CN107419907B - A kind of steel-making tower steel structure platform is staggered installation of welding method - Google Patents

A kind of steel-making tower steel structure platform is staggered installation of welding method Download PDF

Info

Publication number
CN107419907B
CN107419907B CN201710779990.7A CN201710779990A CN107419907B CN 107419907 B CN107419907 B CN 107419907B CN 201710779990 A CN201710779990 A CN 201710779990A CN 107419907 B CN107419907 B CN 107419907B
Authority
CN
China
Prior art keywords
platform
installation
prop
lower prop
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710779990.7A
Other languages
Chinese (zh)
Other versions
CN107419907A (en
Inventor
孔炯
金仁才
朱红刚
周金龙
施光涛
徐峥
吴名
陈志�
郑治飞
汪柱兵
琚志海
郭建华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710779990.7A priority Critical patent/CN107419907B/en
Publication of CN107419907A publication Critical patent/CN107419907A/en
Application granted granted Critical
Publication of CN107419907B publication Critical patent/CN107419907B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

Welding method is staggered installation of the invention discloses a kind of steel-making tower steel structure platform, utilize supporting role of halfpace during interlayer stage+module,, basic repetition measurement the welding deformation generated due to welding concentrated stress is resisted, step is substantially are as follows: one, preparation of construction: 1);2), component is marched into the arena repetition measurement;Two, lower platform and component installation: steel column is first installed, then one layer of platform and two-layer platform are successively installed, welds one layer of platform after the installation is completed in two-layer platform;Three, upper brace and component installation: upper prop installation, then three layers of platform member are installed, two-layer platform is welded, after the installation is completed with this upward erecting and welding.Erecting and welding method of the invention, ensure that the orderly progress of erecting and welding, while improve construction efficiency and installation accuracy.

Description

A kind of steel-making tower steel structure platform is staggered installation of welding method
Technical field
The present invention relates to technical field of buildings, and in particular to a kind of steel-making tower steel structure platform is staggered installation of welding side Method.
Background technique
The skyscraper of full steel structure compares more at home at present, and main pooled applications are in conference and exhibition center, grand theater, sport In terms of shop and individual Business Buildings.And the high-rise steel structure of metallurgical system construction is concentrated mainly on converter and blast furnace region, highly exists 60m or 80m or so.The characteristics of converter system steel structure platform is that the more height differences of layer are big, and centralized arrangement has heavy equipment, converter system The comprehensive progress of Steel Structure Installation directly affects the installation effectiveness of steelmaking system.
In general, technique steel construction in converter region takes incremental mode to be installed by chapter, lift, install, Installation, welding of landing beam etc., but for multi-storey steel structure installation, welding sequence is affected to structure both shrinks how Ensuring to make steel tower steel structure platform orderly, precisely to install is the emphasis controlled.
Summary of the invention
The purpose of this invention is welded aiming in steel-making high building multi-storey steel structure conventional mounting welding process due to concentrating It scoops out power and leads to the offset of steel columns of steel structures verticality, welding contraction distortion, solve control platform erecting and welding method, to improve The efficiency of Steel Structure Installation, quality stability and the problem of reduce operation safety risk.
To solve the above problems, the present invention the following technical schemes are provided:
A kind of steel-making tower steel structure platform is staggered installation of welding method, is using halfpace in interlayer stage+module The welding deformation generated due to welding concentrated stress is resisted in supporting role in the process, and construction procedure is as follows:
Step 1: preparation of construction
A, surveying setting-out carries out repetition measurement to steel-column foundation using theodolite and level, and measuring goes out steel-column foundation in length and breadth To center line;
B, component site acceptance checks the component marched into the arena, and the size of component carries out repetition measurement and is identified;
Step 2: lower platform and component installation
A, lower prop I, lower prop II, lower prop III are successively lifted, measures lower prop I, lower prop II, lower prop using theodolite and level III verticality and absolute altitude;
B, once grouting is carried out to lower prop I, lower prop II, lower prop III after centering, grouting height control is away from steel column base Plinth upper surface about 200mm;
C, one layer of platform of construction:
Construction transverse frame beam and longitudinal framing beam: the first installation transverse frame beam between lower prop I and lower prop II utilizes Vierendeel girder is lifted the bracket upper surface to steel column I and steel column II by lifting equipment, and Vierendeel girder and steel column I and steel column II is made to keep water It is flat, connecting plate I is installed and high-strength bolt that two sides take, high-strength bolt need to be by just twisting and twisting eventually;
Longitudinal framing beam is identical with the installation mode of transverse frame beam as the connection type of steel column;In this way, longitudinal frame Set a roof beam in place, transverse frame beam lower prop I, lower prop II, lower prop III are connected it is integral, connection type be high-strength bolt connection, wouldn't weld It connects;
The longitudinal platform secondary beam of construction and horizontal platform secondary beam: it after girder I and girder II are installed, is lifted using lifting equipment Secondary beam successively installs connecting plate II, installation bolt, then welded seam;Other longitudinal platform secondary beams, horizontal platform in the platform Secondary beam mounting means is identical;
D, it constructs two-layer platform, the component mounting means same layer platform in two-layer platform;
E, two-layer platform starts to weld the component in one layer of platform after the installation is completed;First soldering frame is set a roof beam in place and steel column I, steel column The beam upper end weld seam of II connection, then welded grider lower end weld seam;
Step 3: upper brace and component installation
A, while Member Welding in one layer of platform, start that upper prop I, upper prop II, upper prop III are installed, and respectively under Column I, lower prop II, III butt welding of lower prop;
B, the component in three layers of platform, mounting means same layer platform and two-layer platform are installed;
C, the component in three layers of platform after the installation is completed, then carries out Vierendeel girder in two-layer platform and steel column I, steel column II connect The welding of the beam upper end weld seam, beam lower end weld seam that connect, the welding manner of welding manner same layer platform;
D, the component installation in four layers of platform is carried out, mounting means is identical with above one layer of platform, then carries out three layers of platform Interior Vierendeel girder connecting welding work;
E, the Vierendeel girder connecting welding work in four layers of platform is finally carried out;
F, back-grouting work is carried out to the suspension column of lower prop I, lower prop II, lower prop III.
Further, in above-mentioned steps three the installation centering of upper prop I, upper prop II, upper prop III with the lower prop in step 2, but The centering point of verticality is with upper prop I, upper prop II, III top center of upper prop and lower prop I, lower prop II, III suspension column center pair of lower prop It should be worth.
Compared with prior art, the invention has the benefit that
1) verticality of steel column is influenced this method avoids welding deformation is caused due to the concentration welding because of Vierendeel girder, then The difficulty for causing upper platform to install guarantees the orderly progress of erecting and welding, improves construction efficiency and installation accuracy;
2) present invention improves product quality and working efficiency, significantly reduces security risk, reduces large-scale crane Using working hour, engineering cost is reduced;With practicability and operability.
Detailed description of the invention
Fig. 1 is the elevation of steel structure platform construction of the present invention;
Fig. 2 is the top view of steel structure platform construction of the present invention;
Fig. 3 is beam-column scheme of installation of the present invention;
Fig. 4 is the scheme of installation of middle girder and secondary beam of the present invention;
In figure:
1- steel-column foundation, 2- lower prop I, 3- lower prop II, 4- lower prop III, mono- layer of platform of 5-, 6- two-layer platform, 7- steel column, 8- Longitudinal framing beam, 9- transverse frame beam, the longitudinal direction 10- platform secondary beam, 11- horizontal platform secondary beam, 12- upper prop I, 13- upper prop II, 14- upper prop III, tri- layers of platform of 15-, tetra- layers of platform of 16-, 17- once grouting, 18- back-grouting, 19- steel column I, 20- steel column II, 21- Vierendeel girder, 22- connecting plate I, 23- high-strength bolt, 24- beam upper end weld seam, 25- beam lower end weld seam, 26- girder I, 27- girder II, 28- connecting plate II, 29- install bolt, 30- weld seam, 31- secondary beam.
Specific embodiment
To further describe the present invention, below with reference to implementing, the invention will be further described with attached drawing.
As shown in Figures 1 to 4, a kind of steel-making tower steel structure platform of the present invention is staggered installation of welding method, is to utilize The welding deformation generated due to welding concentrated stress is resisted in supporting role of halfpace during interlayer stage+module, Construction procedure is as follows:
Step 1: preparation of construction
A, surveying setting-out carries out repetition measurement to steel-column foundation 1 using theodolite and level, carries out repetition measurement and is to ensure that steel column hangs down The premise of straight degree installation quality, then measuring go out the vertically and horizontally center line of steel-column foundation 1;
B, component site acceptance checks the component marched into the arena, and the size of component carries out repetition measurement and is identified.
Step 2: lower platform and component installation
A, lower prop I 2, lower prop II 3, lower prop III 4 are successively lifted, measures lower prop I 2, lower prop II using theodolite and level 3, the verticality and absolute altitude of lower prop III 4 should carry out the measurement of verticality from capital to suspension column;
B, once grouting 17 is carried out to lower prop I 2, lower prop II 3, lower prop III 4 after centering, grouting height control is away from steel 1 upper surface of column foundation about 200mm, to guarantee the stability of steel column;
C, one layer of platform 5 of construction:
Construction transverse frame beam 9 and longitudinal framing beam 8: the first installation transverse frame beam between lower prop I 2 and lower prop II 3 9, Vierendeel girder 21 is lifted to the bracket upper surface of steel column I 19 and steel column II 20 using lifting equipment, makes Vierendeel girder 21 and steel column I 19 and steel column II 20 keep horizontal, connecting plate I 22 is installed and high-strength bolt 23 that two sides take, high-strength bolt 23 need to be by just twisting It is twisted with whole;
Longitudinal framing beam 8 is identical with the installation mode of transverse frame beam 9 as the connection type of steel column 7;In this way, longitudinal Vierendeel girder 8, transverse frame beam 9 are integral by lower prop I 2, lower prop II 3, the connection of lower prop III 4, and connection type is the company of high-strength bolt 23 It connects, wouldn't weld;
The longitudinal platform secondary beam 10 of construction and horizontal platform secondary beam 11: after girder I 26 and girder II 27 are installed, lifting is utilized Equipment hoisting secondary beam 31 successively installs connecting plate II 28, installation bolt 29, then welded seam 30;Other longitudinal directions in the platform Platform secondary beam 10,11 mounting means of horizontal platform secondary beam are same;
D, it constructs two-layer platform 6, the component mounting means same layer platform 5 in two-layer platform 6;
E, two-layer platform 6 starts to weld the component in one layer of platform 5 after the installation is completed;First soldering frame set a roof beam in place 21 with steel column I 19, the beam upper end weld seam 24 that steel column II 20 connects, then welded grider lower end weld seam 25;
Step 3: upper brace and component installation
A, while Member Welding in one layer of platform 5, start that upper prop I 12, upper prop II 13, upper prop III 14 are installed, and Respectively with lower prop I 2, lower prop II 3, III 4 butt welding of lower prop;
B, the component in three layers of platform 15, mounting means same layer platform 5 and two-layer platform 6 are installed;
C, the component in three layers of platform 15 after the installation is completed, then carry out Vierendeel girder 21 in two-layer platform 6 and steel column I 19, The welding of beam upper end weld seam 24, beam lower end weld seam 25 that steel column II 20 connects, the welding manner of welding manner same layer platform 5;
D, the component installation in four layers of platform 16 is carried out, mounting means is identical with above one layer of platform 5, then carries out three layers and put down 21 connecting welding of Vierendeel girder work in platform 15;
E, 21 connecting welding of the Vierendeel girder work in four layers of platform 16 is finally carried out;
F, back-grouting 18 is carried out to the suspension column of lower prop I 2, lower prop II 3, lower prop III 4 to work.
In the present embodiment, in step 3 the installation centering of upper prop I 12, upper prop II 13, upper prop III 14 in step 2 Lower prop, but the centering point of verticality be with upper prop I 12, upper prop II 13, III 14 top center of upper prop and lower prop I 2, lower prop II 3, under III 4 suspension column center respective value of column.
In the present embodiment, the welding of Vierendeel girder 21 carries out after stage+module above it, and two-layer platform 6 is pacified Install and finish one layer of platform 5 of welding, the construction of three layers of platform 15 finishes welding two-layer platform 6, and so on until the last layer platform Welding is completed.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.

Claims (2)

1. a kind of steel-making tower steel structure platform is staggered installation of welding method, it is characterized in that: flat in interlayer using halfpace The welding deformation generated due to welding concentrated stress is resisted in supporting role in platform installation process, and construction procedure is as follows:
Step 1: preparation of construction
A, surveying setting-out carries out repetition measurement to steel-column foundation (1) using theodolite and level, and measuring goes out the vertical of steel-column foundation (1) Cross central line;
B, component site acceptance checks the component marched into the arena, and the size of component carries out repetition measurement and is identified;
Step 2: lower platform and component installation
A, successively lift lower prop I (2), lower prop II (3), lower prop III (4), using theodolite and level measurement lower prop I (2), under Column II (3), the verticality of lower prop III (4) and absolute altitude;
B, once grouting (17) are carried out to lower prop I (2), lower prop II (3), lower prop III (4) after centering, grouting height control exists Away from steel-column foundation (1) upper surface 200mm;
C, one layer of platform (5) of construction:
Construction transverse frame beam (9) and longitudinal framing beam (8): the first installation transverse direction frame between lower prop I (2) and lower prop II (3) It sets a roof beam in place (9), Vierendeel girder (21) is lifted to the bracket upper surface of steel column I (19) and steel column II (20) using lifting equipment, make frame It sets a roof beam in place (21) and steel column I (19) and steel column II (20) holding is horizontal, the high-strength bolt that connecting plate I (22) and two sides take is installed (23), high-strength bolt (23) need to be by just twisting and twisting eventually;
Longitudinal framing beam (8) is identical with the installation mode of transverse frame beam (9) as the connection type of steel column (7);In this way, vertical To Vierendeel girder (8), transverse frame beam (9) that lower prop I (2), lower prop II (3), lower prop III (4) connection is integral, connection type is High-strength bolt (23) connection, wouldn't weld;
The longitudinal platform secondary beam (10) of construction and horizontal platform secondary beam (11): it after girder I (26) and girder II (27) installation, utilizes Lifting equipment lifts secondary beam (31), successively installs connecting plate II (28), installation bolt (29), then welded seam (30);The platform The longitudinal platform secondary beams (10) of interior other, horizontal platform secondary beam (11) mounting means are identical;
D, it constructs two-layer platform (6), the component mounting means same layer platform (5) in two-layer platform (6);
E, two-layer platform (6) starts to weld the component in one layer of platform (5) after the installation is completed;First soldering frame is set a roof beam in place (21) and steel column The beam upper end weld seam (24) that I (19), steel column II (20) connect, then welded grider lower end weld seam (25);
Step 3: upper brace and component installation
A, while Member Welding in one layer of platform (5), start that upper prop I (12), upper prop II (13), upper prop III are installed (14), and respectively with lower prop I (2), lower prop II (3), lower prop III (4) butt welding;
B, the component in three layers of platform (15), mounting means same layer platform (5) and two-layer platform (6) are installed;
C, the component in three layers of platform (15) after the installation is completed, then carries out Vierendeel girder (21) in two-layer platform (6) and steel column I (19), the welding of the beam upper end weld seam (24), beam lower end weld seam (25) of steel column II (20) connection, welding manner same layer platform (5) welding manner;
D, the component installation in four layers of platform (16) is carried out, mounting means is identical with above one layer platform (5), then carries out three layers and put down Vierendeel girder (21) connecting welding work in platform (15);
E, Vierendeel girder (21) the connecting welding work in four layers of platform (16) is finally carried out;
F, back-grouting (18) work is carried out to the suspension column of lower prop I (2), lower prop II (3), lower prop III (4).
2. a kind of steel-making tower steel structure platform according to claim 1 is staggered installation of welding method, it is characterized in that: step Upper prop I (12) in rapid three, upper prop II (13), upper prop III (14) installation centering with the lower prop in step 2, but verticality is looked for It is with upper prop I (12), upper prop II (13), upper prop III (14) top center and lower prop I (2), lower prop II (3), lower prop III (4) on schedule Suspension column center respective value.
CN201710779990.7A 2017-09-01 2017-09-01 A kind of steel-making tower steel structure platform is staggered installation of welding method Active CN107419907B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710779990.7A CN107419907B (en) 2017-09-01 2017-09-01 A kind of steel-making tower steel structure platform is staggered installation of welding method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710779990.7A CN107419907B (en) 2017-09-01 2017-09-01 A kind of steel-making tower steel structure platform is staggered installation of welding method

Publications (2)

Publication Number Publication Date
CN107419907A CN107419907A (en) 2017-12-01
CN107419907B true CN107419907B (en) 2019-08-06

Family

ID=60435632

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710779990.7A Active CN107419907B (en) 2017-09-01 2017-09-01 A kind of steel-making tower steel structure platform is staggered installation of welding method

Country Status (1)

Country Link
CN (1) CN107419907B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984637B (en) * 2019-12-09 2021-02-19 中国十七冶集团有限公司 Steel structure modular installation method for steelmaking oxygen lance valve station
CN112127477A (en) * 2020-10-30 2020-12-25 中国十七冶集团有限公司 Large-scale steel-making high-span solid-web type steel column and installation method thereof
CN114045370A (en) * 2021-10-29 2022-02-15 中国华冶科工集团有限公司 Method and device for quickly installing blast furnace body frame

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0932349A (en) * 1995-07-24 1997-02-04 Shimizu Corp Construction method of building
CN104563512A (en) * 2015-01-30 2015-04-29 上海绿地建设(集团)有限公司 Construction method of tall building steel structure
CN104631844A (en) * 2014-12-31 2015-05-20 上海市机械施工集团有限公司 Steel column mounting operation platform and mounting method thereof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0932349A (en) * 1995-07-24 1997-02-04 Shimizu Corp Construction method of building
CN104631844A (en) * 2014-12-31 2015-05-20 上海市机械施工集团有限公司 Steel column mounting operation platform and mounting method thereof
CN104563512A (en) * 2015-01-30 2015-04-29 上海绿地建设(集团)有限公司 Construction method of tall building steel structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
某转炉炼钢厂塔楼改建工程钢结构安装技术;李俊龙;《施工技术》;20140131;第43卷(第2期);全文 *
韶钢三钢3号转炉工程塔楼钢结构安装施工技术;李俊龙;《南方金属》;20090430;全文 *

Also Published As

Publication number Publication date
CN107419907A (en) 2017-12-01

Similar Documents

Publication Publication Date Title
CN102864936B (en) Combination lifting construction method for large-scale high hollow building roof of steel structure
CN103291076A (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
CN107419907B (en) A kind of steel-making tower steel structure platform is staggered installation of welding method
CN207294093U (en) A kind of large span steel truss integral lifting apparatus
CN102337782B (en) Lift system for constructing truss platform on top of tall and large space
CN105970819A (en) Installation construction method for steel anchor beams
CN103216103A (en) Pre-deformation construction method for mounting oblique-arc-shaped combined steel-structured column of annular roof
CN205558306U (en) Big profiled steel structure vestibule hoist and mount hoisting frame
CN105804400A (en) Curved surface net frame lifting construction method
CN110984637B (en) Steel structure modular installation method for steelmaking oxygen lance valve station
CN110562868A (en) Hoisting construction method for unit type glass curtain wall of super high-rise building
CN106544959B (en) The construction method of king-tower lifting segment and bridge main tower saddle containing saddle
CN111794529A (en) Modular construction hoisting method for arch type space pipe truss steel structure system
CN105040591A (en) Positioning device for waveform steel web and positioning method thereof
CN102226497B (en) Manufacturing method of large rubber rolling curtain sealed dry-type gas holder
CN113914223A (en) High-pier arc-shaped upper cross beam light-weight bracket system and mounting method thereof
CN107675792A (en) Steel construction is encorbelmented gallery structure and construction method
CN104018680A (en) Lifting method of large-span solid-web type arc beam
CN216007760U (en) Non-counterweight ultrahigh hanging basket suspension device
CN113404199B (en) Installation method of umbrella-shaped roof structure
CN203486787U (en) Integral lifting device for cabinet top of Wiggins coal gas cabinet
CN209179519U (en) Hang the truss splicing steel construction moulding bed of auxiliary installation in a kind of gymnasium top
CN104912339B (en) Long-distance multi-span welding H-section steel roof beam installation method
CN102259794A (en) Method for installing overall combined type crane beam
CN206844680U (en) Steel gallery ground assembly load transfer device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant