CN104631844A - Steel column mounting operation platform and mounting method thereof - Google Patents
Steel column mounting operation platform and mounting method thereof Download PDFInfo
- Publication number
- CN104631844A CN104631844A CN201410854312.9A CN201410854312A CN104631844A CN 104631844 A CN104631844 A CN 104631844A CN 201410854312 A CN201410854312 A CN 201410854312A CN 104631844 A CN104631844 A CN 104631844A
- Authority
- CN
- China
- Prior art keywords
- operation platform
- construction operation
- steel column
- construction
- column fitting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
A steel column mounting operation platform comprises a first construction operation platform, a second construction operation platform and a third construction operation platform. The first construction operation platform further comprises a bearing frame for forming a peripheral closed structure, and a bearing plate arranged on the bearing frame. The second construction operation platform and the third construction operation platform are arranged on the two sides of the first construction operation platform respectively to form an n-shaped structure, the second construction operation platform and the third construction operation platform further comprise bearing frames and bearing plates, the bearing frames are used for forming peripheral closed structures, and the bearing plates are arranged on the bearing frames. By means of the steel column mounting operation platform, the steel column mounting progress is effectively quickened, risk factors in the turning and dismounting process are reduced, in the welding process, personnel are safely in place, a windproof device can be portably erected on the periphery, the platform is beneficial to improvement of quality, cost is saved, and an existing steel pipe rental fee, turning and dismounting labor cost and the like are reduced.
Description
Technical field
The present invention relates to installation of high building technical field of construction, particularly relate to a kind of steel column fitting operation platform and mounting method thereof.
Background technology
At present, in the high-rise installation process of the steel work of routine, column lifting needs to set up a large amount of thick pillar pin hands, thus can form work plane in steel column surrounding, and constructability personnel carry out the work such as the installation of upper joint steel column and electric welding.
Apparently, carry out steel column installation according to existing method, not only the time cycle is long, needs to carry out pin handspring frequently and tears open, and work high above the ground risk is comparatively large, needs full manual type to complete, time-consuming effort, and safety can not get ensureing.In addition, job site pin hand is too much, easily arbitrarily sets up, is unfavorable for standardized management.
Therefore for prior art Problems existing, this case designer is by means of being engaged in the industry experience for many years, and active research improves, so had a kind of steel column fitting operation platform of the present invention and mounting method thereof.
Summary of the invention
The present invention be directed in prior art, carry out steel column installation according to the conventional method, not only the time cycle is long, needs to carry out pin handspring frequently and tears open, and work high above the ground risk is comparatively large, needs full manual type to complete, time-consuming effort, and safety can not get ensureing.In addition, job site pin hand is too much, easily arbitrarily sets up, is unfavorable for that the defects such as standardized management provide a kind of steel column fitting operation platform.
The another object of the present invention is in prior art, and carry out steel column installation according to the conventional method, not only the time cycle is long, need to carry out pin handspring frequently to tear open, and work high above the ground risk is comparatively large, needs full manual type to complete, time-consuming effort, safety can not get ensureing.In addition, job site pin hand is too much, easily arbitrarily sets up, is unfavorable for that the defects such as standardized management provide a kind of mounting method of steel column fitting operation platform.
In order to solve the problem, the invention provides a kind of steel column fitting operation platform, described steel column fitting operation platform, comprising: the first construction operation platform, comprise the bearing frame enclosing structure for the formation of surrounding further, and be arranged on the loaded plate on described bearing frame; Second construction operation platform and the 3rd construction operation platform, described second construction operation platform and described 3rd construction operation platform are separately positioned on the both sides of described first construction operation platform, and form " Π " type structure, and described second construction operation platform and described 3rd construction operation platform comprise the bearing frame enclosing structure for the formation of surrounding all further, and be arranged on the loaded plate on described bearing frame.
Alternatively, described first construction operation platform, the second construction operation platform, and the opening part of " Π " type structure that the 3rd construction operation platform is formed arranges the 4th construction operation platform.
Alternatively, described 4th construction operation platform is steel springboard.
Alternatively, the steel springboard as the 4th construction operation platform is tied up fixing with described 3rd construction operation platform and the second construction operation platform by galvanized wire respectively.
Alternatively, described first construction operation platform, the second construction operation platform, and the peripheral structure of " Π " type structure of being formed of the 3rd construction operation platform and steel column to be installed matches.
Alternatively, described first construction operation platform, the second construction operation platform, and the periphery of " Π " type structure of being formed of the 3rd construction operation platform and described steel column to be installed encircles.
Alternatively, described bearing frame is channel-section steel, and described loaded plate is checkered steel plate.
Alternatively, the first construction operation platform of described steel column fitting operation platform, the second construction operation platform, the 3rd construction operation platform, and the outside of the 4th construction operation platform all arranges safety guide rail.
Alternatively, the steel cat ladder of described construction utensil, catching device are all fixedly installed on the side of described steel column fitting operation platform.
For realizing the another object of the present invention, the invention provides a kind of mounting method of steel column fitting operation platform, the mounting method of described steel column fitting operation platform, comprising:
Perform step S1: connect described first construction operation platform, the second construction operation platform, the 3rd construction operation platform, to form the steel column fitting operation platform in " Π " type structure;
Perform step S2: at the 1 ~ 1.2m place, below apart from steel column top to be installed, four sides welding is shelved with tripod;
Perform step S3: be shelved on described tripod by the steel column fitting operation platform in " Π " type structure described in being connected to form;
Perform step S4: at described first construction operation platform, the second construction operation platform, and the opening part of " Π " type structure that the 3rd construction operation platform is formed arranges the 4th construction operation platform;
Perform step S5: the first construction operation platform of described steel column fitting operation platform, the second construction operation platform, the 3rd construction operation platform, and the outside of the 4th construction operation platform all arranges safety guide rail;
Perform step S5: construction utensil is fixedly installed on the side of described steel column fitting operation platform;
Perform step S6: described steel column fitting operation platform is checked and accepted, and use of listing.
In sum, steel column fitting operation platform of the present invention not only effectively accelerates steel column installation progress, reduce the hazards of turning in the process of tearing open, in welding process, personal security puts in place, and draught exclusion device can be set up at periphery easily, improve favourable to quality, and cost-saving, decrease existing steel pipe rental charge, turn over and tear labour cost etc. open.
Accompanying drawing explanation
Figure 1 shows that the top view of steel column fitting operation platform of the present invention;
Figure 2 shows that the STRUCTURE DECOMPOSITION schematic diagram of steel column fitting operation platform of the present invention.
Detailed description of the invention
By describe in detail the invention technology contents, structural feature, reached object and effect, coordinate accompanying drawing to be described in detail below in conjunction with embodiment.
Refer to Fig. 1, Fig. 2, Figure 1 shows that the top view of steel column fitting operation platform of the present invention.Figure 2 shows that the STRUCTURE DECOMPOSITION schematic diagram of steel column fitting operation platform of the present invention.Shown steel column fitting operation platform 1, comprising: the first construction operation platform 11, described first construction operation platform 11 comprises the bearing frame 111 enclosing structure for the formation of surrounding further, and is arranged on the loaded plate 112 on described bearing frame 111; Second construction operation platform 12 and the 3rd construction operation platform 13, described second construction operation platform 12 and described 3rd construction operation platform 13 are separately positioned on the both sides of described first construction operation platform 11, and form " Π " type structure, and described second construction operation platform 12 and described 3rd construction operation platform 13 comprise the bearing frame 111 enclosing structure for the formation of surrounding all further, and be arranged on the loaded plate 112 on described bearing frame 111.
As the detailed description of the invention of the present invention, preferably, described bearing frame 111 is channel-section steel, and described loaded plate 112 is checkered steel plate.Described first construction operation platform 11, second construction operation platform 12, and the peripheral structure of " Π " type structure of being formed of the 3rd construction operation platform 13 and described steel column 2 to be installed matches.More specifically, i.e. the periphery of " Π " type structure that described first construction operation platform 11, second construction operation platform 12, and the 3rd construction operation platform 13 is formed and described steel column 2 to be installed encircles.
In order to better implement the technical scheme of the present invention, preferably, at described first construction operation platform 11, second construction operation platform 12, and the 3rd opening 113 place of " Π " type structure that formed of construction operation platform 13 the 4th construction operation platform 14 is set, one end of described 4th construction operation platform 14 is connected with one end differing from described first construction operation platform 11 of described second construction operation platform 12, and the other end of described 4th operation platform 14 is connected with one end differing from described first construction operation platform 11 of described 3rd construction operation platform 13.More specifically, described 4th construction operation platform 14 is steel springboard.Steel springboard as the 4th construction operation platform 14 is tied up fixing with described 3rd construction operation platform 13 and the second construction operation platform 12 by galvanized wire (not shown) respectively.
Significantly, described first construction operation platform 11, second construction operation platform 12, the 3rd construction operation platform 13, and described 4th construction operation platform 14 forms the connected operating platform that ring is located at described steel column 10 periphery to be installed, is beneficial to the construction in each orientation.
Simultaneously, in order to strengthen the safety of constructor further, first construction operation platform 11, second construction operation platform 12 of described steel column fitting operation platform 1, the 3rd construction operation platform 13, and the outside of the 4th construction operation platform 14 all arranges safety guide rail (not shown).Described safety guide rail is further steel pipe feet hand, to form four sides enclosed structure system.Described construction utensil, nonrestrictively enumerates, and such as steel cat ladder, catching device are all fixedly installed on the side of described steel column fitting operation platform 1.
In order to disclose the technical scheme of the present invention more intuitively, highlighting the beneficial effect of the present invention, now in conjunction with concrete embodiment, the installation process of described steel column fitting operation platform 1 being set forth.The mounting method of described steel column fitting operation platform 1, comprising:
Perform step S1: connect described first construction operation platform 11, second construction operation platform 12, the 3rd construction operation platform 13, to form the steel column fitting operation platform 1 in " Π " type structure;
Perform step S2: at the 1 ~ 1.2m place, below apart from steel column 2 top to be installed, four sides welding is shelved with tripod 3;
Perform step S3: be shelved on described tripod 3 by the steel column fitting operation platform 1 in " Π " type structure described in being connected to form;
Perform step S4: at described first construction operation platform 11, second construction operation platform 12, and opening 113 place of " Π " type structure that the 3rd construction operation platform 13 is formed arranges the 4th construction operation platform 14;
Perform step S5: the first construction operation platform 11, second construction operation platform 12 of described steel column fitting operation platform 1, the 3rd construction operation platform 13, and the outside of the 4th construction operation platform 14 all arranges safety guide rail;
Perform step S5: construction utensil is fixedly installed on the side of described steel column fitting operation platform 1;
Perform step S6: described steel column fitting operation platform is checked and accepted, and use of listing.
Significantly, steel column fitting operation platform of the present invention not only effectively accelerates steel column installation progress, reduce the hazards of turning in the process of tearing open, in welding process, personal security puts in place, and draught exclusion device can be set up at periphery easily, improve favourable to quality, and cost-saving, decrease existing steel pipe rental charge, turn over and tear labour cost etc. open.
In sum, steel column fitting operation platform of the present invention not only effectively accelerates steel column installation progress, reduce the hazards of turning in the process of tearing open, in welding process, personal security puts in place, and draught exclusion device can be set up at periphery easily, improve favourable to quality, and cost-saving, decrease existing steel pipe rental charge, turn over and tear labour cost etc. open.
Those skilled in the art all should be appreciated that, without departing from the spirit or scope of the present invention, can carry out various modifications and variations to the present invention.Thus, if when any amendment or modification fall in the protection domain of appended claims and equivalent, think that these amendment and modification are contained in the present invention.
Claims (10)
1. a steel column fitting operation platform, is characterized in that, described steel column fitting operation platform, comprising:
First construction operation platform, comprises the bearing frame enclosing structure for the formation of surrounding further, and is arranged on the loaded plate on described bearing frame;
Second construction operation platform and the 3rd construction operation platform, described second construction operation platform and described 3rd construction operation platform are separately positioned on the both sides of described first construction operation platform, and are formed
type structure, and described second construction operation platform and described 3rd construction operation platform comprise the bearing frame enclosing structure for the formation of surrounding all further, and be arranged on the loaded plate on described bearing frame.
2. steel column fitting operation platform as claimed in claim 1, is characterized in that, described first construction operation platform, the second construction operation platform, and the 3rd construction operation platform is formed
the opening part of type structure arranges the 4th construction operation platform.
3. steel column fitting operation platform as claimed in claim 2, it is characterized in that, described 4th construction operation platform is steel springboard.
4. steel column fitting operation platform as claimed in claim 3, it is characterized in that, the steel springboard as the 4th construction operation platform is tied up fixing with described 3rd construction operation platform and the second construction operation platform by galvanized wire respectively.
5. steel column fitting operation platform as claimed in claim 1, is characterized in that, described first construction operation platform, the second construction operation platform, and the 3rd construction operation platform is formed
the peripheral structure of type structure and steel column to be installed matches.
6. steel column fitting operation platform as claimed in claim 5, is characterized in that, described first construction operation platform, the second construction operation platform, and the 3rd construction operation platform is formed
the periphery of type structure and described steel column to be installed encircles.
7. steel column fitting operation platform as claimed in claim 1, it is characterized in that, described bearing frame is channel-section steel, and described loaded plate is checkered steel plate.
8. steel column fitting operation platform as claimed in claim 1, it is characterized in that, first construction operation platform of described steel column fitting operation platform, the second construction operation platform, the 3rd construction operation platform, and the outside of the 4th construction operation platform all arranges safety guide rail.
9. steel column fitting operation platform as claimed in claim 1, it is characterized in that, the steel cat ladder of described construction utensil, catching device are all fixedly installed on the side of described steel column fitting operation platform.
10. the mounting method of steel column fitting operation platform as claimed in claim 1, it is characterized in that, the mounting method of described steel column fitting operation platform, comprising:
Perform step S1: connect described first construction operation platform, the second construction operation platform, the 3rd construction operation platform, to be formed be
the steel column fitting operation platform of type structure;
Perform step S2: at the 1 ~ 1.2m place, below apart from steel column top to be installed, four sides welding is shelved with tripod;
Perform step S3: described in being connected to form be
the steel column fitting operation platform of type structure is shelved on described tripod;
Perform step S4: at described first construction operation platform, the second construction operation platform, and the 3rd construction operation platform is formed
the opening part of type structure arranges the 4th construction operation platform;
Perform step S5: the first construction operation platform of described steel column fitting operation platform, the second construction operation platform, the 3rd construction operation platform, and the outside of the 4th construction operation platform all arranges safety guide rail;
Perform step S5: construction utensil is fixedly installed on the side of described steel column fitting operation platform;
Perform step S6: described steel column fitting operation platform is checked and accepted, and use of listing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410854312.9A CN104631844A (en) | 2014-12-31 | 2014-12-31 | Steel column mounting operation platform and mounting method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410854312.9A CN104631844A (en) | 2014-12-31 | 2014-12-31 | Steel column mounting operation platform and mounting method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104631844A true CN104631844A (en) | 2015-05-20 |
Family
ID=53211039
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410854312.9A Pending CN104631844A (en) | 2014-12-31 | 2014-12-31 | Steel column mounting operation platform and mounting method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104631844A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105756356A (en) * | 2016-03-23 | 2016-07-13 | 中冶建工集团有限公司 | Method for adjusting and aligning steel pipe column casings while installation |
CN107419907A (en) * | 2017-09-01 | 2017-12-01 | 中国十七冶集团有限公司 | A kind of steel-making tower steel structure platform is staggered installation of welding method |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201486120U (en) * | 2009-04-15 | 2010-05-26 | 中国十七冶建设有限公司 | Detachable steel column connecting construction operation platform |
US8042652B2 (en) * | 2008-05-08 | 2011-10-25 | Weir Joe A | Tree stand |
CN202509754U (en) * | 2012-04-18 | 2012-10-31 | 中建二局第三建筑工程有限公司 | High-altitude steel structure node construction working platform |
CN203271096U (en) * | 2013-04-16 | 2013-11-06 | 中建钢构有限公司 | Operating platform |
CN103388401A (en) * | 2013-08-14 | 2013-11-13 | 中国建筑第八工程局有限公司 | Steel post operation platform and construction method thereof |
CN203654693U (en) * | 2013-12-17 | 2014-06-18 | 中建一局集团第五建筑有限公司 | Protective sleeve basket used during assembling and welding of box steel column |
CN203684632U (en) * | 2013-06-09 | 2014-07-02 | 中建钢构有限公司 | Telescopic type welding operation platform |
CN204040441U (en) * | 2014-05-26 | 2014-12-24 | 中国建筑第八工程局有限公司 | Combination assembled operating platform |
-
2014
- 2014-12-31 CN CN201410854312.9A patent/CN104631844A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8042652B2 (en) * | 2008-05-08 | 2011-10-25 | Weir Joe A | Tree stand |
CN201486120U (en) * | 2009-04-15 | 2010-05-26 | 中国十七冶建设有限公司 | Detachable steel column connecting construction operation platform |
CN202509754U (en) * | 2012-04-18 | 2012-10-31 | 中建二局第三建筑工程有限公司 | High-altitude steel structure node construction working platform |
CN203271096U (en) * | 2013-04-16 | 2013-11-06 | 中建钢构有限公司 | Operating platform |
CN203684632U (en) * | 2013-06-09 | 2014-07-02 | 中建钢构有限公司 | Telescopic type welding operation platform |
CN103388401A (en) * | 2013-08-14 | 2013-11-13 | 中国建筑第八工程局有限公司 | Steel post operation platform and construction method thereof |
CN203654693U (en) * | 2013-12-17 | 2014-06-18 | 中建一局集团第五建筑有限公司 | Protective sleeve basket used during assembling and welding of box steel column |
CN204040441U (en) * | 2014-05-26 | 2014-12-24 | 中国建筑第八工程局有限公司 | Combination assembled operating platform |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105756356A (en) * | 2016-03-23 | 2016-07-13 | 中冶建工集团有限公司 | Method for adjusting and aligning steel pipe column casings while installation |
CN105756356B (en) * | 2016-03-23 | 2018-01-09 | 中冶建工集团有限公司 | A kind of steel pipe column casing mounting and adjusting alignment methods |
CN107419907A (en) * | 2017-09-01 | 2017-12-01 | 中国十七冶集团有限公司 | A kind of steel-making tower steel structure platform is staggered installation of welding method |
CN107419907B (en) * | 2017-09-01 | 2019-08-06 | 中国十七冶集团有限公司 | A kind of steel-making tower steel structure platform is staggered installation of welding method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104196222B (en) | The suspension scaffold of tools type section steel builder's jack | |
CN206052555U (en) | Hood type safe operation platform | |
CN205501837U (en) | Steel case roof beam becomes bridge welding simple platform | |
CN104631844A (en) | Steel column mounting operation platform and mounting method thereof | |
CN103243932A (en) | Structure for detaching inner climbing tower crane through roof crane and construction method thereof | |
CN105822076A (en) | Construction edge safety protection warning fence | |
CN206187284U (en) | Pitching pile formula safety railing | |
CN206591443U (en) | Pier stud vertical stratification integrative protection template | |
CN206591818U (en) | Pier stud vertical stratification integrative protection template | |
CN204126290U (en) | Elevator shaft horizontal protective device | |
CN204040556U (en) | A telescopic graduation two electronic box protection canopy | |
CN205935746U (en) | Simple and easy terraced barreled is put | |
CN205577379U (en) | Low -cost external construction platform | |
CN204662926U (en) | A kind of operating platform for steel pipe column top construction operation | |
CN205116854U (en) | Coal scuttle is portable platform for aggregate erection | |
CN204081763U (en) | Outdoor elevators protective door hinge | |
CN204199732U (en) | To encorbelment protection canopy | |
CN103899078B (en) | Attachment automatic lifting protecting screen mounting method | |
CN208749068U (en) | A kind of moveable exterior wall auxiliary finishing cage ladder of reversely hung Yong | |
CN202023349U (en) | Safety device with hard covering plate and turnover plate of climbing type scaffolding platform | |
CN204754265U (en) | Be used for reinforced concrete floor to reserve entrance to a cave safety device | |
CN205822815U (en) | Protection device of elevator shaft | |
CN206467578U (en) | Bridge construction bracket bearing assembly | |
CN206337800U (en) | Elevator shaft operating platform frame | |
CN205527386U (en) | A detachable electric room for port crane |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150520 |
|
RJ01 | Rejection of invention patent application after publication |