- CN107126656A CN107126656A CN201710529426.XA CN201710529426A CN107126656A CN 107126656 A CN107126656 A CN 107126656A CN 201710529426 A CN201710529426 A CN 201710529426A CN 107126656 A CN107126656 A CN 107126656A
- Authority
- CN
- China
- Prior art keywords
- fire
- module
- bim
- tunnel
- wisdom
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 32
- 238000005516 engineering process Methods 0.000 title claims abstract description 21
- 238000012544 monitoring process Methods 0.000 claims abstract description 40
- 238000005286 illumination Methods 0.000 claims abstract description 20
- 239000000523 sample Substances 0.000 claims abstract description 17
- 238000004891 communication Methods 0.000 claims abstract description 16
- 238000012423 maintenance Methods 0.000 claims abstract description 11
- 238000001514 detection method Methods 0.000 claims description 13
- 230000006698 induction Effects 0.000 claims description 6
- 230000002452 interceptive effect Effects 0.000 claims description 6
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 6
- 238000007689 inspection Methods 0.000 claims description 3
- 239000007921 spray Substances 0.000 claims description 3
- 238000012546 transfer Methods 0.000 claims 1
- 238000010276 construction Methods 0.000 description 3
- 238000007726 management method Methods 0.000 description 3
- 238000009423 ventilation Methods 0.000 description 2
- 238000012800 visualization Methods 0.000 description 2
- 238000002485 combustion reaction Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000009191 jumping Effects 0.000 description 1
- 238000005192 partition Methods 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
Classifications
-
- A—HUMAN NECESSITIES
- A62—LIFE-SAVING; FIRE-FIGHTING
- A62C—FIRE-FIGHTING
- A62C31/00—Delivery of fire-extinguishing material
- A62C31/02—Nozzles specially adapted for fire-extinguishing
- A62C31/03—Nozzles specially adapted for fire-extinguishing adjustable, e.g. from spray to jet or vice versa
-
- A—HUMAN NECESSITIES
- A62—LIFE-SAVING; FIRE-FIGHTING
- A62C—FIRE-FIGHTING
- A62C31/00—Delivery of fire-extinguishing material
- A62C31/28—Accessories for delivery devices, e.g. supports
-
- A—HUMAN NECESSITIES
- A62—LIFE-SAVING; FIRE-FIGHTING
- A62C—FIRE-FIGHTING
- A62C37/00—Control of fire-fighting equipment
- A62C37/36—Control of fire-fighting equipment an actuating signal being generated by a sensor separate from an outlet device
- A62C37/38—Control of fire-fighting equipment an actuating signal being generated by a sensor separate from an outlet device by both sensor and actuator, e.g. valve, being in the danger zone
- A62C37/40—Control of fire-fighting equipment an actuating signal being generated by a sensor separate from an outlet device by both sensor and actuator, e.g. valve, being in the danger zone with electric connection between sensor and actuator
Abstract
The present invention relates to tunnel wisdom fire-fighting field, there is provided a kind of tunnel based on BIM technology portable subregion wisdom fire-fighting device and method, including mobile control module, and automation head module, illumination and monitoring probe module, smog and the fire detector module being connected with mobile control module;Also include scalable pipeline, pressue device, fire fighting supply point, wireless communication module, BIM wisdom fire-fightings workbench, working track, maintenance track, scalable pipeline is connected with automation head module and pressue device respectively, pressue device is connected with fire fighting supply point, mobile control module runs on working track and maintenance track, mobile control module uses to be wirelessly transferred with wireless communication module to be connected, and wireless communication module is connected to form the portable subregion wisdom fire-fighting work closed loop in tunnel with BIM wisdom fire-fighting workbenches;The present invention can have found the tunnel condition of a fire in time, and fire multidate information is grasped in real time, is put out a fire automatically.
Description
Technical field
The present invention relates to tunnel wisdom fire-fighting field, particularly a kind of portable subregion wisdom in the tunnel based on BIM technology
Fire plant and method.
