CN205557816U - A hoisting frame for hoist and mount of large -scale truss - Google Patents

A hoisting frame for hoist and mount of large -scale truss Download PDF

Info

Publication number
CN205557816U
CN205557816U CN201620077672.7U CN201620077672U CN205557816U CN 205557816 U CN205557816 U CN 205557816U CN 201620077672 U CN201620077672 U CN 201620077672U CN 205557816 U CN205557816 U CN 205557816U
Authority
CN
China
Prior art keywords
truss
lifting
hoisting frame
hoisting
section steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620077672.7U
Other languages
Chinese (zh)
Inventor
闫慧清
孙明华
李江舵
刘林斌
马特
车向阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Airport Construction Group Co Ltd
Original Assignee
China Railway Airport Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Airport Construction Group Co Ltd filed Critical China Railway Airport Construction Group Co Ltd
Priority to CN201620077672.7U priority Critical patent/CN205557816U/en
Application granted granted Critical
Publication of CN205557816U publication Critical patent/CN205557816U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

一种用于大型桁架吊装的提升架,提供吊装的提升点,将桁架提升至主体结构的预定高度,包括水平伸出主体结构的两根预埋型钢梁,两根预埋型钢梁的预埋高度及外挑长度都相等,其端部梁体的两侧各焊接一个用于固定千斤顶的箱型牛腿;两根预埋型钢梁之间连接有抗扭钢梁;还包括支撑在预埋型钢梁外端与主体结构2之间的桁架立面斜撑,以及从主体结构伸出后与桁架立面斜撑连接固定的劲性柱连接牛腿。抗扭钢梁两端分别与两根预埋型钢梁之间的两个箱型牛腿全熔透焊接。本实用新型设计合理,结构简单,强度大,施工时抗扭钢梁有助于保持四个吊点同步提升,有效解决了大型钢连廊桁架吊装过程中由于面积大、自重大而带来的平衡性差的问题。

A hoisting frame for hoisting large trusses, providing lifting points for hoisting, and hoisting the trusses to a predetermined height of the main structure, including two pre-embedded steel beams extending horizontally from the main structure, and two pre-embedded steel beams The pre-embedded height and overhanging length are equal, and a box-shaped corbel for fixing the jack is welded on both sides of the end beam body; a torsion-resistant steel beam is connected between the two pre-embedded steel beams; The truss façade bracing between the outer end of the pre-embedded steel beam and the main structure 2, and the stiff column connection corbel connected and fixed with the truss façade bracing after protruding from the main structure. The two ends of the torsion-resistant steel beam are fully penetration welded to the two box-shaped corbels between the two pre-embedded steel beams. The utility model has the advantages of reasonable design, simple structure and high strength. During construction, the torsion-resistant steel beam helps to keep the four lifting points lifted synchronously, and effectively solves the problems caused by the large area and self-heavyness during the hoisting process of the large-scale steel corridor truss. Poor balance issues.

Description

一种用于大型桁架吊装的提升架 A lifting frame used for hoisting large trusses

技术领域 technical field

本实用新型涉及桁架吊装施工技术领域,具体涉及一种用于大型桁架吊装的提升架。 The utility model relates to the technical field of truss hoisting construction, in particular to a lifting frame used for hoisting large trusses.

背景技术 Background technique

大型桁架在复杂高层建筑结构体系中应用广泛,其跨度有几米长,也有几十米长。由于一般采用钢结构材料制作,自重极大,目前,大型桁架一般采用地面拼装后整体提升的方法,但在整体进行提升时,由于桁架占地面积大、自重大,吊装过程对提升架体的整体轻度要求极高,且由于跨度大、占地面积大,一般需设置多个吊点同时起吊,吊装过程中极易出现平衡性不易控制或安全性不能保证的技术难题,难以快速进行吊装施工。 Large-scale trusses are widely used in complex high-rise building structural systems, and their spans are several meters long or tens of meters long. Because it is generally made of steel structure materials, its own weight is extremely large. At present, large-scale trusses generally adopt the method of overall lifting after assembling on the ground. The overall lightness requirements are extremely high, and due to the large span and large footprint, it is generally necessary to set up multiple lifting points to lift at the same time. During the lifting process, technical problems such as difficult balance control or safety cannot be guaranteed, making it difficult to quickly lift construction.

