set up the material of temporary support: described temporary support is that in heavy caliber standpipe hoisting process, tower crane (10) needs the support body for temporary fixed standpipe temporarily built time more change steel rope (8), is transported to required floor by setting up temporary support material used;
Step 9, heavy caliber standpipe (1) to be winched to structure roof (7) upper: according to number order, winched to by heavy caliber standpipe (1) in structure roof (7) in batches;
The pre-lifting of step 10, heavy caliber standpipe (1): the hanger hanging heavy caliber standpipe (1) with tower crane (10) slowly lifts by crane, is mentioning and the safety of checkout equipment and technical scheme in moving process; If there is the hidden danger of technology or secure context, stop lifting rectifying and improving immediately, again lift in advance after rectification, until without potential safety hazard;
The formal lifting of step 11, heavy caliber standpipe (1), its method is as follows:
1) slowly lift by crane with the hanger that tower crane (10) hangs heavy caliber standpipe (1), make heavy caliber standpipe (1) level mobile to pipe well (9), after to pipe well (9), hang slowly;
2) temporary support is set up: when tower crane (10) suspension hook has remained wire rope (8) curtailment close to pipe well (9) opening in structure roof (7) or tower crane (10) expects height to make suspension hook drop to, suspend tower crane (10), set up temporary support rapidly, slowly be placed into after on temporary support by heavy caliber standpipe (1), tower crane (10) slowly falls again;
3) adjunction wire rope (8): heavy caliber standpipe (1) to be determined does not act on still after safety and stability by tower crane (10), carries out rapidly the adjunction work of wire rope (8) in structure roof;
4) remove temporary support: after connection, again lift by crane, when heavy caliber standpipe (1) leaves temporary support 1 meter, suspend tower crane (10), rapidly temporary support is removed;
5) tower crane (10) falls again, until lifting is to precalculated position;
Fixing of step 12, heavy caliber standpipe (1): heavy caliber standpipe (1) lifting is to precalculated position, interim clip (14) is used to be fixed on riser cradle (15) by heavy caliber standpipe (1) immediately, after fixing, tower crane (10) continues slowly to decline, relaxed state is in wire rope (8), after determining that heavy caliber standpipe is fixed well, remove wire rope (8);
Step 13, to carry out the lifting of other heavy caliber standpipes of sustained height fixing: repeat step 11 and step 12, carry out the lifting construction of other heavy caliber standpipes of sustained height;
The lifting of step 14, other height heavy caliber standpipes is fixed: after in pipe well (9), the heavy caliber standpipe of sustained height has lifted, repeat step 11 to step 13, carry out the lifting of another height heavy caliber standpipe, integral hoisting order is from lower floor to upper strata, puts in place until the heavy caliber standpipe (1) of the main part of standpipe to be installed all lifts;
The butt welding of step 15, heavy caliber standpipe (1): bottom heavy caliber standpipe (1) and support bracket (2) are welded as a whole by baffle plate, and excise the hanger of heavy caliber standpipe, the heavy caliber standpipe (1) lifted in this lifting construction between each layer of putting in place is carried out butt welding;
Step 10 six, with the fixing heavy caliber standpipe (1) of formal clip (16): interim clip (14) is changed into the formal clip (16) of the annular made with band steel and thicker round steel for fixing heavy caliber standpipe (1);
Step 10 seven, until agent structure again constructed 40 ~ 50 meters time, repeat step one to step 10 six, carry out heavy caliber standpipe (1) lifting construction next time.
