CN108104852A - A kind of low stretch-draw anchor construction method for reducing loss of prestress - Google Patents

A kind of low stretch-draw anchor construction method for reducing loss of prestress Download PDF

Info

Publication number
CN108104852A
CN108104852A CN201711363479.5A CN201711363479A CN108104852A CN 108104852 A CN108104852 A CN 108104852A CN 201711363479 A CN201711363479 A CN 201711363479A CN 108104852 A CN108104852 A CN 108104852A
Authority
CN
China
Prior art keywords
anchor
agent
anchor agent
ultrafast
slow speed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711363479.5A
Other languages
Chinese (zh)
Other versions
CN108104852B (en
Inventor
张农
杨可
韩昌良
冉智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201711363479.5A priority Critical patent/CN108104852B/en
Publication of CN108104852A publication Critical patent/CN108104852A/en
Priority to PCT/CN2018/105355 priority patent/WO2019119900A1/en
Application granted granted Critical
Publication of CN108104852B publication Critical patent/CN108104852B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/003Machines for drilling anchor holes and setting anchor bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

A kind of low stretch-draw anchor construction method for reducing loss of prestress, suitable for mine and geotechnical engineering.Using anchor cable by Anchor Agent according to ultrafast Anchor Agent preceding, the posterior order of Anchor Agent is headed into drilling completely at a slow speed, is sufficiently stirred, and is stood after ultrafast Anchor Agent is fully cured, and tensioning is carried out using stretch-draw jack and anchorage, and protects load a period of time, and tensioning is completed.The process not yet starts to cure preceding completion in Anchor Agent at a slow speed.Most long in stretching process free section of anchor cable, loss of prestress ratio caused by the intermediate plate retraction of anchorage is minimum;It protects to carry and can eliminate the loss of prestress caused by anchoring body front end takes off glutinous sliding.The problems such as ultra stretching load of this method is low, avoids tensioner high loaded process, and anchor cable steel strand wires stock is broken.

Description

A kind of low stretch-draw anchor construction method for reducing loss of prestress
Technical field
It is especially a kind of to be adapted to mine and the reduction of geotechnical engineering in advance the present invention relates to construction prestressed cable technology The low stretch-draw anchor construction method of power loss.
Background technology
In infrastructure construction, usually constructed using anchor cable instead of traditional anchor pole.Compared to traditional anchor pole, anchor From the limitation of construction space, intensity is far above anchor rod strength, can bear more big load the flexible flexible, length of rigging, sharp It can apply the advantages that more high-prestressed with stretch-draw jack and clip type lockset.So that anchor cable is used widely.
Since anchor cable is using stretch-draw jack and strand tapered anchorage application prestressing force, inevitably occur because in anchorage Intermediate plate retraction causes anchor cable to bounce back, and causes loss of prestress;Simultaneously in order to ensure high anchor force, anchorage length often beyond 2m, Free section of anchor cable is shorter, and elongation is smaller, and loss of prestress caused by causing anchor cable retraction is huge, at maximum up to 40%-50%; It anchoring section front end also can the loss of prestress caused by sliding de- stick.
The prior art generally uses the mode of ultra stretching, i.e., is offset the loss by improving stretching force so that lifting jack unloading Residual stress afterwards disclosure satisfy that design requirement.But this method needs to apply nearly 2 times of design pretightning force in tensioning, Machine drawing tool can due to high loaded process the service life die-off, anchor cable steel strand wires stock can because high prestress damage even be broken, the construction time Also can it rise with difficulty.Still lack a kind of anchor cable construction method for reducing loss of prestress in stretching process at present.
The content of the invention
Technical problem:The purpose of the present invention is overcoming the shortcomings of in prior art, a kind of reduction loss of prestress is provided Low stretch-draw anchor construction method.
Technical solution:The low stretch-draw anchor construction method of the reduction loss of prestress of the present invention, its step are as follows:
A. drill according to the size of anchor cable in wall;
B. according to ultrafast Anchor Agent preceding, the posterior order of Anchor Agent fills in drilling at a slow speed, and using anchor cable by ultrafast anchor Gu agent and at a slow speed Anchor Agent head into drilling, poked after ultrafast Anchor Agent and at a slow speed Anchor Agent are headed into drilling bottom by anchor cable ultrafast Anchor Agent and at a slow speed Anchor Agent blend ultrafast Anchor Agent and the at a slow speed packaging of Anchor Agent using anchor cable and are stirred, wherein super Fast Anchor Agent and the at a slow speed interface of Anchor Agent nearby have minimum one section and generate mixing but do not influence actual effect, stand anchor Ultrafast Anchor Agent is fully cured in rope;
C. the part installation strand tapered anchorage outside anchor cable drilling props up wall, coordinates clip type using stretch-draw jack Anchorage carries out tensioning preload and the standard stretching force of maintenance to anchor cable and carries out guarantor's load, ultrafast Anchor Agent solidification at this time and by anchor cable top Part is anchored with the wall of a borehole, and when tensioning, ultrafast Anchor Agent solidification portion outboard was gradually opened with the wall of a borehole, and anchor at a slow speed at this time Gu agent is not solidified also still for fluidised form, become de- glutinous sliding, cause anchor cable relaxation pretightning force loss;
E. jack release is controlled, terminates to protect load process, completes the installation of anchor cable, Anchor Agent curing at a slow speed is waited, completes The construction of anchor cable.
Ultrafast Anchor Agent size only needs to meet design pretightning force requirement, and it is common to meet two section Anchor Agents for Anchor Agent size at a slow speed The anchor force of generation meets design pulling capacity requirement, and ultrafast Anchor Agent length is often the 1/5 of anchor cable length, at a slow speed Anchor Agent length For the 1/5-3/5 of the anchor cable body of rod).
The tensioning and guarantor's load process start to cure preceding completion in Anchor Agent at a slow speed, wherein it is 30s-1min to wrap in the time.
The beginning hardening time of the Anchor Agent at a slow speed is much larger than the ultrafast Anchor Agent model Cka of ultrafast Anchor Agent, coagulates The glue time is 8-25s, and Anchor Agent model M, gel time are at a slow speed>180s.
The standard stretching force load is design pretightning force and the summation of anchor cable retraction lost force
Advantageous effect:By adopting the above-described technical solution, the present invention has the following advantages that compared with prior art:
(1) stretching force additionally applied is needed during ultra stretching, and much smaller than traditional construction method, stretch-draw jack tool is subjected to Load it is small, the tensioning time shortens, and mechanical service life extends, and anchor cable stress during tensioning is smaller, and steel strand wires stock is not easily broken It splits.
(2) compared with the construction method of tensioning again is fully cured in resin anchoring agent, stretching process stream line of the invention is non- Anchoring section is most long, anchor cable under the conditions of equal prestressing force along stretch it is longer, after stretch-draw jack release because anchor cable retraction generate it is pre- Stress loss smaller.
(3) protected in stretching process and carry removal jack again after a period of time, can eliminated and be made because anchoring section front end takes off glutinous sliding Into loss of prestress.
(4) slow resin anchoring agent cures in the case where anchor cable is in pre-stressed state, is equivalent to prestress anchoraging, is more advantageous to Firm coal and rock.
Description of the drawings
Fig. 1 is the low stretch-draw anchor construction method schematic diagram of the present invention.
In figure:The ultrafast Anchor Agents of 1-, 2- Anchor Agents at a slow speed, 3- anchor cables, 4- strand tapered anchorages.
Specific embodiment
One embodiment of the present of invention is further described below in conjunction with the accompanying drawings:
As shown in Figure 1, the low stretch-draw anchor construction method of the reduction loss of prestress of the present invention, its step are as follows:
A. drill according to the size of anchor cable 3 in wall;
B. according to ultrafast Anchor Agent 1 preceding, 2 posterior order of Anchor Agent fills in drilling, Anchor Agent 2 at a slow speed at a slow speed Beginning hardening time much larger than ultrafast 1 ultrafast 1 model Cka of Anchor Agent of Anchor Agent, gel time 8-25s is anchored at a slow speed 2 model M of agent, gel time are>180s, ultrafast 1 size of Anchor Agent only need to meet design pretightning force requirement, at a slow speed Anchor Agent 2 Size meets the anchor force that two section Anchor Agents generate jointly and meets design pulling capacity requirement, and ultrafast 1 length of Anchor Agent is often anchor cable The 1/5 of length, 2 length of Anchor Agent is the 1/5-3/5 of 3 body of rod of anchor cable at a slow speed, using anchor cable 3 by ultrafast Anchor Agent 1 and anchor at a slow speed Gu agent 2 heads into drilling, ultrafast Anchor Agent 1 is poked after ultrafast Anchor Agent 1 and at a slow speed Anchor Agent 2 are headed into drilling bottom by anchor cable 3 Anchor Agent 2 at a slow speed blend ultrafast Anchor Agent 1 and the at a slow speed packaging of Anchor Agent 2 using anchor cable 3 and are stirred, wherein ultrafast Anchor Agent 1 and the at a slow speed interface of Anchor Agent 2 nearby have minimum one section and generate mixing but do not influence actual effect, stand anchor Ultrafast Anchor Agent 1 is fully cured in rope 3;
C. the part installation strand tapered anchorage 4 outside the drilling of anchor cable 3 props up wall, coordinates intermediate plate using stretch-draw jack Formula anchorage 4 carries out anchor cable 3 tensioning preload and the standard stretching force of maintenance carries out guarantor's load, and the standard stretching force load is design Pretightning force and anchor cable 3 bounce back the summation of lost force, and ultrafast Anchor Agent 1 solidifies and by 3 tip portion of anchor cable and the wall of a borehole anchor at this time Gu tensioning and protecting load process and starting to cure preceding completion in Anchor Agent 2 at a slow speed, wherein it is 30s-1min to wrap in the time, when tensioning, surpasses Fast Anchor Agent 1 solidifies portion outboard and is gradually opened with the wall of a borehole, and it is still fluidised form that Anchor Agent 2, which does not solidify also, at a slow speed at this time, into For de- glutinous sliding, anchor cable relaxation pretightning force loss is caused;
E. jack release is controlled, terminates to protect load process, completes the installation of anchor cable 3, Anchor Agent 2 cures at a slow speed for wait, complete Into the construction of anchor cable 3.
Technical scheme is disclosed as above by alternative embodiment.Artisan will appreciate that it is not taking off That is made in the case of from the revealed scope and spirit of the present invention of appended claims of the invention changes and retouches, and belongs to Within the scope of the claims of the present invention.

Claims (5)

1. a kind of low stretch-draw anchor construction method for reducing loss of prestress, it is characterized in that step is as follows:
A. according to anchor cable(3)Size drill in wall;
B. according to ultrafast Anchor Agent(1)Preceding, Anchor Agent at a slow speed(2)Posterior order fills in drilling, and uses anchor cable(3)It will be super Fast Anchor Agent(1)Anchor Agent at a slow speed(2)Drilling is headed into, treats anchor cable(3)By ultrafast Anchor Agent(1)Anchor Agent at a slow speed(2)Top Ultrafast Anchor Agent is poked after entering the bottom that drills(1)Anchor Agent at a slow speed(2), utilize anchor cable(3)Blend ultrafast Anchor Agent(1)With it is slow Fast Anchor Agent(2)Packaging and be stirred, wherein ultrafast Anchor Agent(1)Anchor Agent at a slow speed(2)Interface nearby have Minimum one section generates mixing but does not influence actual effect, stands anchor cable(3), make ultrafast Anchor Agent(1)It is fully cured;
C. in anchor cable(3)Part installation strand tapered anchorage outside drilling(4)Wall is propped up, coordinates intermediate plate using stretch-draw jack Formula anchorage(4)To anchor cable(3)It carries out tensioning preload and the standard stretching force of maintenance carries out guarantor's load, at this time ultrafast Anchor Agent(1)Solidification And by anchor cable(3)Tip portion and the wall of a borehole anchor, ultrafast Anchor Agent during tensioning(1)Solidify portion outboard and the wall of a borehole gradually quilt It pulls open, and Anchor Agent at a slow speed at this time(2)It does not solidify also still for fluidised form, becomes de- glutinous sliding, cause anchor cable relaxation pretightning force loss;
E. jack release is controlled, terminates to protect load process, completes anchor cable(3)Installation, wait Anchor Agent at a slow speed(2)Cure, it is complete Into anchor cable(3)Construction.
2. the low stretch-draw anchor construction method according to claim 1 for reducing loss of prestress, it is characterized in that:Described is super Fast Anchor Agent(1)Size only needs to meet design pretightning force requirement, at a slow speed Anchor Agent(2)Size meets two section Anchor Agents and generates jointly Anchor force meet design pulling capacity requirement, ultrafast Anchor Agent(1)Length is often the 1/5 of anchor cable length, at a slow speed Anchor Agent(2)It is long It spends for anchor cable(3)The 1/5-3/5 of the body of rod).
3. the low stretch-draw anchor construction method according to claim 1 for reducing loss of prestress, it is characterized in that:The tensioning With guarantor's load process in Anchor Agent at a slow speed(2)Start to cure preceding completion, wherein it is 30s-1min to wrap in the time.
4. the anchor cable construction method of low stretch-draw prestressing force loss according to claim 1, it is characterized in that:The anchor at a slow speed Gu agent(2)Beginning hardening time be much larger than ultrafast Anchor Agent(1)Ultrafast Anchor Agent(1)Model Cka, gel time 8- 25s, at a slow speed Anchor Agent(2)Model M, gel time are>180s.
5. the anchor cable construction method of low stretch-draw prestressing force loss according to claim 1, it is characterized in that:The standard Drag load is design pretightning force and anchor cable(3)The summation for the lost force that bounces back.
CN201711363479.5A 2017-12-18 2017-12-18 A kind of low stretch-draw anchor construction method reducing loss of prestress Active CN108104852B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201711363479.5A CN108104852B (en) 2017-12-18 2017-12-18 A kind of low stretch-draw anchor construction method reducing loss of prestress
PCT/CN2018/105355 WO2019119900A1 (en) 2017-12-18 2018-09-13 Low-tension anchor cable construction method capable of reducing prestress loss

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711363479.5A CN108104852B (en) 2017-12-18 2017-12-18 A kind of low stretch-draw anchor construction method reducing loss of prestress

Publications (2)

Publication Number Publication Date
CN108104852A true CN108104852A (en) 2018-06-01
CN108104852B CN108104852B (en) 2019-05-14

Family

ID=62209868

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711363479.5A Active CN108104852B (en) 2017-12-18 2017-12-18 A kind of low stretch-draw anchor construction method reducing loss of prestress

Country Status (2)

Country Link
CN (1) CN108104852B (en)
WO (1) WO2019119900A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019119900A1 (en) * 2017-12-18 2019-06-27 中国矿业大学 Low-tension anchor cable construction method capable of reducing prestress loss
CN113529705A (en) * 2021-07-21 2021-10-22 中国矿业大学(北京) High-prestress nondestructive application device and method for anchor rods and anchor cables

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114062248B (en) * 2021-11-02 2022-09-13 西南交通大学 System and method for testing friction resistance value of free section of rock-soil anchor cable pipeline

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101413396A (en) * 2008-09-26 2009-04-22 中国水利水电第十四工程局有限公司 Injecting and mounting method of stretching anchor rod
CN102116162A (en) * 2011-03-25 2011-07-06 平安煤矿瓦斯治理国家工程研究中心有限责任公司 Tension dispersed anchor cable for coal mine and anchoring method thereof
CN103498690A (en) * 2013-09-04 2014-01-08 中国矿业大学 Double-anchor-cable combination locking device and method thereof
CN104153801A (en) * 2014-08-29 2014-11-19 河南理工大学 Method for automatic, rapid and damage-free application of high pretightening force to mining anchor rod
CN105370303A (en) * 2015-11-26 2016-03-02 湖南科技大学 Tensioning device for deep roadway high-prestress anchor bolt support and operation method thereof

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102011078769A1 (en) * 2011-07-07 2013-01-10 Hilti Aktiengesellschaft rock bolt
CN102337912A (en) * 2011-10-17 2012-02-01 新汶矿业集团有限责任公司华丰煤矿 Rapid anchoring method for coal mine roadway anchor rod
CN105134267B (en) * 2015-09-10 2017-08-01 河南理工大学 A kind of anchorage cable anchoring synergisting method and its structure
CN205172610U (en) * 2015-11-02 2016-04-20 新汶矿业集团有限责任公司协庄煤矿 A stock anchor for tunnel country rock
CN108104852B (en) * 2017-12-18 2019-05-14 中国矿业大学 A kind of low stretch-draw anchor construction method reducing loss of prestress

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101413396A (en) * 2008-09-26 2009-04-22 中国水利水电第十四工程局有限公司 Injecting and mounting method of stretching anchor rod
CN102116162A (en) * 2011-03-25 2011-07-06 平安煤矿瓦斯治理国家工程研究中心有限责任公司 Tension dispersed anchor cable for coal mine and anchoring method thereof
CN103498690A (en) * 2013-09-04 2014-01-08 中国矿业大学 Double-anchor-cable combination locking device and method thereof
CN104153801A (en) * 2014-08-29 2014-11-19 河南理工大学 Method for automatic, rapid and damage-free application of high pretightening force to mining anchor rod
CN105370303A (en) * 2015-11-26 2016-03-02 湖南科技大学 Tensioning device for deep roadway high-prestress anchor bolt support and operation method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019119900A1 (en) * 2017-12-18 2019-06-27 中国矿业大学 Low-tension anchor cable construction method capable of reducing prestress loss
CN113529705A (en) * 2021-07-21 2021-10-22 中国矿业大学(北京) High-prestress nondestructive application device and method for anchor rods and anchor cables

Also Published As

Publication number Publication date
WO2019119900A1 (en) 2019-06-27
CN108104852B (en) 2019-05-14

Similar Documents

Publication Publication Date Title
CN108104852B (en) A kind of low stretch-draw anchor construction method reducing loss of prestress
CN205477690U (en) Antiskid slip casting stock
CN102296605A (en) Device and method for compensating or unloading prestress loads of anchor cable
CN204491425U (en) A kind of external prestressing strengthening structure of T-shaped bridge diaphragm
CN110486069A (en) A kind of high working face coal wall caving control structure and construction equipment based on flexibility reinforcing
CN203065973U (en) Stretch-draw device for monofilament epoxy coating steel strands
CN109267571A (en) There are the anchors and its construction method under cavity condition in a kind of slopes
CN102678147B (en) High-strength, constant-resistance extender for anchorage cables and usage thereof
CN103161484B (en) A kind of lotion fixed length anchoring support method
CN1966937A (en) Once supporting method for reinforced anchor rod in deep tunnel
CN202194135U (en) Anchor cable prestress load compensation or unloading device
CN109823477B (en) Ocean engineering drag anchor capable of improving uplift bearing performance
CN109024622B (en) Use method of slope reinforcement rod piece
CN203834478U (en) Active clamping piece type pinching, tensioning and locking device for pre-stressed anchor cable
CN206844109U (en) A kind of prestress anchorage cable
CN103147777A (en) Pumping paste prestress full bolting anchor rod/cable supporting method
CN201033945Y (en) Short strand wire stretching stopping means
CN109944241B (en) Anchor cable hole bottom reverse traction device and anchor cable installation method
CN107268439B (en) It is a kind of to make the quick construction method in place of main cable strand in Tunnel-Type Anchorage of Suspension Bridge using special fixture
CN207761302U (en) One kind can be used in turn anchor pole tension tool
CN201459718U (en) Flexible pull rod for construction bearing platform
CN109252881A (en) Steel pipe cement mortar prestress anchorage cable and its method for protecting support
CN207212381U (en) A kind of anchor pole for deep tunnel soft-rock slope
CN109113773A (en) A kind of quick tensioning anchor cable structure and its construction method
CN209100066U (en) A kind of quick tensioning anchor cable structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant