CN107675792A - Steel construction is encorbelmented gallery structure and construction method - Google Patents

Steel construction is encorbelmented gallery structure and construction method Download PDF

Info

Publication number
CN107675792A
CN107675792A CN201710804338.6A CN201710804338A CN107675792A CN 107675792 A CN107675792 A CN 107675792A CN 201710804338 A CN201710804338 A CN 201710804338A CN 107675792 A CN107675792 A CN 107675792A
Authority
CN
China
Prior art keywords
plate
steel
connection
cross column
vestibule
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710804338.6A
Other languages
Chinese (zh)
Inventor
王新泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Jiangrun Technology Co Ltd
Original Assignee
Hangzhou Jiangrun Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Jiangrun Technology Co Ltd filed Critical Hangzhou Jiangrun Technology Co Ltd
Priority to CN201710804338.6A priority Critical patent/CN107675792A/en
Publication of CN107675792A publication Critical patent/CN107675792A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0046Loggias
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • E04B2001/2406Connection nodes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • E04B2001/2418Details of bolting

Abstract

Encorbelmented gallery structure, including cross column the present invention relates to a kind of steel construction, built-in connection, steel construction is encorbelmented vestibule and interim lifting securing plate;The cross column is made up of floor, securing plate, link bolt hole, upright post connecting plate, raising plate and cross column end plate;The cross column is connected by cross column bottom plate with ground, with jack Dock With Precision Position when cross column connects post;Encorbelmented vestibule bolt connection by floor built-in connection, pre-buried stabiliser bar and steel construction;Steel construction vestibule one end of encorbelmenting is connected with built-in connection, and the other end is supported on cross column, and steel construction is encorbelmented and enriched with box girder end plate and connection box girder bolt connection, intermediate gaps with backing plate between vestibule.The beneficial effects of the invention are as follows:It is slow to solve Steel corridor speed of application, easily topples during construction, security is low, the technical barrier such as construction cost height.

Description

Steel construction is encorbelmented gallery structure and construction method
Technical field
Encorbelmented vestibule construction method for lifting whole and device the present invention relates to a kind of multi-storey steel structure, belong to Construction of Steel Structure Technical field.
Background technology
With the fast development of domestic city process, construction technology progress is very fast.Large-scale steel structure engineering is last decade Come field with fastest developing speed, therefore class engineering industry, commercialized degree are high, comprehensive benefit is good.The Construction of Steel Structure time is short, uses It can be produced in the steel structure member of construction in factory, assembly is completed at scene, greatly shortens the time of construction.And steel construction is built The construction material built can realize regeneration again, can so reduce substantial amounts of building waste, realize sustainable development.Construction The Normal practice of large-scale steel structure engineering is lifted using single member, and the way construction period is longer, complex procedures, and construction is existing Field high-strength bolt, solder design quality are difficult to control, and construction safety hidden danger is big.Especially center of gravity is located at the outer multilayer abnormity knot of plane Structure, easily turn on one's side during construction, cause security incident.To ensure the rapid construction of multi-storey steel structure, and reach quality And safety requirements, it is necessary to there is a kind of new technology to solve problem above.
The content of the invention
Encorbelmented gallery structure and construction party in view of the above-mentioned deficiencies in the prior art, it is an object of the present invention to provide a kind of steel construction Method.In order to realize above-mentioned technical purpose, present invention employs following technical scheme:
A kind of steel construction is encorbelmented gallery structure, including:Cross column, built-in connection, steel construction, which is encorbelmented, vestibule and to be faced When lift securing plate;The cross column is by floor, securing plate, link bolt hole, upright post connecting plate, raising plate and cross Column end plate forms;The cross column is connected by cross column bottom plate with ground, with thousand when cross column connects post Jin top Dock With Precision Position;Encorbelmented vestibule bolt connection by floor built-in connection, pre-buried stabiliser bar and steel construction;The steel construction Vestibule one end of encorbelmenting is connected with built-in connection, and the other end is supported on cross column, and steel construction, which is encorbelmented, uses case between vestibule Shape girder end plate and connection box girder bolt connection, intermediate gaps are enriched with backing plate;The steel construction encorbelment vestibule lifting when By the use of roller temporary support plate as hanging the drawing strong point, pull-up steel plate, lower supporting steel plate are supporting fixed built-in connection.
The cross column bottom plate is connected by bolt hole A, bolt A with ground, and I-steel fix bar and M shaped steel are fixed Part is as connection reinforcement part.
Steel construction vestibule one end of encorbelmenting is placed on cross column, be welded with advance on cross column top plate and plus Rib;Packing ring and bolt D and steel construction vestibule of encorbelmenting are installed on cross column to be fixedly connected, two steel constructions are encorbelmented vestibule With box girder end plate and connection box girder bolt connection, between hole encrypted with backing plate.
Steel construction is encorbelmented the construction method of gallery structure, including following construction procedure:
Step 1: construction is completed:Pre-buried stabiliser bar is embedded in concrete wall surface, and front-back wall has setting, in advance The pre-buried stabiliser bar through hole for burying stabiliser bar through built-in connection forms overall structure, lower supporting steel plate one end and pre-embedded steel slab Connection, the other end and built-in connection bolt connection;
Step 2: cross column installation:Stud is measured, cross column passes through cross column bottom plate and ground Face is connected, and when cross column connects post, raising plate is jacked to adjust with upright post connecting plate connection cross column, and with jack Cross column orientation;
Step 3: steel construction is encorbelmented, vestibule ground connects:I-steel secondary beam shape of bolt connecting box girder, face on box girder When connection interim lifting securing plate, interim hoisting ring, steel construction vestibule of encorbelmenting uses between basement roof and basement bottom board Temperature pier post is reinforced, and steel construction vestibule bottom of encorbelmenting is lined with temporary cushion block;
The vestibule lifting connection Step 4: steel construction is encorbelmented:Roller temporary support plate is bolted installed in pre-buried company Tensed on fitting and with pull-up steel plate, fixed block be installed with the interim fixed plate of pulley, bolt E on roller temporary support plate, Installation hoist engine, tower crane are set up in installation, and the interim lifting securing plate of steel wire rope connection, interim hoisting ring start to be promoted to specific bit Put, steel construction vestibule one end of encorbelmenting is placed on cross column to be connected one end with cross column and be connected with built-in connection and is used in combination Reinforcement of weld steel plate welds afterwards;
Step 5: construction is completed:Remove hoist engine, tower crane, roller temporary support plate and device, basement face thereon When reinforced column and pull-up steel plate.
The beneficial effects of the invention are as follows:It is slow to solve Steel corridor speed of application, easily topples during construction, security is low, The technical barriers such as construction cost height.
Brief description of the drawings
Fig. 1 is that steel construction of the present invention is encorbelmented the schematic diagram of gallery structure installation.
Fig. 2 is pile extension drawing A of the present invention cross-sectional view.
Fig. 3 is cross upright horizontal structure chart.
Fig. 4 is built-in connection structure chart.
Fig. 5 is column bottom surface section B-B figure.
Fig. 6 is the ground spliced installation top view of vestibule.
Fig. 7 is box girder end plate sectional view.
Fig. 8 is the construction completion figure of construction method step one.
Fig. 9 is the cross column installation diagram of construction method step two.
Figure 10 is that the steel construction of construction method step three is encorbelmented vestibule ground connection figure.
Figure 11 be construction method step four steel construction encorbelment vestibule lifting connection figure.
Figure 12 is the construction completion figure of construction method step five.
In figure:1- hoist engines, 2- tower cranes, 3- steel wire ropes, 4- I-steel fix bars, 5-M shaped steel fixtures, 6- bolt hole A, The cross column bottom plates of 7- bolts A, 8-, the cross columns of 9-, 10- floors, 11- securing plates, 12- link bolt hole, 13- thousand Jin top, 14- upright post connecting plates, 15- raising plates, 16- bolts hole B, 17- bolt B, 18- built-in connections, 19- bolt hole C, 20- I-steel secondary beams, 21- box girders, 22- bolt fixed connecting plates, 23- bolts C, 24- lift securing plate temporarily, and 25- faces When hoisting ring, 26- pre-embedded steel slabs, the pre-buried stabiliser bars of 27-, 28- pull-up steel plates, supporting steel plate under 29-, 30- roller temporary supports Plate, 31- pulleys, 32- truss frame for connecting, 33- bolts D, 34- packing ring, 35- backing plates, 36- top plates, 37- ribbed stiffeners, 38- connecting boxs Shape girder bolt, the cross column end plates of 39-, 40- box girder end plates, 41- connection box girder bolts hole, 42- pulleys face When fixed plate, 43- bolts E, 44- basement bottom board, 45- basement temperature pier posts, 46- basement roofs, 47- is pre-buried steady Fixed pole through hole, 48- temporary cushion blocks, reinforcement of weld steel plate after 49-, 50- floorboards, 51- steel constructions are encorbelmented vestibule.
Embodiment
I-steel secondary beam design parameter and construction technical requirement, cross column design parameter and construction technical requirement, add Rib meets manufacture craft of steel plate etc., is not repeated in present embodiment, and emphasis illustrates that the present invention relates to the embodiment party of structure Formula.
Fig. 1 is that steel construction of the present invention is encorbelmented the schematic diagram of gallery structure installation.Steel construction shown in reference picture 1 is encorbelmented Vestibule attachment structure, including cross column 9 and steel construction are encorbelmented vestibule 51.
According to design requirement, pre-buried stabiliser bar 27 is embedded in concrete wall surface, and front-back wall has setting, pre-buried stabilization Bar 27 through built-in connection 18 pre-buried stabiliser bar through hole 47 formed overall structure, lower one end of supporting steel plate 29 with it is pre-buried Steel plate 26 connects, the other end and the bolt connection of built-in connection 18.Stud is measured, cross column 9 is by cross Column bottom plate 8 is connected with ground;Cross column connects post:When cross column 9 connects post, with the connection cross of upright post connecting plate 14 Column 9, and raising plate 15 is jacked to adjust the cross orientation of column 9 with jack 13;The shape of bolt connecting box of I-steel secondary beam 20 Girder 21, the interim lifting securing plate 24 of interim connection, interim hoisting ring 25 on box girder 21, because steel construction is encorbelmented vestibule 51 Total quality is big, it is necessary to reinforced between basement roof 46 and basement bottom board 44 with temperature pier post 45, temporary cushion block 48, Steel construction is formed to encorbelment vestibule 51;Roller temporary support plate 30 is bolted on built-in connection 18 and used Draw steel plate 28 to tense, fixed block 31, peace are installed with the interim fixed plate 42 of pulley, bolt E43 on roller temporary support plate 30 Dress sets up installation hoist engine 1, tower crane 2, and steel wire rope 3 connects interim lifting securing plate 24, interim hoisting ring 25 starts to be promoted to finger Positioning is put, and steel construction one end of vestibule 51 of encorbelmenting is placed on cross column 9 and is connected one end and built-in connection with cross column 18 connect and are welded with rear reinforcement of weld steel plate 49;Remove hoist engine 1, tower crane 2, roller temporary support plate 30 and thereon device, Basement temperature pier post 45, pull-up steel plate 28.
Steel construction is encorbelmented the construction method of gallery structure, including following construction procedure:
Step 1: construction is completed:According to design requirement, pre-buried stabiliser bar 27 is embedded in concrete wall surface, and preceding Wall has setting afterwards, and the pre-buried stabiliser bar through hole 47 of pre-buried stabiliser bar 27 through built-in connection 18 forms overall structure, under The one end of supporting steel plate 29 is connected with pre-embedded steel slab 26, the other end and the bolt connection of built-in connection 18.
Step 2: cross column installation:Measure stud, cross column 9 by cross column bottom plate 8 with Ground connects, when cross column 9 connects post, with the connection cross column 9 of upright post connecting plate 14, and with the jacking jacking of jack 13 Plate 15 adjusts the cross orientation of column 9;
Step 3: steel construction is encorbelmented, vestibule ground connects:The shape of bolt connecting box girder 21 of I-steel secondary beam 20, box girder The interim lifting securing plate 24 of interim connection, interim hoisting ring 25 on 21, because the steel construction total quality of vestibule 51 of encorbelmenting is big, need To be reinforced between basement roof 46 and basement bottom board 44 with temperature pier post 45, temporary cushion block 48, form steel construction and hang Choose vestibule 51;
The vestibule lifting connection Step 4: steel construction is encorbelmented:Roller temporary support plate 30 is bolted installed in pre-buried Tensed on connector 18 and with pull-up steel plate 28, with the interim fixed plate 42 of pulley, bolt E43 on roller temporary support plate 30 Fixed block 31 is installed, installation hoist engine 1, tower crane 2 are set up in installation, and steel wire rope 3 connects interim lifting securing plate 24, interim lifting Ring 25 starts to be promoted to specified location, and steel construction one end of vestibule 51 of encorbelmenting is placed on cross column 9 and is connected with cross column One end is connected with built-in connection 18 and welded with rear reinforcement of weld steel plate 49;
Step 5: construction is completed:Remove hoist engine 1, tower crane 2, roller temporary support plate 30 and device, underground thereon Room temperature pier post 45, pull-up steel plate 28.

Claims (4)

  1. The gallery structure 1. a kind of steel construction is encorbelmented, it is characterised in that including:Cross column (9), built-in connection (18), steel Structure is encorbelmented vestibule (51) and interim lifting securing plate (24);The cross column (9) by floor (10), securing plate (11), Link bolt hole (12), upright post connecting plate (14), raising plate (15) and cross column end plate (39) composition;It is described cross vertical Post (9) is connected by cross column bottom plate (8) with ground, with jack (13) Dock With Precision Position when cross column (9) connects post; Encorbelmented vestibule (51) bolt connection by floor built-in connection (18), pre-buried stabiliser bar (27) and steel construction;The steel construction Vestibule (51) one end of encorbelmenting is connected with built-in connection (18), and the other end is supported on cross column (9), and steel construction is encorbelmented company Connected between corridor (51) with box girder end plate (40) and connection box girder bolt (38), intermediate gaps are filled with backing plate (35) It is real;The steel construction encorbelment vestibule (51) lifting when by the use of roller temporary support plate (30) as hanging the drawing strong point, pull-up steel plate (28), lower supporting steel plate (29) is supporting fixed built-in connection (18).
  2. 2. encorbelmented gallery structure based on steel construction described in claim 1, it is characterised in that cross column bottom plate (8) passes through bolt Hole A (6), bolt A (7) are connected with ground, and I-steel fix bar (4) and M shaped steel fixture (5) are used as connection reinforcement part.
  3. 3. encorbelmented gallery structure based on steel construction described in claim 1, it is characterised in that put steel construction vestibule (51) one end of encorbelmenting On cross column (9), top plate (36) and ribbed stiffener (37) are welded with advance on cross column (9);Cross column (9) On packing ring (34) and bolt D (33) and steel construction vestibule (51) of encorbelmenting are installed are fixedly connected, two steel constructions are encorbelmented vestibule (51) with box girder end plate (40) and connection box girder bolt (38) connect, between hole with backing plate (35) encryption.
  4. 4. the construction method for gallery structure of being encorbelmented according to steel construction described in claims 1 to 3 any claim, it is characterised in that Including following construction procedure:
    Step 1: construction is completed:Pre-buried stabiliser bar (27) is embedded in concrete wall surface, and front-back wall has setting, in advance The pre-buried stabiliser bar through hole (47) for burying stabiliser bar (27) through built-in connection (18) forms overall structure, lower supporting steel plate (29) one end is connected with pre-embedded steel slab (26), the other end and built-in connection (18) bolt connection;
    Step 2: cross column installation:Measure stud, cross column (9) by cross column bottom plate (8) with Ground connects, when cross column (9) connects post, with upright post connecting plate (14) connection cross column (9), and with jack (13) Raising plate (15) is jacked to adjust cross column (9) orientation;
    Step 3: steel construction is encorbelmented, vestibule ground connects:I-steel secondary beam (20) shape of bolt connecting box girder (21), box girder (21) interim connection is interim on lifts securing plate (24), interim hoisting ring (25), and steel construction encorbelments vestibule (51) in underground ceiling Reinforced between plate (46) and basement bottom board (44) with temperature pier post (45), steel construction vestibule (51) bottom of encorbelmenting is lined with temporarily Cushion block (48);
    The vestibule lifting connection Step 4: steel construction is encorbelmented:Roller temporary support plate (30) is bolted installed in pre-buried company Tensed on fitting (18) and with pull-up steel plate (28), with the interim fixed plate of pulley (42), spiral shell on roller temporary support plate (30) Bolt E (43) installation fixed blocks (31), install and set up installation hoist engine (1), tower crane (2), the interim lifting of steel wire rope (3) connection adds Gu plate (24), interim hoisting ring (25) start to be promoted to specified location, steel construction encorbelment vestibule (51) one end be placed on it is cross vertical One end is connected on post (9) with cross column to be connected with built-in connection (18) and welded with rear reinforcement of weld steel plate (49);
    Step 5: construction is completed:Remove hoist engine (1), tower crane (2), roller temporary support plate (30) and thereon device, Lower room temperature pier post (45) and pull-up steel plate (28).
CN201710804338.6A 2017-09-08 2017-09-08 Steel construction is encorbelmented gallery structure and construction method Withdrawn CN107675792A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710804338.6A CN107675792A (en) 2017-09-08 2017-09-08 Steel construction is encorbelmented gallery structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710804338.6A CN107675792A (en) 2017-09-08 2017-09-08 Steel construction is encorbelmented gallery structure and construction method

Publications (1)

Publication Number Publication Date
CN107675792A true CN107675792A (en) 2018-02-09

Family

ID=61135210

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710804338.6A Withdrawn CN107675792A (en) 2017-09-08 2017-09-08 Steel construction is encorbelmented gallery structure and construction method

Country Status (1)

Country Link
CN (1) CN107675792A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111550060A (en) * 2020-05-14 2020-08-18 广东粤能工程管理有限公司 Construction method of overhanging steel pipe column
CN112523342A (en) * 2020-12-24 2021-03-19 中建五局华东建设有限公司 Steel structure corridor with good wind resistance and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111550060A (en) * 2020-05-14 2020-08-18 广东粤能工程管理有限公司 Construction method of overhanging steel pipe column
CN112523342A (en) * 2020-12-24 2021-03-19 中建五局华东建设有限公司 Steel structure corridor with good wind resistance and construction method thereof

Similar Documents

Publication Publication Date Title
CN103291076B (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
WO1998015696A1 (en) A method of lifting structure from above to below
CN103469724B (en) A kind of steel structure bridge of the foundational system with controlled sedimentation and construction method thereof
CN107090975A (en) A kind of big across the cast-in-situ concrete beam Bailey bracket formwork construction method of superelevation
CN201367728Y (en) Derrick-less hydraulic slip form device used for reinforced concrete water tower supporting tube construction
CN103510541B (en) In a kind of mast-up hole, the device of steel pipe column is installed in lifting
CN105442839A (en) Erecting method of cantilever structure formwork bent
CN110562868B (en) Hoisting construction method for unit type glass curtain wall of super high-rise building
CN107013038A (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN103643800A (en) Lifting installation system for buckling restrained supporting member and construction method thereof
CN102337782B (en) Lift system for constructing truss platform on top of tall and large space
CN103122691A (en) Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method
CN107675792A (en) Steel construction is encorbelmented gallery structure and construction method
CN107419907B (en) A kind of steel-making tower steel structure platform is staggered installation of welding method
CN107816209B (en) The large-scale Roof Truss construction technology of installation is lifted across outer two sides
CN110318468B (en) Auxiliary device and method for installing eccentric space net rack
CN110656723B (en) Rail support for sliding construction of cylindrical arch shell roof
CN207499143U (en) Steel construction overhangs gallery structure
CN209179519U (en) Hang the truss splicing steel construction moulding bed of auxiliary installation in a kind of gymnasium top
CN211473320U (en) Tool type external hanging rack for corridor
CN213572930U (en) Self-locking hinged elevator shaft construction platform device
CN106368434A (en) Supporting device for pumping tube of concrete pumping equipment and construction method
CN108951643B (en) Super high-rise deep foundation pit basement core tube large-span large-area support changing construction method
CN112854702A (en) Large-span silo roof construction platform and erection method
CN203320922U (en) Supporting device for forming of elevator shaft template

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20180209

WW01 Invention patent application withdrawn after publication