Background technology
With the construction of China's freeway net, the scale of vcehicular tunnel gradually increases, especially western mountainous areas, due to it
Terrain environment is complicated, and Exploration on Train Operation Safety, emergency management and rescue problem of mountain area major long tunnel etc. are increasingly serious.With the magnitude of traffic flow
Increase, the complexity of transport article is continuously increased so that the fire risk of vcehicular tunnel is improved, the fire fighting problem of vcehicular tunnel
The major issue that operation management unit be can not ignore is turned into.Tunnel Fire typically has following features:1)Vcehicular tunnel
Properties of fire has higher uncertainty;2)By vcehicular tunnel space it is more long and narrow, more closing, the smaller feature of section shadow
Ring, ventilation condition is poor during tunnel generation fire, smokescope is big, low visibility;3)It is imperfect combustion that tunnel fire hazard is produced
Gas, which is bled around, makes tunnel fire hazard spread with jumping characteristic;4)Emergency management and rescue difficulty is big, the time that emergency vehicles are reached the spot
It is long;5)The difficulty of vcehicular tunnel fire extinguishing fire fighting is larger, and rescue personnel is difficult to close to burning things which may cause a fire disaster.In general, when fire occurs for tunnel,
Professional firefighters and rescue personnel need certain time to get to scene of fire after warning facility response, and site traffic is participated in
Person is lacked experience to fire punishment, and easily fear is fled the scene, and causes the condition of a disaster gradually to increase, and misses the optimum time point of fire extinguishing.
Therefore, the portable subregion wisdom fire-fighting system in tunnel, the emergent punishment efficiency for improving tunnel fire hazard, effective control are built
Fire spreads, and in time eliminates fire among rudiment, reduces the loss caused by tunnel fire hazard, ensure in tunnel vehicle and
The safety of personnel is significant.Instantly, BIM technology is the important technology support of wisdom traffic informatization, builds one
The portable subregion wisdom fire-fighting device in the tunnel based on BIM technology is planted, by tunnel construction information model(BIM)Introduce tunnel movement
Formula subregion wisdom fire-fighting device, can improve tunnel fire-fighting visualization, digitlization, intelligent level.
The content of the invention
The invention aims to solve above-mentioned technical problem, there is provided a kind of portable subregion in tunnel based on BIM technology
Wisdom fire-fighting device and method, the device and portable fire-fighting method have digitlization, visualization, intelligentized feature, can be
Tunnel fire hazard initial stage is positioned to ignition point in tunnel, and fire multidate information is grasped in real time, carries out auto-partition extinguishing operation.
To reach above-mentioned purpose, the present invention is implemented according to following technical scheme:
A kind of portable subregion wisdom fire-fighting device in the tunnel based on BIM technology, including the working track being arranged in tunnel, institute
Working track is stated provided with more than two mobile control modules, mobile control module runs on the working track, the shifting
Dynamic control module is provided with the energy automatic control switch being connected with mobile control module, adjust automatically angle, monitors hydraulic pressure automatically
And the fire condition adjust automatically angle detected according to smog with fire detector module, illumination and monitoring probe module is entered
Row fire extinguishing automation head module, and for tunnel is patrolled and to fire point carry out in real time monitoring and will monitor
The illumination of temporary lighting data are uploaded to mobile control module and occurred for fire simultaneously when and monitoring probe module, and
For smog and the fire spy for the tunnel condition of a fire implement detection and positioning and detection data is uploaded to mobile control module
Survey device module;Also include scalable pipeline, pressue device, fire fighting supply point, wireless communication module, BIM wisdom fire-fightings and work flat
Platform, the water inlet of the scalable pipeline reconnects fire fighting supply point, the delivery port of scalable pipeline after being connected with pressue device
It is connected with the water inlet for automating head module, the mobile control module uses the company of being wirelessly transferred with the wireless communication module
Connect, wireless communication module is connected to form the portable subregion wisdom fire-fighting work closed loop in tunnel, institute with BIM wisdom fire-fighting workbenches
The monitoring data collected by the wireless communication module reception mobile control module are stated, and send data to BIM wisdom
Fire-fighting work platform.
Further, the working track both sides are vertically provided with maintenance track, and mobile control module runs on maintenance track.
Wherein, the BIM wisdom fire-fightings workbench is integrated with complete tunnel BIM models, display tunnel structure thing and
Various electromechanical equipments, affiliated facility, BIM wisdom fire-fightings workbench receive fire information, by fire video monitoring information, fire
Detector information real-time exhibition in control platform BIM models, the BIM wisdom fire-fightings workbench can be to automation Nozzle At The Ingot Mold
Block, illumination and monitoring probe module, mobile control module, smog and fire detector module carry out control in real time, real-time, interactive,
Issue induction instruction, while many set emergency preplans built in the BIM wisdom fire-fightings workbench, automatic according to the fire order of severity
Start, the BIM wisdom fire-fightings workbench records emergency preplan implementation procedure, self-extinguishing implementation procedure, manually done automatically
Pre- process, makes whole fire extinguishing procedure possess trackability.
Preferably, the pressue device carries out disappearing for Self-pressurizing agri for the hydraulic pressure that can be monitored according to automation head module
Anti- booster pump.
There is provided a kind of based on BIM skills based on a kind of above-mentioned portable subregion wisdom fire-fighting device in the tunnel based on BIM technology
The portable subregion wisdom fire-fighting method in the tunnel of art, is comprised the following steps that:
S1, by illumination tunnel is patrolled with monitoring probe module and fire point is monitored in real time, pass through smog
The tunnel condition of a fire is carried out with fire detector module to implement detection and positioning;
S2, video monitoring data is gathered based on S1 and fire monitoring data are uploaded to mobile control module;
S3, the information received based on S2 movements control module, are uploaded to BIM wisdom by fire data through wireless communication module and disappeared
Anti- workbench, BIM wisdom fire-fightings workbench is by fire video monitoring information, fire detector information in control platform BIM
Real-time exhibition in model, and start corresponding emergency preplan;
S4, the fire information received based on S2 movements control module, according to smog and reality of the fire detector module to fire
Shi Dingwei, mobile control module, which is automatically moved into, suitably puts position, illumination and monitoring probe module fire is carried out monitoring in real time and
Illumination, automation head module adjustment spray angle opens self-extinguishing;
S5, based on S4 steps, BIM wisdom fire-fightings workbench receives each module to the responsive state of tunnel fire hazard, control platform
BIM models are by each module working condition real-time exhibition, interactive controlling, issue induction instruction, and administrative staff are to fire extinguishing implementation status
Carry out inspection in real time, real-time manual intervention control;
S6, based on S5 steps, BIM wisdom fire-fightings workbench records emergency preplan implementation procedure, self-extinguishing and performed automatically
Journey, manual intervention process, make whole fire extinguishing procedure possess trackability.
Compared with prior art, the present invention using portable zoned fire detection theory, its clear logic, it is simple in construction, set
Meter is reasonable, operation is efficient;The present invention can improve the emergent punishment efficiency of tunnel fire hazard, in time tunnel fire hazard can be controlled to spread,
And do not influenceed by ventilation condition, smokescope in tunnel;The present invention uses Automated condtrol, can reduce the throwing of fire fighter
Enter, the tunnel fire-fighting response time is short, it is visual that the tunnel wisdom fire-fighting workbench built based on BIM technology improves tunnel fire-fighting
Change, digitlization, intelligentized level.
Brief description of the drawings
Fig. 1 is structural representation of the invention.
Fig. 2 is portable zoned fire detection schematic diagram of the invention.
Embodiment
With reference to specific embodiment, the invention will be further described, the illustrative examples and explanation invented herein
For explaining the present invention, but it is not as a limitation of the invention.
As shown in figure 1, a kind of portable subregion wisdom fire-fighting device in tunnel based on BIM technology of the present embodiment, including
The working track 10 in tunnel is arranged at, the working track 10 is provided with more than two mobile control modules 1, mobile control
Module 1 runs on the working track 10, and the movement control module 1 can be using fire-fighting class usually used in the prior art
The mobile controller of aerial ladder is similar to, with controller(Usually used single-chip microcomputer such as AT89S51 monolithics in the prior art)
With the motor being connected with controller and with by motor-driven driving wheel, motor drives driving wheel in order in working track 10
Upper movement, the mobile control module 1 is provided with the automation head module 2 being connected with mobile control module 1, illumination and monitoring
Probe module 3, smog and fire detector module 4, head module 2 is automated certainly can also use fire-fighting of the prior art
Shower nozzle, it can by the mobile automatic control switch of control module 1, adjust automatically angle, automatic monitoring hydraulic pressure and according to smog with
The fire condition adjust automatically angle that fire detector module 4, illumination are detected with monitoring probe module 3 is put out a fire;Illumination
Fire-fighting lighting apparatus of the prior art and monitoring probe can also be used with monitoring probe module 3, it can be used for tunnel
Patrolled and fire point monitor in real time and Monitoring Data is uploaded to mobile control module 1, while for fire
Temporary lighting during generation;Smog can also use the smog and fire of fire-fighting of the prior art with fire detector module 4
Fire detector, it can be used to the tunnel condition of a fire is carried out implementing detection and positioning and detection data is uploaded into mobile control module 1;
Also include scalable pipeline 5, pressue device 6, fire fighting supply point 7, wireless communication module 8, BIM wisdom fire-fightings workbench 9, institute
State scalable pipeline 5 water inlet be connected with pressue device 6 after reconnect fire fighting supply point 7, the delivery port of scalable pipeline 5 with
The water inlet connection of head module 2 is automated, wherein pressue device 6 is connected with the controller of mobile control module 1, is existing skill
The hydraulic pressure that can be monitored in art used in fire-fighting according to automation head module carries out the fire fighting pressurization pump of Self-pressurizing agri, described
Mobile control module 1 uses to be wirelessly transferred with the wireless communication module 8 to be connected, and the wireless communication module 8 receives the shifting
Monitoring data collected by dynamic control module 1, and BIM wisdom fire-fightings workbench 9 is sent data to, wherein, it is described
BIM wisdom fire-fightings workbench 9 is integrated with complete tunnel BIM models, display tunnel structure thing and various electromechanical equipments, attached
Facility, BIM wisdom fire-fightings workbench receives fire information, by fire video monitoring information, fire detector information in control
Real-time exhibition in platform BIM models, the BIM wisdom fire-fightings workbench can be visited to automation head module, illumination and monitoring
Head module, mobile control module, smog and fire detector module carry out control in real time, real-time, interactive, issue induction instruction, together
Many set emergency preplans built in Shi Suoshu BIM wisdom fire-fighting workbenches, according to fire order of severity automatic start, the BIM intelligence
Intelligent fire-fighting work platform records emergency preplan implementation procedure, self-extinguishing implementation procedure, manual intervention process automatically, makes entirely to go out
Fiery process possesses trackability.
In other the present embodiment, the both sides of working track 10 are vertically provided with maintenance track 11, and mobile control module 1 is run
In maintenance track 11, maintenance track 11 is used to move control module 1 and its connection equipment temporary storage and maintenance;Wherein, work
Track 10 and the maintenance track 11 are all fixed on tunnel top.
There is provided a kind of based on BIM skills based on a kind of above-mentioned portable subregion wisdom fire-fighting device in the tunnel based on BIM technology
The portable subregion wisdom fire-fighting method in the tunnel of art, is comprised the following steps that:
S1, by illumination tunnel is patrolled with monitoring probe module and fire point is monitored in real time, pass through smog
The tunnel condition of a fire is carried out with fire detector module to implement detection and positioning;
S2, video monitoring data is gathered based on S1 and fire monitoring data are uploaded to mobile control module;
S3, the information received based on S2 movements control module, are uploaded to BIM wisdom by fire data through wireless communication module and disappeared
Anti- workbench, BIM wisdom fire-fightings workbench is by fire video monitoring information, fire detector information in control platform BIM
Real-time exhibition in model, and start corresponding emergency preplan;
S4, the fire information received based on S2 movements control module, according to smog and reality of the fire detector module to fire
Shi Dingwei, mobile control module, which is automatically moved into, suitably puts position, illumination and monitoring probe module fire is carried out monitoring in real time and
Illumination, automation head module adjustment spray angle opens self-extinguishing;
S5, based on S4 steps, BIM wisdom fire-fightings workbench receives each module to the responsive state of tunnel fire hazard, control platform
BIM models are by each module working condition real-time exhibition, interactive controlling, issue induction instruction, and administrative staff are to fire extinguishing implementation status
Carry out inspection in real time, real-time manual intervention control;
S6, based on S5 steps, BIM wisdom fire-fightings workbench records emergency preplan implementation procedure, self-extinguishing and performed automatically
Journey, manual intervention process, make whole fire extinguishing procedure possess trackability.
Fire-fighting is moved using the portable subregion wisdom fire-fighting device and method in the tunnel based on BIM technology of the present invention
When, zoned fire detection can be achieved, as shown in Fig. 2 setting three to move mobile control module 1 on the working track in tunnel, by three
Individual mobile control module 1 is designated as X-1 fire fighting units, X-2 fire fighting units and X-3 fire fighting units respectively, while by tunnel points
For tetra- fire-fighting regions on duty of A, B, C, D, shown in figure, its zoned fire detection function is realized as follows in tunnel:X-1 fire fighting units
Fire-fighting region on duty is that A and B, X-2 fire fighting unit fire-fighting region on duty are B and C, X-3 fire fighting unit fire-fighting region on duty
For C and D;Typically when the condition of a fire occur in B regions, X-1 fire fighting units and X-2 fire fighting units can be responded simultaneously, reach fire point attached
Nearly collaboration carries out extinguishing operation;It is same when there is the condition of a fire in C regions, X-2 fire fighting units and X-3 fire fighting units can ring simultaneously
Should, reach collaboration near fire point and carry out extinguishing operation;Tunnel movable type subregion wisdom fire-fighting device is using fire fighting unit point
Area is on duty, same point position response fire fighting unit at least two.
Technical scheme is not limited to the limitation of above-mentioned specific embodiment, and every technique according to the invention scheme is done
The technology deformation gone out, each falls within protection scope of the present invention.
Claims (5)
1. a kind of portable subregion wisdom fire-fighting device in the tunnel based on BIM technology, it is characterised in that including being arranged in tunnel
Working track, the working track is provided with more than two mobile control modules, and mobile control module runs on the work
Make track, the mobile control module be provided with the energy automatic control switch being connected with mobile control module, adjust automatically angle,
Automatic monitoring hydraulic pressure and the fire condition that is detected according to smog and fire detector module, illumination and monitoring probe module from
The automation head module that dynamic adjustment angle is put out a fire, and for being patrolled tunnel and fire point being carried out real-time
Monitor and Monitoring Data is uploaded to mobile control module and while the illumination and monitoring of temporary lighting when occurring for fire
Probe module, and for carrying out implementing detection and positioning to the tunnel condition of a fire and detection data being uploaded into mobile control module
Smog and fire detector module;Also include scalable pipeline, pressue device, fire fighting supply point, wireless communication module, BIM intelligence
Intelligent fire-fighting work platform, the water inlet of the scalable pipeline reconnects fire fighting supply point after being connected with pressue device, scalable
The delivery port of pipeline is connected with automating the water inlet of head module, and the mobile control module is adopted with the wireless communication module
With connection is wirelessly transferred, the wireless communication module receives the monitoring data collected by the mobile control module, and will
Data transfer is to BIM wisdom fire-fighting workbenches.
2. the portable subregion wisdom fire-fighting device in the tunnel based on BIM technology according to claim 1, it is characterised in that:
The working track both sides are vertically provided with maintenance track, and mobile control module runs on maintenance track.
3. the portable subregion wisdom fire-fighting device in the tunnel based on BIM technology according to claim 1, it is characterised in that:
The BIM wisdom fire-fightings workbench is integrated with complete tunnel BIM models, display tunnel structure thing and various electromechanical equipments,
Affiliated facility, BIM wisdom fire-fightings workbench receives fire information, and fire video monitoring information, fire detector information are existed
Real-time exhibition in control platform BIM models, the BIM wisdom fire-fightings workbench can be to automation head module, illumination and prison
Control probe module, mobile control module, smog and fire detector module progress control in real time, real-time, interactive, issue induction refer to
Order, while many set emergency preplans built in the BIM wisdom fire-fightings workbench, described according to fire order of severity automatic start
BIM wisdom fire-fightings workbench records emergency preplan implementation procedure, self-extinguishing implementation procedure, manual intervention process automatically, makes
Whole fire extinguishing procedure possesses trackability.
4. the portable subregion wisdom fire-fighting device in the tunnel based on BIM technology according to claim 1, it is characterised in that:
The pressue device is the fire fighting pressurization pump for the hydraulic pressure progress Self-pressurizing agri that can be monitored according to automation head module.
5. a kind of portable subregion wisdom fire-fighting method in tunnel based on BIM technology as described in claim 1-4 is any, it is special
Levy and be, comprise the following steps:
S1, by illumination tunnel is patrolled with monitoring probe module and fire point is monitored in real time, pass through smog
The tunnel condition of a fire is carried out with fire detector module to implement detection and positioning;
S2, video monitoring data is gathered based on S1 and fire monitoring data are uploaded to mobile control module;
S3, the information received based on S2 movements control module, are uploaded to BIM wisdom by fire data through wireless communication module and disappeared
Anti- workbench, BIM wisdom fire-fightings workbench is by fire video monitoring information, fire detector information in control platform BIM
Real-time exhibition in model, and start corresponding emergency preplan;
S4, the fire information received based on S2 movements control module, according to smog and reality of the fire detector module to fire
Shi Dingwei, mobile control module, which is automatically moved into, suitably puts position, illumination and monitoring probe module fire is carried out monitoring in real time and
Illumination, automation head module adjustment spray angle opens self-extinguishing;
S5, based on S4 steps, BIM wisdom fire-fightings workbench receives each module to the responsive state of tunnel fire hazard, control platform
BIM models are by each module working condition real-time exhibition, interactive controlling, issue induction instruction, and administrative staff are to fire extinguishing implementation status
Carry out inspection in real time, real-time manual intervention control;
S6, based on S5 steps, BIM wisdom fire-fightings workbench records emergency preplan implementation procedure, self-extinguishing and performed automatically
Journey, manual intervention process, make whole fire extinguishing procedure possess trackability.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710529426.XA CN107126656A (en) | 2017-07-02 | 2017-07-02 | A kind of portable subregion wisdom fire-fighting device and method in the tunnel based on BIM technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710529426.XA CN107126656A (en) | 2017-07-02 | 2017-07-02 | A kind of portable subregion wisdom fire-fighting device and method in the tunnel based on BIM technology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107126656A true CN107126656A (en) | 2017-09-05 |
Family
ID=59736752
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710529426.XA Pending CN107126656A (en) | 2017-07-02 | 2017-07-02 | A kind of portable subregion wisdom fire-fighting device and method in the tunnel based on BIM technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107126656A (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108245806A (en) * | 2018-03-23 | 2018-07-06 | 沈阳理工大学 | A kind of vcehicular tunnel integrates fire-fighting system |
CN108261706A (en) * | 2018-03-23 | 2018-07-10 | 沈阳理工大学 | A kind of vcehicular tunnel intelligent fire extinguishing system |
CN108261711A (en) * | 2018-03-23 | 2018-07-10 | 沈阳理工大学 | A kind of vcehicular tunnel self-extinguishing machine people |
CN108853854A (en) * | 2018-05-16 | 2018-11-23 | 武汉科技大学 | Mobile spray gun fire extinguishing system in tunnel |
CN110113572A (en) * | 2019-05-08 | 2019-08-09 | 中铁八局集团建筑工程有限公司 | A kind of outdoor scene loaming method based on Building Information Model |
CN111068222A (en) * | 2019-12-29 | 2020-04-28 | 太仓苏安消防设备有限公司 | Five-axis motion automatic aiming fire extinguishing agent protection system and working method thereof |
CN112933487A (en) * | 2021-02-24 | 2021-06-11 | 中国华能集团清洁能源技术研究院有限公司 | Rail-mounted detection emergency fire-fighting integrated device and method |
CN113267364A (en) * | 2021-07-14 | 2021-08-17 | 四川藏区高速公路有限责任公司 | Model simulation test device for tunnel under-passing existing tunnel |
CN113849998A (en) * | 2021-09-25 | 2021-12-28 | 北京杜普信科技有限公司 | BIM-based tunnel fire early warning processing method and system |
CN116899159A (en) * | 2023-09-12 | 2023-10-20 | 西南交通大学 | Construction management system of high-altitude super-long tunnel based on GIS and BIM |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003126286A (en) * | 2001-10-22 | 2003-05-07 | Tokyo Bosai Setsubi Kk | Fire extinguishing system |
JP2003535660A (en) * | 2000-06-23 | 2003-12-02 | ジャン−ピエール デモール,フレデリック | Fire extinguisher |
JP2004024381A (en) * | 2002-06-24 | 2004-01-29 | Hochiki Corp | Fire extinguishing robot for tunnel |
CN201164675Y (en) * | 2008-02-01 | 2008-12-17 | 山东省科学院自动化研究所 | Intelligent robot system for tunnel fire-fighting emergency |
CN101461986A (en) * | 2008-12-29 | 2009-06-24 | 丁国锋 | Robot, fire-extinguishing system and extinguishment method |
CN204447034U (en) * | 2015-01-15 | 2015-07-08 | 山东科一力电气有限公司 | A kind of suspension type intelligent mobile fire extinguishing system |
KR20150122351A (en) * | 2014-04-23 | 2015-11-02 | 주식회사 경진인터내쇼날 | a nozzel for fire suppression using Building Information Modeling and, a method for fire suppression using Building Information Modeling |
CN106730560A (en) * | 2017-01-06 | 2017-05-31 | 西安思源学院 | Structural fire protection real-time monitoring system based on BIM |
CN206979888U (en) * | 2017-07-02 | 2018-02-09 | 四川藏区高速公路有限责任公司 | A kind of tunnel movable type subregion wisdom fire-fighting device based on BIM technology |
-
2017
- 2017-07-02 CN CN201710529426.XA patent/CN107126656A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003535660A (en) * | 2000-06-23 | 2003-12-02 | ジャン−ピエール デモール,フレデリック | Fire extinguisher |
JP2003126286A (en) * | 2001-10-22 | 2003-05-07 | Tokyo Bosai Setsubi Kk | Fire extinguishing system |
JP2004024381A (en) * | 2002-06-24 | 2004-01-29 | Hochiki Corp | Fire extinguishing robot for tunnel |
CN201164675Y (en) * | 2008-02-01 | 2008-12-17 | 山东省科学院自动化研究所 | Intelligent robot system for tunnel fire-fighting emergency |
CN101461986A (en) * | 2008-12-29 | 2009-06-24 | 丁国锋 | Robot, fire-extinguishing system and extinguishment method |
KR20150122351A (en) * | 2014-04-23 | 2015-11-02 | 주식회사 경진인터내쇼날 | a nozzel for fire suppression using Building Information Modeling and, a method for fire suppression using Building Information Modeling |
CN204447034U (en) * | 2015-01-15 | 2015-07-08 | 山东科一力电气有限公司 | A kind of suspension type intelligent mobile fire extinguishing system |
CN106730560A (en) * | 2017-01-06 | 2017-05-31 | 西安思源学院 | Structural fire protection real-time monitoring system based on BIM |
CN206979888U (en) * | 2017-07-02 | 2018-02-09 | 四川藏区高速公路有限责任公司 | A kind of tunnel movable type subregion wisdom fire-fighting device based on BIM technology |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108245806A (en) * | 2018-03-23 | 2018-07-06 | 沈阳理工大学 | A kind of vcehicular tunnel integrates fire-fighting system |
CN108261706A (en) * | 2018-03-23 | 2018-07-10 | 沈阳理工大学 | A kind of vcehicular tunnel intelligent fire extinguishing system |
CN108261711A (en) * | 2018-03-23 | 2018-07-10 | 沈阳理工大学 | A kind of vcehicular tunnel self-extinguishing machine people |
CN108853854A (en) * | 2018-05-16 | 2018-11-23 | 武汉科技大学 | Mobile spray gun fire extinguishing system in tunnel |
CN110113572A (en) * | 2019-05-08 | 2019-08-09 | 中铁八局集团建筑工程有限公司 | A kind of outdoor scene loaming method based on Building Information Model |
CN111068222A (en) * | 2019-12-29 | 2020-04-28 | 太仓苏安消防设备有限公司 | Five-axis motion automatic aiming fire extinguishing agent protection system and working method thereof |
CN112933487A (en) * | 2021-02-24 | 2021-06-11 | 中国华能集团清洁能源技术研究院有限公司 | Rail-mounted detection emergency fire-fighting integrated device and method |
CN113267364A (en) * | 2021-07-14 | 2021-08-17 | 四川藏区高速公路有限责任公司 | Model simulation test device for tunnel under-passing existing tunnel |
CN113267364B (en) * | 2021-07-14 | 2021-11-09 | 四川藏区高速公路有限责任公司 | Model simulation test device for tunnel under-passing existing tunnel |
CN113849998A (en) * | 2021-09-25 | 2021-12-28 | 北京杜普信科技有限公司 | BIM-based tunnel fire early warning processing method and system |
CN113849998B (en) * | 2021-09-25 | 2022-12-02 | 北京杜普信科技有限公司 | BIM-based tunnel fire early warning processing method and system |
CN116899159A (en) * | 2023-09-12 | 2023-10-20 | 西南交通大学 | Construction management system of high-altitude super-long tunnel based on GIS and BIM |
CN116899159B (en) * | 2023-09-12 | 2023-11-21 | 西南交通大学 | Construction management system of high-altitude extra-long tunnel based on GIS and BIM |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107126656A (en) | A kind of portable subregion wisdom fire-fighting device and method in the tunnel based on BIM technology | |
CN207125992U (en) | A kind of unmanned plane high-altitude fire extinguishing system | |
CN206979888U (en) | A kind of tunnel movable type subregion wisdom fire-fighting device based on BIM technology | |
CN110051953A (en) | A kind of wisdom formula fire-fighting system | |
CN205055270U (en) | Collect fire control and rescue in intelligent device of an organic whole | |
CN112093050B (en) | Modularized unmanned aerial vehicle fire engine | |
CN104888388A (en) | Wall-climbing, detecting and mutually-controlling fire-fighting robot | |
CN115379306B (en) | Outdoor disaster monitoring system and method based on aircraft relay communication | |
CN109147253A (en) | A kind of wisdom fire-fighting safety anticipation management linkage platform | |
CN112044009A (en) | Intelligent monitoring system and method for fire safety facilities | |
CN110060191A (en) | A kind of rescue site command methods and system | |
CN105920760A (en) | High-altitude fire extinguishing equipment | |
CN111428299A (en) | Engineering whole-course monitoring system | |
CN205177260U (en) | Firework simulated training device | |
CN106640184A (en) | Multifunctional suspension track platform for road tunnel | |
CN215867976U (en) | Intelligent road tunnel inspection robot system based on multi-dimensional sensing | |
CN113903203A (en) | Training system and training method for plateau uniform | |
CN103985280A (en) | Building fire altering training system | |
CN206608205U (en) | A kind of vcehicular tunnel multifunction railway slide device | |
CN112650101A (en) | Intelligent road tunnel inspection robot system based on multi-dimensional sensing | |
CN210131279U (en) | Crawler-type indoor fire-fighting patrol robot | |
CN111603704A (en) | Traditional village land-navigation dual-purpose unmanned aerial vehicle-mounted intelligent fire extinguishing technology | |
CN205031833U (en) | Remote control lift platform that puts out a fire | |
CN207186957U (en) | Aerial fire-fighting and rescue system | |
CN116492623A (en) | Fire early-warning and fire-extinguishing intelligent robot and fire-extinguishing method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |