CN107268439B - It is a kind of to make the quick construction method in place of main cable strand in Tunnel-Type Anchorage of Suspension Bridge using special fixture - Google Patents

It is a kind of to make the quick construction method in place of main cable strand in Tunnel-Type Anchorage of Suspension Bridge using special fixture Download PDF

Info

Publication number
CN107268439B
CN107268439B CN201710479900.2A CN201710479900A CN107268439B CN 107268439 B CN107268439 B CN 107268439B CN 201710479900 A CN201710479900 A CN 201710479900A CN 107268439 B CN107268439 B CN 107268439B
Authority
CN
China
Prior art keywords
special fixture
strand
tunnel
place
anchor head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710479900.2A
Other languages
Chinese (zh)
Other versions
CN107268439A (en
Inventor
杨如刚
黄兵
徐国挺
唐中波
李清培
代道芬
陈刚
胡盼
陈勉
黄茂洲
柏国胜
伏冠西
李健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUAN LUQIAO HUADONG BUILDING CO Ltd
Original Assignee
SICHUAN LUQIAO HUADONG BUILDING CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN LUQIAO HUADONG BUILDING CO Ltd filed Critical SICHUAN LUQIAO HUADONG BUILDING CO Ltd
Priority to CN201710479900.2A priority Critical patent/CN107268439B/en
Publication of CN107268439A publication Critical patent/CN107268439A/en
Application granted granted Critical
Publication of CN107268439B publication Critical patent/CN107268439B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/16Suspension cables; Cable clamps for suspension cables ; Pre- or post-stressed cables
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal
    • E01D2101/32Metal prestressed

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

Make the quick construction method in place of strand in Tunnel-Type Anchorage of Suspension Bridge using special fixture the invention discloses a kind of;It is characterized by comprising following steps: (1) special fixture processing;(2) special fixture is connect with strand anchor head;(3) the special fixture of elevator machine travel is in place;Implementation through the invention: 1, anchor face before being drawn using special fixture auxiliary main cable strand to tunnel anchorage.2, avoid traction rope to strand anchor head friction damage using special fixture.3, special fixture is furnished with pulley blocks, and propulsive efficiency can be improved by cabling, is suitable for more tonnage hoist engines.4, special fixture can be recycled, and substantially increase the efficiency in place of main push-towing rope in tunnel anchorage, reduce costs.