2. the dynamo-electric heavy caliber standpipe of a kind of super highrise building according to claim 1 is with the method for main body progress lifting construction, it is characterized in that: described step 2 Large diameter standpipe (1) the lifting construction time has built 12 hours in structure roof (7), now cross-operation amount is less, is the best opportunity that heavy caliber standpipe (1) lifts.
3. the dynamo-electric heavy caliber standpipe of a kind of super highrise building according to claim 1 is with the method for main body progress lifting construction, it is characterized in that: the concrete steps of the cleaning of described step 4 pipe well (9) comprising: template and the scaffold of removing pipe well (9) position, for on-site actual situations, local stiffening is carried out around to pipe well (9) simultaneously, guarantee structure and construction safety.
4. the dynamo-electric heavy caliber standpipe of a kind of super highrise building according to claim 1 is with the method for main body progress lifting construction, it is characterized in that: in described step 7, the installation of pipe well (9) interior temporary illuminating lamp and the concrete grammar of layout are: in every stove pipe well (9), low-voltage lighting is installed, and when formally constructing, every two-layer installation 1 LED bay light, guarantee normal construction throws light on, and no longer repeats to install lighting when the heavy caliber standpipe (1) in later stage pipe well (9) welds.
5. the dynamo-electric heavy caliber standpipe of a kind of super highrise building according to claim 1 is with the method for main body progress lifting construction, it is characterized in that: in described step 11, temporary support is the interim support body set up with plank (5) by frame pipe (4), when setting up, one end of some frame pipes (4) is ridden on the floor (3) of side, the other end rides on the channel-section steel (12) that is fixed on concrete shear force wall (11), lays plank (5) on frame pipe (4).
6. the dynamo-electric heavy caliber standpipe of a kind of super highrise building according to claim 1 is with the method for main body progress lifting construction, it is characterized in that: the support bracket (2) related in described step 6 is trellis rectangle steelframe, comprise rectangular frame and support (21), horizontal support (22) and bearing diagonal (23), the corresponding heavy caliber standpipe (1) of a grid of described trellis rectangular frame, total lattice number and heavy caliber standpipe to be installed (1) number are wanted to adapt to, described frame supported (21), horizontal support (22), all be welded to connect with the pre-embedded steel slab (13) in body of wall with bearing diagonal (23).
7. the dynamo-electric heavy caliber standpipe of a kind of super highrise building according to claim 6 is with the method for main body progress lifting construction, it is characterized in that: the baffle plate (6) being welded with triangle fixation between the upper bottom surface of described support bracket (2) and heavy caliber standpipe (1).
8. the dynamo-electric heavy caliber standpipe of a kind of super highrise building according to claim 6 or 7 any one is with the method for main body progress lifting construction, it is characterized in that: described baffle plate (6) is right-angled triangle, one side weld is connected on heavy caliber standpipe (1), and adjacent one side is welded on heavy caliber standpipe (1) support bracket (2).
CN201310603893.4A 2013-11-26 2013-11-26 The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction Expired - Fee Related CN103603504B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310603893.4A CN103603504B (en) 2013-11-26 2013-11-26 The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310603893.4A CN103603504B (en) 2013-11-26 2013-11-26 The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction

Publications (2)

Publication Number Publication Date
CN103603504A CN103603504A (en) 2014-02-26
CN103603504B true CN103603504B (en) 2015-08-26

Family

ID=50121759

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310603893.4A Expired - Fee Related CN103603504B (en) 2013-11-26 2013-11-26 The dynamo-electric heavy caliber standpipe of super highrise building is with the method for main body progress lifting construction

Country Status (1)

Country Link
CN (1) CN103603504B (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105888198A (en) * 2015-01-02 2016-08-24 华恒建设集团有限公司 Mounting structure of pipeline in pipeline shaft
CN104895174B (en) * 2015-06-02 2016-08-24 神州建设集团有限公司 The construction method of heavy caliber rain sewage conduct assembled modular construction
CN105402868B (en) * 2015-12-21 2018-06-29 中建三局集团有限公司 A kind of fixing bracket system for heavy caliber air-conditioning standpipe in high-rise building
CN106996196A (en) * 2017-05-19 2017-08-01 中国五冶集团有限公司 A kind of large diameter pipeline integral hoisting construction method
CN111364766A (en) * 2020-03-18 2020-07-03 中建三局第二建设工程有限责任公司 Synchronous construction method of vertical pipe along with main structure
CN111519911B (en) * 2020-05-06 2021-10-15 中铁建设集团北京工程有限公司 A construction method for installing pipes under a steel truss
CN113123560B (en) * 2021-03-23 2022-07-08 中建一局集团安装工程有限公司 Layer-by-layer inverted mounting structure and construction method for ultra-large pipe well chimney
CN113251210A (en) * 2021-05-13 2021-08-13 山西四建集团有限公司 Inverted installation construction method for riser of super high-rise tubular well
CN114182790A (en) * 2021-11-25 2022-03-15 中铁建设集团华东工程有限公司 Construction method of tube well vertical tube in super high-rise building engineering
CN114933231B (en) * 2022-04-08 2023-07-04 上海市安装工程集团有限公司 Calandria bundle hoisting tool and construction method thereof
CN115289384B (en) * 2022-07-13 2024-04-16 上海江南长兴造船有限责任公司 Rail type device and method for mounting ultra-large LNG film tank containment system

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FI82739C (en) * 1989-07-19 1993-08-03 Sewatek Ab Oy channel Construction
CN201141483Y (en) * 2007-12-13 2008-10-29 中建三局第一建设工程有限责任公司 A prefabricated composite riser
CN102322141A (en) * 2011-06-30 2012-01-18 黄先锋 Concrete embedded die for water supply and drainage pipe riser and mounting position forming and mounting method
CN102587654A (en) * 2012-02-23 2012-07-18 中国建筑第二工程局有限公司 Construction method of PVC drainage direct-buried pipe fitting
CN103243911A (en) * 2013-04-03 2013-08-14 广西建工集团第一建筑工程有限责任公司 Integral setting and one-step in-position construction method for steel sleeves of inner pipelines of vertical shaft of building

Also Published As

Publication number Publication date
CN103603504A (en) 2014-02-26

Similar Documents

Publication Publication Date Title
CN103603504A (en) Method of hoisting super high-rise building electrochemical large-diameter rises along with progress of main structure
CN103243926B (en) Construction method of hoisting pipe well standpipe in high-rise building engineering
CN102864936B (en) Combination lifting construction method for large-scale high hollow building roof of steel structure
CN103291076B (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
CN102444203B (en) High-altitude long-span overhanging corridor type reinforced concrete structure and construction method
CN101886466B (en) Construction method for support structure of coal tower template for tamping type coke oven
CN202227476U (en) High-altitude large-span overhung corridor-type reinforced concrete structure
CN114232805B (en) Construction method of ultrahigh-height large-span steel concrete beam hanging structure
CN103711301A (en) Construction method and device for two-track movable electric basket and lifting hoist
CN115538792B (en) Building construction method and building construction structure by using residential building machine
CN104032967B (en) Prefabricated assembled frame structure component construction method for hanging
CN105649314A (en) Suspension platform for high and long-span corridor construction
CN106121255A (en) Apparatus installed by a kind of Super High glass curtain wall
CN101775896B (en) Rigid suspended scaffold for installing pipeline of steel roof equipment
CN104947926B (en) Hard protection device for upper formwork system of inner barrel of core barrel and construction method of hard protection device
CN206692235U (en) A kind of steel structure dome lifts by crane erecting device
CN107119921B (en) A kind of skyscraper Bailey beam Demolition Construction method
CN104847102A (en) Wall attaching method and device of attached self-lifting scaffold on retraction section of building outer wall
CN114704064A (en) Flow combination construction method for disk-buckle type self-overhanging operation frame and rope net operation frame
CN111764623B (en) Hanging construction platform module and construction method of high altitude large cantilever steel roof frame
CN205502551U (en) Platform is suspended in midair in high altitude large -span vestibule construction
CN201908447U (en) Lift-type horizontal safety net
CN102061810B (en) Construction method of safe flat net positioned on periphery of building
CN115897978A (en) Cantilevered steel platform and erection method of inner ring corridor between high-rise floors of spherical building
CN211597658U (en) Movable overhanging scaffold

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model