实用新型内容 Utility model content

本实用新型的目的是提供一种用于大型桁架吊装的提升架,解决现有技术中由于大型钢连廊桁架占地面积大、自重大、稳定性差、难以进行吊装施工的问题,有效解决大型钢连廊桁架吊装过程中极易出现平衡性不易控制、安全性不能保证的技术难题。 The purpose of this utility model is to provide a hoisting frame for large-scale truss hoisting, which solves the problems in the prior art that large-scale steel corridor trusses occupy a large area, are heavy, have poor stability, and are difficult to carry out hoisting construction, and effectively solve large-scale trusses. During the hoisting process of steel corridor trusses, technical problems such as uncontrollable balance and unguaranteed safety are prone to occur.

为实现上述技术目的,本实用新型采取如下技术方案: In order to achieve the above technical purpose, the utility model takes the following technical solutions:

一种用于大型桁架吊装的提升架,提供吊装的提升点,将桁架提升至主体结构的预定高度,其特征在于:包括水平伸出主体结构的两根预埋型钢梁,两根预埋型钢梁的预埋高度及外挑长度都相等,其端部梁体的两侧各焊接一个用于固定千斤顶的箱型牛腿;两根预埋型钢梁之间连接有抗扭钢梁。 A hoisting frame for hoisting large trusses, providing lifting points for hoisting, and hoisting the trusses to a predetermined height of the main structure, characterized in that it includes two pre-embedded steel beams extending horizontally from the main The pre-embedded height and overhanging length of the shaped steel beams are equal, and a box-shaped corbel for fixing the jack is welded on both sides of the end beam body; a torsion-resistant steel beam is connected between the two pre-embedded shaped steel beams .

进一步的,还包括支撑在预埋型钢梁外端与主体结构之间的桁架立面斜撑,以及从主体结构伸出后与桁架立面斜撑连接固定的劲性柱连接牛腿。 Further, it also includes a truss façade bracing supported between the outer end of the pre-embedded steel beam and the main structure, and a stiff column connection corbel connected and fixed with the truss façade bracing after protruding from the main structure.

优选的,所述抗扭钢梁为箱型梁,两端分别与两根预埋型钢梁之间的两个箱型牛腿全熔透焊接。 Preferably, the torsion-resistant steel beam is a box-shaped girder, and the two ends are fully penetrated welded to the two box-shaped corbels between the two pre-embedded steel beams.

所述提升架的整体高度可以等于一个楼层高度,预埋型钢梁的标高与上层的楼板标高相同,桁架立面斜撑的底端标高与下层的楼板标高相同。 The overall height of the lifting frame can be equal to the height of a floor, the elevation of the pre-embedded steel beam is the same as that of the upper floor, and the elevation of the bottom end of the diagonal bracing of the truss facade is the same as that of the lower floor.

提升架的整体高度还可以等于两个楼层高度,预埋型钢梁的标高与上层的楼板标高相同,桁架立面斜撑的底端标高与最下层的楼板标高相同。 The overall height of the lifting frame can also be equal to the height of two floors, the elevation of the embedded steel beam is the same as that of the upper floor, and the elevation of the bottom end of the truss façade brace is the same as that of the lowermost floor.

两根预埋型钢梁的端部设为提升点,共两个提升点,两个提升点之间的距离与大型桁架上两个吊点之间的距离相适应,在提升点处梁体两侧的两个箱型牛腿上各安装一个千斤顶,两台千斤顶并行设置。 The ends of the two pre-embedded steel beams are set as lifting points. There are two lifting points in total. The distance between the two lifting points is adapted to the distance between the two lifting points on the large truss. One jack is respectively installed on the two box-shaped corbels on both sides, and the two jacks are set in parallel.

为增加稳固性,所述千斤顶的底端与箱型牛腿的上端面点焊固定。 In order to increase stability, the bottom end of the jack is spot-welded with the upper surface of the box-shaped corbel.

与现有技术相比,本实用新型的有益效果如下: Compared with the prior art, the beneficial effects of the utility model are as follows:

1、提升架上设抗扭钢梁:预埋型钢梁的端头设为提升点,两个提升点之间焊接抗扭钢梁,抗扭钢梁采用箱型梁,两端分别与两根预埋型钢梁中间的箱型牛腿全熔透焊接,抗扭钢梁的设置大大加强了提升架的强度和稳定性; 1. The torsion-resistant steel beam is installed on the lifting frame: the end of the pre-embedded steel beam is set as the lifting point, and the torsion-resistant steel beam is welded between the two lifting points. The box-shaped corbel in the middle of the pre-buried steel beam is fully penetrated and welded, and the setting of the torsion-resistant steel beam greatly enhances the strength and stability of the lifting frame;

2、强度高:提升点处,提升架的劲性柱牛腿和型钢梁均为高强度预埋结构,千斤顶采取限位措施,将千斤顶的底端与箱型牛腿的上端面点焊固定,保证提升架与主体结构的连接牢固度和强度; 2. High strength: at the lifting point, the rigid column corbel and steel beam of the lifting frame are all high-strength pre-buried structures, and the jack adopts limit measures to spot weld the bottom end of the jack to the upper end of the box corbel Fixed to ensure the firmness and strength of the connection between the lifting frame and the main structure;

综上,本实用新型针对大型钢连廊桁架体型大、自重大、稳定性差的问题,设计了专用的提升架,其强度高,设计合理,方便操作过程控制,稳定性好,对大型桁架的吊装施工具有重要的指导意义,特别适用于四个吊点吊装的大型钢连廊桁架的提升吊装。 To sum up, the utility model aims at the problems of large size, self-heavyness and poor stability of the large-scale steel corridor truss, and designs a special lifting frame, which has high strength, reasonable design, convenient operation process control, and good stability. The hoisting construction has important guiding significance, especially suitable for hoisting and hoisting of large-scale steel corridor trusses hoisted at four hoisting points.

附图说明 Description of drawings

通过结合以下附图所作的详细描述,本实用新型的上述和/或其他方面和优点将变得更清楚和更容易理解,这些附图只是示意性的,并不限制本实用新型,其中: The above-mentioned and/or other aspects and advantages of the present utility model will become clearer and easier to understand through the detailed description in conjunction with the following drawings, which are only schematic and do not limit the utility model, wherein:

图1为本实用新型实施例的提升架的整体结构示意图; Fig. 1 is the overall structure schematic diagram of the lifting frame of the utility model embodiment;

图2为本实用新型实施例的提升架与主体结构2的连接示意图; Fig. 2 is a schematic diagram of the connection between the lifting frame and the main structure 2 of the utility model embodiment;

图3为本实用新型实施例的提升架在吊装完成后与桁架1的连接示意图; Figure 3 is a schematic diagram of the connection between the lifting frame and the truss 1 after the hoisting is completed in the embodiment of the present invention;

附图标记:1-桁架、2-主体结构、3-预埋型钢梁、4-桁架立面斜撑、5-劲性柱连接牛腿、6-钢绞线、7-抗扭钢梁、8-千斤顶、9-楼板、10-箱型牛腿。 Reference signs: 1-truss, 2-main structure, 3-embedded steel beam, 4-truss façade brace, 5-stiff column connection corbel, 6-steel strand, 7-torsion steel beam , 8-jack, 9-floor, 10-box corbel.

具体实施方式 detailed description

下面参照附图描述本实用新型涉及的用于大型桁架吊装的提升架的一个实施例。 An embodiment of the lifting frame used for hoisting large-scale trusses according to the present invention will be described below with reference to the accompanying drawings.

如图1,本实用新型涉及一种用于大型桁架吊装的提升架,提供吊装的提升点,将桁架提升至主体结构2的预定高度,可以依据情况在两侧的主体结构2对称各设置一个提升架,一种用于大型桁架吊装的提升架,提供吊装的提升点,将桁架1提升至主体结构2的预定高度,其特征在于:包括水平伸出主体结构2的两根预埋型钢梁3,两根预埋型钢梁3的预埋高度及外挑长度都相等,其端部梁体的两侧各焊接一个用于固定千斤顶8的箱型牛腿10;两根预埋型钢梁3之间连接有抗扭钢梁7;还包括支撑在预埋型钢梁3外端与主体结构2之间的桁架立面斜撑4,以及从主体结构2伸出后与桁架立面斜撑4连接固定的劲性柱连接牛腿5。所述抗扭钢梁7为箱型梁,两端分别与两根预埋型钢梁3之间的两个箱型牛腿10全熔透焊接。 As shown in Figure 1, the utility model relates to a hoisting frame used for hoisting large trusses, which provides lifting points for hoisting and lifts the trusses to a predetermined height of the main structure 2, and one can be symmetrically arranged on the main structures 2 on both sides according to the situation. Lifting frame, a lifting frame used for hoisting large-scale trusses, provides a lifting point for hoisting, and lifts the truss 1 to the predetermined height of the main structure 2, and is characterized in that it includes two pre-embedded steel bars extending horizontally from the main structure 2 Beam 3, the pre-embedded height and overhanging length of the two pre-embedded steel beams 3 are equal, and a box-shaped corbel 10 for fixing the jack 8 is welded on both sides of the beam body at the end; two pre-embedded steel beams 3 A torsion-resistant steel beam 7 is connected between the steel beams 3; it also includes a truss façade bracing 4 supported between the outer end of the pre-embedded steel beam 3 and the main structure 2, and a truss vertical support after extending from the main structure 2. The face brace 4 is connected to the fixed rigid column and the corbel 5 is connected. The torsion-resistant steel beam 7 is a box-shaped beam, and its two ends are respectively welded with two box-shaped corbels 10 between the two pre-embedded steel beams 3 through full penetration.

预埋型钢梁3的端部设为提升点,共两个提升点,两个提升点之间的距离与大型桁架上两个吊点之间的距离相适应,在提升点处两侧的箱型牛腿10上固定千斤顶8;每个提升点固定两台并行设置的千斤顶8。所述千斤顶8的底端与箱型牛腿10的上端面点焊固定。钢绞线6自上往下穿过提升架的梁体,下行穿过桁架吊点后用锚具固定;液压油泵为千斤顶8提供动力,用于驱动千斤顶8运行;液压控制装置用于控制千斤顶8的运行。 The end of the pre-embedded steel beam 3 is set as a lifting point, and there are two lifting points in total. The distance between the two lifting points is adapted to the distance between the two lifting points on the large truss. Jacks 8 are fixed on the box-shaped corbel 10; two jacks 8 arranged in parallel are fixed at each lifting point. The bottom of the jack 8 is spot welded to the upper surface of the box-shaped corbel 10 . The steel strand 6 passes through the beam body of the lifting frame from top to bottom, and is fixed with an anchor after passing through the lifting point of the truss; the hydraulic oil pump provides power for the jack 8 to drive the operation of the jack 8; the hydraulic control device is used to control the jack 8 runs.

支撑架的高度和形状与实施施工中主体结构的情况及施工受力情况共同决定,本实施例中,可以等于一个楼层高度,其预埋型钢梁3的标高与上层的楼板9标高相同,所述桁架立面斜撑4的底端标高与下层的楼板9标高相同;也可以等于两个楼层高度,所述预埋型钢梁3的标高与上层的楼板9标高相同,所述桁架立面斜撑4的底端标高与最下层的楼板9标高相同。本实施例中,如图2,支撑架的高度等于一个楼层高度。 The height and shape of the support frame are determined jointly with the situation of the main structure and the stress situation of the construction during the construction. In this embodiment, it can be equal to the height of a floor, and the elevation of the pre-embedded steel beam 3 is the same as that of the upper floor slab 9. The elevation of the bottom end of the truss facade bracing 4 is the same as the elevation of the floor 9 of the lower floor; it can also be equal to the height of two floors, the elevation of the embedded steel beam 3 is the same as the elevation of the upper floor 9, and the elevation of the truss vertical The bottom elevation of the face diagonal brace 4 is identical with the floor 9 elevation of the lowest floor. In this embodiment, as shown in Figure 2, the height of the supporting frame is equal to the height of a floor.

本实用新型实施例根据施工现场条件及钢结构整体拼装方案,选择将钢结构连廊地面整体拼装焊接成型后,一次提升就位的施工工艺,本工程采用钢连廊液压整体提升,在提升过程中,各吊点之间的同步控制要求比较严格,各吊点的荷载要控制在与理论计算基本一致的范围内,钢结构整体同步提升过程中,应实时监测各提升吊点的位移,以整体提升的同步位移量控制为主,同时监控各个提升点处力值变化。施工时应对关键位置点位严格监控同时兼顾力值的参考,保证提升时结构位移控制精确,同时提升力值满足设计要求。由于同步提升采用计算机控制,若提升不同步,超出设计值,提升则会自动停止。包括如下步骤: According to the construction site conditions and the overall assembly plan of the steel structure, the embodiment of the utility model chooses the construction process of lifting the steel structure corridor into place at one time after the overall assembly and welding of the ground of the steel structure corridor. Among them, the synchronous control requirements between the lifting points are relatively strict, and the load of each lifting point should be controlled within the range basically consistent with the theoretical calculation. During the synchronous lifting process of the overall steel structure, the displacement of each lifting point should be monitored in real time to ensure The synchronous displacement control of the overall lifting is mainly controlled, and the force value changes at each lifting point are monitored at the same time. During construction, the key positions should be strictly monitored while taking into account the reference of the force value, so as to ensure that the structural displacement control is accurate during lifting, and the lifting force value meets the design requirements. Since the synchronous lifting is controlled by computer, if the lifting is out of sync and exceeds the design value, the lifting will stop automatically. Including the following steps:

步骤一、施工计算解析:施工前对整体设计进行计算解析,保证施工过程的安全性; Step 1. Construction calculation and analysis: calculate and analyze the overall design before construction to ensure the safety of the construction process;

步骤二、现场平面布置:依据施工计算解析的结果,对现场进行平面布置; Step 2. Site layout: according to the results of construction calculation and analysis, carry out the site layout;

步骤三、桁架的制作:进行钢连廊桁架的分单元制作,形成待拼接的单元块; Step 3. Fabrication of trusses: Carry out sub-unit fabrication of steel corridor trusses to form unit blocks to be spliced;

步骤四、辅配件制作:包括在钢连廊桁架上交进行临时加强结构设置; Step 4. Production of auxiliary parts: including temporary reinforcement structure setting on the steel corridor truss;

步骤五、千斤顶提升设备的进场前调试:对千斤顶提升设备进行进场前调试,确认其具备进场条件;本工程提升系统在进场前,在车间必须进行软件、硬件的调试,再进行单机、整体联机调试,确保提升过程的顺利进行,锚具进场须经检验合格,单个千斤顶8提升吨位250吨,采用液压千斤顶整体同步提升技术; Step 5. Pre-entry commissioning of the jack lifting equipment: Debug the jack lifting equipment before entering the site to confirm that it meets the entry conditions; before the lifting system of this project enters the site, the software and hardware must be debugged in the workshop, and then Single machine and overall online debugging to ensure the smooth progress of the lifting process. The anchorage must pass the inspection when entering the site. The tonnage of a single jack 8 is 250 tons, and the overall synchronous lifting technology of hydraulic jacks is adopted;

步骤六、施工平台布置:布置并搭设施工操作平台,操作平台两侧进行安全护栏的安装,安全护栏采用脚手管搭设,并使用安全网进行封闭,经检查验收合格后方可上人实施操作。在提升点千斤顶周边增加焊接钢板保护措施; Step 6. Construction platform layout: Arrange and set up the construction operation platform, and install safety guardrails on both sides of the operation platform. The safety guardrails are erected with scaffolding tubes and closed with safety nets. Only after passing the inspection and acceptance can the operator carry out the operation. Add welded steel protection measures around the lifting point jack;

步骤七、工装设备进场:施工操作平台布置完成后,将质检合格的工装设备进场; Step 7. Tooling equipment enters the site: After the construction operation platform is arranged, the tooling equipment that has passed the quality inspection is brought into the site;

步骤八、桁架的地面拼装:利用底部的支撑胎架,将单元模块拼装成整体; Step 8. Ground assembly of the truss: use the support frame at the bottom to assemble the unit modules into a whole;

步骤九、提升架的安装:提升前,需要对提升支架进行安装,安装严格按照设计图纸进行,分别在主体结构上安装成对的悬挑三角架作为提升架,并在第一提升架和第二提升架内的两个悬挑三角架之间各搭设固定一根抗扭钢梁7; Step 9. Installation of the lifting frame: Before lifting, the lifting bracket needs to be installed. The installation is strictly in accordance with the design drawings. A pair of cantilevered tripods are installed on the main structure as the lifting frame, and the first lifting frame and the second A torsion-resistant steel beam 7 is respectively erected and fixed between the two cantilevered tripods in the second lifting frame;

步骤十、千斤顶提升设备的安装与调试:在提升点位置上安装千斤顶8等提升装置,同时布置液压油泵和液压控制装置,千斤顶8带有一套提升用顶压器、一套锚固用顶压器以及一套安全用自动工具锚,安装各种传感器,连接设备,进行现场空载调试;每个提升点处设有两台千斤顶共同完成工作,并由一台液压油泵控制,即1#、2#千斤顶放在一个提升点处, 3#、4#千斤顶放在一个提升点处,由一台油泵控制2个提升点;5#、6#千斤顶放在一个提升点处;7#、8#千斤顶放在一个提升点处,由一台油泵控制控制2个提升点。施工需要液压泵站2台,液压千斤顶8台。另外配备相应的主控系统1台,分控制箱2台以及若干传感器等设备,施工时泵站放置在已有结构上靠近施工操作点的地方,要在此处放置电闸箱;每组开泵人员站在泵站所在的已有结构上;每组测量人员要站在提前搭好的施工操作平台上,即提升点处,1人观测一个提升点; Step 10. Installation and commissioning of jack lifting equipment: Install jack 8 and other lifting devices at the lifting point, and arrange hydraulic oil pumps and hydraulic control devices at the same time. Jack 8 has a set of lifting pressure devices and a set of anchoring pressure devices And a set of automatic tool anchors for safety, install various sensors, connect equipment, and carry out on-site no-load debugging; each lifting point is equipped with two jacks to complete the work together, and is controlled by a hydraulic oil pump, namely 1#, 2 # Jacks are placed at one lifting point, 3# and 4# jacks are placed at one lifting point, and two lifting points are controlled by one oil pump; 5#, 6# jacks are placed at one lifting point; 7#, 8# The jack is placed at one lifting point, and an oil pump controls two lifting points. Construction requires 2 hydraulic pump stations and 8 hydraulic jacks. In addition, it is equipped with a corresponding main control system, 2 sub-control boxes and several sensors and other equipment. During construction, the pump station is placed on the existing structure close to the construction operation point, and the electric switch box should be placed here; each group of pumps Personnel stand on the existing structure where the pump station is located; each group of surveyors must stand on the construction operation platform set up in advance, that is, at the lifting point, and one person observes one lifting point;

步骤十一、钢绞线6的穿束与预紧:所述钢绞线6自上往下穿过抗扭钢梁7和提升架梁体,下行穿过桁架吊点后用锚具固定,本次使用Φ15.2mm1860级的钢绞线6进行提升,每台千斤顶8采用7根Φ15.2mm1860级的钢绞线6,下料仔细检查钢绞线6,不得有锈蚀、泥污、尘土等,确保提升安全可靠,根据桁架需要提升的高度和提升装置所需的高度对钢绞线6下料,应保证足够的富余长度,以便于钢绞线的穿束; Step 11. Threading and pretensioning of the steel strand 6: the steel strand 6 passes through the torsion-resistant steel beam 7 and the lifting frame beam body from top to bottom, and then passes through the truss hanging point and fixes it with an anchor. This time, Φ15.2mm1860 steel strand 6 is used for lifting, and each jack 8 adopts 7 pieces of Φ15.2mm1860 steel strand 6, and the steel strand 6 is carefully inspected for cutting, and there must be no rust, mud, dust, etc. , to ensure safe and reliable lifting, according to the height of the truss to be lifted and the height required by the lifting device, the steel strand 6 should be unloaded, and sufficient excess length should be ensured to facilitate the penetration of the steel strand;

步骤十二、桁架1的整体试提升:按试提升时的步骤进行,如果发现有不正常现象,马上停止,分析原因,解决后继续进行;施工人员进入各自岗位,所有控制指令全部由主控台下达,试提升的时间应为所有前期准备工作完毕,并依据气象预报选取无风的晴天上午,试提升的高度为30cm,稳定时间为1小时,提升速度5mm/min。对整个提升系统进行全面检查,采取有效措施确保每个吊点每根钢绞线6受力均匀,避免部分钢绞线6处于松弛或受力较小状态,如出现上述现象,应立即对松弛或受力较小的钢绞线6采用千斤顶单独张拉,使其处于张紧状态,以达到每根钢绞线6受力均匀的状态; Step 12. The overall test lifting of truss 1: proceed according to the steps of the test lifting. If any abnormal phenomenon is found, stop immediately, analyze the cause, and continue after solving it; the construction personnel enter their respective positions, and all control instructions are all controlled by the main control The stage is issued, and the time for the trial lifting should be when all preliminary preparations are completed, and a windless sunny morning is selected according to the weather forecast. The height of the trial lifting is 30cm, the stabilization time is 1 hour, and the lifting speed is 5mm/min. Carry out a comprehensive inspection of the entire lifting system, take effective measures to ensure that each steel strand 6 at each lifting point is evenly stressed, and avoid some steel strands 6 being in a state of relaxation or low stress. If the above phenomenon occurs, the slack should be corrected immediately. Or the steel strand 6 with less stress is separately tensioned by a jack to make it in a tensioned state, so as to achieve a state where each steel strand 6 is evenly stressed;

步骤十三、桁架1的整体正式提升:试提升全面检查无误后进入提升过程。按试提升时的步骤进行,如果发现有不正常现象,马上停止,分析原因,解决后继续进行。正常提升时每2米停机一次,检查各点之间误差是否控制在50mm以内,如位移相差过大则对提升较慢点单独供油,以保证各点同步性,为确保提升的同步,在提升现场增加全站仪对结构吊点位移差进行测量,作为辅助测量措施; Step 13, the overall formal lifting of the truss 1: after the trial lifting, the overall inspection is correct and the lifting process is entered. Proceed according to the steps during the trial lifting. If any abnormal phenomenon is found, stop immediately, analyze the cause, and continue after solving it. Stop once every 2 meters during normal lifting, check whether the error between each point is controlled within 50mm, if the displacement difference is too large, supply oil to the slower lifting point separately to ensure the synchronization of each point, in order to ensure the synchronization of lifting, in A total station is added to the lifting site to measure the displacement difference of the structural lifting point as an auxiliary measurement measure;

步骤十四、提升至设计结构标高:待桁架整体提升至设计标高下方50~150mm处时,停止提升; Step 14. Elevate to the design structural elevation: When the overall truss is elevated to 50-150mm below the design elevation, stop the elevation;

步骤十五、标高复测及焊接前的准备:对桁架的整体情况进行复测,其中主要包括桁架的挠度、桁架四个吊点的高差情况,同时对于桁架整体的偏移情况进行复测,制定相应的纠偏措施,此过程中需要上方施工人员与设备控制人员统一协调行动;设备控制人员根据施工人员测量结果点动调整设备进而调整桁架的四点位移,最终达到设定标高; Step 15. Elevation retest and preparation before welding: retest the overall situation of the truss, which mainly includes the deflection of the truss, the height difference of the four lifting points of the truss, and retest the overall offset of the truss , to formulate corresponding corrective measures. In this process, the construction personnel above and the equipment control personnel need to coordinate and act in unison; the equipment control personnel adjust the equipment according to the measurement results of the construction personnel, and then adjust the four-point displacement of the truss, and finally reach the set elevation;

步骤十六、焊接成型,拆除工装:如图3,桁架提升就位后,将桁架与提升架合拢连接,合拢处构件通过塔吊进行安装,腹板用高强螺栓固定,钢梁上下翼缘焊接连接,最后拆卸提升设备及工装,至此,完成整个吊装过程。提升架上的杆件均可以看成是原来钢连廊的一部分,提升就位后各个端部对应焊接,形成完整的刚连廊桁架结构。 Step 16. Welding and forming, removal of tooling: As shown in Figure 3, after the truss is lifted into place, the truss and the lifting frame are closed and connected, and the components at the close are installed by the tower crane, the web is fixed with high-strength bolts, and the upper and lower flanges of the steel beam are welded and connected , and finally disassemble the lifting equipment and tooling, so far, the entire hoisting process is completed. The rods on the lifting frame can be regarded as a part of the original steel corridor. After being lifted into place, each end is welded correspondingly to form a complete rigid corridor truss structure.

上述披露的各技术特征并不限于已披露的与其它特征的组合,本领域技术人员还可根据实用新型之目的进行各技术特征之间的其它组合,以实现本实用新型之目的为准。 The technical features disclosed above are not limited to the disclosed combination with other features, and those skilled in the art can also make other combinations among the technical features according to the purpose of the utility model, which shall prevail in order to achieve the purpose of the utility model.

Claims (7)

1. the hoisting frame for the lifting of large-scale truss, the hoist point of lifting is provided, truss (1) is promoted to the predetermined altitude of agent structure (2), it is characterized in that: include protruding horizontally up two pre-buried section steel beams (3) of agent structure (2), the pre-buried height of two pre-buried section steel beams (3) and to choose outward length the most equal, a box bracket (10) being used for fixing jack (8) is respectively welded in the both sides of its end beam body;Connect between two pre-buried section steel beams (3) and have antitorque girder steel (7).
A kind of hoisting frame lifted for large-scale truss the most according to claim 1, it is characterized in that: also include truss facade diagonal brace (4) being supported between pre-buried section steel beam (3) outer end and agent structure (2), and after agent structure (2) is stretched out, be connected fixing stiffened column connection bracket (5) with truss facade diagonal brace (4).
A kind of hoisting frame lifted for large-scale truss the most according to claim 1 and 2, it is characterised in that: described antitorque girder steel (7) is box beam, the two ends two box bracket (10) full penetrations respectively and between two pre-buried section steel beams (3).
A kind of hoisting frame lifted for large-scale truss the most according to claim 3, it is characterized in that: the whole height of described hoisting frame is equal to a story height, the absolute altitude of pre-buried section steel beam (3) is identical with the floor on upper strata (9) absolute altitude, and the bottom absolute altitude of truss facade diagonal brace (4) is identical with the floor of lower floor (9) absolute altitude.
A kind of hoisting frame lifted for large-scale truss the most according to claim 3, it is characterized in that: the whole height of hoisting frame is equal to two story heights, the absolute altitude of pre-buried section steel beam (3) is identical with the floor on upper strata (9) absolute altitude, and the bottom absolute altitude of truss facade diagonal brace (4) is identical with undermost floor (9) absolute altitude.
6. according to a kind of hoisting frame lifted for large-scale truss described in claim 3 any one, it is characterized in that: the end of two pre-buried section steel beams (3) is set to hoist point, totally two hoist points, in distance between two hoist points and large-scale truss, the distance between two suspension centres adapts, upper one jack (8) of each installation of two box brackets (10) of beam body both sides at hoist point, two jack (8) are arranged parallel.
7. according to a kind of hoisting frame lifted for large-scale truss described in any one of claim 4~6, it is characterised in that: the upper surface spot welding of the bottom of described jack (8) and box bracket (10) is fixed.
CN201620077672.7U 2016-01-27 2016-01-27 A hoisting frame for hoist and mount of large -scale truss Expired - Fee Related CN205557816U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620077672.7U CN205557816U (en) 2016-01-27 2016-01-27 A hoisting frame for hoist and mount of large -scale truss

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620077672.7U CN205557816U (en) 2016-01-27 2016-01-27 A hoisting frame for hoist and mount of large -scale truss

Publications (1)

Publication Number Publication Date
CN205557816U true CN205557816U (en) 2016-09-07

Family

ID=56821451

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620077672.7U Expired - Fee Related CN205557816U (en) 2016-01-27 2016-01-27 A hoisting frame for hoist and mount of large -scale truss

Country Status (1)

Country Link
CN (1) CN205557816U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114182963A (en) * 2021-11-10 2022-03-15 浙江精工钢结构集团有限公司 Construction method for reverse-order layered lifting of plane-overlapped multi-layer large-span truss structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114182963A (en) * 2021-11-10 2022-03-15 浙江精工钢结构集团有限公司 Construction method for reverse-order layered lifting of plane-overlapped multi-layer large-span truss structure

Similar Documents

Publication Publication Date Title
CN205558304U (en) Hoist and mount system of large -scale steel gallery truss
CN103291076B (en) Multilayer steel truss fragmented reverse hoisting construction method in arc-shaped frame
CN106836498B (en) Hoisting construction method for steel truss of grand stand roof of super-large span stadium
CN205558306U (en) Big profiled steel structure vestibule hoist and mount hoisting frame
CN103225408B (en) Construction method for long-span net rack multiple-mast independent type integral lifting
CN201158933Y (en) High-rise maintaining scaffold device with extruding structure
CN105507600A (en) Hoisting system and hoisting construction method for large steel corridor trusses
CN102535845A (en) Construction method of bearing frame of corridor structure
CN102493674B (en) Jacking system for buildings
CN104141383A (en) Bailey beam suspension formwork supporting system and construction method thereof
CN203947771U (en) A kind of Bailey beam pendent form support system
CN102337782B (en) Lift system for constructing truss platform on top of tall and large space
CN111794119B (en) Temporary supporting system and hoisting method for basket type steel box tie bar arch
CN114232805B (en) Construction method of ultrahigh-height large-span steel concrete beam hanging structure
CN203654702U (en) Operating platform for construction of reinforced concrete chimney
CN109610834A (en) The high-altitude construction method of Long-span Multi-storey Frame heavy duty concrete structure
CN110318344B (en) Novel steel box girder No. 0 block support and No. 0 block erection construction method
CN112575948B (en) A roof truss composed of a string beam and a cantilever truss and a construction method thereof
CN114215170A (en) Method for lifting super-altitude giant hanging multi-layer connected structure
CN113186836A (en) Construction method of brand-new prestress integral bridge falsework
CN211034860U (en) Hydraulic lifting construction device for steel structure net rack
CN110905261A (en) Ultra-large-span closed stock ground structure for multiple material piling and taking machines and construction method thereof
CN205557816U (en) A hoisting frame for hoist and mount of large -scale truss
CN103754791A (en) Method for lifting water-tower 1000m<3> water tank by utilizing prestressed strands
CN111620223A (en) Construction method for lifting net rack through secondary stress conversion of support

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160907