Description

It is a kind of to make in Tunnel-Type Anchorage of Suspension Bridge main cable strand is quickly in place to apply using special fixture Work method
Technical field
The present invention relates to field of civil engineering, and in particular to a kind of main cable strand realized in Tunnel-Type Anchorage of Suspension Bridge quickly arrives Up to the quick construction method in place in preceding anchor face.
Background technique
After anchorage is drawn using the main rope of suspension bridge strand of tunnel anchorage to tunnel anchorage, because there is space in tunnel anchorage Limit, heavy mechanical equipment can not start tunneling, cause main cable strand cannot reach before anchor face.Elevator machine travel can only be used at this time Anchor face before the method that steel cable pulls strand anchor head reaches it.Directly steel cable is bundled on strand anchor head and is possible to damage anchor head Or rub with strand steel wire, therefore need to be improved.
Summary of the invention
Before so that main rope of suspension bridge strand is quickly reached tunnel anchorage the purpose of the present invention is to provide a kind of special fixture of utilization The method in anchor face;Increase main push-towing rope propulsive efficiency, and main cable strand will not be had an impact.
Step 1: special fixture processing:
Special fixture is all made of 20mm thick steel plate, jig frame by jig frame, pulley blocks, upper lower clamp plate composition, material And 25 bolt hole of φ is arranged in upper lower clamp plate, is connected using M24 plain bolt;
Step 2: special fixture is connect with strand anchor head:
Jig frame is covered in main cable strand anchor head position, lower clamp plate is installed, uses the fixed special fixture of bolt and rope Stock anchor head;
Step 3: it is in place that hoist engine draws strand:
After special fixture and strand anchor head connect, it is connect around pulley cabling with hoist engine by steel cable, starts elevator Machine travel strand reaches anchor face before tunnel anchorage.
It is of the present invention it is a kind of so that main rope of suspension bridge strand is quickly reached tunnel anchorage using special fixture before anchor face construction Method;Main rope of suspension bridge propulsive efficiency is improved, and guarantees construction quality.
The present invention has the advantages that the present invention is connect using special fixture with strand anchor head by improving, then by dragging The mode for dragging fixture can achieve same effect and will not influence strand.In addition pulley blocks are installed on special fixture can be improved Efficiency is pulled, various tonnage hoist engines are suitable for, construction efficiency is high, and cost reduces.The present invention also has the following advantages that;
1, special clamp structure is simple, easy to use, and propulsive efficiency can be improved.
2, special fixture and strand anchor head are easy to connect.
3, special fixture will not damage influence to main cable strand anchor head in use.
4, special fixture can be recycled, and reduce costs.
Detailed description of the invention
Fig. 1 is special fixture and main cable strand anchor head connection schematic diagram;
Fig. 2 is upper and lower clamping plate schematic diagram;
Fig. 3 is the jig frame schematic diagram for assembling pulley.
Wherein: jig frame 1, pulley blocks 2, upper lower clamp plate 3.
Specific embodiment
Below in conjunction with attached drawing 1- Fig. 3, the present invention is described in detail, technical solution in the embodiment of the present invention into Row clearly and completely describes, it is clear that described embodiments are only a part of the embodiments of the present invention, rather than whole realities Apply example.Based on the embodiments of the present invention, those of ordinary skill in the art are obtained without making creative work Every other embodiment, shall fall within the protection scope of the present invention.
The present invention a kind of makes in Tunnel-Type Anchorage of Suspension Bridge main cable strand quickly using special fixture by improving to provide herein The construction method of position;Increase the speed of main rope of suspension bridge strand location and installation in tunnel anchorage, operation becomes simple, to protect Demonstrate,prove construction quality and save the cost.
1-3 the present invention is further explained specific embodiment with reference to the accompanying drawing:
It is a kind of to make the quick construction method in place of main cable strand in Tunnel-Type Anchorage of Suspension Bridge using special fixture, make suspension bridge master The speed of cable stock location and installation in tunnel anchorage increases, and operation becomes simple, to guarantee construction quality and save the cost.
Step 1: special fixture processing: special fixture is made of jig frame 1, pulley blocks 2, upper lower clamp plate 3, and material is equal Using 20mm thick steel plate, 25 bolt hole of φ is arranged in jig frame and upper lower clamp plate, is connected using M24 plain bolt;
Step 2: special fixture is connect with strand anchor head: by 1 set of jig frame in main cable strand anchor head position, being installed Lower clamp plate uses bolt stationary fixture and strand anchor head;
Step 3: hoist engine traction strand is in place: after special fixture is connected with strand anchor head, by steel cable around special Fixture middle pulley cabling is connect with hoist engine, and starting hoist engine traction strand reaches anchor face before tunnel anchorage.
The present invention has the advantages that
1, special clamp structure is simple, easy to use, and propulsive efficiency can be improved.
2, special fixture and strand anchor head are easy to connect.
3, special fixture will not damage influence to main cable strand anchor head in use.
4, special fixture can be recycled, and reduce costs.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.

Claims (1)

1. a kind of make the quick construction method in place of Tunnel-Type Anchorage of Suspension Bridge main cable strand using special fixture, it is characterised in that: packet Include following steps:
Step 1: special fixture processing:
Special fixture is all made of 20mm thick steel plate, fixture by jig frame (1), pulley blocks (2), upper lower clamp plate (3) composition, material 25 bolt hole of φ is arranged in frame (1) and upper lower clamp plate (3), is connected using M24 plain bolt;
Step 2: special fixture is connect with strand anchor head:
Jig frame (1) is covered in main cable strand anchor head position, lower clamp plate (3) are installed, using the fixed special fixture of bolt with Strand anchor head;
Step 3: it is in place that hoist engine draws strand:
After special fixture and strand anchor head connect, it is connect around pulley cabling with hoist engine by steel cable, starting hoist engine is led Straw line stock reaches anchor face before tunnel anchorage.
CN201710479900.2A 2017-06-22 2017-06-22 It is a kind of to make the quick construction method in place of main cable strand in Tunnel-Type Anchorage of Suspension Bridge using special fixture Active CN107268439B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710479900.2A CN107268439B (en) 2017-06-22 2017-06-22 It is a kind of to make the quick construction method in place of main cable strand in Tunnel-Type Anchorage of Suspension Bridge using special fixture

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710479900.2A CN107268439B (en) 2017-06-22 2017-06-22 It is a kind of to make the quick construction method in place of main cable strand in Tunnel-Type Anchorage of Suspension Bridge using special fixture

Publications (2)

Publication Number Publication Date
CN107268439A CN107268439A (en) 2017-10-20
CN107268439B true CN107268439B (en) 2019-02-15

Family

ID=60068604

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710479900.2A Active CN107268439B (en) 2017-06-22 2017-06-22 It is a kind of to make the quick construction method in place of main cable strand in Tunnel-Type Anchorage of Suspension Bridge using special fixture

Country Status (1)

Country Link
CN (1) CN107268439B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021162811A1 (en) * 2020-02-12 2021-08-19 Commscope Technologies Llc Convertible strand and pole small cell mounts and assemblies

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1213110A1 (en) * 1983-10-11 1986-02-23 Куйбышевский институт инженеров железнодорожного транспорта Suspension bridge
ES2367737B8 (en) * 2011-06-30 2012-06-19 Universidad De Cantabria CONTINUOUS DISPLACEMENT DEVICE OF STRUCTURES.
CN202865743U (en) * 2012-11-14 2013-04-10 贺宏亮 Dragline device of large-scale bridge girder
CN104372742A (en) * 2013-08-12 2015-02-25 湖北鄂南起重运输机械有限公司 Puller for paying-off ropes of suspension bridge
CN203890885U (en) * 2014-05-04 2014-10-22 中国水电顾问集团贵阳勘测设计研究院有限公司 Connecting device for steel cable and pull rod of horizontally-stayed cable bridge
CN204455861U (en) * 2015-02-10 2015-07-08 中交一航局第一工程有限公司 A kind of hoisting connecting piece of large sections steel box-girder
CN205501827U (en) * 2016-03-08 2016-08-24 贵州中交贵瓮高速公路有限公司 A horizontal cable bogie for catwalk system of shaking

Also Published As

Publication number Publication date
CN107268439A (en) 2017-10-20

Similar Documents

Publication Publication Date Title
CN101967796B (en) Method for arranging parallel steel wire stay cable
CN107119572A (en) A kind of main rope of suspension bridge strand second traction enters the construction method of tunnel anchorage
CN110042768A (en) A kind of combination beam cable-stayed bridge main-beam binodal section circulation construction method
CN107268439B (en) It is a kind of to make the quick construction method in place of main cable strand in Tunnel-Type Anchorage of Suspension Bridge using special fixture
CN109973130B (en) Construction system and method for realizing one-time traction of extra-long tunnel anchor narrow space by main cable strand
CN102545103A (en) Overhead power line electricity testing and grounding line hanging and disassembling tool and operation method
CN103500964A (en) Method of live-wire replacement of overhead ground wire
CN204139609U (en) A kind of mounting structure of overhanging unloading platform
CN106087759B (en) A kind of threading method of prestressed strand threader and prestressed strand
CN202461363U (en) Disc steel bar straightening machine for building
CN108104852A (en) A kind of low stretch-draw anchor construction method for reducing loss of prestress
CN104242142B (en) The installation method of suspension type tube type bus
CN104724615A (en) Penetrating and winding method of large-diameter variable-amplitude steel wire rope of large moving-arm type tower crane
CN203529710U (en) Special device for hoisting cable reel
CN203345975U (en) Installation device of hoisting steel wire rope and tower crane
CN210457158U (en) Curtain type mounting structure for quickly hoisting square concrete pier column hooping
CN208656387U (en) A kind of wirerope binding method drilling cable mounting mechanism
CN203756202U (en) Rapid feeder for vertical anchor cable
CN105350782B (en) A kind of semi-mechanization steel strand wires laying method for round silo
CN211230287U (en) Guy rope arrangement fixing device for vehicle-mounted workover rig in moving state
CN203486866U (en) Automobile hoisting hydraulic aerial cage balancing device
CN205346692U (en) Swing arm tower machine of supporting multiple mounting means becomes width of cloth pulley yoke
CN105507129B (en) Suspension bridge main cable tightening tool structure and design method
CN203932835U (en) Distribution insulated conductor is carried line car
CN204343649U (en) A kind of tool-type wire rope draw ring

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant